answers08.08.11.doc.docx
DOCX document 13 KB Posted
- Attached to
- Design/Build a Clean Room Federal contract opportunity
- Solicitation number
- BEP-RFP-11-0017
About this file
Answers-08/08/11
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF-30(AMENDMENT1) Clean Room.docx | DOCX document | |
| SF-30(AMENDMENT2) Clean Room.docx | DOCX document | |
| Technical Questions 080811.pdf | ||
| Cleanroomsolitcitation.PDF | ||
| Clean Room Questions.pdf | ||
| Clean Room Questions.pdf | ||
| Clean Room Questions.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Answers to attached questions for the Clean Room- BEP-RFP-11-0017 dated 08/08/2011
(1) The dimensions of each piece of equipment are already in the specifications.
(2) Probably through the roof of the Clean Room.
(3) No
(4) No
(5) We are open to alternate design suggestions.
(6) The room is nothing more than a powder containment facility. In that case, I would state that your assumption is correct.
(7) The concrete pad is part of an area that was formerly used to support another building no longer in use. The pad is reinforced provide support for full-loaded semi-tractor trailers.