BI-MH-139_90 percent CD Phase Narrative Report.pdf
PDF 8 MB Posted
- Solicitation number
- BI-MH-139-CMR-2
- Issued by
- Fairfield County, Connecticut
About this file
Summary
This document is a 90% Construction Documents (CD) Design Narrative Report prepared by WSP USA Buildings Inc. and WSP USA Design Inc. for the State of Connecticut Department of Administrative Services (CT DAS) regarding the Greater Bridgeport Community Mental Health Center (GBCMHC) Sprinkler System and Related Renovations project located at 1635 Central Avenue in Bridgeport, Connecticut. The project scope includes designing and installing a code-compliant fire protection sprinkler system throughout the nine-story, 123,000-square-foot facility, along with upgrades to ceilings, lighting and associated controls, replacement and relocation of the emergency generator, and renovation of the fifth floor to serve as clinical swing space. The project is scheduled for construction completion in Spring 2028 to meet a July 5, 2028 Centers for Medicare & Medicaid Services (CMS) deadline for full sprinkler coverage. The design is based on a proposed construction budget of $15,250,000, with a revised cost estimate of $18.07 million (ranging from $15.36 million to $20.78 million) when including the fifth-floor addition and new garage access. The project has been phased into six major phases incorporating infrastructure work, floor-by-floor renovations, and move management strategies to maintain facility operations during construction.
The project will be implemented through a detailed phasing strategy designed to minimize disruption to ongoing mental health services, inpatient care for over 60 beds, and outpatient programs. Phase 1 establishes fire protection infrastructure, emergency power systems, and temporary facilities; Phases 2 through 6 systematically renovate the eighth, first, fifth, third, sixth, fourth, seventh, second, and ground floors concurrently with administrative floors to expedite the schedule. The design complies with 2026 Connecticut State Building, Fire Safety, and Electrical Codes, along with applicable NFPA standards including NFPA 13 (Sprinkler Systems), NFPA 20 (Fire Pumps), NFPA 72 (Fire Alarm), and NFPA 101 (Life Safety Code). Key project elements include a new 75 HP fire pump rated at 1,000 gpm, replacement of the existing generator, installation of anti-ligature sprinklers and safety improvements in secure psychiatric client areas, and deployment of two temporary office trailers to accommodate approximately 26 displaced staff members during construction phases.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of Connecticut Department of Administrative Services GBCMHC – Sprinkler System and Related Renovations 90% CD Design Narrative Report 2026-11-03
CT DAS Project No.: BI-MH-139-ARC WSP Project No.: US0047700.4237
GBCMHC – Sprinkler System and Related Renovations 90% CD Design Narrative Report – BI-MH-139-ARC 2026-11-03 | WSP Project No.: US0047700.4237 2
Document distribution
State of Connecticut Department of Administrative Services
GBCMHC – Sprinkler System and Related Renovations
90% CD Design Narrative Report 90% Construction documents design phase report for 1635 Central Ave. in Bridgeport, CT
2026-11-03
CT DAS Project No.: BI-MH-139-ARC
WSP Project No.: US0047700.4237
Prepared for State of Connecticut Department of Administrative Services
450 Columbus Boulevard Hartford CT 06103
Prepared by WSP USA Buildings Inc. & WSP USA Design Inc.
100 Summer Street, 13th Floor Boston, MA 02110
2026-11-03 | WSP Project No.: US0047700.4237 3
Table of contents
Abbreviations and glossary 6
1. Executive summary 7
1.1 Introduction 7
1.2 Design Basis and Budget 7
1.3 Implementation and Phasing 8
1.4 Conclusion 9
2. Design Basis 10
2.1 Building Overview and History 10
2.2 Existing Conditions 10
2.3 Existing Program 11
2.4 Governing Codes and Standards 13
2.4.1 Federal and State Codes 13
2.4.2 State and Other Governing Standards 13
2.5 Ongoing and Future Projects 14
2.6 Study Phase 15
2.6.1 Methodology 15
2.6.2 Summary of Findings 16
2.6.3 Preliminary Phasing Approach 17
3. Phasing 18
3.1 Phase 1 – Infrastructure and Enabling Work 18
3.1.1 Phase 1A – Fire Protection Infrastructure 20
3.1.2 Phase 1B – Emergency Power Infrastructure 21
3.1.3 Phase 1C – Temporary Trailers and Site Readiness 22
3.2 Phase 2 22
3.2.1 Phase 2A – Eighth Floor Renovation 22
3.2.2 Phase 2B – First Floor Renovation 24
3.3 Phase 3 26
3.3.1 Phase 3A – Fifth Floor Clinical Swing Space 26
3.3.2 Phase 3B – Third Floor Renovation 28
3.4 Phase 4 30
3.4.1 Phase 4A – Sixth Floor Renovation 30
3.4.2 Phase 4B/4C – Fourth Floor Areas 1 and 2 Renovation 32
3.4.3 Phase 4D – Fourth Floor Pharmacy Renovation 33
3.5 Phase 5 34
3.5.1 Phase 5A – Seventh Floor Renovation 34
3.5.2 Phase 5B – Second Floor Renovation 36
3.5.3 Phase 5C – Second Floor Medical Records Renovation 37
2026-11-03 | WSP Project No.: US0047700.4237 4
3.6 Phase 6 – Ground Floor Renovation 37
3.6.1 Phase 6A/B – Ground Floor Areas 1 and 2 Renovation 38
3.6.2 Phase 6C – Ground Floor Area 3 Renovation 40
3.7 Project Completion 40
4. Existing Conditions and Design Narratives 41
4.1 Architectural 41
4.1.1 Preliminary Impacts and Constraints 41
4.1.2 Finishes 41
4.1.3 Phasing and Swing Space 42
4.2 Fire Protection 44
4.2.1 Existing System Description 44
4.2.2 System constraints and necessary upgrades associated with the project 47
4.3 Mechanical 49
4.3.1 Existing System Description 49
4.3.2 System constraints and necessary upgrades associated with the project 49
4.4 Electrical/Fire Alarm 50
4.4.1 Existing System Description 50
4.4.2 System constraints and necessary upgrades associated with the project 54
4.4.3 Generator Design 55
4.4.4 Fire Pump Electrical Service 56
4.4.5 Lighting Modifications 56
4.4.6 Fire Alarm Modifications 57
4.5 Generator Acoustic Analysis 58
4.5.1 Overview 58
4.5.2 Project Scope and Background 58
4.5.3 Design Criteria 58
4.5.4 Exterior Noise Measurements 59
4.5.5 Generator Selection 61
5. Budget 63
5.1 Estimating Methodology 63
5.2 Accuracy and Data Sources 63
5.3 Budget and Allowances 63
Figure 2.1 Existing Programming Diagrams 11 Figure 3.1 Ground Floor Phasing 19 Figure 3.2 Site Work Areas 19 Figure 3.3 Eighth Floor Phasing 22 Figure 3.4 First Floor Phasing 24 Figure 3.5 Third Floor Phasing Error! Bookmark not defined.
2026-11-03 | WSP Project No.: US0047700.4237 5
Figure 3.6 Fifth Floor Phasing 26 Figure 3.7 Second Floor Phasing Error! Bookmark not defined.
Figure 3.8 Sixth Floor Phasing 30 Figure 3.9 Fourth Floor Phasing 32 Figure 3.10 Seventh Floor Phasing 34 Figure 3.11 Third Floor Phasing Error! Bookmark not defined.
Figure 3.12 Ground Floor Phasing 38 Figure 4.1 Existing Fire Pump Gauge – Inlet static pressure of 75 psi 44 Figure 4.2 Existing Fire Pump Data Plate 45 Figure 4.3 Existing Fire Pump Controller – No Emergency Transfer Switch (ATS) Present 45 Figure 4.4 Existing Sprinkler Control Valve inside Stair # 2 47 Figure 4.5 Existing Main Switchboard 50 Figure 4.6 Existing Generator Nameplate 51 Figure 4.7 Existing Generator Enclosure 52 Figure 4.8 Existing Generator Control Panel 52 Figure 4.9 Existing Emergency Lighting Battery Cabinet 53 Figure 4.10 Existing Notifier NFS-3030 Fire Alarm Control Panel 53 Figure 4.11 Existing Remote Fire Alarm Annunciator 54 Figure 4.12 Example of Electrical Equipment Clearance Non-Compliance 54 Figure 4.13 Existing Fire Pump ATS in Main Switchgear Room G51B 55 Figure 4.14 Measurement Locations 60 Figure 4.15 Meter Configurations 60
Table 4.1 Maximum Allowable Noise Levels by Emitting and Receiving Zones –
Reproduced from The Bridgeport CT Code of Ordinances, §8.80.040 59 Table 4.2 Measurement Equipment Information 59 Table 4.3 Ambient Measurements Results(1) 61
Appendix A – Existing Program Appendix B – Cost Estimate and Budget Appendix C – Project Schedule Appendix D – Existing Documentation
Huckins, Elizabeth Check figure numbers and naming with the adjustments to the phasing
Huckins, Elizabeth Proposed appendices:
Keep A - Program Delete B and C Keep D and E What about F?
Kalach, Stephen Works for me!
Kalach, Stephen Keep existing docs in there.
2026-11-03 | WSP Project No.: US0047700.4237 6
Abbreviations and glossary
Abbreviations
Abbreviation Description
CMS Centers for Medicare & Medicaid Services
DAS Department of Administrative Services
DHMAS Department of Mental Health and Addiction Services
GBCMHC Greater Bridgeport Community Mental Health Center
JCAHO Joint Commission on Accreditation of Healthcare Organizations
SWCMHS Southwest Connecticut Mental Health System
HVAC Heating, Ventilation, and Air Conditioning
NFPA National Fire Protection Association
ADA Americans with Disabilities Act
A/C Air Conditioning
MEP/FP Mechanical, Electrical, Plumbing / Fire Protection
HAZMAT Hazardous Materials
FDC Fire Department Connection
GPM Gallons Per Minute
HP Horsepower
ATS Automatic Transfer Switch
LED Light Emitting Diode
LAEQ Equivalent Continuous Sound Level (dBA)
2026-11-03 | WSP Project No.: US0047700.4237 7
1. Executive summary
1.1 Introduction
The State of Connecticut Department of Administrative Services (CT DAS) has retained WSP USA Buildings Inc., including WSP USA Design Inc. for architectural services, (WSP) to design a code compliant fire protection sprinkler system and associated upgrades at the GBCMHC. In addition to fire protection sprinkler system, the scope of work includes upgrades to existing ceilings, upgrades to lighting and associated controls, and replacement and relocation of the emergency generator. SWCMHS and CT DMHAS operate the nine-story facility located at 1635 Central Avenue Bridgeport, Connecticut.
The Construction Documents Phase finalizes the project’s budget and design concepts, and develops strategies for implementation and phasing. This report builds on the Design Development Phase, identifying the design basis and design approach for major building systems. The Construction Documents phase introduces the fifth floor renovation and new Garage Access design to the package per the contract amendment.
1.2 Design Basis and Budget
The design is based on a proposed construction budget of $15,250,000 and construction completion in Spring 2028. A cost estimate (Appendix B) was performed based on the phasing and scope noted in this report, the design development drawings, the fifth floor renovation drawings provided by DAS, and the additional parking garage access estimate. The estimate notes the overall construction cost (including the fifth floor add and new garage access) will be $18.07 million, ranging between $15.36 million and $20.78 million. Based on the proposed construction phasing it is anticipated the project can be delivered within the project schedule (Appendix C).
To meet the project targets WSP and the project team will need to collaborate on staff relocations, swing space allocation, and phasing requirements. In addition to the fire protection and related systems upgrades, the design basis includes:
1. Providing a new emergency generator per owner coordination.
2. Updating the Fire Alarm system per Option 1 in Section 4.4.6.
3. Safety improvements in areas identified for clinical swing space.
4. Renovation of the 5th floor to match other patient floors.
5. New garage access for trailers.
2026-11-03 | WSP Project No.: US0047700.4237 8
1.3 Implementation and Phasing
To meet the proposed budget and deadline WSP proposes the project be phased as outlined in this report. The intent of this phasing is to limit contractor downtime and to meet the needs of the staff and clients within the building with necessary swing space and appropriate accommodation. This involves installing the new fire pump, sprinkler risers, emergency generator, and temporary office trailers as part of the initial phase to allow the phasing to be completed and tested two floors at a time without impacting other floors. WSP has developed the following phasing approach, which is further detailed in this report, along with move management considerations for each phase.
Phase 1 – Infrastructure and Enabling Work
Phase 1A – Fire Protection Infrastructure
Phase 1B – Emergency Power Infrastructure
Phase 1C – Temporary Facilities and Site Readiness
Phase 2
Phase 2A – Eighth Floor Renovation
Phase 2B – First Floor Renovation
Phase 3
Phase 3A – Fifth Floor Clinical Swing Space
Phase 3B – Third Floor Renovation
Phase 4
Phase 4A – Sixth Floor Renovation
Phase 4B/4C – Fourth Floor Areas 1 and 2 Renovation
Phase 4D – Fourth Floor Pharmacy Renovation
Phase 5
Phase 5A – Seventh Floor Renovation
Phase 5B – Second Floor Renovation
Phase 5C – Second Floor Medical Records Renovation
Phase 6 – Ground Floor Renovation
Phase 6A/B – Ground Floor Areas 1 and 2 Renovation
Phase 6C – Ground Floor Area 3 Reception Renovation
2026-11-03 | WSP Project No.: US0047700.4237 9
1.4 Conclusion
This report, along with other deliverables, establishes a sequenced phasing concept with swing space strategies that consider stakeholders, staff and clients' requirements. The phasing strategy is coordinated in this report with programming materials and a cost estimate, creating a clear, budget aware basis for Construction Documents.
Moving forward developing the design, the team focused on detailed implementation of the proposed changes, phasing, and swing space accommodation required to fully fit-out the building with sprinklers in advance of July 5, 2028, CMS deadline.
2026-11-03 | WSP Project No.: US0047700.4237 10
2. Design Basis
2.1 Building Overview and History
The Greater Bridgeport Community Mental Health Center, located at 1635 Central Avenue in Bridgeport, Connecticut, is a nine-story facility encompassing approximately 123,000 square feet. Established in 1972, the center provides a range of mental health services, including inpatient care with over 60 beds, as well as numerous supportive programs designed to assist individuals transitioning back into the community.
Operated by SWCMHS and CT DMHAS, the facility has undergone multiple repairs and system upgrades throughout its lifespan. There was a recent project for hazardous materials abatement throughout the building. In addition to past improvements, several projects are currently in design, and additional initiatives are in planning or conceptual phases.
2.2 Existing Conditions
As a high rise medical center the Joint Commission has required all buildings of this type to be fully sprinklered by July 5, 2028. The building is currently protected by a standpipe system with three hose valves located on each floor as well as partial sprinklers located in storage, mechanical, and pharmacy spaces. Additionally, to support the sprinkler upgrade, it is noted that the existing fire pump is past its useful life and will need to be replaced along with the existing emergency generator and fuel oil storage.
The existing fire alarm system is outdated and will require upgrades to accommodate the sprinkler upgrade.
Client floors are located on the fifth through eighth floors and will require anti-ligature devices throughout the secure client areas. Interior finishes have been modified throughout the building as renovation projects have occurred. Ceilings, as well as lighting systems within the ceilings, will be impacted by this project. Existing ceilings are generally suspended or direct-applied acoustical ceiling tiles. Existing lighting within acoustic ceilings is generally recessed fixtures with T-8 fluorescent bulbs.
2026-11-03 | WSP Project No.: US0047700.4237 11
2.3 Existing Program
Diagrams of existing building programming, including where staff, clients, and different departments reside, can be found below and in Appendix A.
Figure 2.1 Existing Programming Diagrams
The building is occupied by the following units and groups:
Medical Services – Inpatient Secure Units
Psychiatric Intensive Care Units (PICU) I and II – 42 beds
Co-Occurring Treatment Unit (CTU) – 20 beds
Hospital and Nursing Services
Clinical Education
Infection Control
Dietitian
Social and Rehabilitation Services
Psychology
Community Services
Outpatient Unit – Transitional Resident Program (TRP) – 12 beds
2026-11-03 | WSP Project No.: US0047700.4237 12
Clinical Services Unit (CSU)
Young Adult Services (YAS)
Outpatient Nursing
Deaf & Hard of Hearing Services
Shelter + Care, Homeless Outreach Team (HOT)
Peers Utilizing Skills for Healing (PUSH)
Diagnostic and Evaluation Center
Crisis Intervention Team (CIT)
Mobile Crisis Team
Quality Improvement and Compliance
Health Information Management (HIM)
Medical Records
Pharmacy
Information Technology
Education and Training / Staff Development
Administrative and Fiscal Services
Food and Dietary Services
Business Office
Executive / Leadership
Leased Properties
Plant Facilities and Operations
The building consists of inpatient and outpatient bedrooms and associated support spaces, exam rooms, nurse’s stations, community rooms, dining areas, a commercial-style kitchen, a pharmacy, medical records, enclosed offices, conference rooms, staff lounges and break areas, housekeeping, plant operations, and storage areas. Floors five through seven are dedicated to the inpatient psychiatric clients and support staff, while the eighth floor houses the TRP unit. The second and fourth floors and portions of the first and third floors support outpatient services as well as the Pharmacy and Medical Records.
The remainder of the third-floor houses food services and the kitchen, while the remainder of the first floor houses the administrative staff offices. The ground floor includes the primary building entrance and security team, a small area for community services, plant facilities and operations, and housekeeping and storage areas. Further discussion of where units are located in the building and the potential impact of this project is in discussion in the Phasing section of this report.
2026-11-03 | WSP Project No.: US0047700.4237 13
2.4 Governing Codes and Standards
2.4.1 Federal and State Codes
Connecticut State Codes are due to be updated in 2026, this project will be permitted under the 2026 updated codes.
1. 2026 Connecticut State Building Code – 2024 International Building Code (IBC) with CT amendments
2. 2026 Connecticut State Existing Building Code – 2024 International Existing Building Code (IEBC) with CT amendments
3. 2026 Connecticut State Fire Safety Code - 2024 International Fire Code (IFC) and portions of 2021 NFPA 101 with CT amendments and 2019 NFPA 13
4. 2026 Connecticut State Fire Prevention Code - 2021 NFPA 1 with CT amendments
5. 2026 Connecticut State Plumbing Code - 2024 International Plumbing Code (IPC) with CT amendments
6. 2026 Connecticut State Mechanical Code - 2024 International Mechanical Code (IMC) with CT amendments
7. 2026 Connecticut State Energy Code - 2024 International Energy Conservation Code (IECC) with CT amendments
8. 2026 Connecticut State Electrical Code - 2023 NFPA 70 National Electric Code (NEC) with CT amendments
2.4.2 State and Other Governing Standards
1. DAS Construction Services Standards
2. FGI Guidelines (2022)
3. 2021 IgCC – International Green Construction Code (sections required by 0450 Capital Projects High Performance Buildings Guidelines)
4. NFPA 13 – Installation of Sprinkler Systems
5. NFPA 14 – Installation of Standpipe and Hose Systems
6. NFPA 20 – Installation of Stationary Fire Pumps for Fire Protection
7. NFPA 25 – Inspection, Testing, and Maintenance of Water-Based Systems
8. NFPA 70 – National Electric Code
9. NFPA 72 – National Fire Alarm and Signaling Code
2026-11-03 | WSP Project No.: US0047700.4237 14
10. NFPA 99 – Health Care Facilities Code (2012 per CMS)
11. NFPA 101 – Life Safety Code (2012 per CMS)
12. FM Property Loss Prevention Data Sheet DS 2-0 – Installation Guidelines for Automatic Sprinklers
13. FM Property Loss Prevention Data Sheet 3-7 - Fire Protection Pumps
14. FM Property Loss Prevention Data Sheet 3-29 - Reliability of Fire Protection Water Supplies
15. FM Property Loss Prevention Data Sheet 3-10 - Installation/Maintenance of Fire Service Mains
16. FM Property Loss Prevention Data Sheet 5-40 – Fire Alarm Systems
17. FM Property Loss Prevention Data Sheet 5-48 – Automatic Fire Detection
18. FM Property Loss Prevention Data Sheet 5-23 - Design and Protection for Emergency and Standby Power Systems
19. FM Property Loss Prevention Data Sheet 7-32 – Ignitable Liquid Operations
2.5 Ongoing and Future Projects
Based on existing information provided by CT DAS, the building is planned to undergo substantial renovations in both the short and long term. The following is a list of current and future projects identified for the Greater Bridgeport Community Mental Health Center, extracted from the prior analysis provided by CT DAS (Multiple Project Single Site Process Survey – September 9th) and replicated here for context:
Current Projects Upgrades to Ceilings, Lighting & Sprinkler System (including Generator Replacement) – for which this report provides detail.
5th Floor Patient Ward Renovation – for which this report provides detail, creating swing space for the sprinkler project
Replace Roof and A/C Units
Elevator Modernizations
Future Projects Exterior Façade Upgrades
New ADA Ramp at Patient Garden (Phase 1)
New Ground Floor Exterior Main Entrance
2026-11-03 | WSP Project No.: US0047700.4237 15
New 1st Floor Patient Intake Access
New Storage & Maintenance Building/Addition
Renovation of Former Dining Hall
Replace Domestic Hot Water System
Replace Ground to 4th Floor A/C Units (alternate)
Electrical & Transformer Room Reconfiguration
Patient Garden Expansion – Phase 2
ADA Parking Upgrades
Replace Perimeter Fencing
Electric Vehicle Chargers
New Public Address System
2.6 Study Phase
WSP completed a pre-design study for this project during late summer 2025 to evaluate the existing fire protection and related systems, including the fire pump and required HVAC for a practical, code compliant upgrade in an occupied facility. Additional systems studied include ceilings, lighting, and an exterior emergency generator with fuel storage. The Study Phase review meeting was held on October 29, 2025 and resulting comments were incorporated into the final report. The Study Phase Report – FINAL, dated 2025-11-14, includes additional information and references that informed the design basis for this project.
2.6.1 Methodology
WSP reviewed a collection of historic drawings and reports for the Greater Bridgeport Community Mental Health Center, spanning from the early 1970s to the present. The team conducted a 3D scan (point cloud) of the interior of the building in August 2025 to develop a Revit model of the existing building that supports design and drawing development for this project. Following review of the existing documentation and the 3D scan, the design team conducted targeted investigations throughout the building to gather information needed to evaluate existing systems and develop the detailed design. A summary of findings for each discipline is provided in later sections of this report.
Field investigations were followed by user interviews in the form of a programming and phasing charrette to confirm data collected on-site and collaboratively discuss phasing constraints and opportunities. The charrette was held virtually on September 9, 2025 and was attended by representatives from CT DAS, CT DMHAS leadership, and WSP. The discussions generally progressed floor by floor, starting on the eighth floor, and covered the following topics:
2026-11-03 | WSP Project No.: US0047700.4237 16
Unit operations overview
Level of client access and proximity needed by staff
Flexibility to relocate elsewhere in the building, elsewhere on the premises, or off-site.
Opportunities and requirements for swing space
Timing and logistics for phasing
A copy of the charrette presentation and marked up programming diagrams that serve as notes from the meeting are included in Study Phase Report – FINAL.
2.6.2 Summary of Findings
During the Study Phase WSP reviewed the existing documentation and performed an on-site survey of the building. The following are relevant findings from these investigations:
Architecture
1. The fifth floor and eighth floor, as well as the third floor multi-purpose space, were identified as likely swing space during the renovation. On-site temporary trailers may also be needed to accommodate staff during the renovation, pending further development of the phasing and site constraints.
Fire Protection
1. The existing fire pump is past its useful life and also located in a room that is not currently code compliant for housing a fire pump.
2. The existing standpipe system will be replaced with new piping due to its age and to comply with the current requirements of NFPA 14 and does not need to be modified. WSP plans to add a new fire sprinkler riser to meet the requirements of NFPA 13 and Factory Mutual.
Electrical and Fire Alarm
1. The existing emergency generator and fuel oil storage are past their useful life.
2. The existing floor-by-floor electrical closets do not meet current code for clearances.
3. The existing wiring of the fire pump does not meet current code.
4. The maintenance staff noted it has been difficult to acquire parts for the outdated fire alarm system.
5. New lighting and controls will need to meet IgCC per the High Performance Building Standard
2026-11-03 | WSP Project No.: US0047700.4237 17
2.6.3 Preliminary Phasing Approach
Based on feedback received during the charrette, the design team developed a preliminary phasing approach, considering requirements of each unit, constructability, swing space, and time and budget constraints. The Phasing section of this report provides a breakdown and summary of the phasing approach that has evolved based on feedback received during design review and design progress meetings. The final phasing strategy was developed in coordination with CT DAS, CT DMHAS, and the construction administrator.
2026-11-03 | WSP Project No.: US0047700.4237 18
3. Phasing
The design team further developed the phasing approach presented during the Study Phase based on feedback and additional information received, as well as further evaluation of the project requirements and time and budget constraints. The phasing strategy in this section was revised and developed following the Design Development phase and meeting to review the phasing and move management approach. The phasing strategy was further refined during the Construction Documents phase in coordination with CT DAS, CT DMHAS, and the construction administrator.
The following provides a breakdown and summary of the phasing strategy, which is organized into six major phases. Each phase further defines work areas that can be grouped and executed concurrently within the same general construction window. The overall phasing approach is structured around the move management strategy for the secure client areas. The eighth floor will be renovated first to provide temporary occupancy for fifth-floor clients and staff, followed by renovation of the fifth floor to serve as swing space for the sixth- and seventh-floor units. No more than one of floors five, six, and seven is planned to be closed at a time, and an administrative floor is paired with each of the clinical floors for concurrent work to expedite the project schedule.
Each phase includes a summary of the departments, programs, and client units affected by the work, together with anticipated move-management requirements and relocation assumptions. Refer to the Architectural Design Narrative for further discussion of programming and siting for the temporary on-site trailers.
3.1 Phase 1 – Infrastructure and Enabling Work
Phase 1 will provide the fire protection, emergency power, and temporary-facility infrastructure required to support the subsequent occupied renovation phases. Portions of the ground floor that are impacted by these systems will be completed during Phase 1.
2026-11-03 | WSP Project No.: US0047700.4237 19
Figure 3.1 Ground Floor Phasing
Figure 3.2 Site Work Areas
2026-11-03 | WSP Project No.: US0047700.4237 20
3.1.1 Phase 1A – Fire Protection Infrastructure
During the first phase, a new fire pump room will be constructed on the ground floor, along with riser in Stair #1 and Stair #2, to provide the infrastructure needed to support construction on each floor. The new riser will run the full height of the building, so the related Phase 1 scope is included on each floor in subsequent phase diagrams.
Architectural
A new fire-rated interior wall and door will provide code-required separation of the new pump room from the building interior. A new insulated exterior door will be provided in a new opening in the exterior concrete masonry wall.
A new fire-rated shaft will be created on each floor adjacent to Stair #2 to accommodate the new fire standpipe. On the fourth floor through the eighth floor this shaft will be located within the staff restrooms, requiring reconfiguration of the doors and restroom entrances.
Fire Protection
The existing fire main will be modified and extended to accommodate the installation of a new fire pump, complete with jockey pump, controllers, and a fire pump test header. In addition, a new fire department connection will be provided.
A new combined 6-inch fire standpipe riser, complete with a 3-inch sprinkler floor control valve and a 3-inch drain riser, will be installed to allow for the phased installation of the sprinkler system on each floor.
A second 6-inch fire standpipe and a 3-inch drain riser will be provided within the interior Stair #2.
The existing fire pump will remain active until the entire new system is fully installed.
Mechanical
A new wall mounted split system with a remote condensing unit will be installed to accommodate the new fire pump room. Because the room is located along the perimeter of the building, the split system shall be capable of providing both heating and cooling.
Electrical/Fire Alarm
New electrical and fire alarm devices shall be provided as required with new room layouts. The fire alarm control panel shall be upgraded to ensure connectivity to new fire alarm devices that may be required.
After the new fire pump and jockey pumps are installed and tested, the existing fire pump and jockey pump shall be demolished back to source. Associated equipment and feeders shall also be demolished.
Existing lighting and lighting controls shall be removed back to source. A new lighting design with LED fixtures and lighting controls shall be provided to meet energy code requirements.
2026-11-03 | WSP Project No.: US0047700.4237 21
Move Management Considerations
The following units and groups will be impacted:
Mobile Crisis Team: Staff need to stay together but can be flexible in where and how they work.
Behavior Home Health (BHH): Staff need to stay together but can be flexible in where and how they work.
Ground floor occupants along affected corridors and access routes.
Police/Security, Facilities, Housekeeping, and Stockroom functions where construction affects circulation or utilities.
The intent is to limit disruption and temporary relocation of these groups during Phase 1; overhead work in the corridors will be conducted off-hours to minimize disruption. An area of the ground floor must be made available for office swing space to support public-facing services during renovations of other floors.
Approximately four staff from the Mobile Crisis team and seven staff from the BHH team are anticipated to work remotely or at a different location so their ground floor space can be made available for office swing space. Four BHH staff in the area of the new fire pump room area will need to be permanently relocated within the building upon project completion.
3.1.2 Phase 1B – Emergency Power Infrastructure
This phase includes the new exterior emergency generator, feeder duct banks, generator switchboard, and associated emergency distribution.
Electrical/Fire Alarm
A new generator shall be installed with associated feeders to the building and distribution to support later phases. After the new generator is completely installed and tested, the existing generator and associated feeders shall be demolished.
New fire pump electrical feeder from the new generator and jockey pump electrical connections shall be provided.
Civil
The northern parking lot will be removed along with associated items and the concrete pad and fuel tank.
Utility conduits will be installed, and new pavement will be put in place. The new generator and associated site work will be completed, and the parking lot will be striped.
Move Management Considerations
Ground floor occupants may be affected along corridors and access routes where overhead construction for distribution systems occurs. Overhead work will be conducted off-hours to minimize disruption and avoid temporary relocation of additional ground floor staff during Phase 1.
2026-11-03 | WSP Project No.: US0047700.4237 22
3.1.3 Phase 1C – Temporary Trailers and Site Readiness
This phase prepares the temporary trailer location, contractor staging areas and access route, and parking garage modifications. The temporary trailer office facilities must be ready before affected Phase 2 occupants are required to vacate their spaces inside the building.
Electrical/Fire Alarm
A temporary power feeder and communication feed for the temporary trailer shall be provided from the building to the temporary trailer location on the parking platform. The conduits shall be able to be capped in a handhole once the temporary trailer is removed and shall remain for future use. A step-down transformer will be required to properly connect the trailer to the feeder.
Civil
A curb cut will be installed on Granite Street, and a bituminous driveway will be constructed to the southern facade of the garage. A segment of the existing sidewalk on Granite Street will be replaced. A section of the parapet wall on the garage will be removed. The existing chain link perimeter fence will be replaced and connected to the garage structure. A chain link gate will be installed across the driveway at the garage.
3.2 Phase 2
Phase 2 includes concurrent renovations to the eighth floor and first floor. These work areas support construction sequencing and occupant relocations of later phases.
3.2.1 Phase 2A – Eighth Floor Renovation
Figure 3.3 Eighth Floor Phasing
2026-11-03 | WSP Project No.: US0047700.4237 23
The fifth floor has the greatest potential for swing space to serve clients with safety improvements.
However, the eighth floor has been identified for initial renovations to provide space for the fifth-floor clients and services to relocate to while safety improvements are made to the fifth floor. The layout generally follows that of floors five through seven with many rooms and offices being easily converted back into bedrooms. Critical spaces to accommodate include a Restraint Room (Room 841) and space for the PYXIS medication vending machine (Room 807), which must be connected to the generator.
Other important spaces to include in the renovated space are a nurse’s station, clean and dirty linen, and a washer/dryer room.
First step of Phase 2A will be vacating the eighth floor, followed by selective demolition and fortification of the spaces that will be secured for clients. New sprinklers, ceiling, and lighting will be completed on this floor prior to the fifth-floor clients and staff moving in.
Architectural
Required safety improvements and upgrades include ligature-resistant doors and hardware and accessories, a designated restraint room, accommodation for the PYXIS unit, a nurse’s station, and support spaces. Current offices will be converted back to bedrooms. Modifications will be completed prior to occupancy by the fifth-floor clients. Modifications will likely again be required to revert spaces back to offices from bedrooms. New ceilings will be provided throughout.
Fire Protection
The floor will be provided with sprinkler protection using a looped 3-inch sprinkler main and sprinkler heads throughout the entire floor. Branch lines will be connected to the looped main to serve individual areas as required by NFPA 13 standards. The system will be connected to the combined fire standpipe riser installed under Phase 1.
The existing floor fire standpipe and hose valves will be removed after the new sprinkler system is fully operational and tested. All work will be coordinated to minimize disruption and maintain compliance with fire protection requirements during the transition.
Mechanical
Existing mechanical registers, grilles and diffusers (RGD’s) shall be removed and temporarily capped for future extension. Upon completion of ceiling replacement, new RGD’s shall be installed that match existing RGD’s.
Electrical/Fire Alarm
New electrical and fire alarm devices shall be provided as required with new room layouts for possible swing spaces on this floor.
Existing lighting and lighting controls shall be removed back to source. A new lighting design with LED fixtures and lighting controls shall be provided to meet energy code requirements.
2026-11-03 | WSP Project No.: US0047700.4237 24
Move Management Considerations
The following units on the eighth floor will be impacted:
Transitional Resident Program (TRP): During the charrette, options and challenges were discussed for relocating this program (clients and staff) to leased space for the duration of the project or temporarily suspending the program and reassigning staff elsewhere in the building or to other locations.
Quality Information Services Division (QISD): This team has the flexibility to relocate elsewhere in the building or on the premises. A training room needs to be maintained for the duration of the project.
Hospital Services Division: This team has the flexibility to relocate elsewhere in the building or on the premises.
Approximately seven staff from the eighth-floor QISD team and Hospital Services Division will relocate to the temporary office trailer for the project duration. The TRP program will be temporarily suspended, and staff will be reassigned to other teams in the building or to other locations.
3.2.2 Phase 2B – First Floor Renovation
Figure 3.4 First Floor Phasing
The first floor will be renovated within the same general construction window as the eighth floor. Areas may be vacated or internally subdivided as required to maintain public-facing services. Following completion, portions of the first floor will remain available as office or training swing space for later phases.
2026-11-03 | WSP Project No.: US0047700.4237 25
Architectural
Temporary modification to the former main building entrance wall and glazing assemblies, as well as finishes, may be needed to return it to functional public entrance. Additional modifications may be determined necessary for the temporary relocation of the security screening point. New ceilings will be provided throughout.
Fire Protection
The floor will be provided with sprinkler protection using a looped 3-inch sprinkler main and sprinkler heads throughout the entire floor. Branch lines will be connected to the looped main to serve individual areas as required by NFPA 13 standards. The system will be connected to the combined fire standpipe riser installed under Phase 1.
The existing floor fire standpipe and hose valves will be removed after the new sprinkler system is fully operational and tested.
Mechanical
Existing mechanical RGD’s shall be removed and temporarily capped for future extension. Upon completion of ceiling replacement, new RGD’s shall be installed that match existing RGD’s.
Electrical/Fire Alarm
No new electrical and fire alarm devices are expected to be needed. New devices shall be provided as required to meet code.
Existing lighting and lighting controls shall be removed back to source. A new lighting design with LED fixtures and lighting controls shall be provided to meet energy code requirements.
Move Management Considerations
The following units and groups on the first floor will be impacted:
DEC and Triage Services: Staff need to stay together and be accessible to the public.
Executive: Staff can be flexible in where and how they work. An emergency command location needs to be provided in proximity to this team.
Human Resources: Staff can be flexible where they work; however, they need to be near staff.
Quest Diagnostics: Needs to be near public access and has separate Quest Diagnostics infrastructure that must be accommodated.
Approximately 12 staff from the Executive team and three staff from the Human Resources teams relocate to the temporary executive office trailer on the premises for the project duration. This will create more office swing space within the building, and the Executive Conference Room will also be available for use as training space and for dry goods storage.
2026-11-03 | WSP Project No.: US0047700.4237 26
Approximately three staff from the Diagnostic and Evaluation Center (DEC) and five staff Triage Services team, as well as Quest Diagnostics, will need to temporarily move to swing space on the ground floor while their space is worked on, for ease of maintaining public access. Once new sprinkler, ceiling, and lighting work is completed on the first floor, these staff and functions will move back into their spaces; the remainder of the floor can continue to be used as swing space as needed.
3.3 Phase 3
Phase 3 includes renovations to the fifth floor as the long-term clinical swing space while the third floor is renovated concurrently.
3.3.1 Phase 3A – Fifth Floor Clinical Swing Space
Figure 3.5 Fifth Floor Phasing
The fifth floor houses an inpatient unit with secure client areas. Once the fifth floor is vacated, safety improvements will be made, and it will be used as swing space for clients. The renovation work includes selective demolition, minor reconfiguration, and fortification. New sprinklers, ceiling, and lighting will be completed on this floor prior to becoming swing space.
Architectural
Upgrades to the fifth floor are required for safety improvements in the client area, including around the nurse’s station and common space, prior to occupancy as swing space. The Day Room, Lounge, several Bedrooms, and a restroom will be reconfigured. Finishes will be replaced throughout the client area, including flooring, restroom tile, and wall paint. New ceilings will be provided throughout the whole floor.
2026-11-03 | WSP Project No.: US0047700.4237 27
Fire Protection
Similar to Phase 2, the floor will be provided with sprinkler protection using a looped 3-inch sprinkler main and sprinkler heads throughout the entire floor. Branch lines will be connected to the looped main to serve individual areas as required by NFPA 13 standards. The system will be connected to the combined fire standpipe riser installed under Phase 1.
The existing floor fire standpipe and hose valves will be removed after the new sprinkler system is fully operational and tested. All work will be coordinated to minimize disruption and maintain compliance with fire protection requirements during the transition.
Mechanical
Similar to Phase 2, existing mechanical RGD’s shall be removed and temporarily capped for future extension. Ductwork shall be modified to accommodate new space layout with air terminals being relocated or newly supplied and installed based on the space layout. Upon completion of ceiling replacement, new RGD’s shall be installed that match existing RGD’s.
Electrical/Fire Alarm
New electrical and fire alarm devices shall be provided as required with new room layout due to floor redesign.
Existing lighting and lighting controls shall be removed back to source. A new lighting design with LED fixtures and lighting controls shall be provided to meet energy code requirements.
Move Management Considerations
Once the eighth-floor space is renovated and ready for occupancy, the clients and staff on the fifth floor will move up until renovation of the sixth and seventh floors is complete at the end of Phase 5.
The following units on the fifth floor will be impacted:
Co-Occurring Treatment Unit (CTU): Staff work closely with clients and are required to be in immediate proximity.
Counselors, Therapists, and Social Workers: Staff work with clients in this unit; however, they can be located elsewhere in the building if needed.
Approximately 20 client beds, seven CTU staff, and 10 Counselors, Therapists, and Social Workers will be relocated to the eighth floor until the end of Phase 5.
2026-11-03 | WSP Project No.: US0047700.4237 28
3.3.2 Phase 3B – Third Floor Renovation
Figure 3.6 Third Floor Phasing
The third-floor work will proceed concurrently with the fifth-floor renovation. The third floor will be vacated for the duration of Phase 3 so ceiling, lighting, and sprinkler work can be completed throughout the floor, as well as work to create the cafeteria swing space. Work in the Kitchen could be isolated to limit the amount of time it is closed, and dry goods storage could be temporarily relocated within the third floor to simplify move logistics.
The former cafeteria and serving area will be prepared for flexible office swing space. Potential uses include temporary training space, open office or hoteling space or subdivided office space. Work in this phase will provide improvements needed to use the cafeteria area as swing space for the project duration.
Once new sprinkler, ceiling, and lighting work is completed on the third floor, the staff will move back into their offices, and the Kitchen will reopen.
Architectural
The large open cafeteria and serving area on the third floor will undergo renovation to serve as swing.
The existing serving line will be removed and flooring in that area patched to open additional floor area for swing space. Walls in the area will be patched and painted. The remaining work in the cafeteria and serving area includes removing existing soffits and ceilings. New ceilings will be provided throughout the third floor. Minor wall infill and patching will be required, and walls will be painted throughout.
Fire Protection
The floor will be provided with sprinkler protection using a looped 3-inch sprinkler main and sprinkler heads throughout the entire floor. Branch lines will be connected to the looped main to serve individual areas as required by NFPA 13 standards. The system will be connected to the combined fire standpipe riser installed under Phase 1.
2026-11-03 | WSP Project No.: US0047700.4237 29
The existing floor fire standpipe and hose valves will be removed after the new sprinkler system is fully operational and tested.
Mechanical
Existing mechanical RGD’s shall be removed and temporarily capped for future extension. Upon completion of ceiling replacement, new RGD’s shall be installed that match existing RGD’s. Provide new electric baseboard heating for the bridge.
Electrical/Fire Alarm
New electrical devices shall be provided along the existing walls in the cafeteria area to support flexibility for the swing space. The existing lighting layout may need to be modified or added to within the limits of the existing circuiting to support the swing space. No new electrical and fire alarm devices are expected to be needed beyond that provided for the swing spaces. New devices shall be provided as required to meet code.
New heating is expected for the bridge. A new electrical panelboard and equipment is to be provided as required with the new mechanical equipment.
Existing lighting and lighting controls shall be removed back to source. A new lighting design with LED fixtures and lighting controls shall be provided to meet energy code requirements.
Move Management Considerations
The following units and groups on the third floor will be impacted:
Business Office: Staff can be flexible in where and how they work; however, they do maintain a service window that staff within the building utilize.
Food Services: Staff adjacent to the cafeteria will need to move into swing space elsewhere on the floor. Kitchen equipment located around the serving line will need to be relocated during construction activities in this area and coordinated with swing space requirements if they must be returned to the space while it functions as swing space.
Food Services: Kitchen equipment will need to be relocated during construction activities in this area.
Must maintain 96 hours emergency dry goods storage (the agency will provide volumetric requirements to support design development). During the charrette, options were discussed for staff to coordinate catered meal services while the Kitchen is closed.
CSU: Staff need to stay in the building, and this team needs to stay together.
Approximately four staff from the Business Office team will relocate to the temporary office trailer for the project duration.
During Phase 3, the three Food Service staff and approximately 10 CSU staff will be relocated to existing offices serving as swing space on the first floor. Dry good storage will be relocated to temporary swing space on the first floor.
2026-11-03 | WSP Project No.: US0047700.4237 30
Upon completion of third floor work, the Food Service and CSU staff will return to the third floor and the Kitchen will reopen. The Food Service staff will temporarily occupy the third-floor Business Office space, to remain in proximity to the Kitchen while minimizing disruptions as the cafeteria area is used for swing space through Phase 6.
3.4 Phase 4
Phase 4 includes concurrent renovations to the sixth and fourth floors. Sequential renovation of the fourth floor is recommended to maintain Pharmacy operations as long as possible, as described in Phases 4B, 4C, and 4D.
3.4.1 Phase 4A – Sixth Floor Renovation
Figure 3.7 Sixth Floor Phasing
The sixth floor houses an inpatient unit with secure client areas. Once the fifth-floor swing space is prepared and ready for occupancy, the clients and staff on the sixth floor will move down. The phasing of the sixth floor will be the similar to the fifth floor, except safety improvements are not required beyond the sprinkler upgrades. Once new sprinkler, ceiling, and lighting work is completed on the sixth floor, the clients and staff will move back in, opening up the fifth-floor swing space for the next group.
Architectural
New ceilings will be provided throughout. Minor wall infill and patching will be required, and walls will be painted throughout.
2026-11-03 | WSP Project No.: US0047700.4237 31
Fire Protection
The floor will be provided with sprinkler protection using a looped 3-inch sprinkler main and sprinkler heads throughout the entire floor. Branch lines will be connected to the looped main to serve individual areas as required by NFPA 13 standards. The system will be connected to the combined fire standpipe riser installed under Phase 1.
The existing floor fire standpipe and hose valves will be removed after the new sprinkler system is fully operational and tested. All work will be coordinated to minimize disruption and maintain compliance with fire protection requirements during the transition.
Mechanical
Existing mechanical RGD’s shall be removed and temporarily capped for future extension. Upon completion of ceiling replacement, new RGD’s shall be installed that match existing RGD’s.
Electrical/Fire Alarm
No new electrical and fire alarm devices are expected to be needed. New devices shall be provided as required to meet code.
Existing lighting and lighting controls shall be removed back to source. A new lighting design with LED fixtures and lighting controls shall be provided to meet energy code requirements.
Move Management Considerations
Once the fifth-floor space is renovated and ready for occupancy, the clients and staff on the sixth floor will move down for the duration of Phase 4. Upon completion of Phase 4, they will return to the newly renovated sixth floor.
The following units on the sixth floor will be impacted:
Psychiatric Intensive Care Unit I (PICU I): Staff work closely with clients and are required to be in immediate proximity.
Therapists and Social Workers: Staff work with clients in this unit; however, they can be located elsewhere in the building if needed.
Approximately 21 client beds, 10 PICU I staff, and eight Therapists and Social Workers will be relocated to the fifth floor until the end of Phase 4.
2026-11-03 | WSP Project No.: US0047700.4237 32
3.4.2 Phase 4B/4C – Fourth Floor Areas 1 and 2 Renovation
Figure 3.8 Fourth Floor Phasing
Work on the fourth floor will be staggered sequentially in a way that maintains access to the Pharmacy, allowing it to remain open while work is being done elsewhere on the floor, thereby minimizing the time it will be impacted. The fourth-floor renovations will be divided in the long direction of the building into subphases, which generally aligns with the mechanical system zoning.
As new sprinkler, ceiling, and lighting work is completed in each area on the fourth floor, the staff will return to the completed area.