This is a pricing template for equipment repair and maintenance services at Steamtown National Historic Site. The template is designed for contractors to submit cost proposals for work involving the disassembly, cleaning, inspection, repair, component replacement, balancing, assembly, testing, and adjustment of equipment, with shipping to and from the facility included as separate line items. Each work breakdown element is priced at a unit-of-effort basis (measured in equivalent units ranging from 1 to 2 EA per activity).

The price schedule accommodates three cost categories: labor-based work breakdown costs (with Rate and Amount columns for each activity), equipment costs (organized by equipment type with Hours and Rate/Cost fields), and material costs (organized by quantity and unit amount). All subtotals feed into a Grand Total line item. The template contains no pre-filled pricing information, allowing contractors to insert their proposed rates and calculate cumulative costs. No specific response dates, award information, set-asides, or contract vehicles are specified in this template document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Prepared by:

Project Name:

Work Breakdown Unit - EA Rate Amount

Shipping from STEA 1

Disassemble, clean, and inspect 2

Repair and/or replace components 2

Balance and assemble 2

Test and Adjust 2

Shipping to STEA 1

Equipment (Type) Hours Rate/Cost Amount

Material Quantity Amount Amount

Subtotal Equipment Costs

Subtotal Material Costs

Grand Total

Steamtown National Historic Site

Price Schedule

Subtotal