B08_Solicitation_Attachment_3_Price_Schedule.docx
DOCX document 18 KB Posted
- Attached to
- REPLACE FAN COILS AT PARK HQ Federal contract opportunity
- Solicitation number
- 140P6324Q0005
About this file
This price schedule document outlines the requirements for replacing fan coil units at Mount Rushmore National Monument. The contractor is expected to remove and properly dispose of 28 existing fan coil units and 6 unit ventilators. They must then provide and install brand name or equal Trane replacement units. The schedule also requires the contractor to include pricing for all applicable taxes, hourly rates for HVAC technicians, and any other charges. The total contract cost must be provided.
The related federal contract opportunity is a commercial service Request for Quotes to conduct HVAC services at Mount Rushmore National Monument, solicitation number 140P6324Q0005, issued by the Department of the Interior National Park Service Midwest Region. The work involves replacing fan coils at the park headquarters.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6324Q0005_Amd_0003.pdf | ||
| B09_Solicitation_Amendment_0003_Q_A_docx_0003.pdf | ||
| Sol_140P6324Q0005_Amd_0002.pdf | ||
| Sol_140P6324Q0005_Amd_0001.pdf | ||
| B09_Solicitation_Amendment_0001_Fan_Coil_Drawings_0001.pdf | ||
| Sol_140P6324Q0005.pdf | ||
| B08_Solicitation_Attachment_1_Statement_of_Work_MORU_Fan_Coils_Replacement.docx | DOCX document | |
| B08_Solicitation_Attachment_5_WD-2015-5367.pdf | ||
| B08_Solicitation_Attachment_4_Experience_Questionnaire.xlsx | XLSX spreadsheet | |
| B08_Solicitation_Attachment_2_Drawings_Specs_Fan_Coils_Replacement.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| 140P6324Q0005 | Fan Coils Replacement for | Page 1 of 1 |
| Mount Rushmore National Monument |
Price Schedule
Mount Rushmore National Monument Fan Coils Replacement Price Schedule
The contractor is also expected to account for any additional costs when providing final pricing. Pricing should include all applicable taxes. Detailed Quote showing numbers of HVAC technicians with hourly rates and any other charges/to include all profit, overhead, and South Dakota Excise tax that may be applicable to complete this requirement. Any materials shall be priced and shown in detail. The contractor is encouraged to use the information from the Statement of Work to provide a competitive price for the total cost of the successful completion of the project. Note: Edit as needed. If a more complex price schedule is required, you can make it part of your checklist for submittal and attach to the package.
| Materials |
| Unit |
| Quantity |
| Price/Unit |
| Subtotal |
| Remove and Proper Disposal of 28 existing Fan Coil Units |
| Per square foot |
| 28 |
| Remove and Proper Disposal of 6 Unit Ventilators |
| EA |
| 6 |
| Provide and Install Brand Name or Equal Trane (Fan Coil Units) |
| EA |
| 28 |
| Provide and Install Brand Name or Equal Trane (6 Unit Ventilators) |
| EA |
| 6 |
| Percentage |
| Subtotal |
Excise Tax
Overhead
Profit
Total Contract Cost: _______________