B08_Solicitation_-_Statement_of_Work.pdf
PDF 2 MB Posted
- Attached to
- Duncan House Roof Replacement
- Solicitation number
- 140P6426Q0012
About this file
This is a Project Specifications document for the Duncan House Roof Replacement project at Cuyahoga Valley National Park in Brecksville, Ohio. The work involves removal and replacement of three distinct roofing systems covering approximately 1,118 square feet total: the main roof (670 SF) to be replaced with metal slate shingles, the porch roof (280 SF) with asphalt 3-tab shingles, and the dormer roof (168 SF) with EPDM roofing. Associated work includes replacement of underlayment, metal flashing, drip edge, gutters, and downspouts, with up to 20 percent roof decking replacement permitted as necessary. The contractor must complete all work within 90 calendar days of Notice to Proceed, inclusive of three weather days, and maintain 100 percent watertight conditions daily. Work must be performed Monday through Friday during normal business hours (8 a.m. to 5 p.m.) without work on federal holidays or weekends unless prior written approval is obtained from the Contracting Officer.
The specifications require a site-specific Accident Prevention Plan, comprehensive safety meetings, and adherence to OSHA and NPS regulations. Key submittals include a Construction Schedule with critical path details, Schedule of Values breakdown, Accident Prevention Plan, Quality Control Plan, Waste Management Plan, shop drawings for metal flashing and trim, and product data for all roofing materials. Materials must comply with specific standards: metal slate shingles meeting ASTM specifications with 30-year warranty and hail protection; asphalt shingles with ENERGY STAR certification and Class 4 impact resistance; EPDM roofing meeting FM Approvals standards with 30-year warranty; and aluminum gutters and downspouts with mill finish in specified dimensions. The contractor must provide warranties including one-year construction warranty from final acceptance and maintain the building weather-tight throughout construction. The project is funded through the National Park Service and involves a historic structure listed on the National Register of Historic Places, requiring preservation of historical artifacts and compliance with cultural resource protection requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P6426Q0012_Amd_0001.pdf | ||
| Questions_and_Answers_-_Duncan_Roof_0001.pdf | ||
| Experience_Questionnaire.xls | XLS spreadsheet | |
| Sol_140P6426Q0012.pdf | ||
| B08_Solicitation_-__DOL_Wage_Determination.pdf | ||
| Price_Schedule_-_Roof_Replacement.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Div. 1 V. 2023-11-11 Page | 1
CUYAHOGA VALLEY NATIONAL PARK
BRECKSVILLE OHIO
DUNCAN HOUSE ROOF REPLACMENT
PMIS 342201
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
01/21/2026
Page | 2
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
Section 01 10 00 - Division 01 Short Form General Requirements
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
Section 07 31 13 - Asphalt Shingles Section 07 31 16 - Steel Roofing Shingles Section 07 53 23 - EPDM
PHOTOGRAPHS AND PHOTOGRAPHS
Appendix A – Photographs & Site Plan Appendix B - Drawings Appendix C - Submittal Log
Page | 3
SECTION 01 10 00
DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: Located in Northeastern Ohio, Cuyahoga Valley National Park consists of 33,000 acres and is situated along 22 miles of the Cuyahoga River Valley between the cities of Akron and Cleveland. The Duncan house is a rented housing structure located in the South end of the park that is occupied year-round. The current roof exhibits 3 different roof types of slate, 3-tab asphalt singles, and EPDM. Currently the roof leaks when storms occur, and the failing roof system and associated components must be replaced. For this project the existing main slate roof will be replaced with metal slate shingles. The asphalt shingled porch roof and the EPDM roof over the dormer on the north side will also be replaced with the same” in kind” materials. This roofing project will extend the asset life cycle, reduce service-wide maintenance cost, and prevent unnecessary damage to other building assets.
1.2 Work Covered by the Contract Documents:
A. Project Location: Duncan House, 4731 Riverview Road, Peninsula Ohio 44264.
1. Work consists of: This project will remove and replace the current roofing systems, gutters and downspouts on the Duncan house. The slate roof will be replaced with new metal slate shingles. The porch roof will be replaced with new 3-tab asphalt shingles. The dormer will be replaced with new EDPM roofing system. Roof work will also include removal and installation of new underlayment, metal flashing, drip edge, gutters, and downspouts.
a. Duncan House Main Roof (all quantities and measurements are approximate)
i. 670 SF of metal slate shingles
ii. 670 SF of underlayment
iii. 32 LF of ridge cap
iv. 112 LF of drip edge
v. 5 LF of counter flashing (chimney)
vi. 38 LF of flashing (dormer)
vii. 64 LF of 6” half round gutters, mill finish aluminum, standard bead
viii. 48 LF of 4” smooth round downspouts, mill finish aluminum
ix. Gutter and downspout accessories including mill finish aluminum endcaps, elbows, outlets, downspout brackets, and circle and shank hangers
x. Leaf guards on all gutters
xi. 1 permanent roof top fall protection anchor
b. Duncan House Porch Roof (all quantities and measurements are approximate)
i. 280 SF of asphalt 3-tab shingles
ii. 280 SF of underlayment
iii. 28 LF of flashing
Page | 4
iv. 48 LF of drip edge
v. 28 LF of 6” half round gutters, mill finish aluminum, standard bead
vi. 10 LF of 4” smooth round downspouts, mill finish aluminum
vii. Gutter and downspout accessories including mill finish aluminum endcaps, elbows, outlets, downspout brackets, and circle and shank hangers
viii. Leaf guards on all gutters
c. Duncan House Dormer (all quantities and measurements are approximate)
i. 168 SF EPDM roofing
ii. 38 LF of drip edge
iii. 1 vent boot
iv. 14 LF 6” half round gutters, mill finish aluminum, standard bead
v. 3 LF 4” smooth round downspouts, mill finish aluminum
vi. Gutter and downspout accessories including mill finish aluminum endcaps, elbows, outlets, downspout brackets, and circle and shank hangers
vii. Leaf guards on all gutters
2. Replacement of up to 20% of existing roof decking, as necessary. Limits of replacement to be determined by contractor and COR after removal of existing roof system. Any roof decking needing replaced will be replaced in kind.
3. Temporary roofing during construction where required. Temporary roofing shall maintain the project roof is watertight and able to prevent leaks and damage to the building and structure until the re-roofing work is completed. Contractor is to make sure that at the completion of work each day the projects roof is 100% watertight.
4. Retain 25 SFf existing slate roof for turnover to COR.
5. Contractor receiving award is expected to field verify conditions prior to commencing work.
B. All work will be performed under a single contract.
C. Period of performance: Work shall be completed within 90 calendar days of the start date provided on the Notice to Proceed. The period of performance is inclusive of 3 weather days.
a. Clarification: The Notice to Proceed will be issued with a period of performance that is all inclusive of supply lead times, material deliveries, decommissioning, installation, anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to Proceed. If weather impacts project beyond typical average weather patterns, contractor shall provide documentation in request for additional days.
1.3 Existing Condition Protections:
A. Preservation of Historical and Archeological Fabric:
i. The Historic and Archeological Data Preservation Act of 1974 provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
Page | 5
ii. IF, in connection with operations under this contract, the Contractor, subcontractors, or employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the discovery and notify the Contracting Officer immediately, when safe to do so, and follow up in writing within 2 days, giving the location and nature of the findings. No objects of cultural resource value may be removed. Contracting Officer will contact other entities as required.
iii. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with Changes clause.
iv. The Contractor will be responsible for protecting the cultural resources within and adjacent to the project area from damage. In addition, the Contractor will be liable for all damage to the cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or their representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
v. The Contractor agrees to include this language within all subcontracts.
B. The structure involved in the work of this Contract is a designated historic structure listed in the National Register of Historic Places. Every precaution shall be taken by the Contractor to prevent damage to existing historical materials, structural components of the building and to the surrounding area. Should any damage be incurred as a result of the Contractor’s operations at the site, it shall be repaired, or the damaged materials replaced in kind by the Contractor to the satisfaction of the Contracting Officer at no additional expense to the Government.
i. Should Contractor’s operations or employees uncover or find any historic artifacts or archeological remains not specifically noted within the contract, the Contractor shall suspend operations at the site of discovery; notify the Contracting Officer immediately of the findings and continue operations in other areas outside a 50-foot radius of discovery.
ITEM 2 – PROTECTING EXISTING UTILITIES
2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative
(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.
2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.
2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:
Page | 6
A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.
B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
https://www.nps.gov/cuva/learn/management/superintendents-compendium.htm
A. Communications: Contractor shall provide the Contracting Officer and COR with methods of communications including land and/or cell phone numbers (note some areas of work have limited-service coverage), email and in case of emergency 24-hour contact options for duration of time operations.
B. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
C. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
D. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.
3.2 On-site work hours: Work shall be generally performed during normal business working hours of
8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.
A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.
The following Federal holidays are observed by the National Park Service:
New Year Day Martin Luther King, Jr’s Birthday Washington’s Birthday Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day
Page | 7
Christmas Day
B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding
Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays (opm.gov).
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
C. Do Not disturb site outside of noted disturbance area, including earthwork and clearing of vegetation, to: N/A
D. Utilities
1. General: Cost or use charges for temporary facilities shall be included in the Contract
Sum as required.
2. Water Service: Water from existing water system is not available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.
3. Electric Power Service: Electric power from existing system is not available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.
4. Waste Operation:
a. Toilets: Contractor must provide toilets for contractor personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan. Waste Removal / Recycling: Contractor is responsible for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site. Locate as shown on site plan or coordinated with COR.
E. Security and Protection facilities:
1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental
Page | 8 regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.
Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.
3. Tree and Plant Protection: N/A
4. Pest Control: N/A
5. Temporary Enclosures: N/A
6. Site Enclosure Fence: N/A
7. Hot Work Permit: N/A
3.4 Storage - Staging Areas:
A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. Specific storage units shall be provided by the contractor and exact location within staging area may be discussed at the preconstruction briefing. All storage units provided by the contractor shall be in a clean and acceptable condition to the COR. Security of the materials and equipment on site is the Contractor’s responsibility.
3.5 Preservation of Natural Features: N/A
3.6 Hauling Restrictions: N/A
3.7 Housekeeping:
A. Keep project neat, orderly, and in a safe condition at all times.
1. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters
2. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.
3. Contractor shall sweep entire area around building to 20’ beyond building perimeter with a magnet at the end of each workday that removal or nailing activities take place.
Contractor shall complete a minimum of 1 sweep of entire project site with magnets prior to demobilizing.
Page | 9
3.8 Occupancy Requirements for Buildings:
A. Existing Buildings:
1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO or COR.
b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
B. New /Existing Buildings Unoccupied: N/A
3.9 Photo Documentation:
A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted preferably electronically by email or optional via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.
B. Existing Condition Images:
1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
C. Construction Progress Images:
1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
D. Completion Images:
1. Document all completed work within scope of work.
2. Maintain organized index for photos with date, description, etc.
Page | 10
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
3.10 Fire and Life Safety:
C. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.
D. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
E. Store and handle hazardous materials in accordance with manufacturers and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the CO, COR, and park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.11 Noise and Acoustics Management
A. Contractor shall not have personal radios or other media sources and they shall not be broadcast within NPS property.
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.
Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.
Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed. Contractor is responsible to verify all NPS quantities and material estimates to complete the project.
ITEM 6 - ABBREVIATIONS
6.1 The list of abbreviations, standards and organizations which may be used in/referred within the
Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm
ITEM 7 - ACCIDENT PREVENTION
Page | 11
7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.
7.2 Submittals:
A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name and qualifications of responsible supervisor to carry out the program.
2. First aid and rescue procedures.
3. Training, both initial and continuing.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample JHA template may be provided upon request.
5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
6. Contractor to identify nearest location of medical facility for emergencies
7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.
8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.
B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute
"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.
7.3 Qualification of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.
7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
Page | 12
7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA 29CFR 1926 Subpart E.
B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
C. All PPE will be serviceable at all times. At a minimum, maintain 2 sets of PPE including hard hats and all other Accident Prevention Plan required equipment.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate, if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park Service Emergency Dispatch.
ITEM 8 - PRECONSTRUCTION CONFERENCE
8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.
ITEM 9 - SUBMITTALS
9.1 General Contracting Submittal Procedures:
A. General: Prepare and submit submittals required by individual Technical Specification Sections. Types of submittals are indicated in individual specific sections.
1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using
National Park Service form CM-16 form. The form will be provided by the Contracting Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR
B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.
Page | 13
C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items are to be submitted prior to the Preconstruction Conference or as specified at the CO’s discretion. The timeline for the documents to be submitted will be addressed at the pre-construction conference for those items that were not received and approved prior. Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed.
Work shall not commence until written Notice to Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference:
1. Letter designating Project Superintendent.
2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention (Safety) Plan (see section 7 of this document).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
7. Quality Control Plan.
8. Waste Management Plan: Contractor is required to provide and maintain dumpsters for construction debris through the duration of the project. Location of these dumpsters is identified on the attached site plan.
9.2 Project Submittal Process (Shop Drawings, Product Data, and Samples): Contracting Officer will provide sample cover sheet, and a list of required submittals is included in each technical specification or attached at the end of this document.
A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.
1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.
B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.
1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.
C. Samples: Submit 2 color samples 4” x 6” minimum in size for all product color selections.
Paint samples shall be actual paint finish drawdown for all project colors.
1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.
D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).
Page | 14
E. After approving submittals, Contracting Officer and/or COR will return one copy to the Contractor. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: All brand names noted are subject to ‘or equal’ products. If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.
A. For each item proposed as an “approved equal,” submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendors.
5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
Describe availability of maintenance service and state source of replacement materials.
B. A request for approval constitutes a representation that General Contractor:
1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.
2. Will meet or exceed warranties for the proposed item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the
Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.
9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.
Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in
Page | 15 a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.
ITEM 10 – TEMPORARY SERVICES
10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.
11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.
B. If the work is not determined to be complete following the final inspection, the Contracting Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the
CO.
Page | 16
D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.
E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
F. Disposition of any permits and warranties required by the specifications in this section.
11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of
Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.
B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.
C. Information shall include operation and maintenance manuals for each warranted product.
ITEM 12 - DEFINITION OF CONTRACT LINE ITEMS
12.1 Summary
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut off points where one item ends, and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
12.2 List of Contract Line Items
B. Contract Line-Item No.01 Remove and Replace Roof Systems
1. This item consists of removal of existing roofing systems and replace with roofing systems as specified with associated substrate and drainage improvements.
2. Payment will be made per the contract and percentage of completion level.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXCUTION (NOT USED)
END OF SECTION
Page | 17
SECTION 073113
ASPHALT SHINGLES
PART 1 - GENERAL
1.1 SCOPE OF WORK
C. Project Location: Duncan House 4731 Riverview Rd. Peninsula OH 44264
D. Building(s) Name/Identifier: Duncan House/25671
E. Work consists of the following:
1. Full tear-off of roof system at areas indicated on Drawings or in Photographs provided. Removal of existing roofing system down to existing roof deck.
a. Removal of existing roof system down to existing roof deck includes 100% removal of nails and protrusions.
2. Re-cover preparation of entire roof area where tear-off occurs, including installation of new roofing system.
3. Removal of flashings and counter flashings.
4. Temporary roofing during construction where required. Temporary roofing shall maintain the project roof is watertight and able to prevent leaks and damage to the building and structure until the reroofing work is completed. Contractor is to make sure that at the completion of work each day the projects roof is 100% watertight.
5. Remove and replace the existing roof system and associated roof flashings, down to deck and patch any openings in the roof decking to the nearest rafters to securely nail to structure as required before installing the new roof system, associated metal roof flashings and trims.
Replace existing roof gutters and downspouts.
6. National Park Service (NPS) requires the existing roof decks to be walked after demolition has been completed with the onsite Contracting Office Representative (COR) or designated Project Inspector prior to installation of any new roof materials to ascertain if any water penetration has caused deterioration or corrosion of the existing roof decking which are to remain. If there are areas of concern the COR may require the Contractor to perform pull out tests to determine if the existing decking in question can remain or if it will need to be replaced. This can include visible areas of water damage or insect related damage. Testing and replacement of these types of unforeseen damaged areas will be by Change Order if required.
D. Roof Area:
1. Roof area for asphalt shingle replacement is 280 SF with approximately 28 LF of gutters and 10 LF of downspouts.
2. Note the Contractor is encouraged to field verify roof dimensions prior to bidding.
1.2 SUMMARY
A. Section Includes:
Page | 18
1. Selective Demolition.
2. Glass-fiber-reinforced asphalt shingles.
3. Underlayment materials.
4. Sheet metal flashing and trim.
5. Gutter and downspouts.
1.3 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1.4 ACTION SUBMITTALS
A. Product Data: For the following:
1. Asphalt shingles.
2. Underlayment materials.
3. Asphalt roofing cement.
4. Elastomeric flashing sealant.
5. Sheet metal flashing and trim.
B. Sustainable Design Submittals:
1. Product Test Reports: For roof materials, documentation indicating that roof materials comply with Solar Reflectance Index requirements.
C. Shop Drawings: For sheet metal flashing and trim.
D. Samples: For each exposed product and for each color and blend specified.
1.5 INFORMATIONAL SUBMITTALS
A. Product test reports.
B. Research reports for synthetic underlayment.
C. Sample warranty.
1. Material warranty.
2. Roofing installer warranty and shingle manufacturer certification.
Page | 19
1.6 SUBMITTAL COORDINATION
A. Submittal List: A submittal list has been attached to the end of this Specification Section. The intent is to provide an overall summary of the submittal requirements and not a comprehensive list. The requirements of the individual Specification Sections, terms and conditions of the Contract still apply regardless of what is shown on the submittal list.
1.7 CLOSEOUT SUBMITTALS
A. Maintenance data.
1.8 QUALITY ASSURANCE
A. Installer Qualifications: An authorized installer who is trained and approved by manufacturer.
1.9 WARRANTY
A. Materials Warranty: Manufacturer agrees to repair or replace asphalt shingles that fail within specified warranty period.
1. Materials Warranty Period: 30 years from date of final acceptance, prorated, with first 10 years non-prorated.
2. Wind-Speed Warranty Period: Asphalt shingles will resist blow-off, or damage caused by wind speeds of up to 130 mph (58.1 m/s) for 15 years from date of final acceptance.
3. Algae-Resistance Warranty Period: Asphalt shingles will not discolor for 20 years from date of final acceptance.
B. Roofing Installer’s Warranty: Roofing installer to provide and sign a Roofing Installer’s Warranty in which Installer agrees to repair or replace components of asphalt-shingle roofing that fail in materials or workmanship within specified warranty period.
1. Warranty Period: Five years from date of final acceptance.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Exterior Fire-Test Exposure: Provide asphalt shingles and related roofing materials identical to those of assemblies tested for Class A fire resistance in accordance with American Society of Testing Materials (ASTM) E108 or UL 790 by Underwriters Laboratories or another testing and inspecting agency acceptable to authorities having jurisdiction. Identify products with appropriate markings of applicable testing agency.
B. Wind Resistance: Provide asphalt shingles that comply with requirements of ASTM D7158/D7158M, Class H.
C. Energy Performance, ENERGY STAR: Provide asphalt shingles that are listed on the DOE's "ENERGY STAR Roof Product List" for steep-slope (2:12 or greater) roof products.
Page | 20
D. Solar Reflectance Index (SRI): Three-year-aged SRI not less than 0.15 or initial SRI not less than
0.25 when calculated according to ASTM E 1980, based on testing identical products by a qualified testing agency.
E. Shingles:
1. Mineral granular-surfaced asphalt shingles.
a. Self-sealing.
b. Square tab.
c. Fungus-resistant.
d. Impact resistant shingles, Class 4.
e. Type I, weighing not less than 290 pounds per 100 square feet.
2.2 GLASS-FIBER-REINFORCED ASPHALT SHINGLES
A. Laminated-Strip Asphalt Shingles: ASTM D3462/D3462M, laminated, multi-ply overlay construction; glass-fiber reinforced, mineral-granule surfaced, and self-sealing.
1. Basis of Design: Atlas Pinnacle Pristine High-Performance Shingles.
2. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Atlas Molded Products; a Division of Atlas Roofing Corporation.
b. CertainTeed Corporation.
c. GAF.
d. Owens Corning.
e. Tamko Building Products, Inc.
f. Other Approved Equals.
3. Strip Size: Manufacturer's standard approximately 42 inch.
4. Algae Resistance: Granules resist algae discoloration.
5. Impact Resistance: Underwriters Laboratory (UL) 2218, Class 4.
6. Fire Resistance: UL 790 for Class A.
7. Color and Blends: As selected by COR from manufacturer's full range.
B. Hip and Ridge Shingles: Manufacturer's standard units to match asphalt shingles.
2.3 UNDERLAYMENT MATERIALS
A. Synthetic Underlayment: UV-resistant polypropylene, polyolefin, or polyethylene polymer fabric with surface coatings or treatments to improve traction underfoot and abrasion resistance;
evaluated and documented to be suitable for use as a roof underlayment under applicable codes by a testing and inspecting agency acceptable to authorities having jurisdiction.
1. Basis of design: RhinoRoof U20, as manufactured by InterWrap, Inc.
a. Product requirements include the following minimum characteristics listed below:
1) Permeability ASTM E96 - .05 perms.
2) Water Transmission ASTM D4869 – pass.
Page | 21
3) Tear Strength ASTM D4533 – MD 30 lbs (14 kg).
4) Tensile Strength ASTM D751 – MD 80 lbs (36 kg).
5) Bursts Strength ASTM D751 – 150 psi (1033 kPa)
6) Nominal Thickness ASTM D1777 – 6 mils (0.15 mm).
7) Width Per Roll – 36 inches.
2. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Atlas Roofing Corporation.
b. CertainTeed Saint-Gobain.
c. GAF.
d. Owens Corning.
e. Tamko Building Products, Inc.
f. Other Approved Equals.
3. Grace Ice & Water Shield; Grace Construction Products.
4. WinterGuard Waterproofing underlayment; CertainTeed.
5. RhinoRoof Granulated Self-Adhered underlayment.
6. Other Approved Equals.
2.4 VENTS – N/A
2.5 ACCESSORIES
A. Asphalt Roofing Cement: ASTM D4586/D4586M Type II, asbestos free.
B. Roofing Nails: ASTM F1667, aluminum, stainless steel, copper, or hot-dip galvanized-steel wire shingle nails, minimum 0.120-inch- (3-mm-) diameter, sharp-pointed, with a 3/8- to 7/16-inch- (10- to 11-mm-) diameter flat head and of sufficient length to penetrate 3/4 inch (19 mm) into solid wood decking or extend at least 1/8 inch (3 mm) through sheathing less than 3/4 inch (19
mm) thick.
1. Where nails are in contact with metal flashing, use nails made from same metal as flashing.
C. Synthetic Underlayment Fasteners: As recommended in writing by synthetic-underlayment manufacturer for application indicated.
2.6 SELECTIVE DEMOLITION
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:
1. Full Roof Tear-off: Removal of existing roofing system down to existing roof deck or structure.
2. Temporarily protect existing roofing system and components that are to remain as required from damage.
3. Existing roof drains and roof drainage shall be protected during each stage of reroofing, and roof-drain plugs shall be installed when demolition is taking place so that debris cannot
Page | 22 be lost down the drains. Contractor shall remove all drain plugs when demolition is completed in the area affecting the drain.
4. Do not remove more roof than can be replace in a day, and the roof will be made watertight each night.
5. Remove debris and materials so as not to impose excessive loads on supporting roof, structure or framing.
6. Dispose of demolished items and materials promptly.
B. Removed and Reinstalled Items:
1. Clean and repair items to functional condition adequate for intended reuse.
2. Reinstall items in locations indicated, or in original locations as required. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.
3. Lightning protection to be removed and reinstalled by a certified installer.
C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition.
D. Inspect deck after tear-off of roofing system.
1. If broken or loose fasteners that secure deck panels to one another or to structure are observed, or if deck appears or feels inadequately attached, immediately notify COR.
a. Do not proceed with installation until directed by COR.
2. If deck surface is unsuitable for receiving new roofing or if structural integrity of deck is suspect, immediately notify COR.
a. Do not proceed with installation until directed by COR.
E. Disposal of Demolished Materials:
1. General: Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain NPS's property, remove demolished materials from Project site.
a. Do not allow demolished materials to accumulate on-site.
b. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
2. Burning: Do not burn demolished materials.
3. Disposal: Transport demolished materials off NPS's property and legally dispose of them.
F. Cleaning:
1. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.
2.7 SHEET METAL FLASHING AND TRIM
A. Performance Requirements:
Page | 23
1. General: Sheet metal flashing and trim assemblies shall withstand wind loads, structural movement, thermally induced movement, and exposure to weather without failure due to defective manufacture, fabrication, installation, or other defects in construction. Completed sheet metal flashing and trim shall not rattle, leak, or loosen, and shall remain watertight.
2. Sheet Metal Standard for Flashing and Trim: Comply with National Roofing Contractors Association’s (NRCA's) "The NRCA Roofing Manual" and Sheet Metal and Air Conditioning Contractors National Association’s (SMACNA's) "Architectural Sheet Metal Manual" requirements for dimensions and profiles shown unless more stringent requirements are indicated.
3. Single Ply Roofing Industry (SPRI) Wind Design Standard: Manufacture and install copings and roof edge flashings tested according to SPRI ES-1 and capable of resisting the following design pressure:
a. Design Pressure: 30 psf vertical design pressure.
4. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes to prevent buckling, opening of joints, overstressing of components, failure of joint sealants, failure of connections, and other detrimental effects. Base calculations on surface temperatures of materials due to both solar heat gain and nighttime-sky heat loss.
B. Sheet Metal:
1. General: Protect mechanical and…
This is the start of the file's text. The full file is on GovTribe.