BID 2026-24_May_4_26_solicitation_doc.pdf

PDF 15 KB Posted

Attached to
Structural Concrete Floor Repair - Stratford Transfer Station
Solicitation number
BID 2026-24
Issued by
Fairfield County, Connecticut

About this file

This is an Invitation to Bid (ITB) solicitation issued by the Town of Stratford, Connecticut for structural concrete floor repair work at the Stratford Transfer Station. The scope of work includes removing portions of the existing concrete slab within the repair area to a specified depth and installing a new reinforced topping slab, with an optional Alternate #1 to encase three steel columns in concrete. The project requires phased work to maintain continuous transfer station operations throughout construction. The solicitation opened April 6, 2026 at 4:00 PM EDT with a submission deadline of May 7, 2026 at 10:00 AM EDT. A non-mandatory pre-bid site meeting is scheduled for April 14, 2026 at 10:00 AM, and written requests for information must be submitted by April 29, 2026 at 12:00 PM EDT. Construction is scheduled to commence June 1, 2026 with substantial completion targeted for June 30, 2026 and final closeout by July 31, 2026. All bids must be submitted in sealed envelopes marked "BID #2026-24" to the Purchasing Department; electronic submissions are explicitly prohibited.

The contract will be awarded to the lowest responsible bidder meeting all specifications, with payment terms of Net 30 days upon review and approval by all relevant Town boards. Bidders must include a $5,000 allowance for unforeseen conditions and changes and submit a five percent bid bond with their proposals. The successful bidder must furnish both a Performance Bond and Payment Bond equal to 100 percent of the award amount within seven business days of contract notification, with five percent retainage held for 45 days after final payment. All workers must comply with Connecticut prevailing wage rates as of March 31, 2026, with annual adjustments effective July 1st, and all covered employees must provide proof of OSHA 10-Hour Construction Safety and Health Course completion. The anticipated total bid value exceeds $100,000, and there are no specific set-aside designations, incumbent vendors, or current contractors identified in the available documentation. All requests for information must be submitted in writing to Phillip Ryan, Purchasing Agent, at pryan@townofstratford.com; verbal communication and phone calls are not accepted.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number: BID 2026-24

Structural Concrete Floor Repair - Stratford Transfer Station

Invitation to Bid (ITB)

Stratford, Town of

April 06, 2026 - May 07, 2026

Page:2

General Header Information

This bid has no questions defined.

BID 2026-24

No. BID 2026-24 Title: Structural Concrete Floor Repair - Stratford Transfer Station Start Date: April 06, 2026 at 4:00:00 PM EDT End Date: May 07, 2026 at 10:00:00 AM EDT Vendor Q&A Start Date: April 06, 2026 at 4:15:00 PM EDT Vendor Q&A End Date: April 29, 2026 at 12:00:00 PM EDT Estimated Total Value:

Who can respond to this bid? : All Vendors Description: Remove portions of existing slab within repair area to indicated depth.

Install new reinforced topping slab. Alternate #1: Encase three (3) steel columns in concrete. Transfer station shall remain open and operational during the work; therefore, all work needs to be phased accordingly.

***DO NOT SUBMIT BIDS ELECTRONICALLY***

Delivery Terms: N/A: Not Applicable Payment Terms: Net 30 Days Payment Notes: 30 days upon review and approval by all relevant Town boards.

Contact Information: Stratford, Town of

Phillip Ryan, Purchasing Agent Email: pryan@townofstratford.com Submit all requests for information (RFI) in writing to email address above.

Note verbal communication will NOT be accepted. No calls.

Contact Details: If you have any questions, please contact:

Phillip Ryan, Purchasing Agent Email: pryan@townofstratford.com Submit all requests for information (RFI) in writing to email address above.

Note verbal communication will NOT be accepted. No calls.

Selected Categories:

Page:3

Documents:

2026-24 Structural Concrete Floor Repair - Transfer Station.pdf

2026-24 Sign-in Sheet.pdf

2026-24 Addendum 1.pdf

Page:4

Item Specifications Solicitation has been designated as having no line items.

Page:5

File details come from the government source that posted it. Updated .