This Statement of Work (SOW) details a demolition project for the Tom's Cove Visitor Center at Assateague Island National Seashore in Chincoteague, Virginia. The National Park Service seeks a contractor with minimum 5 years of construction/demolition experience to completely remove the visitor center structure, including a ~2,300 sq ft commercial building, elevated boardwalks, structural pilings, utilities, four wastewater holding tanks, and associated infrastructure. The project requires specialized asbestos removal of approximately 2,800 sq ft of non-friable asbestos-containing material, with all materials to be recycled or disposed of according to environmental regulations.
The contract is valued between $500,000 and $1,000,000, with performance scheduled from November 1, 2025, through March 31, 2026. The 150-day delivery timeline is non-negotiable, and the contractor must comply with extensive safety, environmental, and operational requirements, including maintaining a site-specific safety plan, providing daily work logs, and ensuring minimal disruption to park operations. Key deliverables include comprehensive documentation such as waste disposal summaries, hazardous material manifests, certified payroll records, and a construction work schedule. The project aims to return the ecologically sensitive site to natural conditions after demolition.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
National Park Service U.S. Department of the Interior
Northeast Region Assateague Island National Seashore Facility Management Division
DEMOLISH TOM’S COVE VISITOR CENTER
Project Location: 8586 Beach Road Chincoteague, Virginia 23336
STATEMENT OF WORK FOR CONSTRUCTION SERVICES
1. GENERAL
Assateague Island National Seashore (ASIS), headquartered in Berlin, Maryland seeks a contractor with a minimum of 5 years of construction and/or demolition experience, to provide contracted services to demolish and remove the Tom’s Cove Visitor Center, structural piles, ramps, boardwalks, elevated boardwalks, inground wastewater holding tanks, all ancillary building utilities and return the site to natural conditions. The National Park Service has conducted a hazardous materials assessment (Attachment 6) which indicates there is asbestos present in the built-up roof which is currently under the pitched roof. Period of Performance on this contract shall take place between November 1, 2025, through March 31, 2026. The delivery date is 150 Days After Issuance of Notice to Proceed and is not negotiable.
It is strongly recommended that the contractor’s visit and inspect the site during the pre-bid site visit to verify all estimated quantities, and existing conditions provided by the Government and to observe the complexities of conducting demolition over tidal wetlands. All quantities are provided as informational only. Contractors shall be responsible for verifying all measurements and acquiring all quantities to complete this requirement. Quotes will be broken down by using a government provided price schedule, which will provide a lump sum for all elements.
The term ‘Contractor’ herein, includes the prime contractor and all subordinate contractors employed on their behalf, and are subject to the same guidelines for this contract.
The term ‘Park” herein, refers to the National Park Service unit, Assateague Island National Seashore.
2. PURPOSE AND BACKGROUND
The area of Tom’s Cove Visitor Center and the surrounding environment has become unsustainable to manage due to sea-level rise and accelerated shoreline retreat. Due to this, the recreational beach that the Visitor Center serves is being relocated rendering the outdated Tom’s Cove Visitor Center obsolete.
3. TASKS
Provide all labor, supervision, materials, tools, supplies, transportation, license, certificates, permits (Asbestos), personal protection equipment, professional services, and equipment incidental to and necessary to provide demolition services, as specified in the SOW at Assateague Island National Seashore. The contractor shall know and understand the complexities of performing demolition work over an ecologically sensitive landscape.
3.1. Requirements
3.1.1. The main structure (Visitor Center including immediate decks or ancillary structures, anything directly attached to main structure) will need to be removed from the wetlands and work area (see Attachment 1. Tom's Cove Visitor Center Work Area) before any demolition to those structures can occur. It is approximately 215 feet off a paved surface. Please see attachments for layout and pictures for structure dimension and weight approximation.
3.1.2. Preparing work site for demolition. Acceptable materials for demolition work will only include temporary materials include matting, skids, cribbing and other protective barriers (silt fencing). Anything else will not approved to use based on permitting for this work.
3.1.2.1. Asbestos Roof Removal:
3.1.2.2. Expose the built-up roof that contains the asbestos material. This roof is under and supports the outside/exposed pitch roof that is visible from the outside of the structure. The pitched roof consists of modern asphalt roofing shingles and lumber framing and is considered construction/demolition debris.
3.1.2.3. Remove approximately 2,800 sq. ft of non-friable asbestos containing material (ACM) roof and all ancillary components (framing, braces etc.).
3.1.2.4. ACM roofing material will need to be separated out from other construction debris and disposed of accordingly (Refer to Section 5: Environmental).
3.1.2.5. Demolition and Removal of Remaining Tom’s Cove Visitor Center Structure:
3.1.2.6. Demolish, remove, and dispose of all of Tom’s Cove Visitor Center and elevated boardwalk in the Tom’s Cove Visitor Center Work Area (see attachments). This will include, but not limited to, a ~2,300 sq ft. commercial structure (Visitor Center), utilities, elevated boardwalks, structural pilings, ramps, parking signs, four 1,000-gallon concrete above/below grade wastewater holding tanks (see attachment 3 for wastewater holding tank locations), fencing and waysides and all other ancillary components. This does not include the shell or asphalt paved roadways or parking areas. *Refer to Section 5 (Environmental) for disposal/recycling guidance.
3.1.3. Coordinate with COR on what materials are being salvaged and what materials are being recycled/disposed of. For bidding purpose assume all material will be recycled/disposed of.
3.1.4. Remediate site to natural conditions by filling in holes/excavations where objects were removed below grade with material provided by the NPS.
3.1.5. Clean up all equipment, tools, supplies, materials, refuse and/or anything related to the performance of this contract.
3.2. Project Specifications
| Required (Not Limited To) Deliverables |
| Due |
| 1 |
| Written Designation of Superintendent and Alt Superintendent |
| With proposal package |
| 2 |
| Designated Superintendent & Alt. Superintendent Resumes |
| With proposal package |
| 3 |
| Bid Bond @ 20% on SF 24 |
| With proposal package |
| 4 |
| Active SAM Registration w/ UEI # Clearly Visible |
| With proposal package |
| 5 |
| Contractor’s License – Construction/Demolition |
| With proposal package |
| 6 |
| Contractor’s License – Asbestos Contractor’s License/Certification (EPA and VA) |
| With proposal package |
| 7 |
| Performance and Payment Bonds @ 100% on SF25 and SF 25A |
| 14 Days After Award |
| 8 |
| Certificate of Insurance |
| 10 Days After Award |
| 9 |
| SF 1413 for all Subcontractors |
| 10 Days After Award |
| 10 |
| Schedule of Values (SOV) |
| 14 Days After Award |
| 11 |
| Waste Management/Hazardous Material Plan |
| 14 Days After Award |
| 12 |
| Site Specific Safety Plan |
| 14 Days After Award |
| 13 |
| Construction Work Schedule in Gantt Chart Format |
| 14 Days After Award & Ongoing |
| 14 |
| Quality Control Plan |
| 14 Days After Award |
| 15 |
| Waste Disposal/Recycling Summary |
| Prior to Final Invoice |
| 16 |
| Hazardous Material Disposal Manifests |
| Prior to Final Invoice |
| 17 |
| Daily Work Logs |
| Weekly |
| 18 |
| Certified Payroll on WH-347 w/Updated Schedule and SOV |
| Weekly |
| 19 |
| Release of Claims DI-137 |
| Closeout/With Final Invoice |
3.2.1. Contractor shall take into consideration the existing ancillary equipment, building support systems, and environment, as well as the potential presence of unknown structures, utilities, and ancillary infrastructure to provide a proposal that meets the project objectives.
3.2.2. Unless otherwise noted all demolition waste becomes property of Contractor.
3.2.3. Contractor shall coordinate and dispose/recycle of all refuse materials generated with performance of work. Designated worksite area and exterior are to be maintained in a tidy manner, with loose debris collected and properly stored (i.e. in tarped covered dumpster) and/or removed each day and disposed/recycled per Section 5 (Environmental).
3.2.4. Temporary staging and storage locations shall be coordinated with COR 14 calendar days in advance of work.
3.2.5. The local electric utility will disconnect the service electric connection from the building before work commences. All other electrical work will be the responsibility of the contractor.
3.2.6. Wastewater tanks will be emptied by NPS before demolition, but tanks may still contain residual wastewater. Attachment 3 is the locations of the wastewater holding tanks.
3.2.7. All plumbing exposed during removal of wastewater tanks should be removed and disposed of according to Section 5 (Environmental) stated methods of disposal. Piping that is being abandoned in place will need to be capped or plugged with similar type material.
3.2.8. The contractor will need to provide dumpsters and other waste disposal containers for the performance of this contract and will not be able to use dumpsters used by the NPS for daily operations.
3.2.9. Waste Disposal and Recycling Summary (Submittal 14), this should include weight of hazardous materials and demolition materials disposed of and weight of material recycled.
3.2.10. All requirements associated with disposal, including but not limited to hazardous materials reporting, hazardous waste removal, hauling, tare reporting, fees, rental of dumpsters, and tipping fees, shall be the responsibility of the contractor.
3.2.11. This work will require a closure of the road leading to and from the work area, it is the contractor’s responsibility to ensure the closure is maintained to prevent unauthorized individuals from entering the worksite.
3.2.12. Access to the work site may be limited at times due to unforeseen weather and/or tidal events.
3.2.13. Cutting materials at grade will not be approved or accepted, all materials need to be physically removed above and below ground.
3.2.14. We will requesting the Asbestos Supervisors/Worker training for anyone engage in Asbestos work.
3.2.15. Salvaged items will need to be cleaned by the contractor and securely stored until the NPS can transport items to off-site storage area.
3.2.16. NPS has made a reasonable effort to determine if the structure has hazardous materials present by performing a hazardous materials assessment (see HAZMAT report). This report provides clarity over a large amount of the structure concerning hazardous materials, but it is not to say that there couldn’t be other hazardous materials present in the structure. The contractor will need to take this into consideration during bidding and performance of this contract.
4. SAFETY
4.1. The contractor shall comply with all pertinent provisions of the Occupational Safety and Health Administration (OSHA) Standards, 29 CFR 1910 and provide all necessary supervision, safety protection devices, and certified personal protective equipment (ANSI etc.), required for complete and safe operations on site in accordance with OSHA guidelines. All OSHA requirements may be obtained without cost to the general public at www.osha.gov. NPS will request from contractor any pertinent safety communication, certifications or required trainings for any employee(s) engaged in work that require such. Protective measures shall prevent injury to the public, Federal employees, contractors, visitors, Contractor’s employees, and damage to or contamination of surrounding property and/or the environment.
4.2. All tools/machinery/equipment/vehicles shall be safeguarded from the public. Tools/machinery/equipment/vehicles shall not be left unattended. All tools/equipment shall not be allowed to lie around except in the immediate work area. Any tools not in immediate use shall be staged or stowed in such manner so as not to create a hazard. The government and contractor will agree on delineating the work area around the project.
4.3. The Contracting Officer (CO) or Project Manager may include additional safety measures or procedures if determined necessary or required by other Federal, State, or local law, or park policy.
4.4. Contractor shall provide a comprehensive site-specific safety plan for approval before any work begins. An onsite qualified Safety Representative shall be identified including contact information.
4.5. Traffic Control (If Applicable):
4.5.1. The contractor is responsible for placing warning signs to warn the public of any work area or closed areas. Whether this is through signs, cones, flagger, labels or danger signals, the public or employees need to be fully aware of the risk associated with the contractor’s work.
4.5.2. Maintain open traffic on Park roads outside of the work closure to the greatest extent possible. Temporary traffic delays shall be kept to the minimum and only as necessary. Limit traffic impacts to 10 minutes maximum for each delay period, unless otherwise authorized by the COR.
4.6. Staging and Access:
4.6.1. All work, parking of vehicles, equipment, materials, and all other operations in connection with this contract shall be confined to the specified hours and stagging/work areas designated and approved in writing by the CO and/or COR.
4.6.2. No overnight parking in the park is authorized unless prior approval is requested and received in writing from the COR--NO EXCEPTIONS. Violators will be towed at the Contractor’s expense.
4.6.3. Confine on-site material and equipment for storage and laydown equipment in staging or storage areas or other areas specifically designated by the COR.
5. ENVIROMENTAL
5.1. The Contractor shall comply with Executive Order 13834, pertaining to Sustainability, work shall incorporate the following:
5.1.1. Reduce waste and implement recycling programs for construction and demolition materials whenever possible.
5.2. The Contractor shall comply with all Federal, State and Local government regulations pertaining to waste disposal, recycling and hazardous material use, storage, and disposal.
5.2.1. Materials and chemicals shall be stored, used, and disposed of in such a manner as to not endanger or threaten the environment and the health and safety of Park employees and visitors.
5.3. The Contractor shall have a Hazard Communication Program in place as required by 29 CFR 1910.1200 where Safety Data Sheets (SDS) / Technical Data Sheets shall be obtained by the contractor for all hazardous materials to be used in the performance of this contract. This plan shall be furnished to the NPS prior to the start of work. These SDS’s and an inventory of hazardous materials must be provided to the CO or COR prior to bringing the material on site. SDS shall be maintained at any jobsite where a substance requiring a SDS is being used. It shall also be available in any vehicle carrying such substance while in the Park. These SDS will be available to all employees of the Contractor, employees of the Park, concessionaires and the public when any member of these groups might come in contact with, or be exposed to, any substance requiring a SDS due to its hazardous status.
5.4. Hazardous waste must be re-claimed/captured for recycling by the contractor. Hazardous Waste Manifests shall be submitted prior to final invoice.
5.5. The park has both natural and man-made protected resources. It is the Contractor’s sole responsibility to ensure they are always protected during this project.
5.5.1. The Contractor is responsible for confirming with NPS Staff regarding the identification of these assets prior to the start of work or at any time any questionable or unforeseen items arises. Work shall stop until clarification by the NPS is made.
5.6. Erosion, Waste and Sediment Control (If Applicable):
5.6.1. The Contractor is responsible for the design, installation, maintenance and removal of all erosion, waste, and sediment control devices in accordance with all local, state, and federal regulations having jurisdiction, as required for the project.
5.6.2. Prior to project start, submit proposed erosion, waste and sediment control plan for approval by the COR/CO/CS.
5.6.3. Install sediment/refuse barriers and other measures intended to trap sediment or refuse before land disturbance takes place.
5.6.4. Maintain all erosion and sediment control devices to assure continued performance of their intended function. Replace damaged and deteriorated control devices as needed.
5.6.5. During construction, stabilize or protect soil stockpiles, on-site borrow areas, and soil transporting with sediment trapping measures.
5.6.6. When approved by the COR, remove all temporary waste, erosion and sediment control measures within 30 days after final site stabilization or after the temporary measures are no longer needed.
6. CONTRACTORS RESPONSIBLITIES AND REQUIREMENTS
6.1. A written designation of a supervisor(s) and an alternate supervisor(s) with the same qualifications as the proposed supervisor will need to be submitted (see required submittals): The supervisor and/or alternate supervisor is required to be always present on-site during all operations to direct contract personnel and maintain operations. The on-site supervisor MUST:
6.1.1. Be fluent in the English language in order to effectively communicate with the contractor’s employees and/or subcontractors as well as the COR and other Government personnel.
6.1.2. Be available for phone calls during all working hours, and have the authority to stop all work for unsatisfactory performance as directed by the COR.
6.1.3. Possess 5-years verifiable experience and technical competence in work prescribed in 3.1 (Requirements) as well as 2-years supervisory experience, submitted as a resume.
6.1.4. Be responsible for controlling the quality of work and inspecting all completed work to ensure that correct performance requirements are met.
6.2. The requirements set forth are intended to provide general guidelines for the services that shall be provided by the Contractor. The contractor needs to use their knowledge to understand the project scope and nuisances of work even if not stated in scope. All work performed by the contractor shall be performed in accordance with manufacturers specifications, guidelines and recommendations, industry standards, and commercial practices.
6.3. Provide sufficient trained, certified (up to date pertinent certifications), and experienced manpower and equipment to complete the project within the period of performance. The total daily productive man hour requirements and quantity of personnel necessary to performance of all services specified herein is the sole responsibility of the contractor and shall be quoted accordingly. Davis Bacon Wages shall be utilized.
6.4. Quality workmanship is required at the full performance level of specified work, beginning at the contract start date. The contractor shall be responsible for professional quality, technical accuracy, project coordination, equipment installation, training, disposal of existing equipment, and all other ancillary items required and provide all deliverables that meets the requirements of the NPS.
6.5. Submittals:
6.5.1. The contractor shall maintain a daily work log by filling out completely with pictures, as applicable. The Daily Work Log Form will be provided to them by the Government. The daily work log or approved equivalent shall be submitted to the COR, courtesy copying the CS/CO via email after a week of work and or any time requested by the COR, CS/CO.
6.5.2. The contractor shall also note in the daily work log the presence of any damage or conditions that may affect the contractor ability to perform work. The contractor shall note and report to the COR any issues or problems that arise, which are within the statement of work.
6.6. Provide Submittals and implement them after approved by the CO/COR. A CM 16 Submittal Form shall be used as a cover sheet for every submittal and will be provided by the Government to the contractor at award. Multiple submittals may be listed on a single CM 16 submittal form.
6.7. Contractor will be required submit all pertinent manufacturer’s data for all equipment, components, and materials BEFORE install occurs. Pertinent data could include installation, operations and maintenance manuals, product data and warranty information. All data shall be annotated to show the specific material identification information, catalog number, type, color, and size of each item.
6.8. All materials and labor must carry a minimum one-year warranty from the date of final inspection.
6.9. Submit a construction schedule no later than 14-days after project award and update it as the project progresses to reflect the most current timeline. Include a revised Construction Work Schedule in all pencil copies and attached to all payment applications. Invoices shall be rejected if this document is not attached.
6.10. Contractor Employee Conduct:
6.10.1. The Contractor’s employees shall conduct themselves in a professional, orderly, and safe manner will on the job site. A contractor’s employee shall be subject to removal from the premises upon determination by the Contracting Officer that such action is in the best interests of the Government. Such removal from the job site or dismissal from the premises shall not relieve the Contractor of the requirement to provide sufficient personnel to perform the service as specified.
6.10.2. Rudeness, fighting, being under the influence of alcohol and/or drugs or bringing and/or consuming alcohol and/or drugs, gambling, soliciting, stealing, and any immoral or otherwise undesirable conduct shall not be permitted on the job site. Any employee engaging in such conduct shall be immediately removed from the job site.
6.10.3. Photographs, social media posts, online content, or any form of communication is strictly prohibited regarding all aspects of this requirement unless authorized in writing by the COR.
6.10.4. In instances where the contractor finds pre-existing conditions or damage to park resources that may reflect upon the quality of the work or cause undue liability, the contractor shall not start work until the contractor and COR have agreed on the responsibility for these pre-existing conditions.
7. GOVERNMENT PROVIDED INFORMATION
7.1. Forms:
7.1.1. CM-16 Submittal Form
7.1.2. Daily Work Log
7.2. Links to Pertinent Information Related to This Work:
Management - Assateague Island National Seashore (U.S. National Park Service) (nps.gov)
MUTCD
OSHA
Code of Federal Regulations (CFR)
ANSI
Federal, State and Local Environmental Laws, Regulations, and Policies
7.3. Attachments:
| 1 |
| Statement of Work |
| 2 |
| Tom's Cove Visitor Center Proposed Work Area |
| 3 |
| Tom’s Cove Visitor Center Pictures |
| 4 |
| Location of Septic Tanks at Tom's Cove VC |
| 5 |
| Tom's Cove Visitor Center Layout |
| 6 |
| Tom’s Cove Visitor Center HAZMAT Survey Report |
| 7 |
| DOL Wage Determination VA20250007 |
| 8 |
| Limitations on Subcontracting Report Template |
| 9 |
| Construction Contract Administration Provision |
8. HOURS OF OPERATION
8.1. Construction operations shall be conducted between the hours of 6:30 am –3:30 pm ET, Monday – Friday, except when there’s a federal government holidays (Federal Holidays), local or national emergencies, administrative closings, or similar Government directed facility closings.
8.2. The contractor will be notified by the COR (7) business days in advance, if possible, for days there shall be no work conducted outside of regularly scheduled federal holidays.
8.3. All work outside of the designated performance hours are required to be requested seven (7) business days in advance, in written form, by the Contractor to the Contracting Officer’s Representative (COR) for approval.
9. ADDITIONAL APPLICABLE REGULATIONS AND POLICIES
9.1. All supplies, materials, equipment, processes, and tools are subject to the submittal process and approval by the COR/CO/CS. Supplies, materials, tools, processes, and equipment that doesn’t meet the project requirements set forth in this contract could be rejected. Contractor shall take this into consideration during the bidding process.
9.2. Only changes as approved in writing by the CO shall be deemed authorized. Any other form of changes performed under this contract that are unauthorized shall be the burden of the Contractor and shall be at no cost to the Government.
9.3. Damages and liability for any loss (tangible or intangible) during the performance of this contract caused by the contractors’ operations:
9.3.1. The contractor shall assume full responsibility for any and all damages or claims for damage resulting from injury to persons, property, or equipment, which might result from any work performed under this contract.
9.3.2. All damage resulting from such operations shall be repaired to its original condition to the satisfaction of the COR at no additional cost to the Government.
9.3.3. The contractor shall take all immediate actions necessary to prevent further damage.
9.3.4. All losses and/or damages shall be reported to the COR, within two (2) hours of any loss and/or damage being determined and before leaving the area loss occurred. Contractor shall provide a detailed written documentation of the loss and/or damage to the CO and COR within 24 hours of occurrence.
9.3.5. The contractor is responsible for all costs associated with reported damages and/or losses to persons, property or environment that occur because of the contractor’s negligence.
9.3.6. Liquidated damages, per FAR 11.5 – Liquidated Damages, may or may not apply to this contract, please refer to contracting documents for more information.
END OF STATEMENT OF WORK