This is a Firm Fixed Price contract for the design, fabrication, installation, and integration of a Low-Temperature Scanning Probe Microscope (SPM) system into an existing multiprobe ultra-high-vacuum surface analysis system at Brookhaven National Laboratory's Center for Functional Nanomaterials. The contract is between Brookhaven Science Associates, LLC (BSA) and an unnamed contractor, with contract number 475591. The overall value amount, firm fixed price, contract period of performance, contractor name and address, and BSA technical representative are all marked as "TBD." Mark Brock serves as BSA's contractual representative (mbrock@bnl.gov, 613-344-2713). The contract is a direct procurement from BSA under prime contract DE-SC0012704 with the United States Department of Energy and is not a federal contract set-aside or awarded under a federal contract vehicle.
The scope of work requires the contractor to design a custom SPM chamber with sample-transfer wobble stick and carousel, fabricate the chamber, deliver SPM components (scanner, sample stage with seven electrical contacts, removable magnet, preamplifiers, and internal electronics), and perform on-site installation and integration within an existing cryostat. All work shall comply with Statement of Work Version 3 (dated May 21, 2026) and Technical Specification cfn_LTSPM_001, Version 1 (dated March 26, 2026). Key deliverables include SPM chamber design (due 3 weeks after receipt of order), chamber fabrication (12 weeks), delivery (13 weeks), installation (14 weeks), and atomic-resolution verification testing for both STM and AFM modes (18 weeks). Payment terms are Net 30 days for large businesses/foreign entities or Net 10 days for small businesses, with invoices submitted electronically in PDF format to apinvoices@bnl.gov. Freight terms are FOB BSA National Laboratory, 98 Rochester Street, Upton, New York, with freight prepaid. The contractor must comply with detailed labeling, packing, notification, and shipping requirements, including special procedures for radioactive shipments and ocean freight 10+2 form requirements for foreign shipments. The contractor is required to provide a one-year warranty on all parts and labor, including remote diagnosis and troubleshooting within 24 hours during regular workdays. All work must comply with Brookhaven Science Associates General Terms and Conditions (Rev. 24, April 2026), Supplemental Terms and Conditions for Work by Contractors Onsite at Brookhaven National Laboratory (Rev. 24, April 2026), and BNL Quality Assurance requirements (BNL-QA-101). The contractor must provide a Job Hazard Analysis (JHA) in accordance with the supplemental terms and conditions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B1 RFQ 475591.pdf | ||
| B1 Enclosure C Quotation Pricing Sheet1.docx | DOCX document | |
| B1 Enclosure F_W8 Form.pdf | ||
| B1 Enclosure D ACH Authorization Form.pdf | ||
| B1 Enclosure E W9 2024.pdf | ||
| B1 Enclosure B AMS-FORM-050 Reps and Certs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
April 9, 2025 1 Rev. 10
BSA’s Contractual Representative
Overall Value Amount
Contract Type Contract Number
Mark Brock TBD Firm Fixed Price 475591
BROOKHAVEN NATIONAL LABORATORY
Brookhaven Science Associates
P.O. Box 5000
UPTON, L.I., N.Y. 11973-5000
Name and Address of Contractor
CONTRACT
This Contract (the “Contract”) is between the party named above (the “Contractor”), and Brookhaven Science Associates, LLC (“BSA”), the latter acting under a Prime Contract (DE- SC0012704) with the United States of America (the “Government”) represented by the United States Department of Energy (“DOE”).
I. SCOPE OF WORK
The Contractor shall provide Low-Temperature (LT) Scanning Probe Microscope (SPM).
All work shall be conducted in strict accordance with the attached BSA, Attachment A, Statement of Work Version 3, dated May 21, 2026 and Attachment B, Specification No.
cfn_LTSPM_001, Version 1, dated March 26, 2026.
A. Reports/Deliverables: The Contractor shall provide the following deliverable(s) to BSA’s Technical Representative (Tech Rep):
Deliverable Description Due Date (in # of days or weeks after contract award) Do not put a specific date in here.
SPM chamber design The Supplier will design the SPM chamber with a sample-transfer wobble stick and a sample storage carousel based on technical specifications provided by CFN staff, including sample transfer distances, orientation, frame structure, and system dimensions.
The Supplier will complete the design within 3 weeks after receipt of the order
(ARO).
April 9, 2025 2 Rev. 10
Ship Radiation Shield Box to Supplier
CFN will ship the radiation shield box to the Supplier for manufacturing modification.
1 week ARO
SPM Chamber Design Approval
CFN will review and confirm that the SPM chamber design drawings are compatible with the existing multiprobe system..
4 weeks ARO
SPM chamber fabrication The Supplier shall complete fabrication of the SPM chamber at its facility in accordance with the approved design.
12 weeks ARO
Delivery of the SPM Chamber to CFN
The Supplier will ship the completed SPM chamber to CFN.
13 weeks ARO
Installation of the SPM Chamber
The CFN Operation’s Group will assist with installation of the delivered SPM chamber into the multiprobe system.
14 weeks ARO
Relocation of the Cable Tray
The cable tray above the system will be relocated approximately 2 feet away from the system, relative to its current position, by the CFN Operation’s Group.
15 weeks ARO
Installation of the Crane Boom and cryostat
Install the existing crane boom into the multiprobe system for lifting the cryostat above the installed SPM chamber by the CFN Operation’s Group
16 weeks ARO
Delivery of SPM Components
Deliver to CFN the SPM scanner, SPM sample stage with electrical contacts and a removable magnet and its holder, all internal electronics, wiring, and related customized cables.
16 weeks ARO
Upgrade of the Scienta Omicron STM Controller with Received AFM Electronics
Installation and testing of the previously received AFM electronics in the existing MATRIX STM controller prior to Supplier’s on-site service.
18 weeks ARO
April 9, 2025 3 Rev. 10
SPM components installation and all wirings
The Supplier will perform on-site installation of all SPM components on the cryostat, including the SPM scanner, sample stage with seven additional electrical contacts, a removable magnetic field assembly, the SPM preamplifiers , all required internal electronics, and components, modified N₂ shield box , fully wire all components to the existing cryostat feedthrough, and cabling to connect the cryostat feedthroughs to the Scienta Omicron SPM controller.
18 weeks ARO
Atomic-Resolution Verification for STM and
AFM
The STM and AFM performance shall be re-tested on an Au(111) or graphite crystal by the Supplier’s field engineer, using either the supplier’s controller or the existing Scienta Omicron MATRIX SPM controller with assistance from CFN staff, to verify atomic resolution of the STM/AFM and compliance with the technical specifications.
B. Key Personnel (Reserved)
II. PERIOD OF PERFORMANCE
This Contract shall be effective as of the date executed by both parties. It shall remain in effect through _TBD_.
III. FIRM FIXED PRICE AND PAYMENT
A. Firm Fixed Price: In full consideration of the Contractor's performance hereunder, BSA shall pay the Contractor the firm fixed price of ____TBD_________ U.S.
Dollars ($0.00). The said sum shall constitute full compensation for all services and materials furnished hereunder.
B. Payment: Payment will be made upon receipt and approval of properly certified invoices.
Payment terms are Net XX (for large businesses/foreign 30 days or for small businesses 10days).
Invoices shall be directed to BSA’s Accounts Payable Department via electronic
April 9, 2025 4 Rev. 10 or regular mail.
Electronic invoice submittal is preferred by BSA. The Contractor shall make every effort to have systems in place that allow for electronic invoice transmittal.
Invoices shall be submitted in PDF format, via email, to apinvoices@bnl.gov.
Hard copy invoices, if applicable, shall be directed to BSA's Accounts Payable Department, Contracts Division, Bldg. No. 400D.
The Contractor shall indicate the final invoice by clearly marking such invoice as “FINAL.” A copy of the final invoice must be submitted to BSA’s Contractual Representative.
C. Freight: Freight terms shall be FOB BSA National Laboratory, 98 Rochester
Street, Upton, Long Island, New York. Freight Prepaid.
D. Labelling, Packing, and Notification Requirements:
More detailed instructions are available at https://www.bnl.gov/shipping/ or by emailing WarehouseOperations@bnl.gov.
Labeling Requirements
All shipments must comply with the following labelling requirements. Failure to do so may result in delayed payments. Labels must be placed on the upper left portion of the container when possible and contain:
Brookhaven National Laboratory Brookhaven’s Contract Number 98 Rochester St.
Upton, NY 11973 Box Number / Number of Boxes
Packing List Requirements
Every shipping container must include a packing list. The packing list must be clearly identified and affixed to a side of the shipping container. At a minimum, the packing list should contain the following information:
Ship from company name and address Supplier contact name Supplier telephone number Ship to address as instructed by Buyer/Contracts Specialist Brookhaven’s Contract number Part number, description, quantity, unit of measure, and corresponding BNL
Contract line number
Special Notification of Delivery
April 9, 2025 5 Rev. 10
If a shipment is heavier than 3,000 lbs., longer than 8 feet in any direction, or has a high center of gravity, it will require rigging upon receipt and the shipper shall provide a minimum of 3 days’ advance notice of delivery to BNL’s Receiving Department via email to WarehouseOperations@bnl.gov. The shipper must obtain acknowledgement from BNL that delivery notification was received. Failure to contact BNL will result in delays during delivery and any resulting demurrage will be at the shipper’s expense.
Marking of Outer Package
Each shipping container (transport package) with a gross weight equal to or greater than 400 lbs. (180 kilograms) must be marked with the center of gravity location and gross weight on at least one side or end panel. It must also meet the requirements of the latest revision of ASTM Standard D 3951, Standard Practice for Commercial Packaging. This applies to any item shipped (originally packaged or repackaged) to BNL or other locations cited in the Contract.
Protection of Material and Equipment
The Contractor shall employ procedures which ensure adequate protection of material and equipment during shipment and while in storage. Such protection shall include special environmental packaging as necessary. All items shipped (originally packaged or repackaged) to BNL or other locations cited in the PO or Contract shall comply with the requirements for preservation, packaging, and marking as stated in the latest revision of ASTM Standard D 3951-10, Standard Practice for Commercial Packaging.
Unacceptable Packing Material
Do not use vermiculite as a packaging material inside any shipments to BNL unless required by shipping regulation. “Vermiculite” as defined in this specification means the hydrous, silicate mineral classified as a phyllosilicate that has been expanded by heating. Vermiculite used as a packaging material in shipments must be determined to be free of asbestos (<1% chrysolite, amosite, crocidolite, tremolite, anthophyllite, and actinolite). All shipments containing vermiculite must be accompanied by documentation stating that the vermiculite used is certified asbestos-free. This documentation must be affixed to the outside of the package.
Radioactive Shipments
Shipments to Brookhaven National Laboratory (BNL) containing radioactive material require pre-authorization prior to shipment. Contact the following staff in the Packaging & Transportation Group for instructions:
Brett Fagan, Ext. 5645, bfagan@bnl.gov
April 9, 2025 6 Rev. 10
Kenneth Hansen, khansen2@bnl.gov Steven Woodburn, Ext. 3271, woodburn@bnl.gov
Ocean Shipments
Foreign shipments transported via ocean freight must use the 10+2 REQUIREMENTS Form (PDF). The form must be completed by the Contractor 72 hours before departure of the vessel. Send form to the following:
Interfreight Harmonized Logistics, Inc.
Fax: 516-371-6880 bnl@interfreight.net
Brookhaven National Laboratory WarehouseOperations@bnl.gov
Once the form is submitted to customs, an acceptance number will be provided.
Freight will not be loaded onto a vessel without an acceptance number. Failure to submit the 10+2 form may result in fines. It is the Contractor's responsibility to make sure the 10+2 form is submitted 72 hours prior to the vessel sailing. BSA shall withhold payment from the Contractor's final invoice for any penalties incurred by BSA due to late or incorrect ISF filing by the Contractor.
IV. AUTHORIZED REPRESENTATIVES
A. BSA’s Technical Representative: _TBD___________, telephone no. ____, ___________(email), is BSA's Technical Representative, and shall act as liaison between BSA and the Contractor in technical matters only.
B. BSA’s Contractual Representative: Mark Brock, telephone no. 613-344-2713, mbrock@bnl.gov (email), is BSA's Contractual Representative. Any change or modification in the terms and conditions of this Contract shall require the written approval of BSA's Contractual Representative or designee.
C. Contractor’s Technical Representative: _TBD_, telephone no. _____, ___________(email), is the Contractor’s authorized Technical Representative, and shall act as point of contact between BSA and the Contractor in technical matters only.
D. Contractor’s Contractual Representative: _TBD_, telephone no. __________, ___________(email), is the Contractor’s authorized Contractual Representative and shall act as liaison between BSA and the Contractor.
V. PATENT CERTIFICATION (Reserved)
VI. GOVERNMENT PROPERTY (Reserved)
VII. ADDITIONAL TERMS
April 9, 2025 7 Rev. 10
The provisions of Brookhaven Science Associates, LLC, General Terms and Conditions for Commercial Items and Services, (Rev.24, April 2026) are incorporated herein and made a part hereof.
The provisions of Brookhaven Science Associates, LLC, Supplemental Terms and Conditions for Work by Contractors Onsite at Brookhaven National Laboratory, (Rev.24, April 2026) are incorporated herein and made a part hereof.
As noted in this Contract, Supplemental Terms and Conditions for Work by Contractors Onsite at Brookhaven National Laboratory are incorporated herein. In accordance with Article 8 of these Supplemental Terms and Conditions, the Contractor is required to provide a Job Hazard Analysis (JHA).
This Contract is issued pursuant to Brookhaven Science Associates General and/or Supplemental Terms and Conditions listed above, which are incorporated herein by reference. The complete text of these terms and conditions can be viewed at PPM | Terms and Conditions. Should the Contractor have any questions and/or not have access to these terms and conditions, contact the Buyer or Contracts Specialist immediately.
The following documents attached hereto and made a part hereof, contain additional provisions of this Contract:
Attachment A Statement of Work V3 Attachment B Specification cfn_LTSPM_001, V1 Attachment C BNL QA 101
This Contract does not bind nor purport to bind the Government of the United States.
ACCEPTED:
CONTRACTOR BROOKHAVEN SCIENCE
ASSOCIATES, LLC.
By: By:
Name: Name: Mark Brock
Title: Title: Subcontracts Supervisor
Date: Date: See Electronic Signature
The Contractor shall sign and return one (1) copy of this contract via email to the attention of Mark Brock, Procurement and Property Management Division at mbrock @bnl.gov.
May 2026 Statement of Work 1
Statement of Work Title Integration of a Low-Temperature SPM into a Multiprobe UHV Surface Analysis System
Sponsor Center for Functional Nanomaterials, Brookhaven National Laboratory
Lead PI & contact info
Technical Representative
Duration of Performance
SOW Version
Xiao Tong xtong@bnl.gov
Stein, Aaron stein@bnl.gov
20 weeks
Version 3
Date May 21, 2026
Project Objective
The Center for Functional Nanomaterials (CFN) will partner with the contract to build a low-temperature (LT) scanning probe microscope (SPM) using an existing cryostat. The LT-SPM will be integrated into the existing multiprobe ultra-high-vacuum (UHV) surface analysis system at CFN. Integration of the LT-SPM with the existing room-temperature to high-temperature STM (RT HT STM) will extend STM operation over a temperature range from approximately 5 K to 500 K and will add new capabilities, including atomic force microscopy (AFM) and electrical transport measurements at ~5 K.
These enhancements will provide significant new capabilities for the user and scientific communities, particularly in quantum informatiolckln science (QIS), nanoscience, two-dimensional functional materials research, and surface science. The project is designed to preserve all original functionalities and capabilities of the system that have demonstrated excellent performance, ensuring that none of these are compromised or sacrificed, and avoiding any prolonged system shutdown that would impact the user community.
Project Scope This SOW covers the following activities.
The contract supports the design and implementation of a low-temperature scanning probe microscope (LT-SPM) and its integration into the existing multiprobe system without compromising or sacrificing any original system functionality. The LT-SPM will include a new SPM scanner, a sample stage with seven additional electrical contacts, a removable magnetic field assembly, required internal electronics, and all necessary wiring and cabling, while utilizing an existing cryostat previously purchased from the same Supplier for a prior LT-STM system. All SPM cabling will be compatible with the existing Scienta Omicron MATRIX SPM controller.
Attachment A
"This document contains BNL procurement requirements specifications for solicitation and technical evaluation. The information is high-level and does not include the details necessary for "development" or ''production" as defined under 15CFR § 772.1, 22 CFR §120.33, or 10 CFR Part 810; therefore, it does not constitute export-controlled technology or technical data."
May 2026 Statement of Work 2
A UHV SPM chamber will be designed and built by the Supplier in close collaboration with CFN staff to ensure full compatibility with the existing multiprobe system, enabling smooth sample and STM tip transfer between chambers and reliable SPM operation under UHV conditions. The Supplier will install all new components within the cryostat at CFN, including internal electronics, wiring, and cabling, and will perform system performance and quality tests on an Au(111) crystal or graphite surface to demonstrate atomic resolution for both STM and AFM.
Requirements:
Design of an SPM chamber, including a sample-transfer wobble stick and a sample-storage carousel, fully compatible with the existing multiprobe system to enable seamless inter-chamber transfer of samples and SPM tips/sensors and reliable SPM operation under UHV conditions (~ 2 × 10 ¹¹ Torr) at temperatures of 5 mK and above.
Environment, Safety and Health (ESH)
May 2026 Statement of Work 3
Electrical Safety.
On-site Work and Hazard Assessment
Schedule & Deliverables
Deliverable Description Due Date (in # of days or weeks after contract award) Do not put a specific date in here.
SPM chamber design The Supplier will design the SPM chamber with a sample-transfer wobble stick and a sample storage carousel based on technical specifications provided by CFN staff, including sample transfer distances, orientation, frame structure, and system dimensions.
The Supplier will complete the design within 3 weeks after receipt of the order (ARO).
Ship Radiation Shield Box to Supplier
CFN will ship the radiation shield box to the Supplier for manufacturing modification.
1 week ARO
May 2026 Statement of Work 4
SPM Chamber Design Approval
CFN will review and confirm that the SPM chamber design drawings are compatible with the existing multiprobe system..
4 weeks ARO
SPM chamber fabrication The Supplier shall complete fabrication of the SPM chamber at its facility in accordance with the approved design.
12 weeks ARO
Delivery of the SPM Chamber to CFN
The Supplier will ship the completed SPM chamber to CFN.
13 weeks ARO
Installation of the SPM Chamber
The will assist with installation of the delivered SPM chamber into the multiprobe system.
14 weeks ARO
Relocation of the Cable Tray
The cable tray above the system will be relocated approximately 2 feet away from the system, relative to its current position, by the CFN .
15 weeks ARO
Installation of the Crane Boom and cryostat
Install the existing crane boom into the multiprobe system for lifting the cryostat above the installed SPM chamber by the
CFN
16 weeks ARO
Delivery of SPM Components
Deliver to CFN the SPM scanner, SPM sample stage with electrical contacts and a removable magnet and its holder, all internal electronics, wiring, and related customized cables.
16 weeks ARO
Upgrade of the Scienta Omicron STM Controller with Received AFM Electronics
Installation and testing of the previously received AFM electronics in the existing MATRIX STM controller prior to on-site service.
18 weeks ARO
SPM components installation and all wirings
The Supplier will perform on-site installation of all SPM components on the cryostat, including the SPM scanner, sample stage with seven additional electrical contacts, a removable magnetic field assembly, the SPM preamplifiers , all required internal electronics, and components, modified N shield box , fully wire all components to the existing cryostat feedthrough, and cabling to connect the cryostat feedthroughs to the Scienta Omicron SPM controller.
May 2026 Statement of Work 5
Atomic-Resolution Verification for STM and
AFM
The STM and AFM performance shall be re-tested on an Au(111) or graphite crystal by the Supplier using the existing Scienta Omicron MATRIX SPM controller with assistance from CFN staff, to verify atomic resolution of the STM/AFM and compliance with the technical specifications.
18 weeks ARO
Assumptions This Statement of Work is based on the following
Brookhaven Science Associates will provide the following at the CFN:
Supplier-provided SPM scanner, sample stage with electrical contacts and removable magnet, custom-designed SPM chamber, on-site installation, full wiring, cabling, and performance testing.
CFN- provided cable tray relocation and installation of the SPM chamber, an old crane -site installation and testing.
Acceptance Testing at BNL
The Instrument shall be tested at BNL by the Contractor to demonstrate full compliance with this SOW and the Technical Specification documents. The tests listed in the SOW and the Technical Specification documents shall be conducted on the Instrument at BNL prior to final acceptance.
Commissioning
The Contractor shall be responsible for the commissioning of the Instrument. Commissioning shall be defined as all test and demonstration work performed on site at BNL.
Commissioning of the Instrument on site in its final configuration shall be performed with samples supplied by BSA and agreed to by Contractor. The Instrument shall be able to demonstrate the performance specifications as outlined in the separate Technical Specification document.
Warranty
May 2026 Statement of Work 6
The Contractor shall provide a one-of the installed and tested Instrument. A recommended spare parts list shall be available from the Contractor. Remote diagnosis and troubleshooting from Contractor shall be available upon request within 24 hours during regular workdays.
Reporting
A monthly email detailing progress, schedule, and any issues will be submitted to the CFN. A videoconference may occur in place of the email if both PI deems necessary.
Lead PI: XiaoTong xtong@bnl.gov Technical Representative: Stein, Aaron stein@bnl.gov Center for Functional Nanomaterials
Documentation Requirements Upon completion of the services, the Contractor shall provide comprehensive documentation consisting of the following:
1. Delivery and Installation Report A detailed report documenting delivery and installation, including tested qualifications and specifications of all hardware components, as well as verified operational performance qualities of the STM and qPlus- AFM systems.
2. Performance Limitation Analysis If atomic resolution cannot be achieved or if any performance issues exist, the Contractor shall provide a documented and detailed analysis of the possible causes, together with proposed corrective actions and technical solutions.
3. Operation and Maintenance Manuals Complete operation and maintenance manuals for the STM and qPlus-AFM systems, as well as procedures for filling liquid nitrogen (LN ) and liquid helium (LHe) in the cryostats, and for maintaining the specified operating temperatures.
May 2026 Statement of Work 7
Proposed System Configuration of UHV Multiprobe Surface Analysis System: LT HT SPM/XPS/UPS/LEIS/LEED/TPD/MBE/AP-HT Reaction Cel
May 2026 Statement of Work 8
May 2026 Statement of Work 9
May 2026 Statement of Work 10
December 2025 Technical Specifications 1
Technical Specifications
Title Construction and Integration of a Low-Temperature SPM into a Multiprobe UHV Surface Analysis System
Sponsor Center for Functional Nanomaterials, Brookhaven National Laboratory
Specification Number
Lead PI
& contact info
Technical Representative
Duration of Performance
Version cfn_LTSPM_001
Xiao Tong xtong@bnl.gov
Stein, Aaron stein@bnl.gov
18 weeks
V1
Date
March 26, 2026
"This document contains BNL procurement requirements specifications for solicitation and technical evaluation. The information is high-level and does not include the details necessary for "development" or "production" as defined under 15CFR § 772.1, 22 CFR §120.33, or 10 CFR Part 810; therefore, it does not constitute export-controlled technology or technical data."
General
This specification defines the requirements for a low-temperature (LT) ultra-high-vacuum
(UHV) scanning probe microscope (SPM) for the Center for Functional Nanomaterials (CFN) at Brookhaven National Laboratory. The microscope shall support simultaneous operation without cross-talk in two modes, scanning tunneling microscopy (STM) and tuning-fork-based atomic force microscopy (TF-AFM), both capable of achieving atomic resolution. The system shall operate at a base temperature of 5 K within a fully shielded, low-noise environment under UHV condition of ~10-11 torr .
The LT-SPM shall consist of an existing cryostat mounted on a new custom-made SPM chamber, within which are installed an existing spring suspension system with eddy-current damping and a modified existing liquid-nitrogen shield box providing optical
Attachment B
December 2025 Technical Specifications 2 access and effusion cell access, together with new components including an SPM scanner; a sample stage with seven additional electrical contacts; a removable magnetic field assembly; and internal electronics including STM and AFM preamplifiers, heaters, and temperature sensors. All of the above components shall be installed and fully wired to feedthroughs located at the top of the cryostat on site by the contractor. All new components and modified existing components shall be provided by the contractor.
The LT-SPM shall be compatibly integrated into an existing UHV multiprobe surface analysis system at the Center for Functional Nanomaterials (CFN) without sacrificing or disabling any original functionalities of the system. The custom-made SPM chamber shall support rapid and convenient in situ exchange and transfer of samples and probes within the chamber and interchambers.
The LT-SPM shall be controlled and operated by an existing Scienta Omicron MATRIX
SPM controller. Custom-made high-frequency cables shall be provided for connections between the cryostat feedthroughs and the SPM controller to support operation of both STM and QPlus-based AFM modes.
Both STM and AFM modes shall be tested by the contractor, with the assistance of CFN staff, to verify atomic resolution and the technical specifications stated in this document on Au(111) or graphite crystals. Testing performed in air is acceptable; however, testing in UHV and at a temperature of 5 K is preferred. If atomic resolution cannot be achieved, the contractor shall provide a documented, detailed analysis of possible causes and propose corrective actions and solutions.
STM (Scanning Tunneling Microscope)
Capabilities
STM, STS, and IETS with atomic resolution
PAN-slider–based STM head with ultra-high stability
Resolution and Stability
Vertical noise: < 1 pm
Lateral resolution: atomic (sub-angstrom)
Drift stability:
o XY: < 0.2 nm/h (guaranteed) o Z: < 0.1 nm/h (guaranteed)
Electrical Performance
Tunneling current: < 200 fA to several nA
December 2025 Technical Specifications 3
Current noise: < 10 fA (typical)
Bias voltage: ±10 V (configurable)
Minimum tunneling current set points with Femto DLPCA-200:
I < 2 pA guaranteed, I < 1 pA achieved using gain 10^9 V/A in low noise mode (max. current 10 nA).
Operating Conditions
Temperature: ~5 K to 300 K (base < 5 K)
Scan range: ~1.2 µm × 1.2 µm × 0.4 µm (at 5 K); 4.8 um x 4.8 um x 1.4 um (at 300K) Coarse motion: X - Y : +/- 2 mm; Z: 6-7 mm
The STM and AFM will be tested by the contractor’s field engineer to ensure proper operation using the Scienta Omicron MATRIX controller.
The cryostat with the SPM installed will be mounted onto the custom-made SPM chamber within the system by the CFN operational support team.
Smooth sample interchamber transfer among the SPM chamber, neighboring chambers, and inner SPM chambers will be tested by the contractor’s field engineer.
The STM and AFM performance of the system will be re-tested at approximately 5 K using an Au(111) crystal by the contractor’s field engineer, employing the Scienta Omicron MATRIX controller with the assistance of CFN staff to verify atomic resolution and ensure compliance with all specifications outlined in the technical documentation.
STS (Scanning Tunneling Spectroscopy)
Capabilities
Point STS, grid STS (CITS), and line spectroscopy
Compatible with simultaneous STM imaging
Energy Resolution and Stability
Energy resolution: < 1 meV (at < 5 K)
Bias voltage noise: < 100 µV RMS
Current noise: < 10 fA
Operating Conditions
Bias voltage: ±10 V
Tunneling current: < 200 fA to several nA
December 2025 Technical Specifications 4
Temperature: ~5 K to 300 K
AFM (Atomic Force Microscope)
Structure
Integration of a qPlus AFM into the LT-STM shall consist of the following:
Quartz tuning fork stage setup (running at 25-31 kHz with mounted tip, 32 kHz bare sensor)
Electrically isolated tunneling tip to separate the force signal from the tunneling current
External bandpass / filter / amplifier for the qPlus© signal
Additional analogue I/O board (500kHz) to provide the excitation and read the qPlus* signal into the DSP forming a PLL.
Including license for qPlus© from Prof. Giessibl (qPlus is a registered trademark of Prof. F.
Giessibl, University of Regensburg, Germany)
Including 2 qPlus© sensors including in-situ AFM preamplifier
Resolution and Stability
Vertical noise: < 1 pm ( < 2 pm @ 5 K guaranteed )
AFM oscillation amplitude:
o Typical: 50 pm o Achieved: 10 pm
Drift stability:
o XY: < 0.2 nm/h o Z: < 0.1 nm/h
Operating Conditions
Temperature: ~5 K to 300 K
Scan range: ~1.2 µm × 1.2 µm × 0.4 µm at ~5K
Constant-frequency and constant-height modes
Combined STM/AFM Performance Simultaneous STM and qPlus AFM measurements without cross-talk, allowing both tunneling current and force detection in constant frequency or constant height feedback modes.
qPlus sensors optimized for atomic resolution in both metallic and insulating samples.
December 2025 Technical Specifications 5
Atomic Manipulation
Capabilities
Lateral, vertical, and field, current -induced atomic manipulation
Single -atom positioning precision
Performance High repeatability under low-temperature UHV conditions < 1 pm Z noise: enables stable imaging and manipulation feedback at atomic resolution < 0.02 nm/h XY drift: allows controlled repositioning of individual atoms over time without drift smearing atomic sites.
Sub-nanoamp-to-femtoamp tunneling current sensitivity: critical for atomic manipulation protocols that rely on controlled tip–sample electronic interaction.
QPlus AFM oscillation amplitude ~10 pm achieved: supports combined force and tunneling based manipulation with high force sensitivity.
SPM sample holder stage
The SPM sample stage shall be equipped with seven terminal device electrodes, with a minimum of five required, including Source (S), Drain (D), back gate (BG), front gate (FG), positive voltage probe (V+), negative voltage probe (V−), and Grounding .
In combination with a sample holder incorporating an electrical contact bar, this configuration shall enable in situ electrical property measurements of samples and devices inside the scanner
The sample stage shall be capable of operation with a removable magnetic field insert.
Basic Magnetic Field
Removable permanent magnetic field assembly with a field strength of up to ~1 T Field orientation: out-of-plane Compatible with STM, STS, AFM, and atomic manipulation
Atomic resolution maintained under applied field
LHe Preamplifier with Power Converter
A fixed-gain LHe preamplifier intended for mounting at the bottom of the liquid-helium cryostat shall be provided. The preamplifier shall amplify the qPlus signal with a gain of 10⁷ V/A and shall serve as the internal preamplifier for AFM measurements. The unit shall be mounted inside the LHe radiation shield and enclosed in an aluminum housing for thermal shielding. The system shall include DC supplies for the STM section (±12 V) and the AFM section (±2 V), powered
December 2025 Technical Specifications 6 from a standard DSP-unit outlet providing ±12.8 V to ±15 V. The system shall consist of the following components:
LHe Preamplifier with chassis (P/N 1032049) Power Converter for LHe Preamplifier (P/N 1032550) UHV cabling and feedthrough for LHe Preamplifier (P/N 1032552)
Power supply cable to SPM electronics
SPM installation
The following components shall be installed at the bottom of the cryostat on site by the contractor.
STM/AFM scanner
Sample holder stage with seven additional electrical contacts Existing spring suspension system with eddy-current damping Internal electronics including STM and AFM preamplifiers
Heaters and temperature sensors Modified existing liquid-nitrogen shield box providing optical access and effusion cell access All above components shall be fully wired to feedthroughs located at the top of the cryostat
SPM chamber A custom SPM chamber shall be equipped with a rotatable, height-adjustable multi-sample storage carousel and a wobble stick for sample/tip/sensor transfer between the storage carousel and the SPM sample stage. Interchamber transfer among the SPM chamber, an adjacent analysis chamber, and an MBE chamber, whose central axes are perpendicular to each other, shall be accomplished via a magnetic transfer rod, enabling samples or tips held at the end of the rod to be transferred to the SPM sample stage or the sample storage carousel. The SPM chamber shall also incorporate ports and windows for optical access, evaporators, pumps, gauges, and sample transfer, and shall be designed and fabricated by the contractor as follows:
Port list of SPM chamber
1 x NW 250 CF SPM cryostat
1 x NW 63 CF optical access
1 x NW 40 CF optical access
1 x NW 40 CF optical access
1 x NW 63 CF optical access
1 x NW 100 CF viewport for transfer
1 x NW 63 CF viewport for transfer
December 2025 Technical Specifications 7
1 x NW 40 CF wobble stick for tip / sample transfer
1 x NW 40 CF tip / sample storage
1 x NW 160 CF ion pump
1 x NW 40 CF BA gauge
1 x NW 16 CF leak valve for gas inlet
1 x NW 40 CF effusion cell
1 x NW 40 CF QMS
1 x NW 40 CF spare
2 × CF114 (4.5-inch CF) ports, one designated for sample transfer to the adjacent analysis chamber and one reserved as a transfer port for connection to an MBE system, oriented perpendicular to the transfer direction of the analysis chamber.
Including :chamber straps for frame mounting, UHV clean, all flanges covered with aluminum foil; He-leak checked
SPM Sample storage unit
Mounted on linear feedthrough with base flange DN 40 CF (OD 2.75”)
For 7 flag-style sample holders or tip transfer tools
For 4 STM-tips or AFM tips
SPM Wobble Stick
Wobble stick with 5 degrees of freedom mounted on base flange NW 40 CF (OD 2.75”)
To enable UHV transfer of sample holders and STM tip holders between the multi-sample storage carousel, and the SPM sample stage and scanning head within the SPM chamber, as well as interchmber transfer magnetic rod in the adjacent analysis chambers, Incl. airside parking station
Modification of Radiation Shields
Modification of existing radiation shields to accommodate the new SPM scanner, including widening of window openings, modification of the shutter mechanism, and integration of existing adjustable eddy-current damping.
December 2025 Technical Specifications 8
Set of SPM cables
A set of cables connecting the feedthroughs on the LT-SPM cryostat to the existing Scienta Omicron MATRIX SPM controller shall be designed and fabricated based on CFN-provided electronics documentation, including the output and interface scheme of the SPM controller.
High-frequency cables Shall support operation of the LT-SPM scanner in both STM mode and qPlus-based
AFM modes.
The cable length shall be 10 m.
Heating and Thermocouple (TC) Cable
Custom cables for sample heating and temperature sensing shall be provided, with one end designed to connect to the feedthroughs on the existing cryostat and the other end terminated with banana connectors for the heating power supply, as well as branch connections for the temperature meter.
The cable length shall be 10 m
PPMS cables
PPMS (Physical Property Measurement System) cable with one end terminated for connection to the cryostat feedthrough and the other end terminated with seven separate BNC connectors.
The cable length shall be 10 m
CreaTec engineer on-site service visit (total 7 days)
Mounting, installation, and integration of all qPlus AFM and STM components under the existing cryostat, including the new SPM scanner; a sample stage with seven additional electrical contacts; a removable permanent magnetic field assembly; the existing spring suspension system with eddy-current damping; internal electronics including STM and AFM preamplifiers, heaters, and temperature sensors; and the modified existing radiation shields and all other associated components.
All above components shall be installed and fully wired to feedthroughs located at the top of the cryostat.
Basic functional testing of STM and AFM operation in air, including verification of atomic resolution on graphite or Au(111) surfaces in both STM and AFM modes using the existing Scienta Omicron MATRIX SPM controller. If atomic resolution cannot be achieved, the contractor shall provide a written analysis report documenting possible causes and proposed solutions.
Testing of rapid, smooth transfer of samples, SPM probes, and removable magnetic inserts among the sample storage carousel, the SPM head and sample stage within the
December 2025 Technical Specifications 9
SPM chamber, as well as among the SPM chamber and the adjacent analysis chamber and MBE chamber.
Reporting
A monthly email detailing progress, schedule, and any issues will be submitted to the CFN. A videoconference may occur in place of the email if both PI deems necessary.
XiaoTong Lead PI Center for Functional Nanomaterials xtong@bnl.gov
BROOKHAVEN NATIONAL LABORATORY
SUPPLIER QUALITY ASSURANCE REQUIREMENTS
(BNL-QA-101)
5.2/2d01e011.docx Page 1 of 6 (04/2025)
PO/Contract No.: 475591
INSTRUCTIONS: At least one sub-clause in Clause 3.1 must be selected which will automatically invoke Clauses 3.2 through 3.22 collectively on purchase orders. If applicable, the Special Requirements of Section 4.0 need to be individually selected and can be modified as required.
1.0 PURPOSE & SCOPE
1.1 This document establishes quality assurance requirements to which Suppliers to Brookhaven Science Associates (BSA) must conform when specified in the procurement documentation.
1.2 This document contains two main sections. Section 3.0 covers the general requirements that are applicable to all Suppliers.
Section 4.0 contains special quality requirements that are applicable only when specifically invoked in the procurement documentation.
2.0 DEFINITIONS
2.1 The term Procurement documentation means the purchase order
(PO), contract, subcontract, Request for Proposal (RFP), Request for Quotation (RFQ) or other written agreement with the Supplier (seller) in which the requirements of BSA are incorporated.
2.2 The term Buyer means BSA operating Brookhaven National
Laboratory, acting by and through its Procurement & Property Management Division (PPM) issuing the PO/contract.
2.3 The term Supplier (seller) means the legal entity, which is the contracting party, with the Buyer with respect to the procurement documentation.
2.4 The term article or item means a product and/or a service.
3.0 GENERAL REQUIREMENTS
Unless otherwise specified in the procurement documentation, the following General Requirements apply:
3.1 Supplier’s Quality System and Quality Requirements
The Supplier must have and maintain an effective quality system that will, as a minimum, comply with all of the requirements as designated by the following:
3.1.1 A quality system certified/registered to the ISO
9001 standard: (latest revision as of the date of issuing the procurement documentation).
3.1.2 A quality system that meets the requirements of the
ISO 9001 standard: “Quality Management Systems – Requirements” (latest revision as of the date of issuing the procurement documentation).
3.1.3 Conformance to Supplier’s/Manufacturer’s quality
program or system.
3.1.4 Other: Refer to procurement documentation, (e.g. PO, Statement of Work [SOW], specifications, drawings) for quality requirements.
NOTE: Clauses 3.2 through 3.22 apply to all POs and will be included collectively in other procurement documentation when required/specified.
3.2 Assessment by Buyer
The Supplier’s quality system is subject to assessments by the Buyer’s Representative(s) for conformance with the requirements of the PO. Supplier or Distributor must allow BSA representatives, BSA customers, and regulatory agencies right of entry into the Supplier’s facilities to determine and verify product, processes, records, personnel, material, procedures, and systems.
3.3 Change Approval
No change(s) are permitted to be made to any Buyer requirements, (e.g. part number, model number, etc.) without the prior written approval of the Buyer.
3.4 Responsibility for Subcontractors
It is the responsibility of the Supplier to impose applicable requirements from this document upon their subcontractors.
Additionally, the Buyer reserves the right to disapprove, in writing, any subcontractor. For nuclear facility requirements per NQA-1, the Supplier must incorporate NQA-1 requirements in sub-tier procurement documents.
3.5 Responsibility for Conformance
The Supplier is responsible to provide items that conform to the requirements of the PO regardless of any assessments, surveillances, inspections and/or tests by the Buyer or its representatives at either the Supplier’ or Buyer’s facility. The Buyer reserves the right to request failure analysis and corrective action for non-conforming articles or items submitted or supplied to the Buyer. The Supplier is responsible for notifying the Buyer of any recalls or alerts associated with this
PO.
When NQA-1 requirements are imposed, prior to shipment, the Supplier must report any nonconformance that cannot be corrected to full conformance and obtain approval from BNL for possible Use-As-Is or Repair dispositions. Additionally, for commercial grade services, a service performance record must be provided that documents the adequacy of the service performed to the identified critical characteristics documented in the PO/contract.
3.6 Protection of Material and Equipment
The Supplier must employ procedures that assure adequate protection of material and equipment during shipment and while in storage. Such protection must include special environmental packaging, as necessary. All items shipped (originally packaged or repackaged) to BNL or other locations cited in the PO or contract, must comply with the requirements for preservation, packaging and marking as stated in the latest revision of ASTM Standard D 3951 Standard Practice for Commercial Packaging.
3.7 Measuring and Test Equipment (M&TE) Calibration
The Supplier must calibrate any M&TE used in the fulfillment of the PO requirements against certified standards that are traceable to the National Institute of Standards and Technology (NIST), or some other recognized national or international standard, or physical constant. The Supplier must notify the Buyer of any condition found during the calibration, servicing or
Attachment C
SUPPLIER QUALITY ASSURANCE REQUIREMENTS BNL-QA-101
5.2/2d01e011.docx Page 2 of 6 (04/2025) repair of measuring and test equipment that can affect the end item requirements.
3.8 Suspect Counterfeit Parts
The Supplier shall verify the procurement source and associated documentation certifying authenticity.
Appropriate incoming inspection and / or test methods shall be used to detect potential suspect counterfeit items.
The Supplier shall flow this requirement down to all sub-tier suppliers to prevent the inadvertent use of suspect counterfeit items.
Distributors shall not modify, rework or repair any items shipped on this order.
For reference only, a list of authorized/franchised distributors for electronic components can be found at:
https://www.trustedparts.com/
* For more information refer to the following Department of Energy website: https://www.energy.gov/ehss/corporate-reporting-analysis/databases/suspectcounterfeit-and-defective-items
3.9 Electrostatic Discharge Control
Items that are susceptible/sensitive to electrostatic discharge (ESDS) must be handled and packaged to protect them from damage. Items and/or packages must be labeled to indicate the susceptibility to electrostatic discharge.
3.10 Electrical or Fire Protection Equipment, Material, and
Systems All electrical or fire protection equipment, material, and systems delivered to BNL must be certified, listed, or labeled by a Nationally Recognized Testing Laboratory (NRTL). The CE mark is NOT a recognized NRTL certification mark. (For a listing of OSHA-recognized NRTLs, refer to http://www.osha.gov/)
For electrical or fire protection equipment, material, and systems which no NRTL accepts, certifies, lists, labels, or otherwise determined to be safe, the Supplier must determine the equipment to be safe for its intended use. The determination must be made on the basis of test data. The determination and test data documents must be made available to BSA prior to or upon delivery for review and acceptance by the applicable BSA Authority Having Jurisdiction
(AHJ).
In accordance with 29 CFR 1910.147(c)(2)(iii) whenever new machines or equipment are provided with energy isolating devices, those devices must be designed to accept a lockout device.
3.11 Hoisting & Rigging Equipment
All hoisting & rigging equipment used at BNL must meet the requirements of the latest applicable OSHA Regulations and ASME B30 Series standards for design, construction, markings, and proof load testing.
When proof load testing is required by the standards, a certificate must be provided upon delivery documenting the proof test.
3.12 Deleted – requirements were added to each Purchase Order as the “Advance Notification of Delivery.”
3.13 Powered Machine Shop Equipment
All powered machine shop equipment (e.g., lathe) delivered to BNL must meet the requirements of the latest applicable OSHA 1910 Regulations (e.g., part subpart O). Equipment purchased must include an integrated NFPA 79 compliant emergency stop and an anti-restart device.
3.14 Vehicle-Mounted Elevating and Rotating Aerial Devices
All vehicle-mounted and rotating aerial devices equipment used at BNL must meet the requirements of ANSI A92.2.
3.15 Self-propelled Elevating Work Platform Equipment
All self-propelled elevating work platform equipment (e.g., scissor lift) used at BNL must meet the requirements of ANSI A92.6.
3.16 Manually Propelled Elevating Aerial Platform Equipment
All manually propelled elevating aerial platform equipment used at BNL must meet the requirements of ANSI 92.3.
3.17 Boom Supported Elevating Work Platform Equipment
All boom supported elevating work platform equipment used at BNL must meet the requirements of ANSI 92.5.
3.18 Powered Industrial Trucks and Attachments
Powered industrial trucks (e.g. forklifts, hi-lows) must meet the requirements of the ANSI/ITSDF B56 series for design, construction, markings, and test loading. Industrial truck attachments must be approved by the truck manufacturer and supplied with an attachment data plate indicating the new truck capacities.
3.19 Used Industrial Equipment
For used industrial equipment (e.g. scissor lifts, forklifts, etc.), a Certificate of Conformance as defined in clause 4.16 must be provided as objective evidence and must additionally state that all maintenance and manufacturing alerts have been screened and all required repairs and improvements have been completed. The Supplier must provide records of the last year of maintenance.
3.20 Global Harmonized System Compliance
The supplier of chemicals must deliver the chemical in full compliance with the Department of Labor, Occupational Safety & Health Administration (OSHA)’s Globally Harmonized System (GHS) Hazard Communication Standard (29CFR1910.1200), available at:
https://www.osha.gov/dsg/hazcom/HCSFinalRegTxt.html
All hazardous chemicals delivered to BNL must be accompanied by an GHS Safety Data Sheets (SDS) with the format and content specified in 29CFR1910.1200. For information on the GHS SDS see OSHA Brief- Hazard Communication Standard: Safety Data Sheets Publication 3514 available at:
https://www.osha.gov/Publications/OSHA3514.pdf
All hazardous chemicals delivered to BNL after 12/01/2015 must have a label with the elements specified in 29CFR1910.1200 [product identifier; pictograms; signal words; hazard statement(s);
precautionary statement(s); and manufacturer, importer, or distributor’s name, address, and telephone number]. For information on the GHS label, see OSHA Brief- Hazard Communication Standard: Labels and Pictograms Publication 3636 available at:
https://www.osha.gov/Publications/OSHA3636.pdf
3.21 Age/Shelf Life and Storage Control
The Supplier must have an effective storage and age control system for items where acceptability is limited by the age or manner of storage of the item. The system must include a method of identifying the expiration date on the containers in which material is delivered to the Buyer. Special handling conditions must be recorded on certifications and shipping documents covering the material delivered to the Buyer. At the time of receipt, the material must not have less than three-quarters of its shelf life remaining, without prior written approval from the Buyer for each shipment.
3.22 Product Recalls/Product Bulletins/Safety Alerts
5.2/2d01e011.docx Page 3 of 6 (04/2025)
Any and all product recall alerts, product bulletins, or safety alerts must be communicated by email directly to ProductRecallAlert@BNL.gov. Provide the Purchase Order Number(s) and names of purchasers with notification to assist BNL in locating and identifying the subject material.
4.0 SPECIAL REQUIREMENTS
The following Special Requirements are applicable only when specified in the procurement documentation or as indicated by check mark hereon. These Requirements can be modified as required.
INSTRUCTIONS: Since sub-clauses (e.g., 4.4.1) are tied to the main clause (e.g., 4.4), the requirements of the main clause will apply by default whenever any sub-clause is selected (regardless of whether the main clause was selected/checked).
4.1 Quality Assurance Program or Manual
The Supplier must submit a copy of their Quality Assurance Program or Manual with their proposal for review and evaluation.
Suppliers providing A1/A2 but without a quality system compliant with NQA-1, i.e., Commercial Grade Supplier, must follow applicable Commercial Grade Dedication Instructions as defined in the SOW.
OR
Supplier must utilize the QA Program audited and approved by BNL.
4.2 Configuration Control System
The Supplier must establish and maintain a system to assure that all end items (including spares) are of the proper configuration, and that all approved configuration changes are incorporated at the specified effectivity points. Records must be maintained to verify the configuration of each item.
4.3 Process Sheets, Travelers, etc.
The Supplier must maintain a system of process sheets, shop travelers, or equivalent means to define the sequence of manufacturing,…