A06_Drawings_-_Designs.pdf
PDF 12 MB Posted
- Attached to
- EO14398 PAINT PIERCE HAY AND HORSE BARN - PORE
- Solicitation number
- 140P8426Q0045
About this file
This document is a Project Specifications file for a federal construction contract with the National Park Service to repaint two historic barns at Point Reyes National Seashore in California.
The project involves surface preparation, priming, and painting of approximately 12,400 total square feet of previously painted exterior surfaces at the Pierce Ranch Hay Barn (6,300 sq ft) and Horse Barn (6,100 sq ft), plus selective in-kind replacement of deteriorated wood elements. Wood replacement work includes 119 linear feet of redwood battens (Hay Barn), 53 square feet of redwood drop siding, 32 linear feet of redwood fascia, and 47 linear feet of redwood gutters (Horse Barn). The contractor must comply with EPA lead-safe work practices for surface preparation due to presumed lead-based paint on these 19th-century structures. The project period is 90 calendar days from Notice to Proceed. Key requirements include submission of a Historic Preservation Treatment Plan, Site-Specific Safety Plan, Quality Control Plan, and Waste Management Plan prior to the preconstruction conference. All work must follow specified painting systems with latex exterior primers (MPI #6) and low-sheen topcoats (MPI #15, Gloss Level 3-4), with colors to be matched to existing coatings. The contractor must provide one gallon of each finish coat color for maintenance purposes and furnish three years of operation and maintenance documentation. Environmental protections include restrictions on vegetation disturbance, invasive species prevention, endangered species precautions, and archaeological resource protocols. Work hours are generally 8 a.m. to 5 p.m. Monday through Friday, with no weekend or holiday work without prior approval. The contract requires a one-year workmanship warranty and a 10-year manufacturer's warranty for paint products.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
POINT REYES NATIONAL SEASHORE
REPAINT HISTORIC PIERCE RANCH
HAY BARN AND HORSE BARN
PMIS 184231
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
April 16, 2026
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
Section 01 00 00 - General Requirements
Section 01 35 91 � Historic Preservation Treatment Procedures
DIVISION 02 � EXISTING CONDITIONS
Section 02 41 91 - Selective Historic Demolition
DIVISION 06 � WOOD, PLASTICS, AND COMPOSITES
Section 06 20 00 � Finish Carpentry
DIVISION 09 � FINISHES
Section 09 91 13 - Exterior Painting
APPENDIX A � SITE PLAN
APPENDIX B � PROJECT PHOTOS AND DRAWINGS
PORE - 184231
01 00 00 - 1
GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 � SUMMARY OF WORK
ITEM 1 - WORK COVERED BY CONTRACT DOCUMENTS
1.1 General: All work outlined below will be performed under a single contract.
1.2 Project Location: The work shall be performed at the Hay Barn and Horse Barn at the Historic
Pierce Ranch located at 8180 Pierce Point Road, Inverness, CA within the Point Reyes National
Seashore. Pierce Ranch is located at the end of Pierce Point Road, approximately 16 miles from the Point Reyes National Seashore�s Bear Valley Visitor Center (See Location Map).
1.3 Project Background: The purpose of this project is to prepare and paint the exterior of the historic
Pierce Ranch Hay Barn and Horse Barn to maintain a sound exterior envelope and improve the visual appearance of the building.
1.4 General Site and Building Descriptions:
A. Site: The Pierce Ranch Hay Barn and Horse Barn are contributing resources to the Pierce
Ranch Historic District and are essential components of a heavily utilized historic site. A large number of park visitors visit the Historic Pierce Ranch to be immersed in the interpretation of the regions ranching history that is illustrated by the ranch buildings and onsite interpretive panels. A number of visitors also encounter the Pierce Ranch incidentally, as the ranch is situated at the trailhead of one of the park most popular and heavily visited trailheads.
B. Pierce Ranch Hay Barn (Hay Barn): The Hay Barn is a 19th century milking barn and the largest building on the property, measuring 65 by 180 feet. The barn is a wood framed structure with vertical board siding, painted white. There are 6 exterior doors and 18 window openings The roof is a wood shingled gable of medium pitch. There are central gabled dormers at each of the main doors, located at the mid-points of each long side. The interior is a single space divided into five aisles by the structural bay system. It has a foundation of 15 transverse stone masonry walls and a continuous masonry perimeter wall.
C. Pierce Ranch Horse Barn (Horse Barn): This building is a 19th century horse barn of rectangular shape measuring 115 by 50 feet. On the east side at the north corner there is another rectangle, this one a shed roofed addition measuring 45 by 15 feet. The barn is wood framed and the primary exterior finish is horizontal board siding, painted white. There are 13 exterior doors and 19 exterior windows. The roof is of medium pitch with wood shingles. The building is located on a slight slope so that at the low corner the structure is two stories in height and has a group of 4 open stock stalls cut into the hill under the main floor. The interior is divided into a number of spaces and loft areas.
1.5 Project Scope of Work:
A. The work of this contract consists of the general construction of providing all the materials, labor, and equipment necessary to conduct surface preparation, priming, and painting of all
01 00 00 - 2
GENERAL REQUIREMENTS
previously painted exterior surfaces of the Hay Barn and Horse Barn at the Historic Pierce
Ranch. The Horse Barn includes and estimated 6,100 square feet of surface to be prepped and painted, and the Hay Barn includes an estimated 6,300 square feet of surface to be prepped and painted.
B. Typical of buildings constructed during this period, these buildings are presumed to have been coated previously with lead-based paints. It is not the NPS�s intention to abate lead-based paint under this contract. Surface preparation is to be conducted in a manner consistent with Federal, State and local regulations and best practices and guidelines for lead-related construction work (including the EPA lead-safe work practices as specified in the
Renovation, Repair, and Painting Program rule); provides for the safety of workers, park staff, residents and visitors; avoids the creation of lead hazards; and provides for the proper handling, storage and disposal of lead contaminants.
C. The work of this contract also includes select, in-kind replacement of deteriorated wood elements including sections of wood siding, fascia, and wooden gutter. The elements to be repaired/replaced are identified in annotated photographs included in Appendix C and quantities are outlined below.
a. Replace in-kind 119 linear feet of missing redwood battens (Hay Barn)
b. Replace in-kind 53 square feet of deteriorated redwood drop siding (Horse Barn)
c. Replace in-kind 32 linear feet of deteriorated redwood fascia (Horse Barn)
d. Replace in-kind 47 linear feet of deteriorated redwood gutter (Horse Barn)
D. All measurements and dimensions are approximate and must be verified in the field. All offerors are highly encouraged to attend the site visit and examine existing conditions before submitting quotes. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
All offerors will be held to have the same knowledge concerning the site and the on-ground conditions as if they had inspected the job site.
1.6 Period of Performance: Work shall be completed within 90 calendar days of the start date provided on the Notice to Proceed.
ITEM 2 � EXISTING CONDITIONS
2.1 Existing Resources:
A. Preservation of Historical and Archeological Fabric:
1. The Pierce Ranch Hay Barn and Horse Barn are contributing resources to the Pierce
Ranch Historic District.
01 00 00 - 3
GENERAL REQUIREMENTS
2. The Historic and Archeological Data Preservation Act of 1974 provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
i. If, in connection with operations under this contract, the Contractor, subcontractors, or employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological remains or data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts not specifically noted within the contract. The
Contractor shall immediately suspend all operations in the vicinity and continue work in other areas outside a 50 foot radius of discovery and notify the
Contracting Officer immediately. When safe to do so, follow up in writing with photographs within 2 days, giving the location and nature of the findings. No objects of cultural resource value may be removed. Contracting Officer will contact other entities as required.
ii. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with Changes clause.
iii. The Contractor will be responsible for protecting the cultural resources within and adjacent to the project area from damage. In addition, the Contractor will be liable for all damage to the cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or their representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
iv. The Contractor shall include this language within all subcontracts.
2.2 Existing Utilities: Contractor shall be responsible for locating and preventing damage to known utilities. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.
A. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by
Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:
a. Notify CO and COR not less than two business days in advance of proposed utility interruptions.
b. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.
01 00 00 - 4
GENERAL REQUIREMENTS
2.3 Existing Use of Site: Pierce Ranch is a popular destination for park visitors. A number of visitors also encounter the Pierce Ranch incidentally, as the ranch is situated at the trailhead of one of the park most popular and heavily visited trailheads. The trail also runs adjacent to the Hay Barn.
A. General: The contractor shall conduct his operations to ensure the least inconvenience to the public and staff. Temporary closures may be permitted upon specific written approval of the Contracting Officer.
B. General area surrounding the Project Area: The area surrounding the Project Area shall be open to the public and/or staff during construction.
a. The Main House at Pierce Ranch serves as a residence for park staff.
C. Hay Barn and Horse Barn: Project Area shall be closed to the public during construction.
The barns are used by park staff for storage and shall remain accessible to staff as needed to perform park operations.
ITEM 3 - CONTRACTOR�S USE OF SITE
3.1 Conduct of Operations: At all times the contractor and their personnel (contractors, subcontractors, and vendors) shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent. Park rules and regulations prescribed by the Park Superintendent are not limited to but can be found in the
Superintendent�s Compendium:
https://www.nps.gov/pore/learn/management/lawsandpolicies_superintendents_compendium.htm
A. Communications: Contractor shall provide the Contracting Officer and COR with methods of communications including land and/or cell phone numbers (note some areas of work have limited service coverage), email and in case of emergency 24-hour contact options for duration of time operations.
B. Signs: No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the
Contracting Officer.
C. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
D. Public/Staff Use of Site: The project site will be open to the public and/or staff during construction. The contractor shall conduct his operations to ensure the least inconvenience to the public and staff. Temporary closures may be permitted upon specific written approval of the Contracting Officer.
3.2 On-site work hours: Work shall be generally performed during normal business working hours of
8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent
01 00 00 - 5
GENERAL REQUIREMENTS
from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.
The following Federal holidays are observed by the National Park Service:
New Year�s Day
Inauguration Day
Martin Luther King, Jr�s Birthday
Washington�s Birthday
Memorial Day
Juneteenth National Independence Day
Independence Day
Labor Day
Columbus Day
Veterans Day
Thanksgiving Day
Christmas Day
Note: Any of the above holidays falling on a Saturday will be observed on the preceding
Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal
Holidays (opm.gov)
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
1. Contractor shall access the project site as outlined on the attached site map. Do not drive vehicles off road or access non-project areas without permission from the Contracting Officer or their COR.
C. Contractor shall provide appropriate matts for equipment on turf areas to reduce soil compaction. Contractor shall remediate soil compaction as directed to do so by the CO/COR.
3.4 Security and Protection Requirements:
A. Contractor shall be responsible for and protect the entire facility and construction site from notice to proceed through final acceptance.
B. Cultural Resource Protection: Every precaution shall be taken by the Contractor to prevent damage to existing historical materials, structural components of the building and to the surrounding area. Should any damage be incurred as a result of the Contractor�s operations at the site, it shall be repaired, or the damaged materials replaced in kind by the Contractor to the satisfaction of the Contracting Officer at no additional expense to the Government.
01 00 00 - 6
GENERAL REQUIREMENTS
1. Archaeological Resources: Archaeological resources are physical evidence of past human activity, including evidence of the effects of that activity on the environment.
Archaeological resources are found above and below ground and underwater. The Contractor�s Project Superintendent, or designee, will observe all ground-disturbing activities in archaeological sensitive areas. If the Contractor discovers resources, the Contractor shall stop work or relocate to a non-sensitive area and contact the Contracting Officer immediately. The Park may also have an Archaeological Monitor at the jobsite who is authorized to stop work upon discovery of archaeological resources.
Archaeological resources typically found in the park or at the project site will be discussed further at the preconstruction meeting.
C. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
1. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.
Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.
2. Vegetation Protection: Coordinate with COR to construct protection fence at drip line of any vegetation impacted within construction and grading limits. Any damaged vegetation are to be restored to original conditions via replacement at no additional expense to the Government.
i. Protection fence to be a temporary barrier, meeting the following requirements:
High-density plastic, extruded and stretched polyethylene fabric with 2 inch maximum opening pattern, highly visible orange color, 48 inches high, supported by tubular or T-shape galvanized steel posts spaced not more than 96 inches apart.
ii. Coordinate with COR prior to any vegetation removals. Consult with COR for any unplanned removals required for vegetation that interferes with construction.
Carefully supervise excavating, grading, filling, and other construction operations near vegetation to prevent damage.
3. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles (especially the tires), equipment, tools, supplies, and materials prior to packing / loading. The park requires and will perform inspections to prevent transport of non-native species PRIOR to arriving at the park entrance. Contact the Equipment Inspector at least (3) three days in advance of park entry to arrange for inspection(s) at the loading dock or point of origin.
4. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and watch for animals on or alongside road or at the jobsite. Contact Park Dispatch at immediately if animal is hit or injured or will not move off the road.
01 00 00 - 7
GENERAL REQUIREMENTS
The following measures are required to minimize disturbance to endangered wildlife:
iii. Work shall be conducted to ensure the work area is cleaned up at the end of each work shift so that loose tools, debris, and materials are not left out in a manner that could present a hazard to a listed species.
iv. Noise and vibrations of equipment shall be kept to a minimum when working in the vicinity of a listed species.
v. Hazmat spill prevention protocols shall be employed when using gas-powered equipment.
vi. Tarps shall be used to contain all paint chips and building debris from exterior surfaces that may fall to the ground.
vii. Ensure loose nails and screws do not make it to the ground when working on exterior surfaces as these can be detrimental to listed species.
D. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so
Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.
E. Temporary Enclosures: Provide and maintain temporary enclosures as required for protection of construction in progress and from access by visitors or staff, other construction operations, and similar activities.
F. Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer�s
Representative (COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of
Work.
3.5 Vehicles / Heavy Equipment:
A. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings. Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.
B. Vehicle Parking: The contractor shall park vehicles and heavy equipment in designated areas as established at the preconstruction meeting. Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts.
C. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.
D. Vehicle Exhaust: All vehicles will be properly maintained to ensure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of
01 00 00 - 8
GENERAL REQUIREMENTS
State and Federal laws regarding emissions as well as those regarding threatened and endangered species.
E. Spills: The Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. Contractor must immediately notify the Contracting
Officer of spills.
F. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.
G. Slow Vehicles: The Contractor is to notify the Contracting Officer of slow vehicles that may cause traffic delays or extended traffic lines. Vehicles that are slow are requested to enter the
Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.
H. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road). Oversized vehicles must not exceed the clearances along the Park road corridor. Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The
Contractor is to notify the Contracting Officer of oversized vehicles, scheduled dates, and estimated arrival times at the park entrance; and the identity of who is escorting the vehicle
(e.g., police, contractor, etc.). Vehicles that are oversized are requested to enter the Park
AFTER 2:00 p.m. and exit the Park BEFORE sunset.
I. Road & Weight Restrictions: All vehicle load, weight, and size limitations, as established by
State law, apply to vehicles operated on the Park road (36 CFR § 4.11). No loads heavier than the current load rating for park roads and bridges will be permitted.
3.6 Storage - Staging Areas:
A. Confine Storage of materials and equipment to the project staging area noted on the plans.
Specific storage units shall be provided by the contractor and exact location within staging area shown in appendix A below may be discussed at the preconstruction briefing. All storage units provided by the contractor shall be in a clean and acceptable condition to the
COR. Security of the materials and equipment on site is the Contractor�s responsibility.
3.7 Hauling Restrictions: Contractor shall verify and be responsible for the path accessing the site and obtaining / maintaining all local, state and federal permits/licenses associated with hauling/road requirements and dumping of materials associated with the project.
3.8 Waste Removal, Recycling, and General Housekeeping:
A. Keep project site in a neat, orderly, and safe condition at all times.
1. Contractor is responsible for providing dumpsters for waste and recycling and for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site.
01 00 00 - 9
GENERAL REQUIREMENTS
Coordinate with COR for approved dumpster locations prior to commencing construction.
2. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters.
3. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to the extent possible during this project, recycling material as much as possible within local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.
4. For all waste and recycling removals offsite, contractors shall provide estimates and/or tickets to quantify material weights and report back to the park, submit to COR for review and record filing.
3.9 Photo Documentation:
A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted preferably electronically by email or optional via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.
B. Existing Condition Images:
1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
C. Construction Progress Images:
1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
D. Completion Images:
1. Document all completed work within scope of work.
2. Maintain organized index for photos with date, description, etc..
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
3.10 Fire and Life Safety:
01 00 00 - 10
GENERAL REQUIREMENTS
A. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.
B. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
C. Store and handle hazardous materials in accordance with manufacturers and OSHA
29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration
(osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the CO, COR, and park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.11 Noise and Acoustics Management
A. Noise Control: Perform operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer or COR.
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.
Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.
Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed.
ITEM 6 - ABBREVIATIONS
6.1 The list of abbreviations, standards and organizations which may be used in/referred within the
Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under �Contracting and Procurement� labeled �NPS
Reference Standards.� https://www.nps.gov/orgs/1671/do-business-with-us.htm
ITEM 7 � SAFETY REQUIREMENTS
01 00 00 - 11
GENERAL REQUIREMENTS
7.1 The contractor shall comply with all applicable local, state, and federal safety and environmental regulations and requirements, whichever is more stringent. The contractor shall also, at a minimum:
A. Develop, implement, and comply with the Site-Specific Safety Plan (SSSP) accepted by NPS.
B. Provide and maintain worksites that minimize exposure to safety and health hazards to individuals exposed to its operations including but not limited to its employees, NPS employees, and visitors, as well as reducing risks to property, materials, supplies, and equipment.
C. Rectify all identified unsafe or unhealthful working conditions.
D. Cooperate with all informal and formal, unannounced and announced safety and health inspections by the Contracting Officer�s Representative (COR) and/or NPS Safety
Representative.
7.2 Site Specific Safety Plan Requirements: The Site Specific Safety Plan (SSSP) shall be specific to the job task and scope and shall contain the following at a minimum:
A. Signature Sheet: Title, signature and phone number of the following:
1. The plan preparer, company representative authorized to approve the plan, Project Manager/Superintendent, and Project Safety Professional
2. Background Information: Include the following:
3. Contractor
4. Contract number
5. Project name
6. Brief project description of project and work to be performed
7. A map of general work locations.
B. Responsibilities and Authority: A statement of the employer�s ultimate responsibilities for the implementation of its safety and health program. Also included is:
1. Identification and accountabilities of personnel responsible for safety at both the corporate and project level and lines of authority
2. Listing of policies and procedures regarding noncompliance with safety requirements to include disciplinary actions for violations, including written company procedures for holding managers and supervisors accountable for safety
3. The names of the competent and/or qualified person(s) and proof of competency or qualifications to meet specific OSHA competent/qualified person(s) requirements
4. Requirements that no work is to be performed unless a designated competent person is present on the worksite
01 00 00 - 12
GENERAL REQUIREMENTS
C. Subcontractors and Supplier:. If applicable, procedures for coordinating safety and health activities with the other employers on the worksite:
1. Identification of subcontractors and suppliers
2. Safety responsibilities of subcontractors and suppliers
D. Training:
1. Requirements for new employee safety and health orientation training at the time of initial hire.
2. Outline requirements for mandatory training and certification that are applicable to the project (i.e. vehicle operator, HAZWOPER training and certification, hazard communication, respiratory protection, fall protection, scaffolding, excavation, PPE).
3. Outline requirements for periodic retraining/recertification.
4. Procedures for periodic safety and health training for supervisors and employees.
5. Requirements for emergency response training.
6. Specify the name(s) of the individual(s) responsible for maintaining training records.
i. Include or make available for review actual certifications (such as: First Aid/CPR.
Lead/asbestos worker, scaffolding, fall protection, etc.) applicable to the project
E. Risk Assessment/Management: Provide a list of major work tasks or job phases and submit a
Job Hazard Analysis (JHA) or Phase Hazard Analysis (PHA) for each major task or phase
(i.e., breakdown of the task or phase in major steps, identify what hazards or safety exposures are present, then what measures will be in place to control these identified concerns).
F. Plans, Programs, and Procedures: Based on the risk assessment conducted for the identified activities that will be performed and on the mandatory OSHA compliance programs, the contractor will describe how they will address all applicable occupational hazards (e.g., protective measures/risk management) and compliance plans (i.e., Emergency response plans; Spill plans; Hazard Communication; etc.)
G. Housekeeping: Identify sanitation and job site housekeeping procedures including toilet facility requirements, hand washing requirements, drinking water availability, and any other requirements that may be applicable to this project.
H. Safety and Health Inspections: Identify specific responsibilities for minimal daily worksite safety and health inspections during the period of work including who will conduct, proof of inspector�s training/qualifications, when inspections will be completed, procedures for documentation, and recording of corrective actions.
01 00 00 - 13
GENERAL REQUIREMENTS
I. Emergency Contacts/Medical Support: Identify emergency contacts for the project and provide the name, phone number, map, and driving directions from the worksite to the nearest hospital/emergency medical facility.
J. Accident Reporting: Identify person(s) responsible for providing the following information:
1. Exposure data (man-hours worked).
2. Accident investigations, reports, and logs. The contractor will report all incidents as soon as possible but not more than 24 hours after occurrence to the COR. The contractor must conduct a thorough investigation into the incident and provide the findings and corrective actions to the COR no later than five (5) working days following the incident. Implement corrective actions as soon as reasonably possible. The following require immediate notification:
3. Fatality
4. Permanent total disability
5. Permanent partial disability
6. Overnight hospitalization of 1 or more people resulting from a single occurrence
7. NPS property damage
K. Fire Protection and Prevention: Include a list of the major workplace fire hazards specific to the project, potential ignition sources, types of fire suppression equipment or systems appropriate to the control of fire, assignments of responsibilities for maintaining the equipment and systems, and personnel responsible for controlling fuel source hazards.
L. Hazard Communication: If chemicals will be used or brought on site during the course of the project, the contractor will develop a section overviewing Hazard Communication, provide or make available documentation that employees have received Hazard Communication training, and attach or make available copies of Safety Data Sheets (SDS) for each hazardous material that will be onsite.
M. NPS Staff and Public Risk Management: Identify mitigations to protect the NPS staff and the public during the contract work (e.g., pedestrian management, traffic control, signage).
N. Severe Weather: The contractor will provide a Contingency Plan for Severe Weather. The section will outline procedures addressing each potential severe weather event that is likely to occur at the project site, such as heavy rain, high winds, fires, slides, power outages, etc.
Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure for persons and property.
7.2 Safety Meetings: At a minimum, conduct weekly "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the week.
7.3 Qualification of Employees:
01 00 00 - 14
GENERAL REQUIREMENTS
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.
7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA
29CFR 1926 Subpart E.
B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
C. All PPE will be serviceable at all times. At a minimum, maintain 2 sets of PPE including hard hats and all other Accident Prevention Plan required equipment.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park
Service Emergency Dispatch.
ITEM 8 � PROJECT MEETINGS
8.1 Preconstruction Conference: Before the start of construction, the Contracting Officer will arrange an on-site meeting with Construction Contractor. Meeting agenda will include the following as a minimum:
1. NPS Roles & Responsibilities
2. Key Contractor Personnel
01 00 00 - 15
GENERAL REQUIREMENTS
3. Coordination with Subcontractors
4. Correspondence & Submittal Procedures
5. Submittals
a. Status of Division 01 Submittals
b. Schedule & SOV
c. Safety & Accident Prevention Plan
d. Storm Water Pollution Prevention Plan
e. Status of Division 02-49 Submittals
6. Park Rules & Regulations
7. Work Hours and Weekend, Holiday, and Night Work
8. Project Information
a. Park Access & Vehicle Reporting
b. Jobsite Access & Parking
c. Staging, Storage, and Lay Down Area(s)
d. Temporary Facilities & Controls
e. Jobsite Restrictions
f. Resource Protection
g. Weather, Climate, Environmental Conditions
h. Reference Documents
i. Other Contracts / Ongoing Work
9. Labor Standards Provisions
10. Labor Interviews
11. Payroll Reports
12. Payments to the Contractor
13. Change Orders / Modifications
14. Progress Meetings
15. QC Daily Reports
16. Inspections
17. Acceptance and Rejection of Work
18. Closeout Procedures & Submittals
19. Contract Period of Performance
20. Notice to Proceed
8.2 Meeting Minutes: Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
8.3 Reporting: Distribute minutes of meetings to each party present and to other parties requiring information.
ITEM 9 � SUBMITTAL REQUIREMENTS
9.1 General Contracting Submittal Procedures:
A. General: Prepare and submit submittals required by individual Technical Specification
Sections. Types of submittals are indicated in individual specific sections.
1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using
National Park Service form CM-16 form. The form will be provided by the Contracting
Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR
9.2 Division 01 Required Submittals:
01 00 00 - 16
GENERAL REQUIREMENTS
A. Satisfactory evidence of liability insurance coverage and workman�s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award.
B. The following items are to be submitted prior to the Preconstruction Conference or as specified at the CO�s discretion. For items that were not received and approved prior to the preconstruction-conference, the timeline for the documents to be submitted will be addressed at the pre-construction conference. Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed.
Work shall not commence until written Notice to Proceed has been issued. Contracting
Officer will notify Contractor of tentative date for the Pre-Construction Conference:
1. Letter designating Project Superintendent.
2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)
3. A comprehensive breakdown of the Schedule of Values.
4. Site Specific Safety Plan (see Item 7 of this document).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
7. Quality Control Plan.
8. Waste Management Plan.
9. Temporary Storm Water Pollution Prevention Plan (SWPPP or UPPP)
10. Historic Preservation Treatment Plan
11. List of Construction Permits. Include the following information for each permit:
a. Name of Permit.
b. The Agency(ies) with Jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
9.3 Division 02-49 Submittal Documents: The following documents shall be submitted to the
Contracting Officer prior to construction start. If these documents have not been received and approved by the NPS prior to construction, the construction start date may be delayed.
A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.
1. Drawings shall be developed in AutoCAD or similar drafting software.
2. Drawings shall include details, dimensions, notational information and other data to ensure the contractor has a complete understanding of the work.
3. Drawings shall be submitted to the Contracting Officer in PDF format. Allow 2 weeks for the drawings to be reviewed by NPS staff. The Contractor shall incorporate review comments into the shop drawings and resubmit for final approval.
B. Product Data: Submit product cut sheets / material data on all products to be used for approval. Indicate the size, model, or type of each recommended product.
1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.
01 00 00 - 17
GENERAL REQUIREMENTS
C. Samples: When requested, submit a physical sample of a product or an array of color choices for approval.
1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.
D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).
E. After approving submittals, Contracting Officer and/or COR will return one copy to the
Contractor. If submittals are not approved, Contracting Officer will return all copies to
Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: All brand names noted are subject to �or equal� products. If an item in this solicitation is identified as �brand name or equal� or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government�s needs as demonstrated by the salient physical, functional, or performance characteristics that �equal� products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.
A. For each item proposed as an �approved equal,� submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Manufacturer�s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
Describe availability of maintenance service, and state source of replacement materials.
B. A request for approval constitutes a representation that General Contractor:
1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.
2. Will meet or exceed warranties for the proposed item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the
Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.
01 00 00 - 18
GENERAL REQUIREMENTS
9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.
Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of
Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.
ITEM 10 � REQUESTS FOR INFORMATION (RFIs)
10.1 General: On discovery of the need for additional information or interpretation of the Contract
Documents, the Contractor shall prepare and submit a RFI utilizing the form attached.
A. Contracting Officer will only respond to RFIs submitted by the Contractor.
B. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
10.2 RFI Form: Include a detailed, legible description of the subject or item needing information or interpretation on the RFI Form with:
A. RFI number, numbered sequentially.
B. Date.
C. RFI subject.
D. Specification Section number and title and related paragraphs, as appropriate.
E. Drawing number and detail references, if applicable.
F. Photographs or sketches if applicable.
G. Contractor's suggested resolution. If the Contractor's suggested resolution impacts the contract time or the contract sum, Contractor shall state impact in the RFI.
01 00 00 - 19
GENERAL REQUIREMENTS
10.3 Response to the RFI: The Contracting Officer will review each RFI, determine the action required, and respond accordingly.
ITEM 11 � QUALITY REQUIREMENTS
11.1 General: The Contractor is responsible for all quality control to guard against defects and deficiencies in the work. Inspect and test work as needed to ensure that the quality of materials, workmanship, construction, finishes, and functional performance are in compliance with applicable specifications, drawings, building codes and standards.
11.2 Quality Control (QC) Daily Reports: Submit quality control daily reports documenting the progress and quality of the work. The Contractor�s Quality Control Supervisor shall utilize the forms attached at the end of this Section. The submission frequency of the QC Daily Report to the contracting officer will be determined at the preconstruction meeting.
ITEM 12 - TEMPORARY FACILITIES & CONTROLS
12.1 General: The contractor will be allowed to set up temporary facilities and controls as outlined. All temporary facilities and controls shall be removed from the site before final acceptance of the work.
12.2 Temporary Utilities: The following utilities / services are available for use at the project site:
A. Electrical Power Service: Electrical power service is available from facilities at or near the project site for use on the contract without charge. Provide all connections and extensions of services in a safe manner in compliance with NEC, NEMA, and UL standards and regulations.
B. Water Service: Non-potable water service is not available from facilities at or near the project site…