Base Paving and Civil Works IDIQ Specifications - 2026 Basic.pdf

PDF 963 KB Posted

Attached to
Base Paving & Civil Works IDIQ
Solicitation number
EEPZ267762
Issued by

About this file

This is a Sources Sought announcement and specifications document for a Firm-Fixed Price Indefinite Quantity Indefinite Delivery (IDIQ) contract to provide paving and civil works construction services at Columbus Air Force Base, Mississippi. The Construction Flight of the 14th Contracting Squadron is conducting market research to identify interested contractors for this future acquisition. The contract will have a base period of two years plus four three-year option periods, with an estimated ceiling of $25 million. The designated NAICS code is 237310 (Highway, Street, and Bridge Construction), with a small business size standard of $45,000,000.

Interested parties must submit responses by 26 June 2026 at 3:30 P.M. CST. This announcement is for market research purposes only, and respondents should be aware that if a formal solicitation is issued, it will be announced separately and will require independent responses to that solicitation announcement. No reimbursement will be provided for costs associated with responding to this sources sought announcement. The contracting agency is the Department of the Air Force Air Education and Training Command. The specifications document provides detailed technical requirements for the paving and civil works that will be required under the eventual contract.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE 04/06/2026

14 CONTRACTING SQUADRON

BASE PAVING AND CIVIL WORKS INDEFINITE DELIVERY INDEFINITE QUANTITY CONTRACT

COLUMBUS AIR FORCE BASE, MISSISSIPPI

Table of Contents

DIVISION 1 – GENERAL REQUIREMENTS

SECTION 01011 – GENERAL DESCRIPTION

SECTION 01620 - ENVIRONMENTAL CONSIDERATIONS

DIVISION 2 - SITEWORK

SECTION 02222 - EXCAVATION, TRENCHING, AND BACKFILLING FOR UTILITIES SYSTEMS

SECTION 02225 - EARTHWORK FOR ROADWAYS AND AIRFIELDS

SECTION 02226 - RECONSTRUCT BASE COURSE

SECTION 02232 - SELECT-MATERIAL SUBBASE COURSE

SECTION 02233 - GRADED-CRUSHED-AGGREGATE BASE COURSE

SECTION 02235 - LIMEROCK BASE COURSE

SECTION 02239 - PORTLAND CEMENT-STABILIZED BASE OR SUBBASE COURSE

SECTION 02241 - STABILIZED-AGGREGATE BASE COURSE

SECTION 02511 - CONCRETE SIDEWALKS AND CURBS AND GUTTERS

SECTION 02515 - CONCRETE PAVEMENT FOR ROADS AND AIRFIELDS

SECTION 02551 - BITUMINOUS INTERMEDIATE AND WEARING COURSES FOR ROADS AND

STREETS (CENTRAL-PLANT HOT-MIX)

SECTION 02555 - DOUBLE BITUMINOUS SURFACE TREATMENT (DBST)

AGGREGATE GRADATION

SECTION 02556 - BITUMINOUS INTERMEDIATE AND WEARING COURSES FOR AIRFIELDS,

HELIPORTS, AND HEAVY-DUTY PAVEMENTS (CENTRAL-PLANT HOT-MIX)

SECTION 02558 - BITUMINOUS TACK COAT

SECTION 02559 - BITUMINOUS PRIME COAT

SECTION 02562 - RUBBERIZED COAL-TAR EMULSION SAND SLURRY SEALCOAT FOR

BITUMINOUS PAVEMENT

SECTION 02574 - PATCHING OF RIGID PAVEMENTS

SECTION 02576 - RUBBER AND PAINT REMOVAL FROM AIRFIELD PAVEMENTS

SECTION 02577 - PAVEMENT MARKINGS

SECTION 02580 - RANDOM CRACKS SEALING IN BITUMINOUS PAVEMENTS

SECTION 02581 - SEALING AND RESEALING JOINTS AND RANDOM CRACKS IN CONCRETE

PAVEMENTS

SECTION 02598 - COLD MILLING OF BITUMINOUS PAVEMENTS

SECTION 02722 - SITE STORM SEWERAGE SYSTEMS

SECTION 02935 - TURF

01011- 1

DIVISION 1 – GENERAL REQUIREMENTS

SECTION 01011 – GENERAL DESCRIPTION

PART 1 GENERAL

1.1 GENERAL REQUIREMENTS

The work will include providing all labor, equipment, plant, tools, transportation, and materials to perform various types of site work. The site work will include, but is not limited to, repair and construction of asphalt and concrete pavements including subbase and base course, installation of associated utilities, drainage structures, sidewalks, curb and gutters, rubber removal and painting of runways, taxiways, and aprons, and turf. All work indicated in the specifications, drawings, and bid schedule shall be accomplished for the original bid price. The work will be issued in incremental task orders throughout each year as money becomes available. Each task order will be separately negotiated to determine quantities, not price determined by Gordian estimating methods. The Contractor will only apply the applicable requirements of the specifications to each separate task order. Unique items of work not priced in the (catalog) will be determined through Gordian procedures. This general outline of work does not, in any way, limit the responsibility of the Contractor to perform all work as specified herein.

1.2 LOCATION

The work will be located at Columbus Air Force Base, Columbus, Mississippi, SEA-RAY Remote Airfield, Macon, Mississippi and the Auxiliary Airfield, Shuqualak, Mississippi. The exact location of each task order will be indicated by the Contracting Officer.

1.3 SITE CONDITIONS

The Contractor acknowledges satisfaction as to the nature and location of the work, the general and local conditions, access to job site; disposal, handling, and storage of materials; availability of labor, water, electric power or similar physical conditions at CAFB and the auxiliary airfield; the character of equipment and facilities needed preliminary to and during the performance of the work; and all other matters that can in any way affect the work or the cost thereof under this contract. The Contractor shall protect existing underground and above ground structures from damage. The Contractor will provide temporary support for all structures in the areas of excavation. Where existing utilities or any other structures are damaged during construction, and which are not included for removal in the design and specifications, the Contractor shall restore them to their original condition at the Contractor's own expense. The Contractor shall notify the Contracting Officer of any damaged underground structure and make repairs or replacements before backfilling.

1.4 NOTIFICATION:

The Contractor will be notified of a site work requirement by the Contracting Officer. Each notification will contain a project description for the task order. Upon receipt of notification, contact the Contracting Officer

01011- 2 to arrange an appointment for a joint site visit with Civil Engineering. The initial site visit will be held within five (5) working days from receipt of notification and at a time convenient to both parties.

1.5 SITE VISIT

The Contractor will be escorted to the work site by a Government representative to view the scope of work for all work to be accomplished in the task order. Any clarification of the scope can be discussed at that time. If applicable, a task order detailing the scope of work will be issued following completion of negotiations.

1.6 PERFORMANCE PERIOD

Contractor shall perform the work within the time as specified in each task order. Work days for this contract will be Monday through Friday between the hours of 7:30AM and 4:30PM. Flight line work may be done on weekends, after duty hours, or during other times approved by the Government. The Government will issue a Notice to Proceed (NTP) to the Contractor for initiation of work. The Contractor will give a five (5) day notice to Construction Management before he/she plans to perform the work.

Written permission from the Contracting Officer shall be obtained for any deviation from the approved schedule.

1.7 AVAILABILITY OF UTILITY SERVICES

All reasonable quantities of utilities will be made available to the Contractor. The Government will not be held responsible for interruptions of utility services and will not be liable for Contractor delays, damages, or increased cost incurred by any such interruption of service. The Contractor will be responsible for providing all labor, equipment, and materials to make necessary temporary utility connections. The temporary connections shall be coordinated with the proper Government Representative before being made and will be removed upon project completion.

1.8 SAFETY REQUIREMENTS

The Contractor shall abide by all applicable sections of EM 385-1-1, 15 March 2024 during all phases of completing the specified work. This regulation is available for reference at Engineering and Environmental Planning Branch, Bldg 385, or at the following web site: https://www.usace.army.mil/Missions/Safety-and- Occupational-Health/

1.9 RECORD DRAWINGS

The Contractor shall maintain at the job site one set of full-size contract drawings, marking them in red to show all variations between the construction actually provided and those indicated or specified in the contract documents. Within thirty (30) days of completion of the work the marked-up drawings and an electronic file showing variations shall be delivered to the Contracting Officer and will be subject to his/her approval before acceptance.

https://www.usace.army.mil/Missions/Safety-and-Occupational-Health/ https://www.usace.army.mil/Missions/Safety-and-Occupational-Health/

01011- 3

1.10 CLEAN-UP

All debris and rubbish resulting from construction work will be disposed of by the Contractor off Government property. Disposal shall be in compliance with federal, state, and local hauling and disposal regulations. The Contractor will submit dump tickets unless otherwise specified by the Contracting Officer.

Site clean-up will be maintained daily.

1.11 AIRFIELD DRIVING PROCEDURES

The Contractor will be briefed on proper rules for driving on the airfield. This briefing will be accomplished before on site work begins. All workers driving on the airfield shall attend this briefing. All rules will be obeyed to the strict letter of the law. All vehicles used by the Contractor on the airfield shall be operated in such a manner as not to create any Foreign Object or Debris (FOD) in the airfield areas. The Contractor will be fully responsible for keeping the areas used by his/her vehicle free of FOD. FOD will be removed from airfield as it occurs. The Contractor will supply vehicle mounted vacuum sweeper capable of removing all FOD, dirt, debris, and foreign matter as a result of his operation. Before the Contractor uses vehicles on the airfield, the vehicles shall be registered at base operations.

1.12 GOVERNMENT PROPERTY

Government property to be maintained and/or retained will be identified on individual task orders.

1.13 SUBMITTALS

Material submittals and testing reports shall be identified and submitted on individual task orders. Materials to be used shall be submitted on AF Form 3000 for approval prior to use. Contractor shall submit progress reports to Contracting. Contractor shall submit employee listing to Contracting for badges/passes.

1.14 REFERENCES

All references cited in these specifications will be the most current.

END OF SECTION

01620- 1

SECTION 01620 - ENVIRONMENTAL CONSIDERATIONS

PART 1 GENERAL

1.1 CONTRACTOR LIABILITIES FOR ENVIRONMENTAL PROTECTION

1.1.1 Contractor Responsibility: The Contractor bears full responsibility and liability for compliance with all Occupational Safety and Health Administration (OSHA) and applicable state and local safety and health regulations for this Project and holds the Government harmless for any Contractor action resulting in illness, injury, or death. Contractor is solely responsible for ensuring the safety of all Contractor and non-contractor personnel whenever and wherever present on CAFB. Additional safety and health requirements stated or implied herein apply to Contractor work that could affect non- contractor personnel at CAFB.

1.1.2 Compliance: Contractor is responsible for compliance with all federal, state and local environmental laws and regulations. These requirements include, but are not limited to, items discussed in this section.

1.1.3 This installation is subject to federal, state, and local inspections to review compliance with environmental protection laws. An inspection by the Environmental Protection Agency (EPA), Mississippi Department of Environmental Quality (MDEQ), or any other environmental or safety enforcement agency may include questioning and inspection of Contractor personnel, sites, and processes.

1.1.4 Applicable Publications: The publications listed below form a part of these Base Standards to the extent referenced herein or in the Project scope. The publications are referred to by basic designation only. Wherever listed publications are applicable, the Contractor shall comply with the latest extant publication.

Code of Federal Regulations (CFR)

• OSHA General industry Safety and Health Standards (29 CFR 1910) Publications

• OSHA Construction Industry Standards (29 CFR 1926)

• National Emission Standards for Hazardous Air Pollutants (40 CFR 61)

• Oil Pollution Prevention (40 CFR 112)

• Standards Applicable to Generators of Hazardous Waste (40 CFR 262)

• Used Oil Specifications (40 CFR 279.11)

• Hazardous Chemical Reporting (40 CFR 370)

Federal Standards (Fed Std)

• 313A Safety Data Sheets, Preparation and the Submission of Safety and Health requirements, DA Circular 40-83-4

01620- 2

1.1.5 No asbestos containing materials may be used in the performance of this contract or anywhere on

CAFB.

1.1.6 Safety Program: The Contractor shall organize, maintain and document a program to ensure compliance with safety requirements, with personnel assigned to manage its functions including administrative, liaison, and technical to implement, direct, monitor, control, and allocate resources for all safety tasks within all aspects of the work. The Contractor shall ensure full compliance of all on- site subcontractors with all safety requirements. All safety documents and related data shall be available in the Contractor site office for re-view by the CO at any time.

1.1.7 Confined Spaces: Before entering a Confined Space, the Contractor shall develop a Confined Space plan and obtain a Confined Space permit. Government provided information and issued permit notwithstanding, the Contractor shall remain fully responsible for the safety of anyone directly or indirectly affected by work in that confined space.

1.2 LEGAL AUTHORITY

Safe Drinking Water Act http://water.epa.gov/lawsregs/rulesregs/sdwa/index.cfm

Clean Water Act http://www2.epa.gov/laws-regulations/summary-clean-water-act

Clean Air Act https://www.epa.gov/laws-regulations/summary-clean-air-act

Emergency Planning and Community Right-to-Know Act (EPCRA) https://www.epa.gov/sites/production/files/2017- 08/documents/epcra_fact_sheet_overview_8-2- 17.pdf

Resource Conservation and Recovery Act (RCRA), https://www.epa.gov/rcra

Comprehensive Environmental Response, Compensation and Liability Act, https://www.epa.gov/laws-regulations/summary-comprehensive-environmental-response-compensation-and-liability-act

Code of Federal Regulations (CPR) series 29 (OSHA), 40 (Environmental) and 49

(DOT).

1.2.1 Contractors shall follow the listed clauses. This guide has given local information pertaining to the listed clauses and is not to be considered complete information. The contractor is instructed to become familiar with the full text of each clause as they have specific applications.

1.3 GENERAL

1.3.1 The Contractor shall complete and provide documentation as requested by the CO or by the Government inspectors, including documentation of any environmental training required by federal, state, or local regulations.

http://water.epa.gov/lawsregs/rulesregs/sdwa/index.cfm http://www2.epa.gov/laws-regulations/summary-clean-water-act http://www.epa.gov/laws-regulations/summary-clean-air-act http://www.epa.gov/sites/production/files/2017-http://www.epa.gov/rcra http://www.epa.gov/laws-regulations/summary-comprehensive-environmental-response-

01620- 3

1.3.2 If a Notice of Violation is issued to the Government or Contractor due to the Contractor's error or omission, the Contractor shall be held liable for damages—including fines, penalties, or corrective actions imposed by federal, state, or local agencies.

1.3.3 If there is an accidental spill, the Contractor shall follow installation spill reporting and clean up procedures as outlined herein.

1.4 HAZARDOUS MATERIALS

1.4.1 Submit the following list before the project starts:

1.4.1.1 The Contractor shall submit a list of all wet and dry chemical materials to be used during the performance of the contract with an estimated total annual use on site to the CO a minimum of ten (10) calendar days before project start, via a Contractor Usage Tracking Form.

1.4.1.2 Materials are to be checked in through the 14 CES/CEIE Hazmat Pharmacy as they arrive onto CAFB with a current Safety Data Sheet specific to the manufacturer, container quantity, and total quantity.

1.4.1.3 Changes of quantity or manufacturer are to be immediately cleared through the CO and the Hazmat Pharmacy.

1.4.1.4 All drums and/or containers of liquid materials shall be marked to indicate contents. Unmarked containers are not allowed on site. All containers shall be kept closed when not in use.

1.5 PROJECT EXECUTION

1.5.1 Hazardous materials shall be stored and used in accordance with all federal, state, and local laws and regulations. Hazardous materials shall not be stored in containers in direct contact with the ground.

Containers shall be in good condition with no holes, leaks, creases, or excessive rust. Containers shall be kept closed when not in use. No hazardous materials/waste will be stored on the installation without CO approval.

1.5.2 Safety Data Sheets (SDS) shall be available on site (at the location) for all hazardous materials.

1.5.3 Any hazardous or special waste generated shall be handled in accordance with all local, state, and federal laws and regulations, including Resource Conservation and Recovery Act (RCRA) requirements for waste management and Department of Transportation (DOT) requirements for waste transport. The Contractor shall be responsible for obtaining all necessary permits, licenses, and approvals unless otherwise specified in writing by the CO.

01620- 4

1.6 HAZARDOUS WASTE GENERATION/DISPOSAL

1.6.1 The Contractor shall maintain records of all waste determinations, including appropriate results of analysis performed, substances and sample locations, date and time of collection, and other pertinent data as required by 40 CFR 262 Subpart D, 40 CFR 279.11 and 40 CFR 280.74.

1.6.2 The Contractor shall provide a copy of all hazardous waste manifests to the CO by close-of- business on the same day waste is transported off base. The Contractor shall provide a closed copy of the hazardous waste manifests not later than 30 days after the waste is transported off base or before final payment, whichever occurs first. Since CAFB’s EPA identification number will be used on all hazardous waste manifests, 14 CES/CEIE shall sign the manifest. The Contractor still retains all liabilities associated with containerizing, loading, shipping, and disposing of the hazardous waste.

1.7 DISPOSAL & RECYCLING

1.7.1 The Government, at Government expense, will support recycling and diversion within limits as follows.

It is in the Government’s best interest to provide appropriate size containers for the collection of materials, the Contractor shall transport them to the recycle facility and process the materials. Contractors are responsible for the cost of the disposal of all solid waste and hazardous waste not surrendered for recycling on CAFB.

1.7.2 Further diversion of construction debris (C&D) is encouraged. The tonnage of reused asphalt, concrete, wood, and other materials is reportable to the CO for the duration of the project.

1.7.3 Contractors may elect (via the task order) to manage their own recycling of materials. In such cases, tonnage (weight slips) of material disposed of and reused or recycled (including reports of “no activity” in a given month) shall be reported to the CO no later than the fifth (5th) of each month until the contract is completed.

1.7.4 The Contractor shall notify the CO a minimum of three (3) calendar days prior to the need for recycle materials containers or changes in container size or delivery schedule so the appropriate containers and delivery schedule can be established. The Contractor may elect to transport materials directly to the CAFB recycling facility during hours of operation, but this is not a reimbursable action.

1.7.5 The Contractor is encouraged to contact Environmental, CEIEC or the CAFB Recycling Center for on-base recycling.

1.7.6 The following materials are acceptable for inclusion in the container provided for recycling:

• Copper: sheeting, wire, devices with an extension cord, electronics, motors.

• Steel: iron, sheet, structural beams, components

• Aluminum: sheet, structural components, cast material and containers.

• Lead: batteries, sheeting, pipe

• Paper: cardboard, office paper, mixed paper

01620- 5

1.7.7 The following items may be included in the provided containers with exceptions as noted. Again, the saving to the contractor is the avoided disposal fees.

• Oversized materials (limbs/steel/aluminum) may not need reducing by the Contractor.

Contact the recycling center directly to have exceptions inspected for handling at Government expense.

• Glass: bottles only, not mixed with construction debris collection. Office material recycling allows for the mixing of paper/glass/cans/plastic to be dropped off at the recycling center during business hours.

• Wood/scrap lumber/limbs: under 8” diameter, nail/screw/mixed material free. Wood not meeting the criteria are construction debris.

• Only plastics labeled as PETE (#1) or HDPE (#2), empty of any liquid or dry material.

Rinsing is not required.

• Other materials shall be cleared with the recycling staff.

• C&D diversion on or off base is reportable in tons to the CO. Items and exceptions are:

o Wood: limbs, pallets, clean straight lumber scrap may be collected for wood mulch BUT no screws, hardware, metal straps, bolts, plastic, Formica or treated products are wanted. The dumping of unwanted materials is a contract violation, and the Contractor will be directed to dispose of the material properly at their expense.

o Concrete: as fill, riprap, cut and reused, or crushed.

o Asphalt: millings used for new construction.

o Gravel: used decorative gravel may be counted as a diverted material if it is suitable for another purpose. Plastic and other materials are to be removed prior to reusing as ground cover.

1.7.8 Materials NOT meeting any of the above criteria will be considered “construction debris” and shall be disposed of at the Contractor’s expense. The following are examples of construction debris:

• Foam, Styrofoam, sheet plastic contaminated with dirt, furniture, chairs, office dividers, plate glass, glass objects, table-tops, Pyrex, Wood with nails or paint, brick, masonry, sheetrock.

1.7.9 Liquids are generally not acceptable. Oil may be recycled but not in the provided mixed material container.

1.7.10 Mixed material items are generally not acceptable. The Contractor shall NOT recycle pressurized containers, containers with free liquid, free solids, or other material. Any container puncturing, emptying, 01620- 6 crushing, or cutting SHALL be in accordance with MDEQ and installation air, water, and disposal regulations and permit conditions.

1.8 PROHIBITED MATERIAL/ACTIONS

1.8.1 If materials not indicated in the current contract requirements are encountered that may be dangerous to human health upon disturbance at any time, such as polychlorinated biphenyl's (PCBs), lead-based paint, and friable and non-friable asbestos, the Contractor shall take no action that would disturb or further disturb the material encountered and shall notify the CO, and assigned Quality Assurance Evaluator (QAE) or Construction Inspector (CI) immediately. Failure to make such notification relieves the Government from all liability for cost and/or performance time impacts until such time proper notifications are received by the CO.

Verbal notification shall be followed up with written notification within three (3) workdays.

1.8.2 Class I Ozone Depleting Substances (ODS) as defined in Section 602(a) of the Clean Air Act shall not be used in the performance of this contract. Radioactive materials or instruments capable of producing ionizing radiation—as well as materials that contain asbestos, mercury or PCBs—are also prohibited, as are materials that contain potentially hazardous concentrations of lead. The Consumer Product Safety Commission states that potentially hazardous concentrations of lead are greater than 90 parts per million or 0.009%. Exceptions to the use of the above excluded materials may be considered by the CO, upon written request by the contractor; however, their use is a violation of federal law, Air Force Instruction (AFI), executive orders, or policy.

1.9 SPILLS AND CLEANUP

1.9.1 If there is a spill—of any amount or type—of hazardous materials or waste to include all petroleum products, the Contractor shall immediately call 911 to call the installation fire dispatch providing description of material spilled (including SDS), time and location of spill, estimate of amount spilled, spill surface, and path of spill (i.e., Did the material enter or will it soon enter a drain inlet, waterway, soil, etc.). Note that spills used here include releases of materials from ruptured or leaking storage receptacles (such as tanks), from transmission lines and valves, either as a part of contract work or as a result of contract work on nearby storage or transmission lines, or the leak of hazardous gases such as chlorine into the air. A follow-up written report to the CO shall be required within three (3) calendar days.

1.9.2 The Contractor shall take immediate action to contain and clean up spills. If the Contractor is unable to begin cleanup action within 15 minutes of the spill, the Government reserves the right to begin cleanup, continue cleanup efforts/actions until the Contractor can properly take over, or enlist the services of another Contractor to begin and continue cleanup as determined by the CO.

1.9.3 All costs incurred by the Government until Contractor are capable of taking control, as determined by the on-scene commander, will be the sole responsibility of the Contractor. The Contractor shall ensure equipment, material, and trained personnel are available to meet response times and cleanup requirements.

01620- 7

1.9.4 Spill cleanup personnel shall be trained and certified to perform spill cleanup. The Contractor shall assume responsibility for the proper characterization and disposal of any waste and cleanup materials generated. All waste and associated cleanup material shall be removed from the base and transported/stored in compliance with applicable regulations until final disposal.

1.9.5 The Government may control spill cleanup activities. The on-scene commander will determine best practices for spill cleanup. The CO remains as the only Air Force representative who may amend contract requirements.

1.9.6 The Contractor is responsible for restoring a spill site to the condition of the site prior to the spill or to an improved condition.

1.10 AIR CONSIDERATIONS

CAFB is in an air attainment zone. The base operates under a true minor permit that requires extensive data gathering to verify no violations of the permit. Fueling operations, painting other than buildings, media blasting, and dust generation require reporting to the CO. The requirements for monthly reporting, if needed, shall be coordinated with the CO.

1.11 AFFIRMATIVE/GREEN PROCUREMENT/BIO-BASED/ENERGY

Pursuant to Executive Order 13834, energy and materials used on government installations should be procured in a manner that increases efficiency, optimizes performance, eliminates unnecessary use of resources, and protects the environment. For example, whenever possible—and assuming comparable quality, availability, and price—supplies are to be of the appropriate minimum energy efficiency or better;

made from re-covered, recycled, or renewable materials. Certified materials with appropriate labeling are a good guide. The CO has fiduciary obligation to follow executive orders and enforce them on the Contractor.

1.12 ASBESTOS/LEAD BASED PAINT

1.12.1 After coordination with the CO, all asbestos manifests shall be signed by 14 CES/CEIE Hazardous Waste manager before leaving the installation. Deliver a copy of certifications to the CO three (3) calendar days before start of work.

1.12.2 No lead-based paint will be utilized by any Contractor on any base facility or equipment. Removal of paint or disturbing of surfaces may result in being exposed to lead-based paint. All such loose material, chips, and debris shall be removed and not allowed to contaminate the ground or other areas as part of the contract work. All lead-based paint and contaminated dust/chips shall be surrendered to the Government following coordination with the CO and CE Construction Management. Government will dispose of such dust/chips at Government cost.

01620- 8

1.13 DRINKING WATER

1.13.1 Report water main breaks immediately. The base 911 system will take emergency reports and after-hours calls. The Contracting Office may become involved with liability or repair issues. Note: cell phone users will be transferred to CAFB dispatch when they identify their location.

1.13.2 Back Flow Prevention is MANDATORY on all connections to the drinking water system. The Contractor shall not take water directly from hydrants for Contractor use without using a back flow preventer.

Drinking water utility use may be metered; estimated use shall be agreed to in advance.

1.14 ENVIRONMENTAL MANAGEMENT SYSTEMS (EMS)

1.14.1 Upon reading and signing the contract all Contractors are considered to have met the EMS General Awareness training requirements. It is the expressed responsibility of the Contractor to ensure all employees and sub-contractors are aware of all environmental requirements stated herein. Where workers are transitory (less than 160 hrs. annually), the requirement may be waived as long as a supervisor or foreman is trained.

The USAF does NOT automatically recognize ISO 7000 or 14001 training or certification as equivalent.

1.14.2 All Contractors are required to be aware of the CAFB Environmental Policy Statement which is:

CAFB is committed to conducting the mission in a manner that will adhere to federal, state and Air Force standards and protect human and environmental health. In support of our goal, we shall:

• Maintain a culture of continuous improvement to daily activities which impact environmental and occupational health.

• Identify and act to reduce waste and prevent pollution of all kinds.

• Promote conservation and sustainable use of natural resources.

• Develop economically feasible and environmentally sound objectives and targets to address significant aspects.

1.14.3 The framework for setting and reviewing environmental objectives and targets is a cooperative effort between all base personnel, Cross Functional Team (CFT) and Environmental, Safety and Occupational Health (ESOH) Council.

1.14.4 All contractors must understand that all on-base activities are scored and those scored highest are critical and are identified as “significant aspects.” The most significant aspect at CAFB is storm water quality. The Contractor shall take particular care with activities that could affect this area; to include, but not limited to, activities causing erosion/sediment runoff.

1.15 HISTORICAL AND CULTURAL ARTIFACTS

Upon discovery of human remains, pottery, or other artifacts that may or may not be of Native American origin, the work site SHALL BE secured, work in the area of discovery SHALL be halted, and the contracting

01620- 9 officer SHALL immediately be notified. Contractor shall also immediately notify the CO about any damage to such artifacts. The worksite shall be released to the CO (or all practical portions) by 14CES/CEIE archaeological representative. Although CAFB has no registered historic buildings or sites, there are culturally significant attributes of the chapel, there is a known cemetery on site, and WWII debris could be discovered.

1.16 NATURAL RESOURCES

1.16.1 The Contractor shall preserve natural resources within project boundaries and outside limits of permanent work and shall not cut, deface, or remove trees or shrubs without CO permission unless allowed under the contract. The Contractor shall protect existing trees that may be damaged by contractor activities.

Do not fasten ropes, cables, or guying to trees without CO approval.

1.16.2 The Contractor shall not disturb fish and wildlife nor alter water flows or significantly disturb native habitat adjacent to the project site.

1.17 NOISE

Noise in excess of 85dB within 50 feet of occupied space shall be avoided, muffled, baffled, or of short duration. Occupants are to be notified in advance should long-term (6hrs or more) noise be anticipated due to contractor work.

1.18 PESTICIDES/FERTILIZERS

1.18.1 Contractors shall be licensed to apply any pesticide and shall coordinate and report all pesticide and fertilizer application with the CO. All quantities used/applied shall be reported by the 5th of the month.

1.18.2 If pest control, termite treatment for new slabs, or any type of similar actions are required by the Contract, see individual task order for additional requirements.

1.19 STORM WATER PROTECTION

1.19.1 CAFB has a Mississippi Baseline Storm Water General NPDES Permit. All discharges to storm drains, surface water, or indirectly to the ground are regulated and reportable. Even “clean” water is subject to the permit. The washing of vehicles will be in designated areas only. The use of soap is strictly prohibited. Wash water will not be dumped on the ground, parking lots, or in storm drains. Paint and paint brushes shall NOT be rinsed outside. Such actions shall be done in a sink that has a septic hookup. Options may include capture of all fluids and transfer to an agreed upon sanitary sewer dump point. Situations and specifics are open to discussion; however, fluids shall not be disposed of on the ground without MDEQ approved Industrial Storm Water Permit modification.

1.19.2 Work sites are to be inspected at least weekly, and records of these inspections are to be maintained onsite and available upon request.

01620- 10

1.19.3 If any project involves soil disturbance (including open excavations and staging areas), surface water diversion methods shall be taken in order to minimize entrance of runoff into the excavations. If site characteristics present a potential for sediment removal due to storm water, drains in the area shall be protected using wattles, silt screens, drain seals, or other approved equivalent sediment control methods.

1.20 REQUEST FOR CE SERVICE/ACTION/CLEARANCE; AF FORMS 332/813

1.20.1 AF Forms 332/813 are the specific forms for getting Government furnished space repaired, clearing trenching operations outside of the originally identified work area, or bringing in/ending an operation. The CO shall help to coordinate these documents, if and when needed.

1.20.2 The Contractor shall use Mississippi One Call 811 before the start of any dirt work.

1.21 TANKS

1.21.1 The Contractor shall prevent oily or other hazardous substances from entering the ground, drainage areas, or local bodies of water. Secondary containment is required around temporary fuel oil or petroleum storage tanks of any size, if any leakage could enter a storm drain, ditch or other waterway. Notify the CO prior to bringing any tanks onsite. Any container 55 gallons or greater is regulated as requiring secondary containment in the state of Mississippi.

1.21.2 Contractor tanks shall meet all tank, air, and storm water requirements, be in good repair, not rusted, labeled, sheltered, and be removed when no longer needed.

1.22 LIMITS AND EXCEPTIONS

1.22.1 General: These guidelines apply to all Contractors working on CAFB, except those with tasks transient in the nature (such as delivery operations that have no other presence on base).

1.22.2 EMS Training: Services of a transitory nature may be exempt from EMS training. Qualifying transitory contracts have very limited presence on the installation, making EMS training impractical. The CO is to include all Contractors unless there is a compelling reason not to.

Example: A carpet cleaning service working completely out of a service truck, preforming a single short-term task, having no on-site presence would qualify as exempt. A lawn service storing fuel overnight would not. Non-resident delivery and freight services are exempt (such as FedEx).

1.23 BARRICADES

1.23.1 Adequate barricades and warning signs shall be furnished, installed, and maintained by the Contractor.

The Contractor shall maintain the barricades in good condition throughout the construction performance period and remove the barricades from CAFB before Final Completion.

1.23.2 These barricades, including FOD barriers, are not included in the Coefficient.

01620- 1

1.23.3 Barricades on streets shall have battery-powered flashers. The Contractor shall use cones only for temporary diversions of pedestrian traffic. Extended diversions of pedestrian or street traffic shall use barricades with tape strung between. Barricades, cones, etc., are not included in the Coefficient.

1.23.4 To prevent injury, the Contractor shall surround an excavation, its tools, and equipment with a four-foot-high nylon web construction fence a minimum of five (5) feet away from the excavation, its tools and equipment. Place flashing lights along the top of the fence a maximum of five feet apart.

1.23.5 Excavations not supervised by the Contractor shall be covered with sheets of metal, plywood or other material that span the opening and prevent any load of people from falling into the excavation.

1.24 ENVIRONMENTAL PROTECTION

1.24.1 The Contractor shall comply with all applicable federal, state, local, and Air Force environmental regulations and their supplements. These regulations take precedence if they conflict with the Technical Specifications.

1.24.2 Contaminants: Contractor shall dispose of all solid, liquid, and gaseous contaminants including asbestos in accordance with applicable federal, state, and local codes and regulations, as described elsewhere herein.

1.24.3 Refuse Disposal: The Contractor shall remove all project related refuse from CAFB. The Government will not provide asbestos disposal sites.

1.24.4 Covered Chutes: The Contractor shall cover all refuse chutes and similar items or otherwise fully confine dumped material to prevent the dissemination of dust and debris.

1.24.5 Disturbances: For land disturbances less than one acre, the site superintendent must complete sediment and storm water construction training on the AETC Environmental, Safety and Occupational Health Training Network (ESOHTN). Disturbances of one or more acres require a Storm Water Permit from

MDEQ.

1.24.6 Hazardous Spill Prevention: Contractor shall handle & store Hazardous liquid materials in approved areas and shall comply with spill prevention and response requirements of CAFB. A copy is available at the Base CES Environmental Element. Handling and disposal of hazardous materials must conform to the latest version of the FAR Clause 52.223-3 Hazardous Material Identification and Material Safety Data.

1.24.7 Asbestos & Lead Removal: A Contractor removing asbestos or lead shall be licensed or certified by Mississippi Department of Environmental Quality (MDEQ) in conformance with 29 CFR 1910.1101. While this SOW is in effect, abatements are anticipated to be small removals of asbestos containing materials encountered during renovations. The Government shall inform the Contractor of all known asbestos or lead in TOs. The Contractor shall design and execute abatements in conformance with applicable EPA standards.

The Contractor shall submit completed copies of Waste Shipment Records, signed by the CAFB

01620- 2

Environmental Element representative, along with the waste manifest shipment records within three (3) days of landfill delivery of all waste shipments containing asbestos or lead.

1.25 USE OF ELECTROMAGNETIC EMISSION DEVICES

Electromagnetic emission devices include radio/RADAR transmitters, navigational aids, instrumentation, signaling, intrusion detection and identification devices, mobile and fixed business radio communication equipment, and Military Affiliate Radio Station (MARS), Citizen Band (CB) and amateur radio stations. If the Contractor plans to bring any electromagnetic emissions devices on base, the Contractor shall coordinate with the CO to have all equipment verified and approved by the CAFB Frequency Manager. The Contractor and all equipment pertaining to this section shall also comply with AFI 17-220.

1.26 MISCELLANEOUS

Radioactive Material (RAM): Non-Air Force organizations that desire to bring RAM, such as soil density meters, onto Columbus AFB, or conduct operations involving RAM on base, shall obtain written approval through the CO and the base Radiation Safety Officer (14 OMRS/SGXB). In addition, the Contractor shall provide the CO a copy of their radioactive material permit and training certificates if radioactive material will be brought onto base. The permit and training certificates will be coordinated through 14 OMRS/SGXB.

02222- 1

DIVISION 2 - SITEWORK

SECTION 02222 - EXCAVATION, TRENCHING, AND BACKFILLING FOR UTILITIES SYSTEMS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)

ASTM D 422 Particle-Size Analysis of Soils

ASTM D 1556 Density and Unit Weight of Soil in Place by the Sand-Cone Method

ASTM D 1557 Standard Test Method for Laboratory Compaction Characteristics of Soil Using

Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3))

ASTM D 2487 Classification of Soils for Engineering

Purposes (Unified Soil Classification System)

ASTM D 6938-10 Standard Test Method for In-Place Density and Water Content of Soil and Soil-

Aggregate by Nuclear Methods (Willow Depth)

UNIFIED FACILITIES CRITERIA (UFC)

UFC 3-220-01 Geotechnical Engineering, with Change 1

UFC 3-220-04FA Backfill for Subsurface Structures

UFC 3-220-10 Soil Mechanics (DM7.1)

1.2 MEASUREMENTS AND PAYMENTS

All measurements and payment will be based on completed work performed in accordance with the drawings and specifications.

1.2.1 Trench Excavation

Trench excavation will be the number of cubic yards excavated and measured to the depths and widths specified for the pipe size. Payment for trench excavation as measured will constitute full payment for excavation and backfilling. Unstable trench bottoms will be replaced by select granular material and paid

02222- 2 for as specified below. Trench excavation will also include the additional width at manholes and similar structures, the furnishing, placing and removal of sheeting and bracing, pumping and bailing, and all incidentals necessary to complete the work required by this section.

1.2.2 Sheeting and Bracing

Sheeting and bracing when shown or authorized by the Contracting Officer to be left in place, will be paid for as the number of square feet of sheeting used below finish grade.

1.2.3 Select Granular Material

Select granular material will be measured in place as the actual cubic yards replacing wet or unstable material in trench bottoms within the limits shown and in authorized over depth areas. The unit price will include furnishing and placing the granular material, excavation and disposal of unsatisfactory material, and additional requirements for sheeting and bracing, pumping, bailing, cleaning, and other incidentals necessary to complete the work. Payment for select granular material will be made in addition to the bid price for trench excavation.

1.3 DEFINITIONS

1.3.1 Degree of Compaction

Degree of compaction shall be expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D 1557.

1.4 SUBMITTALS

The following shall be submitted:

*SD-70, Test Reports*

Copies of all laboratory and field test reports shall be submitted to the Contracting Officer within 24 hours of completion of the test.

PART 2 PRODUCTS

2.1 MATERIALS

2.1.1 Satisfactory Materials

Satisfactory materials shall consist of any material classified by ASTM D 2487 as GW, GP, GC, SW, and

SP.

2.1.2 Unsatisfactory Materials

02222- 3

Unsatisfactory materials will be materials that do not comply with the requirements for satisfactory materials. Unsatisfactory materials include but are not limited to those materials containing roots and other organic matter, trash, debris, frozen materials and stones larger than two (2) inches, and materials classified in ASTM D 2487, as PT, OH, and OL. Unsatisfactory materials also include man-made fills, refuse, or backfills from previous construction.

2.1.3 Cohesionless and Cohesive Materials

Cohesionless materials will include materials classified in ASTM D 2487 as GW, GP, SW, and SP.

Cohesive materials include materials classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM and SM will be identified as cohesionless only when the fines are non-plastic.

2.1.4 Unyielding Material

Unyielding material will consist of rock and gravelly soils with stones greater than 2 inches in any dimension or as defined by the pipe manufacturer, whichever is smaller.

2.1.5 Select Granular Material

Select granular material will consist of well-graded sand (when approved), gravel, crushed gravel, or crushed stone composed of hard, tough and durable particles, and shall contain no more than 10 percent by weight of material passing a No. 200 mesh sieve and no less than 95 percent by weight passing the one (1) inch sieve. The maximum allowable aggregate size will be two (2) inches, or the maximum size recommended by the pipe manufacturer, whichever is smaller.

2.1.6 Plastic Marking Tape

Plastic marking tape shall be acid and alkali-resistant polyethylene film, six (6) inches wide with minimum thickness of 0.004 inch. Tape shall have a minimum strength of 1750 psi lengthwise and 1500 psi crosswise. The tape will be manufactured with integral wires, foil backing or other means to enable detection by a metal detector when the tape is buried up to three (3) feet deep. The tape will be of a type specifically manufactured for marking and locating underground utilities. The metallic core of the tape will be encased in a protective jacket or provided with other means to protect it from corrosion. Tape color shall be as specified in TABLE 1 and shall bear a continuous printed inscription describing the specific utility.

TABLE 1. Tape Color

Red: Electric Yellow: Gas, Oil, Dangerous Materials Orange: Telephone, Telegraph, Television, Police, and Fire Communications Blue: Water Systems Green: Sewer Systems

02222- 4

PART 3 EXECUTION

3.1 EXCAVATION

Excavation will be performed to the lines and grades indicated. Earth excavation will include removal and disposal of material not classified as satisfactory for backfilling. During excavation, material satisfactory for backfilling will be stockpiled in an orderly manner. Excavated material not required or not satisfactory for backfill will be removed from the site and will be disposed of off Government property. Grading will be done as may be necessary to prevent surface water from flowing into the excavation, and any water accumulating therein will be removed to maintain the stability of the bottom and sides of the excavation.

Unauthorized over-excavation will be backfilled in accordance with paragraph “BACKFILLING AND COMPACTION” at no additional cost to the Government.

3.1.1 Trench Excavation

The trench will be excavated as recommended by the manufacturer of the pipe to be installed. Trench walls below the top of the pipe will be sloped, or made vertical, and of such width as recommended in the manufacturer's installation manual. Where no manufacturer's installation manual is available, trench walls will be made vertical. Trench walls will be shored, cut back to a stable slope, or provided with equivalent means of protection for employees who may be exposed to moving ground or cave in as required by Occupational Safety and Health Administration. Special attention will be given to slopes which may be adversely affected by weather or moisture content. The trench width below the top of pipe will not exceed 24 inches plus pipe outside diameter (O.D.) for pipes of less than 24 inches inside diameter and will not exceed 36 inches plus pipe outside diameter for sizes larger than 24 inches inside diameter. Where recommended trench widths are exceeded, redesign, stronger pipe, or special installation procedures will be utilized by the Contractor. The cost of redesign, stronger pipe, or special installation procedures will be borne by the Contractor without any additional cost to the Government.

3.1.1.1 Bottom Preparation

The bottoms of trenches will be accurately graded to provide uniform bearing and support for the bottom quadrant of each section of the pipe. Bell holes will be excavated to the necessary size at each joint or coupling to eliminate point bearing. Stones of two (2) inches or greater in any dimension, or as recommended by the pipe manufacturer, whichever is smaller, will be removed to avoid point bearing.

3.1.1.2 Removal of Unyielding Material

Where over depth is not indicated and unyielding material is encountered in the bottom of the trench, such material will be removed four (4) inches below the required grade and replaced with suitable materials as provided in paragraph “BACKFILLING AND COMPACTION”.

3.1.1.3 Removal of Unstable Material

Where unstable material is encountered in the bottom of the trench, such material will be removed to the depth directed and replaced to the proper grade with select granular material as provided in paragraph

02222- 5

“BACKFILLING AND COMPACTION”. When removal of unstable material is required due to the fault or neglect of the Contractor in his performance of the work, the resulting material will be excavated and replaced by the Contractor without additional cost to the Government.

3.1.1.4 Excavation for Appurtenances

Excavation for manholes, catch-basins, inlets, or similar structures will be of sufficient size to permit the placement and removal of forms for the full length and width of structure footings and foundations as shown. Removal of unstable material will be as specified above. When concrete or masonry is to be placed in an excavated area, special care will be taken not to disturb the bottom of the excavation. Excavation to the final grade level will not be made until just before the concrete or masonry is to be placed.

3.1.1.5 Jacking, Boring, and Tunneling

Unless otherwise indicated, excavation will be by open cut except that sections of a trench may be jacked, bored, or tunneled if, in the opinion of the Government Representative, the pipe, cable, or duct can be safely and properly installed and backfill can be properly compacted in such sections.

3.1.1.6 Stockpiles

Stockpiles of satisfactory and unsatisfactory and wasted materials will be placed and graded as specified.

Stockpiles will be kept in a neat and well drained condition, giving due consideration to drainage at all times. The ground surface at stockpile locations will be cleared, grubbed, and sealed by rubber-tired equipment, excavated satisfactory and unsatisfactory materials will be separately stockpiled. Stockpiles of satisfactory materials will be protected from contamination which may destroy the quality and fitness of the stockpiled material.