About this file
Request for Qualifications for Bayou Chico Sediment Remediation (Final and Post-Design) - RESTORE
This is a Request for Qualifications (RFQ) issued by Escambia County, Florida, for professional engineering and design services related to the Bayou Chico Sediment Remediation Project, funded through the RESTORE Act administered by the Gulf Coast Ecosystem Restoration Council. Escambia County seeks qualified firms to complete final design (90% and 100% plan sets), permitting coordination, and post-design services for Phase I implementation of a contaminated sediment remediation project affecting approximately 62.5 acres across seven dredge management units (DMUs) in Bayou Chico. The project aims to remove and remediate legacy contaminants including metals, PAHs, PCBs, and dioxins that have accumulated in bayou sediments over more than a century of industrial and maritime activity. The mandatory pre-solicitation meeting is scheduled for November 24, 2026, at 1:00 PM via Microsoft Teams. Questions must be submitted by December 2, 2026, at 3:00 PM, and proposals are due December 17, 2026, at 11:30 AM via the OpenGov e-procurement portal. Phase I implementation is estimated to require nine months and will involve dredging contaminated sediment using a barge-mounted excavator, transferring sediment to a water treatment system for processing, and transporting treated sediment to the Escambia County Perdido Landfill for disposal.
The RFQ specifies a base scope of services including administration, permitting, final design, and Phase I bid document preparation and support, with optional services available for cultural resource assessments, NEPA documentation, sampling and testing, surveying, public outreach, limited construction support, and as-built certification, to be funded through change orders as necessary. Proposals are limited to 20 pages and must address project approach, relevant experience with similar dredging and contaminated sediment remediation projects, team qualifications and availability, and compliance with Escambia County purchasing requirements. Insurance requirements include $1,000,000 per occurrence/$2,000,000 aggregate general liability coverage, $1,000,000 business auto liability, workers' compensation at statutory limits, and professional errors and omissions coverage. The project is funded through RESTORE Act grants administered by the Florida Department of Environmental Protection (FDEP) under the Comprehensive Plan Component (RES09 agreements) and State Expenditure Plan funds (Account 210025011) for design and implementation. Firms must comply with federal contract provisions, demonstrate readiness to meet project timelines and budgets, and ensure key personnel are readily accessible. Award will be made on an "all-or-none total" basis to the most responsive and responsible firm, with the successful respondent required to execute the contract within five days of receiving the Notice of Award.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ
PD 26-27.013
BAYOU CHICO SEDIMENT REMEDIATION (FINAL AND POST-
DESIGN) - RESTORE
Escambia County
213 Palafox Place
Pensacola, FL 32502-5822
RELEASE DATE: November 17, 2026
DEADLINE FOR QUESTIONS: December 2, 2026
RESPONSE DEADLINE: December 17, 2026, 11:30 am
RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:
https://secure.procurenow.com/portal/escambiacountyfl https://secure.procurenow.com/portal/%7bproject.government.code%7d
Escambia County
RFQ
Bayou Chico Sediment Remediation (Final and Post-Design) - RESTORE
1. Introduction
2. Scope of Work
3. Solicitation Terms & Conditions
4. General Terms and Conditions
5. Standard Insurance Requirements and Certificates
6. Professional Errors and Omissions
7. Evidence/Certificates of Insurance
8. Vendor Submissions
9. Evaluation Process
10. Evaluation Criteria
Attachments:
A - 210025011 A1 Bayou Chico - Executed_ADA
B - 210025011 A2 Bayou Chico -EXECUTED_ADA
C - RES09 A1 Executed 6.29.21
D - NOA to Esc Cty 210025011-Bayou Chico-Executed_ADA
E - RES09 A2 Bayou Chico - Executed 5.8.24
F - RES09 A3 Bayou Chico EXECUTED 3.31.26
G - RES09 Bayou Chico SR - Executed 3.22.20
H - Permit-Draft_Gaillot_58270_68770_0_ENG_6082_PCN
I - BAYOU CHICO 60 Percent_08272026
J - FDEP Application for Conceptual Approval ERP - Bayou Chico Sediment
Rem_with LOI
K - Bayou Chico-Sed Rem-BODR_REV 2_FINAL_01152026
L - 2024-05-15_Bayou Chico_CSM_Risk Assessment-FINAL
RFQ #PD 26-27.013
Title: Bayou Chico Sediment Remediation (Final and Post-Design) - RESTORE
M - Exhibit.FederalContractProvisions_10.22.26
1. Introduction
1.1. Summary
Escambia County is requesting proposals from qualified professional firms to complete design, permitting, and post-design services for the Bayou Chico Sediment Remediation Project. The Project will remove and remediate contaminated sediments from the bayou to improve benthic habitat and water quality in Bayou Chico. Data collection, modeling, and design through 60% plans have been completed.
Permit applications have been submitted to state and federal permitting agencies. The selected consultant will work with Escambia County to complete design and permitting and advance
Implementation of Phase I of the Project through bid solicitation, implementation, and as-built certification.
1.2. Background
The purpose of the Project is to remove contaminated sediments from the open waters of Bayou Chico, with no submerged aquatic vegetation (SAV) or wetland impacts. The Project is anticipated to meet the following objectives: (1) improve sediment and water quality; (2) restore benthic invertebrate habitat and conditions for recovery of SAV; and (3) enhance the economic and recreational opportunities along the working waterfront through improved water quality and habitat as well as improved navigation as an incidental effect of dredging.
Bayou Chico has experienced the lasting effects of more than a century of human activity associated with its role as a working waterfront, including early industrial development, extensive maritime operations, historical use as a receiving water for wastewater effluent, untreated stormwater runoff, and other legacy pollutant sources. Over time, these activities contributed to the accumulation of fine-grained, organic-rich sediments containing legacy contaminants and elevated nutrient levels. Numerous scientific investigations beginning in the 1970s documented degraded sediment conditions within Bayou
Chico, including elevated concentrations of metals, polycyclic aromatic hydrocarbons (PAHs), pentachlorophenol (PCP), dioxins and furans, polychlorinated biphenyls (PCBs), and other pollutants associated with historical industrial activities, wastewater discharges, and urban runoff.
While state regulatory actions and nearly $100 million in restoration investments by Escambia County and other partners have reduced or eliminated many ongoing sources of pollution within the watershed, these historically impacted sediments remain a persistent source of environmental stress that must be addressed to achieve long-term recovery of the bayou and support improved water quality and ecological conditions throughout the broader Pensacola Bay estuary.
1.3. Contact Information
Angela Jones
Senior Purchasing Coordinator
213 Palafox
2nd Floor
Pensacola, FL 32502
Email: ajjones@myescambia.com
Phone: (850) 595-4953 mailto:ajjones@myescambia.com tel:(850)595-4953
Department:
Purchasing
1.4. Timeline
Release Project Date November 17, 2026
Pre-Solicitation Meeting (Mandatory) November 24, 2026, 1:00pm
Microsoft Teams meeting
Join:
https://teams.microsoft.com/meet/291091969325
9083?p=UyHU9CbCfVp3Dh1Ahv
Meeting ID: 291 091 969 325 908 3
Passcode: XC2ZH6GQ
Dial in by phone
+1 863-333-5817,,565744169# United States, Lakeland
Phone conference ID: 565 744 169#
OR
Office of Purchasing
213 Palafox Pl 2nd Floor
Pensacola, FL 32502
Question Submission Deadline December 2, 2026, 3:00pm https://teams.microsoft.com/meet/2910919693259083?p=UyHU9CbCfVp3Dh1Ahv https://teams.microsoft.com/meet/2910919693259083?p=UyHU9CbCfVp3Dh1Ahv
Submission Deadline December 17, 2026, 11:30am
Microsoft Teams meeting
Join:
https://teams.microsoft.com/meet/292986717169
9142?p=RfPs250bcitgwdm3fP
Meeting ID: 292 986 717 169 914 2
Passcode: Vs93Hf3F
Dial in by phone
+1 863-333-5817,,502340968# United States, Lakeland
Phone conference ID: 502 340 968#
OR
Office of Purchasing
213 Palafox Pl 2nd Floor
Pensacola, FL 32502
2. Scope of Work
2.1. General Information
The Project will remediate contaminated sediments to improve benthic habitat and water quality in
Bayou Chico. An analysis of contaminant types, concentrations, and vertical and horizontal distribution has been completed and remediation methodologies and technologies have been evaluated to determine the most appropriate means of remediation. See the Basis of Design Report (AECOM, 2026).
Historical sources of contamination, investigations, and dredging activities are summarized in the
Conceptual Site Model/Risk Assessment (AECOM, 2024).
Design has been developed through 60% plans. Permit applications have been submitted to the Florida
Department of Environmental Protection (FDEP) and the U.S. Army Corps of Engineers (USACE).
Implementation of the remediation project may occur in one or more phases, with Phase I consisting of dredge management units (DMUs) 1 and 2. Phase I implementation is estimated to take 9 months.
The Project involves dredging contaminated sediment from Bayou Chico using a barge-mounted excavator equipped with an environmental bucket. The sediment will be placed into a hopper barge and transported to the barge processing area where overlying water will be pumped to the barge-mounted water treatment system (WTS) to be designed by the selected consultant. After completion of dewatering and stabilization, sediment will be transferred to haul trucks for transport and disposal at the Escambia County Perdido Landfill. After the water has been treated in the WTS and is in compliance with a temporary discharge permit, it will be discharged to the Bayou.
https://teams.microsoft.com/meet/2929867171699142?p=RfPs250bcitgwdm3fP https://teams.microsoft.com/meet/2929867171699142?p=RfPs250bcitgwdm3fP
General scope of services:
• Engineering services to be provided will include completion of design and permitting of the entire project area, as well as bid document preparation and bid support for Phase I of implementation.
• Optional services such as cultural resource assessment, NEPA review, sampling and testing, data analysis and modeling, surveying, and public outreach may be funded through the change order process if necessary.
• Optional engineering services are also requested throughout Phase I implementation, including limited construction support and as-built certification, and may be funded at a later date through the change order process when additional funding is secured.
2.2. Project Area
Bayou Chico is located within the Pensacola Bay watershed in south central Escambia County. The bayou has a surface water area of approximately 235 acres with a surrounding drainage basin of more than
6,600 acres. The total project area consists of seven DMUs comprising approximately 62.5 acres.
The eastern half of the bayou and associated contributing basin is generally located within the City of
Pensacola with the remaining western bayou and associated contributing basin located outside city limits in unincorporated Escambia County. Information regarding private submerged lands rights can be obtained through FDEP online portal Map Direct at https://ca.dep.state.fl.us/mapdirect/ .
A federal navigational channel extends northwest through the mouth of the bayou terminating into an existing large vessel turning basin. The DMUs are outside of the navigation channel. Average water depth in the bayou is approximately eight feet, with deeper areas located within the navigational channel. Maximum water depth exceeds 20 feet. Two state owned/maintained bridges cross the bayou along Barrancas Avenue (SR292) and Navy Boulevard (Hwy 98). Additional project location information is provided in the attached project location map.
2.3. Grant Funding
The Deepwater Horizon oil spill led to passage of the RESTORE Act in 2012, dedicating 80 percent of all
Clean Water Act administrative and civil penalties related to the spill to the Gulf Coast Restoration Trust
Fund. The Gulf Coast Ecosystem Restoration Council (Council) was established by the RESTORE Act to administer 60 percent of the total Trust Fund. The Council approved the initial Funded Priorities List
(FPL) in 2015, identifying the Bayou Chico Contaminated Sediment Remediation Project as a Tier One
Project. The Council entered into an agreement with the State of Florida to oversee the project as part of the Comprehensive Plan Component (RESTORE Pot 2). The Florida Department of Environmental
Protection (FDEP) entered into a subrecipient agreement (RES09 and amendments attached) with
Escambia County to plan and design the project.
In addition, the Escambia County Board of County Commissioners selected the Bayou Chico
Contaminated Sediment Remediation Project for inclusion with the State Expenditure Plan (SEP) for
Florida’s portion of the Spill Impact Component (RESTORE Pot 3) funds designated by the RESTORE Act.
The SEP funds have been awarded for design (210025011.01 and amendments attached) and have been https://ca.dep.state.fl.us/mapdirect/ allocated for implementation of the project. The final design shall be consistent with the SEP, available at https://www.gulfconsortium.org/state-expenditure-plan.
This Project shall comply with terms and conditions of the grants and with all applicable rules and laws including attached Federal Contact Provisions.
2.4. Scope of Services: Tasks and Deliverables
The following scope establishes minimum requirements. Respondents may recommend additional tasks or deliverables that they determine necessary to meet the project objectives. The Project scope, as stated, will include but is not limited to the following items:
Base Services: Final Design, Permitting, and Phase I Bid Support
Task 1: Administration
• Attend meetings with and coordinate with Escambia County Natural Resources Management
Department, Escambia County Waste Services, City of Pensacola and Port of Pensacola.
• If necessary, attend meetings with and coordinate with other potential disposal sites, other potential offloading sites, and utilities.
• Routinely submit invoices, progress reports, and schedule updates.
• Submit change order requests as needed.
Task 2: Permitting
• Respond to request for additional information (RAIs) from permitting agencies.
• Submit payment of permit fees.
• Identify and obtain all permits and regulatory approvals necessary for implementation of the project.
• Coordinate and attend meetings with permitting agencies as necessary.
Task 3: Final Design
• Develop and submit 90% and 100% plan sets for all DMUs. Plans should be reproducible to 40 scale 11”x17” and 20 scale 24”x36” sheets size.
• Provide all required construction details and specifications for the project.
Task 4: Phase I Bid Documents and Support
• Provide a cost estimate, estimated implementation schedule, and all required bid documents.
• Assist in preparing the solicitation for construction.
• Attend bid preparation meetings with County staff.
https://www.gulfconsortium.org/state-expenditure-plan
• Attend the pre-solicitation meeting.
• Respond to questions from vendors and all requests for information.
• Issue any necessary addendums.
• Tabulate bids and provide low bid verification.
Optional Services: Additional Design & Permitting Services and Phase I Post-Design Services
Task 5: Cultural Resources
• Perform cultural resource assessment survey (CRAS) fieldwork conforming to the Florida DHR standards and guidelines for Phase I archaeological assessments.
o In general, the terrestrial portion of this work will include systematic surface inspection of the project area and the excavation of shovel test pits.
o The potential underwater portion will consist of a marine geophysical survey to identify significant submerged cultural resources on the bay floor or partially buried near the bay floor surface that are located within the area of potential effects (APE) for direct effects.
• Submit a summary report assessing the potential for more detailed cultural resources investigation to Escambia County and to the Florida Division of Historic Resources.
Task 6: NEPA Evaluation / Documentation
• Determine the project’s environmental impact and prepare all required National Environmental
Policy Act (NEPA) documentation requirements. The evaluation shall include:
o Wetland delineation using both U.S. Army Corps of Engineers and FDEP methodology;
o Habitat assessment of dominant ecotypes within project boundaries;
o Biological assessment for potential threatened or endangered species and critical habitat;
o Evaluation of existing site conditions including water quality parameters (such as water clarity, color, salinity, total suspended solids, and dissolved oxygen);
o Grant compliant monitoring plan; and o Environmental permitting including permit fees.
Task 7: Sampling, Testing, and Analysis
Extensive sampling, testing, and modeling have been completed. The County will rely on the expertise and experience of the firm, in consultation with state and federal permitting agencies and other entities, to determine the number of samples required to adequately quantify and qualify contaminated sediment and effluent and meet the requirements to successfully obtain all necessary permits and agreements.
• Sample sediment, water, and/or effluent.
• Test for contaminants of concern (COCs).
• Analyze results and report findings.
• Perform hydrologic modeling.
Task 8: Surveying and Environmental Site Assessments
• Perform additional surveying of Bayou Chico (geographic, bathymetric, etc.).
• Survey other potential offloading sites.
• Perform Environmental Site Assessments of other potential offloading sites.
Task 9: Public outreach
• Coordinate one or more public meetings to present the project design and collect public input.
• Prepare agendas, presentations, attendance log, and post-meeting notes.
• Attend public meetings and present information about the project.
Task 10: Phase I Limited construction support
• Attend the pre-construction meeting.
• Attend biweekly construction progress meetings and monthly site visits.
• Attend substantial completion site visit and develop a punch list.
• Attend final completion site visit.
• Review shop drawings.
• Respond to requests for information (RFIs) from the contractor.
• Review change order requests related to design.
• Perform design modifications as needed.
Task 11: Phase I As-built certification
• Review post-construction survey.
• Provide as-built certification upon substantial completion of construction.
• Complete construction completion documentation, including forms and documents required by grants, permits, and Escambia County.
2.5. Submission Guidelines
Proposals shall be limited to 20 pages.
• Tab 1 - Introduction o Provide organization information and address, including point of contact name, phone, and email.
o Provide a brief narrative summarizing the firm’s understanding of the scope of work and project goals.
• Tab 2 - Project Approach and Work Plan o Provide a project approach narrative detailing a draft workplan for permitting and final design of the project and post-design services for Phase 1 of implementation.
• Tab 3 - Project Experience o Submit at least 2 projects of similar scope and complexity, with date completed, summary of services provided, organization/client for whom services were provided, and other relevant information.
o Relevant projects should include similar scale dredging and contaminated sediment remediation/removal engineering and design, permitting with the Corps of Engineers and the Florida Department of Environmental Protection, and limited construction support.
• Tab 4 - Qualifications & Availability o Describe the ability of the firm to manage this project within the specified project time and within budget. Project team members should be readily accessible to avoid unnecessary delays in the project schedule. Firm should demonstrate how their team will be readily accessible and be able to quickly respond to the County.
o Provide a list of key personnel who will be working on this project, along with their availability within the specified project time. Show the current workload of key personnel and hours projected on this project.
o Key personnel should have experience with contaminated sediment remediation/removal design, engineering, analysis, and permitting with the Corps of Engineers and the Florida
Department of Environmental Protection. Only team members who will have considerable involvement in this project should be considered for their experience and technical expertise.
o Include relevant certifications and licenses, roles and responsibilities, and any subcontractors to be utilized.
• Tab 5 - Escambia County Purchasing Documents (not included in page limits).
o Please upload all required documents from Vendor Submissions in Tab 5.
3. Solicitation Terms & Conditions
Submission of a proposal in accordance with these Terms and Conditions and the General Terms and
Conditions provided in Section IV below constitutes a binding offer from the respondent. The Terms and
Conditions incorporated herein will become a part of the written agreement between the parties.
Pre-Proposal Inquiries
All inquiries concerning the solicitation, including, but not limited to, the scope of work, specifications, additional requirements, attachments, general or supplemental terms and conditions, must be submitted to the Office of Purchasing through the e-procurement portal hosted by OpenGov.
All questions or inquiries must be received no later than the last day for questions stated on the cover page of the solicitation. Any modification to the solicitation documents will be in the form of a written addendum issued by the County not less than five (5) days prior to the date and time of solicitation closing. Addenda will be provided to each respondent via email and will be posted to the Escambia
County website at Escambia County Solicitations
(https://procurement.opengov.com/portal/escambiacountyfl). Such written addenda or modification shall be part of the solicitation documents and shall be binding upon each respondent. Each respondent is required to submit with the proposal a written acknowledgment to confirm receipt of any and all addenda. No respondent may rely upon any verbal modification to or interpretation of the solicitation documents, and no interpretation shall be considered binding unless provided in writing by the Office of
Purchasing as provided in this provision.
Examination of Documents and Site
Before submitting a proposal, the Respondents shall familiarize themselves with the nature and extent of the work and any local conditions that may in any manner affect the work to be done and the equipment, materials, and labor required. Respondent shall also examine all drawings, specifications, addenda, and other relevant documents to be thoroughly informed regarding any and all conditions and requirements that may in any manner affect the work to be performed under the contract.
Preparation of Proposal
The Proposal shall be based upon the completion of the Scope of Work according to the drawings and specifications, together with all addenda thereto. The proposal must be executed by an individual listed as an authorized representative with the records on file with the Florida Division of Corporations website (Sunbiz) with the principal address provided below the signature. The proposal shall include evidence of respondent’s authority and qualification to do business in the State of Florida.
As applicable, a state contractor license # for the State of Florida shall also be included in the proposal, and Respondent shall be licensed in accordance with the requirements of Chapter 489, Florida Statutes.
Recommended Proposal Preparation Guidelines
All respondents shall provide a straightforward and concise description of their ability to meet the proposal requirements. The proposal shall clearly show the technical approach to include work tasks, estimated time phasing and the proposed approach. The County discourages overly lengthy or costly proposals, all proposals shall be submitted in one electronic file.
https://procurement.opengov.com/portal/escambiacountyfl
Integrity of Documents
Respondents shall use the original solicitation documents in the format provided by the Escambia
County Office of Purchasing and enter information only in the spaces where a response is requested.
Submittal of Proposal
A proposal shall be submitted no later than the date and time prescribed in the Request for Proposal or
Qualifications and shall be accompanied by all required documents. It is the respondent’s responsibility to ensure that its proposal is delivered at the proper time.
Each submittal shall include all the items listed in the Vendor Submissions section.
The Purchasing Department reserves the right to extend the solicitation due date within ten (10) minutes of the proposal opening when the required number of proposals has not been received. Any extension will be determined by the Purchasing Department and communicated prior to the scheduled proposal opening to prospective respondents through OpenGov.
Identification of Subconsultants/Changes After the Fact
After submitting a proposal in response to this solicitation, respondents are prohibited from substituting, modifying, or amending the sub-consultants identified in the submittal at any time during the course of the solicitation process up to the final award of contract and including question and answer sessions, presentations or technical clarifications and submittals as may be required by the
Review/Selection Committee. A substitution or addition of sub-consultants or any other material changes to the submittal after the initial response will cause the submittal to be invalid for review and selection purposes.
Withdrawal of Submittals
Any respondent may withdraw its submittal, either personally or by written request, at any time prior to the scheduled time for opening submittals. Requests to alter or withdraw an offer must be submitted in writing to the Purchasing Director. Submittals may not be altered or unilaterally withdrawn by the respondent after the scheduled time for submittal opening. All offers not so withdrawn shall constitute an irrevocable offer and will remain subject to acceptance or rejection by the County for a period of 90 calendar days.
Proposal to Remain Subject to Acceptance
All proposals will remain subject to acceptance or rejection by Escambia County for ninety (90) calendar days after opening Submittals.
Conditional or Incomplete Proposals
Escambia County specifically reserves the right to reject any conditional or incomplete proposal.
Addition/Deletion of Item(s)
The County reserves the right to add or delete any item from this solicitation or resulting contract when deemed to be in the County’s best interest.
https://procurement.opengov.com/portal/escambiacountyfl/projects/325913?section=undefined
Changes to Specification
Specifications are based on the most current literature available. The Office of Purchasing must be notified in writing of any proposed changes to the manufacturer’s specifications, including, but not limited to, materials used, manufacturing process, or construction, that conflict with the specifications provided in the solicitation. Proposed changes must be explained in detail along with a copy of the relevant manufacturer’s specifications. Proposed changes to the specifications provided in the solicitation shall not be binding upon the County unless evidenced by a Change Notice issued and signed by the Purchasing Director. Should Respondent fail to comply with this provision, Respondent will be liable for any costs incurred by the County to comply with the specifications provided in the solicitation.
Disqualification of Respondents
Any of the following reasons may be considered as sufficient for the disqualification of a respondent and the rejection of its proposal:
• Submission of more than one proposal for the same work from an individual, firm, or corporation under the same or different name. Evidence that the respondent has a financial interest in the firm of another respondent for the same work.
• Evidence of collusion among respondents. Participants in such collusion will receive no recognition as respondents for any future work of the County until such participant has been reinstated as a qualified respondent.
• Uncompleted work which in the judgment of the County might hinder or prevent the prompt completion of additional work if awarded.
• Failure to pay or satisfactorily settle all bills due for labor and material on contracts in effect at the time of issuing the solicitation or default under a previous contract.
• Listing of the respondent by any Local, State or Federal Government/Agency on its debarred/suspended vendor list.
Investigation of Respondent
The County may make such investigations, as it deems necessary to determine the stability of the respondent to perform the work and that there is no conflict of interest as it relates to the project. The respondent shall furnish to the County any additional information and financial data for this purpose as the County may request.
Negotiations
Should negotiations be required, the contents of the proposal of the successful firm shall become a basis for contractual negotiations.
Evaluation of Proposals and Award of Contract
Escambia County will review all proposals and will provide the recommendation to award to the County
Administrator, and the Board of County Commissioners. The County will award the proposal to the most responsive and responsible firm(s). The County reserves the right to award the proposal to the respondent submitting a responsive proposal with a resulting negotiated agreement which is most advantageous and in the best interest of the County, and to reject any and all proposals or to waive any irregularity or technicality in proposals received. Escambia County shall be the sole judge of the proposal and the resulting negotiated agreement that is in its best interest and its decision shall be final.
Escambia County reserves its right to reject any or all Proposals, including without limitation nonconforming, nonresponsive, unbalanced, or conditional Proposals. The County further reserves the right to reject the Proposal of any Respondent whom it finds after reasonable inquiry and evaluation to not be responsible. In evaluating Respondents, the County may consider the qualifications of
Respondents and may consider the qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other individuals or entities must be submitted as a part of the Proposal.
Escambia County reserves the right to waive any informalities or reject any and all submissions, in whole or part, to utilize any applicable state contracts in lieu of or in addition to this solicitation, and to accept the proposal that in its judgment will best serve the interest of the County.
Award
Award shall be made on an “all-or-none total” basis.
Form of Agreement
The Contract form shall be provided by the Office of Purchasing. The successful respondent shall, within
5 days after receipt of the Notice of Award and the contract forms or documents, sign and deliver to the
County Legal Office all required contract documents. Failure to execute the contract within such period shall constitute a default, and the county may award the contract to the next responsive and responsible proposal or re-solicit and charge against the respondent the difference between the amount of the offer and the amount for which a contract is subsequently executed, irrespective of whether the amount due exceeds the amount of the bid surety. The awarded respondent shall also deliver the policies of insurance or insurance certificate as required. All insurance documents shall be approved by Escambia
County Risk Manager before the successful respondent may proceed with the work.
Indemnification
Offeror agrees to save harmless, indemnify, and defend County and their elected and appointed officials, agents, officers and employees from any and all claims, losses, penalties, interest, demands, judgements, and costs of suit, including attorneys' fees and paralegals' fees, for any expense, damage or liability incurred by any of them, whether for personal injury, death, property damage, direct or consequential damages, or economic loss, including environmental impairment, arising directly or indirectly on account of or in connection with the work performed by Offeror under this Agreement or by any person, firm or corporation to whom any portion of the Work is subcontracted Offeror; or resulting from the use by Offeror, or by any one for whom
Offeror is legally liable, of any materials, tools, machinery or other property of County.
County and Offeror agree the first $100.00 of the Contract Amount paid by County to Offeror shall be given as separate consideration for this indemnification, and any other indemnification of County by
Offeror provided for within the Contract Documents, the sufficiency of such separate consideration being acknowledged by Offeror by Offeror’s acceptance and execution of the Agreement.
The Offeror's obligation shall not be limited by, or in any way to, any insurance coverage or by any provision in or exclusion or omission from any policy of insurance. The Offeror agrees to pay on behalf of
Escambia County, as well as provide a legal defense for the County, both of which will be done only when requested by the County, for all claims made. Such payment on behalf of the County shall be in addition to all other legal remedies available to the County and shall not be the County's exclusive remedy.
4. General Terms and Conditions
Any and all Supplemental Terms and Conditions and specifications referenced within the solicitation that vary from these General Terms and Conditions shall have precedence. Submission of an offer in accordance with these General Terms and Conditions and Supplemental Terms and Conditions constitutes a binding offer from the offeror. The terms and conditions incorporated herein will become a part of the written agreement between the parties.
Prospective offerors may utilize the Office of Purchasing Home Page to obtain Vendor Information and
Solicitation Information, including Bid/Proposal Tabulations, Recommended Award(s), etc. In order to participate in a solicitation, offerors must establish an account via the e-procurement portal of the
County’s vendor management software hosted by OpenGov. Once the vendor registration is completed, the offeror will receive all notifications relating to the relevant solicitation via e-mail to the address registered with the account.
1. Sealed Solicitations: All solicitation forms shall be executed and submitted in the e-procurement portal of the County’s vendor management software. The file name shall contain the solicitation number and title and the contractor/vendor’s name. All solicitations are subject to the terms and conditions specified herein. Solicitation offers which do not comply with these terms and conditions are subject to rejection.
2. Execution of Solicitation: Solicitation forms shall be manually or electronically signed by an authorized representative in the space provided. Persons signing on behalf of a corporate entity must be identified as President or Vice President with the records on file with the Florida Division of Corporations or otherwise authorized by corporate resolution of the Board of Directors.
Persons signing on behalf of a limited liability company must be identified as a managing member or other authorized representative with the records on file with the Florida Division of
Corporations.
3. No Offer: If not submitting an offer, respond by selecting the “NO BID” option in the e-procurement portal of the County’s vendor management software, specify the reason in the drop-down menu, and confirm the “NO BID” before the expiration of the Submission Deadline.
4. Conduct of Participants: The following policy will apply to all solicitations:
The Cone of Silence shall prohibit any communication regarding a solicitation between prospective respondents, including bidders, proposers, contractors, lobbyists, consultants, or their representatives; and any County Commissioner, County employee, evaluation committee member, or any other individual involved in or able to influence the procurement process, except as expressly permitted herein.
This policy applies to all competitive procurement methods, including, but not limited to, Invitations to Bid (ITB), Requests for Proposals (RFP), Requests for Qualifications (RFQ), and
Invitations to Negotiate (ITN).
The Cone of Silence shall be in effect from the time of public advertisement of a solicitation until occurrence of either of the following:
1. Final action by the Board of County Commissioners; or
2. Cancellation of the solicitation.
During the Cone of Silence period, the following are strictly prohibited:
o Any oral, written, electronic, or other communication regarding the solicitation outside of the authorized process;
o Contact through third parties, intermediaries, or representatives intended to influence the procurement; or o Attempts to obtain non-public information or provide information not made available to all respondents.
The following communications are permitted:
o Written inquiries submitted through the designated procurement platform (e.g., OpenGov) to the assigned Purchasing Representative. All official responses to vendor inquiries shall be issued through formal addenda;
o Communications during any duly noticed pre-bid or pre-solicitation meeting; or o Communications made during any related publicly noticed Board meeting.
Sanctions. Violation of the Cone of Silence may result in one or more of the following sanctions:
o Disqualification of the respondent;
o Rejection of a bid or proposal;
o Termination of negotiations;
o Suspension or debarment, as provided in the Escambia County Code of Ordinances; or o Contract termination, if discovered post-award.
The County reserves the right to investigate any alleged violation and to require disclosure of all communications related to the procurement. Failure to cooperate with such an investigation may result in disqualification or contract termination.
Ignorance of this policy shall not be considered a valid defense.
5. Additional Terms and Conditions: No additional terms and conditions included with the offer will be considered, and any and all such additional terms and conditions shall have no force and effect and are inapplicable to this solicitation. It is understood and agreed that the General and
Supplemental Terms and Conditions in this solicitation are the only terms and conditions applicable to this solicitation, and the contractor’s authorized signature affixed to the offer attests to this.
6. Mistakes: Contractors are expected to examine the specifications, delivery schedule, solicitation prices, extensions, and all instructions pertaining to supplies and services described in the solicitation. Failure to do so will be at contractor’s risk. In the event of an error in the extension of the unit price, the unit price will govern.
7. Prices: All offers shall include firm unit prices that include all packing, handling, shipping charges, and delivery to any point within Escambia County, Florida.
8. Discounts: Discounts for prompt payments shall not be considered when determining the lowest net cost for solicitation evaluation purposes except in cases of tie solicitations.
9. Product Literature: Offeror shall provide a copy of any relevant product literature and price list(s) with the offer.
10. Abnormal Quantities: Should any unusual or abnormal quantity requirements arise, the County reserves the right to solicit separate offers as a multiple award.
11. Additional Quantities: For a period not exceeding one hundred eighty (180) days from the date of the offer, the County reserves the right to purchase additional quantities at the prices offered in this solicitation. If additional quantities are not acceptable, the contractor must specify “OFFER
IS FOR SPECIFIED QUANTITY ONLY”.
12. Approved Equivalents: Any manufacturer’s name, trade name, brand name, information and/or catalog numbers listed in a specification are for information and not intended to limit competition. The contractor may offer any brand for which it is an authorized representative that meets or exceeds the specifications for any item(s). Customary measurements appearing in these specifications are not intended to preclude offers for commodities with metric measurements. If an offer includes equivalent products, indicate the manufacturer’s name and number. The contractor shall submit with its offer applicable cuts, sketches, and descriptive literature and/or complete specifications. Reference to literature submitted with a previous solicitation will not satisfy this provision. Escambia County reserves the right to determine acceptance of item(s) as an approved equivalent. Offers that do not comply with these requirements are subject to rejection.
13. Nonconformance to Specifications: Items may be tested for compliance with the contract specifications by a testing laboratory acceptable to the County. The County may require the contractor to reimburse all costs incurred by the County in connection with the examination or testing of the commodity, including costs relating to transporting the commodity samples to the testing site, actual test costs, personnel costs and other applicable costs should the items fail testing. The data derived from any tests for compliance with the contract specifications are public records and open to examination in accordance with Chapter 119, Florida Statutes. Items delivered that do not conform to the contract specifications may be rejected and returned at contractor’s expense. These items and items not timely delivered by the delivery date specified in the solicitation and/or purchase order may result in the contractor being found in default, in which event, any and all re-procurement costs may be charged against the defaulting contractor.
Any violation of these stipulations may also result in contractor’s name being removed from the
Office of Purchasing registered vendor list, and the County not doing business with the contractor until such time as the County has been reimbursed for all re-procurement costs.
14. Service and Warranty: Unless otherwise specified, the offeror shall define any warranty service and replacements that will be provided at no cost to the County during and subsequent to the contract term.
15. Condition and Packaging: All items shall be a new, current standard production model available at the time of the solicitation. All containers shall be suitable for storage or shipment, and all prices shall include standard commercial packaging.
16. Safety Standards: Unless otherwise stipulated in the solicitation, all manufactured items and fabricated assemblies shall comply with applicable requirements, standards, and regulations of the Occupational Safety and Health Act (OSHA).
17. Delivery: Delivery shall be Monday through Friday during regular business hours, excluding
County designated holidays, unless otherwise specified. Unless a date is specified, contractor must provide the number of days required to make delivery after receipt of purchase order. The
County may utilize delivery time as a factor for recommending the award.
18. Inspection, Acceptance and Title: Inspection and acceptance will be at “the place of destination” unless otherwise provided. Title and risk of loss or damage to all items shall be the responsibility of the contractor until accepted by the County, unless loss or damage results from negligence by the County. The contractor shall be responsible for filing, processing, and collecting all damage claims.
19. Samples: Samples of items shall be furnished at no expense to the County. If not destroyed and upon written request, samples will be returned at the contractor’s expense. Each sample shall be labeled with the contractor’s name, manufacturer’s brand name, and serial number (as appropriate), solicitation number, and item reference. Requests to return samples must be received within 10 days after the solicitation opening date and must be accompanied by instructions with the applicable shipping authorization number and name of carrier. If instructions are not received, sample items become the sole property of the County and may be disposed of at the County’s discretion.
20. Protests: Any actual bidder/proposer who is aggrieved in connection with a pending award may submit a protest in writing to the Purchasing Director within two business days after the posting of the award recommendation as provided in Sec. 46-100, Escambia County Code of Ordinances.
21. Solicitation Expenses: The County accepts no responsibility for any expenses incurred by the offeror in the solicitation preparation and submittal as well as any other requirements as may be specified in the solicitation. All such expenses are borne solely by the offeror.
22. Taxes: Escambia County does not pay Federal Excise and Sales taxes on direct purchases of tangible personal property. See exemption number on face of purchase order. This exemption does not apply to the purchases of tangible personal property by contractors who use the tangible personal property in the performance of contracts for the improvement of County owned real property.
23. Invoicing and Payment: Payments shall be made in accordance with the Local Government
Prompt Payment Act, §§218.70, et seq., Florida Statutes, as amended.
24. Improper Invoice; Resolution of Disputes: Improper invoices for construction services and non-construction services will be processed in accordance with Sections 218.735(2)-(5) and
218.736(1), Florida Statutes, respectively. In the event a dispute occurs between a contractor and the County concerning payment of an original invoice, such dispute shall be finally determined by the County pursuant to the County’s Dispute Resolution Procedure established in accordance with
Section 218.76(2), Florida Statutes.
25. Conflict of Interest: The offeror represents that it presently has no interest and shall acquire no interest, either direct or indirect, which would conflict in any manner with the performance of services required hereunder. The offeror further represents that no person having any such interest shall be employed by it during the agreement term and any extensions. The offeror shall promptly notify the Purchasing Director, in writing, of any potential conflict of interest which may influence or appear to influence the contractor’s judgment or quality of services.
26. Contingent Fees: The offeror warrants that it has not employed or retained any company or person, other than a bona fide employee working solely for the offeror to solicit and that it has not paid or agreed to pay any person, company, corporation, individual, or firm, other than a bona fide employee working solely for the offeror any fee, commission, percentage, gift, or other consideration contingent upon or resulting from the award or making of an agreement. For the breach or violation of this provision, the County shall have the right to terminate any resulting contract without liability and at its discretion, to deduct from the contract price, or otherwise recover the full amount of such fee, commission, percentage, gift, or consideration.
27. Code of Ethics; Gifts: The award hereunder is subject to the provisions of Chapter 112, Part III, Florida Statutes, regarding the Code of Ethics for Public Officers and Employees, and the Escambia
County Code of Ethics Policy. Contractors are required to promptly disclose to the Purchasing
Director any gifts or gratuities offered to or solicited by any County employee or public officer.
The right of the contractor to proceed may be terminated by the County if, after notice and hearing, the Purchasing Director determines that the contractor, its agent, or another representative offered or gave a gratuity, including, but not limited to, money, services, travel, entertainment, or gifts to an officer, official, or employee of the County under circumstances where it may be reasonably inferred that the action of the contractor was intended to obtain a contract or favorable treatment under a contract. If the resulting contract is terminated under this clause, the County will be entitled to pursue all available legal remedies, including an action for breach of contract. The rights and remedies of the County provided in this clause shall not be exclusive and are in addition to any other rights and remedies provided by law or under the contract.
28. Governmental Restrictions: In the event any governmental restrictions may be imposed which would necessitate alteration of the material, quality, workmanship, or performance of the items prior to delivery, it shall be the responsibility of the contractor to provide written notice to the
Office of Purchasing identifying the applicable restrictions or regulation(s) that necessitate the alteration. The County reserves the right to accept any such alteration, including any price adjustments occasioned thereby, or to cancel the contract at no further expense to the County.
29. Legal Requirements: This solicitation shall be conducted in accordance with the provisions of the
Escambia County Purchasing Ordinance, and all applicable laws and regulations of the State of
Florida and the Escambia County Code of Ordinances shall apply to any resulting contract.
Applicable provisions of all federal, state, and local laws, ordinances, rules, and regulations shall govern development, submittal, and evaluation of all offers received in response hereto and shall govern any and all claims and disputes which may arise regarding this solicitation or any resulting contract; and lack of knowledge by any offeror shall not constitute a cognizable defense against the legal effect thereof.
30. Compliance with Laws: The contractor agrees to comply with all applicable federal, state and local laws, rules, policies, or guidelines related to this offer and the performance of any resulting contract, including, but not limited to, the requirements of the Americans with Disabilities Act
(ADA), the Occupational Safety and Health Act (OSHA), the Equal Employment Opportunity (EEO)
Act, and the Illegal Immigration Reform and Immigrant Responsibility Act, as amended, (8 U.S.C.A.
§1324a).
31. Patents and Royalties: In addition to any other indemnification obligation, the contractor shall hold harmless, indemnify and defend the County and its officers, agents, and employees from liability of any nature or kind, including cost and expenses for or on account of any copyrighted, patented, or unpatented invention, process, or article manufactured or supplied by the offeror.
The contractor has no liability when such claim is solely and exclusively due to the combination, operation or use of any article supplied hereunder with equipment or data not supplied by contractor or is based solely and exclusively upon the County’s alteration of the article. The
County will provide prompt written notification of a claim of copyright or patent infringement and will afford the contractor full opportunity to defend the action and control the defense. Further, if such a claim is made or is pending, the contractor may, at its option and expense, procure the right to continue use of, replace or modify the article to render it non-infringing. (If none of the alternatives are reasonably available, the County agrees to return the article on request to the contractor and receive reimbursement, if any, as may be determined by a court of competent jurisdiction.) If the contractor uses any design, device, or materials covered by letters, patent or copyright, it is mutually agreed and understood that the offered prices shall include all royalties or costs arising from the use of such design, device, or materials in any way involved in the work.
32. Public Records: Any documents submitted in response to this solicitation may be subject to disclosure pursuant to the provisions of Florida’s Public Records Act, Chapter 119, Florida
Statutes. contractor waives any claim of confidentiality upon submission of its offer. Records that are exempt or exempt and confidential will not be disclosed to any third-party except as authorized by law. Pursuant to Section 119.071 (1)(b)-2., Florida Statutes, sealed bids, proposals, or replies received by the County pursuant to a competitive solicitation are exempt from public disclosure until such time as the County provides…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .