This is a submittal list for federal contract 140P8426Q0045 that outlines documentation required prior to the post-award kick-off meeting and issuance of Notice to Proceed.

The contractor must submit twelve categories of documents before project commencement. Financial and insurance requirements include Performance & Payment Bonds and proof of Liability Insurance with Worker's Compensation. Project management submissions consist of a Project Superintendent identification letter, Detailed Project Schedule, Detailed Schedule of Values, and Quality Control Plan. Environmental and safety documentation includes a Site Specific Safety and Accident Plan, Waste and Recycle Plan, and Temporary Storm Water Pollution Prevention Plan. Additionally, the contractor must provide a Historic Preservation Treatment Plan, a list of intended subcontractors, and a comprehensive list of all required Construction Permits. For each permit, the contractor must identify the permit name, the issuing agency with jurisdiction, and specify what information the government must provide to complete the permit application.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBMITTAL LIST – 140P8426Q0045

Due Prior to Kickoff Meeting

The following submittal documents are required prior to Post-award kick-off meeting and issuance of Notice to Proceed.

1. Performance & Payment Bonds

2. Proof of Liability Insurance with Worker’s Compensation

3. Site Specific Safety and Accident Plan

4. Waste and Recycle Plan

5. Project Superintendent Identified in Letter

6. Quality Control Plan

7. Detailed Project Schedule

8. Detailed Schedule of Values

9. List of intended Subcontractors

10. Temporary Storm Water Pollution Prevention Plan

11. Historic Preservation Treatment Plan

12. List of Construction Permits, with the following information on each.

a. Name of permit

b. Agency with jurisdiction issuing the permit.

c. Information required from the Gov’t to complete the permit application.