Base Offer Price Breakdown - 1 page.xlsx
XLSX spreadsheet 23 KB Posted
- Solicitation number
- 36C24826Q0450
About this file
This is a Base Offer Price Breakdown template for a federal construction project. The spreadsheet is designed for offerors to submit pricing for the Department of Veterans Affairs solicitation 36C24826Q0450, titled "BB Install Alternate Connections for Steam and Chilled Water – Lee County" (Project Number 516-22-602). The template requires offerors to itemize labor and material costs across 26 construction divisions, including General Requirements, Concrete, Masonry, Metals, Wood and Plastic, Thermal & Moisture Protection, Doors and Windows, Finishes, Specialties, Equipment, Furnishings, Special Construction, Conveying Equipment, Fire Suppression, Plumbing, HVAC, Electrical, Communications, Electronic Safety & Security, Earthwork, Exterior Improvements, Utilities, and Transportation. Each division row requires separate labor cost and material cost entries, with automatic calculation of total division costs.
The template further requires offerors to calculate overhead as a percentage of total division costs, profit as a percentage of division costs plus overhead, and bond as a percentage of division costs plus overhead and profit. The total base offer cost is automatically computed as the sum of all divisions, overhead, profit, and bond. The solicitation, issued by the Department of Veterans Affairs Network Contracting Office on April 3, 2026, has a quote due date of May 11, 2026 at 1:00 PM EST. The project magnitude is between $1,000,000.00 and $2,000,000.00, and work will be performed at VAMC Cape Coral in Cape Coral, Florida. Offerors are instructed to provide detailed price breakdowns avoiding lump sum submissions, as this pricing template serves as the basis for government price analysis. A mandatory site visit is scheduled for April 15, 2026 at 11:00 AM EST, and offers must provide at least 120 calendar days for government acceptance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| WD-FL20260211-DATED 05-18-2026.pdf | ||
| 36C24826Q0450 0003.docx | DOCX document | |
| 36C24826Q0450 0002.docx | DOCX document | |
| Sign in Sheet 1 1.pdf | ||
| 36C24826Q0450 0001.docx | DOCX document | |
| WD-FL20260211 01-02-2026.pdf | ||
| VA NOTICE OF LIMITATIONS ON SUBCONTRACTING.pdf | ||
| PPQ -Request form.docx | DOCX document | |
| EMR 1 page.pdf | ||
| Site Map Update.pdf | ||
| DRAWINGS 516-22-602 Cape Coral Alt Steam.pdf | ||
| 36C24826Q0450_1.docx | DOCX document | |
| 01 00 00 - GENERAL REQUIREMENTS.docx | DOCX document | |
| VA ICRA.pdf | ||
| VA Handbook 6500.6 Appendix B.pdf | ||
| 516-22-602 - Cape Coral Alt Steam - Specifications.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Offer Base Offer Cost Breakdown
Project Number: N/A Edward L Roy: VA assigned project #
| Date: | |
| Project Title |
| Edward L Roy: VA assigned Project Title | Project Location | ||
| Offeror Name | |||
| Offeror Street | |||
| Offeror City | State | Zip |
Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division
| Material Cost | |
| Edward L Roy: Enter all Material Costs by Division | Total Cost |
Edward L Roy: This Column is the sum of the Division's Labor and Material Costs
| Division 1 | General Requirements | |||
| Division 2 | Existing Conditions | - 0 | ||
| Division 3 | Concrete | - 0 | - 0 | |
| Division 4 | Masonry | - 0 | ||
| Division 5 | Metals | - 0 | - 0 | |
| Division 6 | Wood and Plastic | - 0 | ||
| Division 7 | Thermal & Moisture Protect | - 0 | - 0 | |
| Division 8 | Doors and Windows | - 0 | - 0 | - 0 |
| Division 9 | Finishes | - 0 | - 0 | - 0 |
| Division 10 | Specialties | - 0 | - 0 | - 0 |
| Division 11 | Equipment | - 0 | - 0 | - 0 |
| Division 12 | Furnishings | - 0 | - 0 | - 0 |
| Division 13 | Special Construction | - 0 | - 0 | |
| Division 14 | Conveying Equipment | - 0 | - 0 | - 0 |
| Division 21 | Fire Suppression | - 0 | - 0 | - 0 |
| Division 22 | Plumbing | - 0 | - 0 | - 0 |
| Division 23 | HVAC | - 0 | - 0 | - 0 |
| Division 26 | Electrical | - 0 | - 0 | - 0 |
| Division 27 | Communications | - 0 | - 0 | - 0 |
| Division 28 | Electronic Safety & Security | - 0 | - 0 | - 0 |
| Division 31 | Earthwork | - 0 | - 0 | - 0 |
| Division 32 | Exterior Improvements | - 0 | - 0 | - 0 |
| Division 33 | Utilities | - 0 | - 0 | - 0 |
| Division 34 | Transportation Subtotal | - 0 | - 0 | - 0 |
| Division Subtotals : | $ - 0 | $ - 0 | $ - 0 |
Overhead % Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).
Edward L Roy: Date Offer Prepared/Submitted
| - 0 | ||
| Profit % | ||
| Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38). | - 0 | |
| Bond % |
Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).
Edward L Roy: Enter all Labor Costs by Division
| - 0 | ||
| Overhead/Profit Subtotals : | $ - 0 |
Edward L Roy: Sum of Overhead, Profit and Bond %.
Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0
Offerors shall provide additional price breakdown to avoiding lump sum, etc. This price offer breakdown is the overall base offer price for Government price analysis
File details come from the government source that posted it. Updated .