Amendment 0002 Question and Answer.docx
DOCX document 14 KB Posted
- Solicitation number
- BAA-RV-10-02
About this file
Question and Answer
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0003 Questions and Answers.docx | DOCX document | |
| Amendment 0002 Two Changes.docx | DOCX document | |
| Amendment 0001 Section K.docx | DOCX document | |
| Amendment 0001 Questions and Answers.docx | DOCX document | |
| BAA RV-10-02 CALL 001.docx | DOCX document | |
| CALL 001 Atch 3 SIRF Factsheet.pptx | PPTX presentation | |
| CALL 001 Atch 4 PnPSat Factsheet.docx | DOCX document | |
| CALL 001 Atch 1 STP-SIV Users Guide.docx | DOCX document | |
| CALL 001 Atch 2 IDRG.docx | DOCX document | |
| BAA RV-10-02-Final 25Feb10 Word 2003.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BAA RV-10-02, CALL 001, Amendment 0002 Space Situational Awareness Environmental Monitoring (SSAEM) Sensor Risk Reduction Question and Answer
Question: If an Offeror proposes an instrument that is intended to meet multiple objectives would that instrument be evaluated against a combination of the Size Weight and Power (SWaP) goals of the objectives met, or would some other set of goals be applied?
Answer: In the case of an instrument that is designed to meet more than one objective, the SWaP goals will be cumulative (e.g. Objective X SWaP + Objective Y SWaP + …).