This document is a Project Experience Questionnaire related to Solicitation 140P9724R0002 for the replacement of fuel tanks at the Eagle Airstrip in Alaska. The questionnaire requests information about a referenced project, including a description of the work performed, any changes to the original price or schedule, problems encountered and how they were resolved, and the successful means and methods used. The key details include:
The solicitation is for the REPLACE FUEL TANKS AT EAGLE AIRSTRIP, AK, issued by the Department of the Interior National Park Service Alaska Region. The questionnaire requests information demonstrating relevant experience for projects of a similar nature and scope. Offerors are to provide details on the referenced project, including the project title, location, description, owner, and key contractors (prime and subcontractors) and their specific roles, pricing, and performance periods. Offerors are then asked to respond to 7 questions covering the project work, relevant experience elements, changes to original price and schedule, problems encountered and resolutions, and successful means and methods.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P9724R0002_Amd_0003.pdf | ||
| B09b_Attach_A_rev5-13_0002.pdf | ||
| Sol_140P9724R0002_Amd_0002.pdf | ||
| B09b_Attach_B_rev5-13_0002.pdf | ||
| Sol_140P9724R0002_Amd_0001.pdf | ||
| Sol_140P9724R0002.pdf | ||
| B08f_Attach_D.pdf | ||
| B08j_Attach_H.pdf | ||
| B08d_Attach_B.pdf | ||
| B08i_Attach_G.pdf | ||
| B08c_Attach_A.pdf | ||
| B08e_Attach_C.pdf | ||
| B08k_Attach_I.pdf | ||
| B08g_Attach_E.docx | DOCX document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
3/21/24 Project Experience Questionnaire Solicitation: 140P9724R0002
Submit responses to the questions below that demonstrate your relevant experience successfully completing projects of a similar nature and scope as this requirement per the instructions provided in Section L of the Solicitation. Limit submittals to the quantity of projects and timeframes required in the solicitation. Expand the response sections shown below as needed to adequately address each question (this questionnaire may be expanded to multiple pages if needed).
| Offeror |
| Company Name |
REFERENCED PROJECT INFORMATION
| Project Title |
| Title |
| Project Location |
| City, State |
| Brief Project Description |
| Description |
| Project Owner |
| Company Name |
| POC: |
| First & Last Name |
| Phone: |
| (XXX) XXX-XXXX |
CONTRACTOR LIST
List Contractor(s) whose experience on the referenced project is being submitted for evaluation on this proposed project. If more than one contractor is listed (i.e. prime and subcontractors), provide information specific to that contractor.
| Contractor Name |
| Role on Referenced Project |
(Prime or Sub)
| Trade |
| Price |
(list for each contractor’s specific work) Performance Period (calendar days) (list for each contractor’s specific work)
| Original |
| Final |
| Original |
| Final |
| Sparky’s Electrical Company |
| Prime |
| Prime |
| $XXX,XXX |
| $X,XXX,XXX |
| XX |
| XX |
| ABC Plumbing & Heating, Co |
| Subcontractor |
| Plumbing & Mechanical |
| $X,XXX,XXX |
| $X,XXX,XXX |
| XXX |
| XXX |
Subcontractor
PROJECT EXPERIENCE QUESTIONS
1. Describe the project work performed by all contractors listed above.
Response
2. Identify which Project Experience elements listed in section L of the solicitation each contractor’s work addresses.
Response
3. Describe & provide reasons for any changes to the original price for the work described in question 2 above.
Response
4. Describe and provide reasons for any changes to the original schedule for the work described in question 2 above.
Response
5. Describe problems, associated with the work described in question 2 above, which were encountered and how they were resolved. Describe how the offeror’s proposal accounts for similar issues.
Response
6. Describe the means and methods, associated with the work described in question 2 above, which were successful. Would you implement the same means and methods on the proposed project? Why or why not?
Response
7. Provide any other additional project information you believe should be presented.
Response