Pay Item Summ - Sched of Values
| DAVID E. DISNEY TENNIS & PICKLEBALL CENTER (B-26-10) | | | | | |
| Pay Item Summary - Schedule of Values | | | | | |
| P A Y I T E M S U M M A R Y | CIVIL | | | | | |
| ITEM NO. | ITEM DESCRIPTION | UNIT | QTY | UNIT PRICE | EXTENDED AMOUNT |
| 1 | Mobilization & Demobilization | LS | 1 | | $0.00 |
| 2 | SWPPP/BMP | LS | 1 | | $0.00 |
| 3 | Clearing and Grubbing | LS | 1 | | $0.00 |
| 4 | Removal of Pavement (including sidewalks, driveways, curb and gutter, | LS | 1 | | $0.00 |
| 5 | Removal of Ex. City Utilities (Sanitary sewer & Laterals, WM & Services) | LS | 1 | | $0.00 |
| 6 | Earthwork Grading (Excavation and Embankment) | LS | 1 | | $0.00 |
| 7 | Construct 6-foot wide, thickened edge Conc. Sidewalk | LF | 320 | | $0.00 |
| 8 | Construct FDOT Standard Curb and Gutter (Type F Style) | LF | 22 | | $0.00 |
| 9 | Milling Existing Asphalt - 2" average depth | SY | 710 | | $0.00 |
| 10 | Construct 2-Inch FDOT Type FC-12.5 (Traffic Level "C") Asphalt | TN | 43 | | $0.00 |
| 11 | Construct 8-Inch Crushed Conc. Base Course | SY | 300 | | $0.00 |
| 12 | Construct 12-Inch Stabilized Subgrade | SY | 300 | | $0.00 |
| CIVIL SUB-TOTAL | | | | | $0.00 |
| UTILITY | | | | | |
| ITEM NO. | ITEM DESCRIPTION | UNIT | QTY | UNIT PRICE | EXTENDED AMOUNT |
| 13 | Permit Fees | LS | 1 | | $0.00 |
| 14 | Furnish and Install 1-inch HDPE Potable Service Laterals and Fittings | LF | 80 | | $0.00 |
| 15 | Furnish and Install 2-inch HDPE Potable Service Lines and Fittings | LF | 1,060 | | $0.00 |
| 16 | Furnish and Install Above Ground Water Spigot | EA | 6 | | $0.00 |
| 17 | Connect to Existing 1-inch Water Service | EA | 1 | | $0.00 |
| 18 | Furnish and Install 18-inch PVC C-900 Reclaim Watermain | LF | 200 | | $0.00 |
| 19 | Furnish and Install 18-inch Gate Valve | EA | 1 | | $0.00 |
| 20 | Furnish and Install 18-inch 45-Bends | EA | 3 | | $0.00 |
| 21 | Connect 18-inch Proposed Reclaim Main to existing 18" Reclaim Main | EA | 2 | | $0.00 |
| 22 | Furnish and Install 6-inch Sanitary Cleanout and Connection to Building | EA | 1 | | $0.00 |
| 23 | Furnish and Install 6-inch Sanitary Sewer Service Lateral | LF | 101 | | $0.00 |
| 24 | Connect to existing Sanitary gravity main | EA | 1 | | $0.00 |
| UTILITY SUB-TOTAL | | | | | $0.00 |
| STORMWATER | | | | | |
| ITEM NO. | ITEM DESCRIPTION | UNIT | QTY | UNIT PRICE | EXTENDED AMOUNT |
| 25 | Furnish and Install 18-inch HDPE Storm Pipe | LF | 136 | | $0.00 |
| 26 | Furnish and Install 12-inch HDPE Storm Pipe | LF | 132 | | $0.00 |
| 27 | Furnish and Install 8-inch HDPE Storm Pipe | LF | 16 | | $0.00 |
| 28 | Furnish and Install FDOT Type "C" inlet | EA | 1 | | $0.00 |
| 29 | Furnish and Install 18" MES | EA | 1 | | $0.00 |
| 30 | Furnish and Install FDOT Type "E" inlet | EA | 1 | | $0.00 |
| 31 | Furnish and Install 8" ADS Nyoplast Drainage Inlet | EA | 3 | | $0.00 |
| 32 | Furnish and Install 12" ADS Nyoplast Drainage Inlet | EA | 1 | | $0.00 |
| 33 | Furnish and Install 18" ADS Nyoplast Drainage Inlet | EA | 3 | | $0.00 |
| 34 | Furnish and Install 24" ADS Nyoplast Drainage Inlet | EA | 1 | | $0.00 |
| 35 | Stone Swale / Stone Flume | CF | 1,100 | | $0.00 |
| STORMWATER SUB-TOTAL | | | | | $0.00 |
| HARDSCAPE | | | | | |
| ITEM NO. | ITEM DESCRIPTION | UNIT | QTY | UNIT PRICE | EXTENDED AMOUNT |
| 36 | Sports Courts (Surfacing/Fencing/Windscreen/Nets) | LS | 1 | | $0.00 |
| 37 | Gateway Feature | LS | 1 | | $0.00 |
| 38 | Custom Tables | EA | 4 | | $0.00 |
| 39 | Synthetic Turf | SF | 2800 | | $0.00 |
| 40 | Sidewalk (Standard Concrete) | SF | 5900 | | $0.00 |
| 41 | Planter (Wall/Veneer/Cap/ Skate Deterents) | LF | 250 | | $0.00 |
| 42 | Synthetic Turf Concrete Edging (4'x6") | LF | 60 | | $0.00 |
| 43 | 4' Fencing (Additional to Sports Courts) | LF | 1500 | | $0.00 |
| 44 | 8' Fencing (Additional to Sports Courts) | LF | 1100 | | $0.00 |
| 45 | 10' Fencing (Additional to Sports Courts) | LF | 450 | | $0.00 |
| 46 | Gates (Pedestrian & Sliding | LS | 1 | | $0.00 |
| 47 | Landscape Edging | LF | 500 | | $0.00 |
| 48 | Bench | EA | 12 | | $0.00 |
| 49 | Waste Receptacle | EA | 2 | | $0.00 |
| 50 | Bike Rack | EA | 2 | | $0.00 |
| HARDSCAPE SUB-TOTAL | | | | | $0.00 |
| LANDSCAPE & IRRIGATION | | | | | |
| ITEM NO. | ITEM DESCRIPTION | UNIT | QTY | UNIT PRICE | EXTENDED AMOUNT |
| 51 | Small Tree | EA | 10 | | $0.00 |
| 52 | Date Palm | EA | 1 | | $0.00 |
| 53 | 1 Gal. Grasses and Groundcover | EA | 702 | | $0.00 |
| 54 | 3 Gal Shrubs | EA | 323 | | $0.00 |
| 55 | Turf | SF | 12000 | | $0.00 |
| 56 | Decorative Stone | SF | 1700 | | $0.00 |
| 57 | Pine Bark Mulch | YD | 30 | | $0.00 |
| 58 | Tree Staking | LS | 1 | | $0.00 |
| 59 | Irrigation System | LS | 1 | | $0.00 |
| LANDSCAPE & IRRIGATION SUB-TOTAL | | | | | $0.00 |
| SPORTS LIGHTING & SITE LIGHTING | | | | | |
| ITEM NO. | ITEM DESCRIPTION | UNIT | QTY | UNIT PRICE | EXTENDED AMOUNT |
| 60 | Sports Court Lighting - Outdoor Courts (F&I by others, Coordination only) | LS | 1 | | $0.00 |
| 61 | Sports Court Lighting - PEMB/Indoor Court (Furnished by others, Installation only) | LS | 1 | | $0.00 |
| 62 | Lighted Bollard | EA | 10 | | $0.00 |
| 63 | Tree Uplight | EA | 12 | | $0.00 |
| 64 | Gateway Uplight | EA | 12 | | $0.00 |
| 65 | Linear Wall Lighting | LS | 1 | | $0.00 |
| 66 | Site Electrical | LS | 1 | | $0.00 |
| SPORTS LIGHTING & SITE LIGHTING SUB-TOTAL | | | | | $0.00 |
| S C H E D U L E O F V A L U E S | BUILDING RENOVATION & NEW ADDITION | | | | | |
| ITEM NO. | ITEM DESCRIPTION | UNIT | QTY | UNIT PRICE | EXTENDED AMOUNT |
| 67 | DIVISION 01: GENERAL REQUIREMENTS | LS | 1 | | $0.00 |
| 68 | DIVISION 02: EXISTING CONDITIONS | LS | 1 | | $0.00 |
| 69 | DIVISION 03: CONCRETE | LS | 1 | | $0.00 |
| 70 | DIVISION 04: MASONRY | LS | 1 | | $0.00 |
| 71 | DIVISION 05: METALS | LS | 1 | | $0.00 |
| 72 | DIVISION 06: WOOD AND PLASTICS | LS | 1 | | $0.00 |
| 73 | DIVISION 07: THERMAL & MOISTURE PROTECTION | LS | 1 | | $0.00 |
| 74 | DIVISION 08: OPENINGS | LS | 1 | | $0.00 |
| 75 | DIVISION 09: FINISHES | LS | 1 | | $0.00 |
| 76 | DIVISION 10: SPECIALTIES | LS | 1 | | $0.00 |
| 77 | DIVISION 11: EQUIPMENT | LS | 1 | | $0.00 |
| 78 | DIVISION 12: FURNISHINGS | LS | 1 | | $0.00 |
| 79 | DIVISION 13: SPECIAL COSTRUCTION | LS | 1 | | $0.00 |
| 80 | DIVISION 22: PLUMBING | LS | 1 | | $0.00 |
| 81 | DIVISION 23: HEATING, VENTILIATION, & AIR CONDITIONING | LS | 1 | | $0.00 |
| 82 | DIVISION 26: ELECTRICAL | LS | 1 | | $0.00 |
| 83 | DIVISION 28: ELECTRONIC SAFETY & SECURITY | LS | 1 | | $0.00 |
| 84 | DIVISION 31: EARTHWORK | LS | 1 | | $0.00 |
| BUILDING RENOVATION & NEW ADDITION SUB-TOTAL | | | | | $0.00 |
| PRE-ENGINEERED METAL BUILDING | | | | | |
| ITEM NO. | ITEM DESCRIPTION | UNIT | QTY | UNIT PRICE | EXTENDED AMOUNT |
| 85 | DIVISION 01: GENERAL REQUIREMENTS | LS | 1 | | $0.00 |
| 86 | DIVISION 02: EXISTING CONDITIONS | LS | 1 | | $0.00 |
| 87 | DIVISION 03: CONCRETE | LS | 1 | | $0.00 |
| 88 | DIVISION 05: METALS | LS | 1 | | $0.00 |
| 89 | DIVISION 07: THERMAL & MOISTURE PROTECTION | LS | 1 | | $0.00 |
| 90 | DIVISION 09: FINISHES | LS | 1 | | $0.00 |
| 91 | DIVISION 10: SPECIALTIES | LS | 1 | | $0.00 |
| 92 | DIVISION 13: SPECIAL COSTRUCTION | LS | 1 | | $0.00 |
| 93 | DIVISION 22: PLUMBING | LS | 1 | | $0.00 |
| 94 | DIVISION 23: HEATING, VENTILIATION, & AIR CONDITIONING | LS | 1 | | $0.00 |
| 95 | DIVISION 26: ELECTRICAL | LS | 1 | | $0.00 |
| 96 | DIVISION 28: ELECTRONIC SAFETY & SECURITY | LS | 1 | | $0.00 |
| 97 | DIVISION 31: EARTHWORK | LS | 1 | | $0.00 |
| PRE-ENGINEERED METAL BUILDING SUB-TOTAL | | | | | $0.00 |
| SHADE STRUCTURE | | | | | |
| ITEM NO. | ITEM DESCRIPTION | UNIT | QTY | UNIT PRICE | EXTENDED AMOUNT |
| 98 | DIVISION 01: GENERAL REQUIREMENTS | LS | 1 | | $0.00 |
| 99 | DIVISION 02: EXISTING CONDITIONS | LS | 1 | | $0.00 |
| 100 | DIVISION 03: CONCRETE | LS | 1 | | $0.00 |
| 101 | DIVISION 05: METALS | LS | 1 | | $0.00 |
| 102 | DIVISION 09: FINISHES | LS | 1 | | $0.00 |
| 103 | DIVISION 10: SPECIALTIES | LS | 1 | | $0.00 |
| 104 | DIVISION 13: SPECIAL COSTRUCTION | LS | 1 | | $0.00 |
| 105 | DIVISION 26: ELECTRICAL | LS | 1 | | $0.00 |
| SHADE STRUCTURE SUB-TOTAL | | | | | $0.00 |
| P | TOTAL | $0.00 |
| CONTINGENCY 5% | $0.00 |
A TOTAL BASE BID ITEMS AMOUNT (Sum of Extended Amounts for each Base Bid Item + Contingency) $0.00
| CONTRACT TIME | | | |
| B | Contractor agrees to reach Substantial Completion in | 210 | days |
| C | Contractor agrees to reach Final Completion in | 240 | days |