Berkshire SC - VRF Installation - Addenda 1.pdf
PDF 90 KB Posted
- Attached to
- Berkshire SC - VRF Installation
- Solicitation number
- BD-27-1107-FREG5-ACCOU-132395
- Issued by
- Berkshire County, Massachusetts
About this file
This is Addendum #1 to a Request for Proposal issued by the Commonwealth of Massachusetts Executive Office of the Trial Court, Office of Court Management, Facilities Management Department for VRF system installation at the Berkshire Superior Court Clerk's Office in Pittsfield, Massachusetts. The addendum provides clarification regarding the system configuration in response to a vendor question. The project requires installation of a four-zone mini/multi-split heat pump system with one outdoor condenser unit and four indoor heads, where each head operates with individual temperature setpoint control but all heads function in the same heating or cooling mode simultaneously. The bid is identified as BD-27-1107-FREG5-ACCOU-132395, with bids due September 9, 2026, at 12:00 p.m., and a mandatory pre-bid walkthrough scheduled for September 1, 2026, at 10:00 a.m. Project completion is required by April 30, 2027.
This addendum clarifies that the system is not a variable refrigerant flow (VRF) system where individual zones can operate independently in different modes, but rather a four-zone mini/multi-split configuration with synchronized operational mode requirements. Bidders must acknowledge receipt of Addendum #1 on their proposal forms. The clarification addresses a critical system design specification that affects equipment selection, installation methodology, and cost estimation for prospective contractors. Massachusetts prevailing wage requirements apply to all trades involved in the project, and Daikin or Mitsubishi systems are preferred by the agency.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Office Of Court Management Facilities Management & Capital Planning
COMM Buys Bid BD-27-1107-FREG5-ACCOU-132395
Berkshire SC – VRF Installation
ADDENDA #1
8/25/2026
The ATTENTION OF THE BIDDERS SUBMITTING PROPOSALS FOR THE ABOVE-
MENTIONED BID, IS HEREBY CALLED TO THE FOLLOWING ADDENDUM. THE ITEMS SET
FORUTH HEREIN, WHETHER OF OMISSION, ADDITION, SUBSTITUTION OR
CLARIFICATION ARE TO BE INCLUDED IN AND FORM A PART OF THE PROPOSAL
SUBMITTED.
THE NUMBER OF THIS ADDENDUM (#1) MUST BE ACKNOWLEDGED ON THE PROPOSAL
FORM.
Addenda #1 is being issued to provide clarification to a vendor submitted question.
Question:
The scope specifies one outdoor condenser, four indoor heads, and individual room setpoint control. Please confirm whether the intended system is:
A four-zone mini/multi-split heat-pump system, where each head has an individual temperature setpoint, but all heads operate in the same heating or cooling mode.
Response:
The system as intended is a four-zone mini/ multi split system where each head has individual temperature control and all heads will operate in the same heating or cooling mode.
File details come from the government source that posted it. Updated .