This document is a Statement of Work (SOW) related to the restoration of the Samuel Gompers statue and Edmund Burke memorial located in Washington, D.C. as part of a federal contract opportunity.
The SOW outlines the specific tasks required for the project, including mobilization, bronze conservation of the statues, masonry cleaning and restoration of the bases, and high-level heritage documentation of the monuments. The work must be performed by a contractor that is a Professional Associate of the American Institute for Conservation of Historic and Artistic Works. Key requirements include the development of a detailed work plan, mock-ups, and adherence to federal safety and sustainability standards. The work is expected to take approximately 120 days to complete and is part of a solicitation issued by the National Park Service for the National Mall and Memorial Parks. The SOW provides specifics on submittals, quality control, and federal contract clauses that the selected contractor must follow.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work National Park Service - National Mall and Memorial Parks (NAMA) Restore Samuel Gompers Statue and Edmund Burke Memorial PMIS Project # 311668C October 2023
PART I: GENERAL INFORMATION
I. NATIONAL PARK SERVICE
The National Park Service (NPS) is a bureau of the U.S. Department of the Interior (DOI) that has been entrusted with the care of our national parks since 1916. The NPS preserves unimpaired natural and cultural resources, and values of the National Park System for the enjoyment, education, and inspiration of this and future generations. The NPS cooperates with partners to extend the benefits of natural and cultural resource conservation and outdoor recreation throughout this country and the world.
II. NATIONAL CAPITAL REGION
The NPS - National Capital Region (NCR) supports natural wonders to man-made marvels in Virginia, West Virginia, Maryland, and the District of Columbia. The NCR parks include Antietam National Battlefield, Catoctin Mountain Park, Chesapeake & Ohio Canal National Historical Park, George Washington Memorial Parkway, Harpers Ferry National Historical Park, Manassas National Battlefield Park, Monocacy National Battlefield, National Capital Parks - East, National Mall and Memorial Parks, Potomac Heritage National Scenic Trail.
III. BACKGROUND
The NPS National Mall and Memorial Parks (NAMA) is America’s front yard right in the heart of the nation’s capital that brings visitors face to face with larger-than-life presidents and visionaries, open park lands, and elaborate memorials honoring our nation’s veterans and military history. NAMA is visited by approximately 25 million visitors each year from around the world that want to experience the unique collection of structures and spaces honoring the nation, its democracy, and its citizenry.
The National Mall is the great swath of green in the middle of Washington, DC that stretches from the foot of the United States Capitol building to the Potomac River. Both inside, as well as, outside the boundaries of the National Mall there are numerous iconic monuments and memorials that make up the Memorial Parks aspect of NAMA. NAMA protects the National Mall and its iconic monuments and memorials, and over 1,000 acres of greenspace in Washington, DC. NAMA is host and/or the backdrop to hundreds events each year, from the Presidential Inauguration every four (4) years to the yearly National Independence Day Celebration and other large public events. Except for the Washington Monument, the National Mall and Memorial Parks is open 24/7 to the General Public. For more detailed and general information checkout the website at: Basic Information - National Mall and Memorial Parks (U.S. National Park Service) (nps.gov)
IV. SAMUEL GOMPERS STATUE AND EDMUND BURKE
The Samuel Gompers Memorial is located at the intersection of 10th Street, L Street, and Massachusetts Avenue, Northwest, Washington, DC. The Gompers Memorial is part of the National Park Service (NPS)- National Capital Area (NCA)- National Mall and Memorial Parks (NAMA) located in Washington, DC in Reservation 069. The Gompers Memorial is a bronze statue listed on the National Register of Historic Places and is in memory of Samuel Gompers, an English-born American cigar maker, labor union leader and a key figure in American labor history. The memorial was dedicated in 1933 by architect Robert Aitken in the Beaux Arts style.
The Edmund Burke Memorial is located at the junction of 11th Street and Massachusetts Avenue, Northwest, Washington, DC. The Edmund Burke statue was dedicated in October 12, 1922. Burke was an Enlightenment era philosopher that was America’s main ally in Great Britain. He defended our call for liberty within the British Parliament and as a sign of esteem for his support, Burke is now honored in the American capital city. The bronze statue of Edmund Burke is a copy of an 1894 statue in Bristol, England. The original was cast by a Welsh sculptor named John Harvard Thomas. The statue is meant to remind us of the old ties between America and Britain as well as the enduring friendship that has evolved between these two great countries.
V. PURPOSE
The intent of this project is to provide cyclic maintenance to the Gompers and Burke statues so that they are maintained and brought to a restored status. There is no known history of past interventions on either of these two memorials and maintenance has been minimal.
The purpose of this project is to provide conservation services to conduct an initial condition assessment, develop a work plan based on found conditions, implement treatment recommendations and provide a treatment report to include narrative and images describing the conditions found, work performed and recommendations for future treatment and maintenance practices.
The principal features of the work include the erection, maintenance and removal of scaffolding required to carry out the work of this project; the conservation of the bronze elements, the conservation of the granite bases, submission of a conservation treatment report, and high level resource documentation including high resolution digital photographs (minimum 300 dpi) in TIFF format, laser scanning, measured drawings, and anufacturery. For the purposes of this contract, all existing building material is considered historic fabric and the following provides additional details on the requirements to carry out this work.
The project is limited to the bronze Gompers statue and granite base and excludes the cast stone aggregate walkway and steps. For the Burke Memorial, the project is limited to the bronze statue of Burke and the granite base. Unlike the Gompers statue, the Burke statue and base are set on on grass, so walkways or stairs are not a consideration.
This project includes the completion of high level resource documentation for the statuary in the memorial parks using a combination of tools, including high resolution digital photography (minimum 300 dpi in TIFF format), measured drawings, photogrammetry and laser scanning.
VI. PROJECT BACKGROUND
There are no known past projects at these sites.
PART II: DEFINITIONS & ACRONYMS
I. DEFINITIONS (Not included in Federal Acquisition Regulations)
Wherever in these provisions, or in other contract documents, the following terms, or pronouns in place of them, are used, the intent and meaning shall be interpreted as follows:
2-Cycle Engine Oils - Lubricants designed for use in 2-cycle engines to provide lubrication, decreased spark plug fouling, reduced deposit formation, and/or reduced engine wear.
Adhesive and Mastic Removers - Solvent products formulated for use in removing asbestos, carpet, and tile mastics as well as adhesive materials, including glue, tape, and gum, from various surface types.
Asphalt Restorers - Products designed to seal, protect, or restore poured asphalt and concrete surfaces.
Asphalt and Tar Removers - Cleaning agents designed to remove asphalt or tar from equipment, roads, or other surfaces.
Blast Media - Abrasive particles sprayed forcefully to clean, remove contaminants, or condition surfaces, often preceding coating.
Calendar Days - Every day shown on the calendar, Saturdays, Sundays and holidays included.
Change Order - An order issued to the Contractor by the Contracting Officer, pursuant to the “change” clause included in Section I of this contract, requiring work to be performed, within the general scope of the contract.
Contract Pay Item - A pay item designated on the bid schedule and described by a specification.
Concrete and Asphalt Cleaners - Chemicals used in concrete etching as well as to remove petroleum-based soils, lubricants, paints, mastics, organic soils, rust, and dirt from concrete, asphalt, stone and other hard porous surfaces. Products within this item include only those marketed for use in commercial or residential construction or industrial applications
Concrete and Asphalt Release Fluids - Products that are designed to provide a lubricating barrier between the composite surface materials (e.g., concrete or asphalt) and the container (e.g., wood or metal forms, truck beds, roller surfaces).
Contracting Officer (CO) - The person executing this contract on behalf of the Government, including any duly appointed successor and authorized representatives of the Contracting Officer acting within the limits of his/her authority.
Contracting Officer's Representative (COR) - The on-site contract administrator for the Contracting Officer. The duties and responsibilities of the Contracting Officer’s Representatives are defined below in this Section or in a letter of designation issued by the Contracting Officer.
Contractor - The individual, partnership, joint venture, or corporation undertaking the execution of work under the terms of the contract and acting directly or through their agent, employees, or subcontractors.
Corrosion Preventatives – Products designed to prevent the deterioration (corrosion) of metals.
Diesel Fuel Additives - (1) Any substance, other than one composed solely of carbon and/or hydrogen, that is intentionally added to diesel fuel (including any added to a motor vehicle's fuel system) and that is not intentionally removed prior to sale or use. (2) Neat biodiesel, also referred to as B100, when used as an additive. Diesel fuel additive does not mean neat biodiesel when used as a fuel or blended biodiesel fuel (e.g., B20).
Drawings - The approved documents and reproductions of these documents, including plan and profile sheets, cross sections, site plants, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, and similar documents showing details for construction of a facility.
Dust Suppressants - Products formulated to reduce or eliminate the spread of dust associated with gravel roads, dirt parking lots, or similar sources of dust, including products used in equivalent indoor applications.
Erosion Control Materials - Woven or non-woven fiber materials manufactured for use on construction, demolition, or other sites to prevent wind or water erosion of loose earth surfaces, which may be combined with seed and/or fertilizer to promote growth.
Equipment - All machinery and equipment, together with the necessary supplies for upkeep and maintenance, including tools and apparatus necessary for the proper construction and acceptable completion of the work.
Gasoline Fuel Additives - Chemical agents added to gasoline to increase octane levels, improve lubricity, and provide engine cleaning properties to gasoline-fired engines.
Gear Lubricants - Products, such as greases or oils, that are designed to reduce friction when applied to a toothed machine part (such as a wheel or cylinder) that meshes with another toothed part to transmit motion or to change speed or direction.
General Purpose Household Cleaners - Products designed to clean multiple common household surfaces. This designated item does not include products that are formulated for use as disinfectants. Task-specific cleaning products, such as spot and stain removers, upholstery cleaners, bathroom cleaners, glass cleaners, etc., are not included in this item.
Graffiti and Grease Removers - Industrial solvent products formulated to remove automotive, industrial, or kitchen soils and oils, including grease, paint, and other coatings, from hard surfaces.
Industrial Cleaners - Products used to remove contaminants, such as adhesives, inks, paint, dirt, soil, and grease, from parts, products, tools, machinery, equipment, vessels, floors, walls, and other production-related work areas. The cleaning products within this item are usually solvents, but may take other forms. They may be used in either straight solution or diluted with water in pressure washers, or in hand wiping applications in industrial or manufacturing settings, such as inside vessels. Task-specific cleaners used in industrial settings, such as parts wash solutions, are not included in this definition.
Interior Paints and Coatings – Latex and Waterborne Alkyd - Pigmented liquids, formulated for use indoors, that dry to form a film and provide protection and added color to the objects or surfaces to which they are applied.
Interior Paints and Coatings – Oil-based and Solventborne Alkyd - Pigmented liquids, formulated for use indoors, that dry to form a film and provide protection and added color to the objects or surfaces to which they are applied.
Intermediates – Binders - Materials used to provide cohesiveness throughout an entire finished product. Binders are generally polymers or polymer precursors (such as epoxies) and include the polymeric materials used to formulate coatings, adhesives, sealants, and elastomers. The product category does not include adhesives and glues that are finished products used to attach the surfaces of two or more distinct and separate components to one another.
Intermediates – Chemicals - Ingredients used as reactants for organic synthesis reactions rather than for their functional properties in a chemical mixture; those used as building block chemicals and secondary chemicals such as glycerol, succinic acid, propanediol, and monomers such as lactic acid and propylene; those used for specific functional properties during manufacturing of other products such as pH regulators, flocculants, precipitants, neutralizing agents, emulsifiers, viscosity reducers, rheology modifiers, adhesion agents, detergents, wetting agents, foaming agents, or dispersants; those that are added to end-use products for their specific functional properties including polyols, polymers, and solvents for thinning and drying applications but excluding solvents used for cleaning; and those used for dyes, pigments, and scents including flavorings for non-food products such as lip balm.
Intermediates – Cleaner Components - Ingredients used specifically for formulating finished cleaning products. Examples of Intermediates - Cleaner Components include chelating agents, surfactants, hydrotropes, fatty acids, or solvents.
Intermediates – Paint and Coating Components - Ingredients used to formulate finished waterborne or solvent borne paint and coating products. Examples of Intermediates – Paint and Coating Components include binders, pigments, thickeners, curing agents, modifiers, humectants, open time additives, alkyd latex resins, polymers, polyols, reactive oligomers, or reactive diluents.
Intermediates – Plastic Resins - Materials that are typically viscous liquids with the ability to harden permanently and may exist in liquid or solid (powder or pellets) states. Intermediates – Plastic Resins may be used in a variety of finished products neat, consisting of a single resin or polymer, or a homogeneous blend of two or more neat resins or polymers, or a composite, containing two or more distinct materials such as fiber-reinforced resins. Additionally, Intermediates – Plastic Resins may be used in finished products as additives such as plasticizers, pigments, thermal stability agents, or impact modifiers.
Labor Standards Provisions - Those statutory and regulatory requirements pertaining to the Contractor’s employees and employment practices.
Materials - Any substances for use in the construction of the project and its appurtenances.
Multipurpose Lubricants - Products designed to provide lubrication under a variety of conditions and in a variety of industrial settings to prevent friction or rust. Greases, which are lubricants composed of oils thickened to a semisolid or solid consistency using soaps, polymers or other solids, or other thickeners, are not included in this item. In addition, task-specific lubricants, such as chain and cable lubricants and gear lubricants, are not included in this item.
Notice of Noncompliance - A written notice from the Contracting Officer’s representative or inspector which documents, for the Contractor’s attention, specific performance deficiencies.
Packing and Insulating Materials - Pre-formed and molded materials that are used to hold package contents in place during shipping or for insulating and sound proofing applications.
Paint Removers - Products formulated to loosen and remove paint from painted surfaces.
Penetrating Lubricants – Products formulated to provide light lubrication and corrosion resistance in close tolerant internal and external applications including frozen nuts and bolts, power tools, gears, valves, chains, and cables.
Right of Way - A general term denoting land, property, or interest therein acquired for or devoted to a road or a construction site.
Roof Coatings - Coatings formulated for use in commercial roof deck systems to provide a single-coat monolith coating system.
Schedule of Items - Schedule in the contract which contains a listing and description of construction items, quantities, units of measure, method of measurement, unit price and amount.
Special Project Specifications - Specifications which detail the conditions and requirements peculiar to the individual project, including but not limited to CSI format specifications and additions and revisions to Standard Specifications.
Specifications - A general term applied to all written directions and requirements pertaining to performance of work.
Standard Specifications - Specifications established for Region wide use for construction of facilities which cover most items of work likely to be performed; such as Earthwork, Base Courses, Pavement, Concrete, etc.
Utility Services - Are services such as electricity, gas, steam, water and sewage.
Wastewater Systems Coatings - Coatings that protect wastewater containment tanks, liners, roofing, flooring, joint caulking, manholes and related structures from corrosion. Protective coatings may cover the entire system or be used to fill cracks in systems.
Water Tank Coatings – Coatings formulated for use in potable water storage systems.
Wood and Concrete Sealers – Membrane Concrete Sealers - Products that are penetrating liquids formulated to protect wood and/or concrete, including masonry and fiber cement siding, from damage caused by insects, moisture, and decaying fungi and to make surfaces water resistant. Concrete sealers that are formulated to form a protective layer on the surface of the substrate.
Wood and Concrete Sealers – Penetrating Liquids - Products that are penetrating liquids formulated to protect wood and/or concrete, including masonry and fiber cement siding, from damage caused by insects, moisture, and decaying fungi and to make surfaces water resistant. Wood and concrete sealers that are formulated to penetrate the outer surface of the substrate.
Wood and Concrete Stains - Products that are designed to be applied as a finish for concrete and wood surfaces and that contain dyes or pigments to change the color without concealing the grain pattern or surface texture.
Work Order - An order written by the Contracting Officer or Contracting Officer’s Representative, which directs the Contractor to correct deficient performance. It may also be used to document acceptable completion of units and to approve starting on additional work units.
II. THE ROLE OF GOVERNMENT PERSONNEL AND RESPONSIBILITY FOR CONTRACT ADMINISTRATION
1) Contracting Officer: The Contracting Officer (CO) has the overall responsibility for the administration of this contract. The CO alone, without delegation, is authorized to amend, modify, or deviate from the contract. Other responsibilities may be delegated to authorized representatives.
2) Contracting Officer's Representative (COR): The COR will be designated in writing at the time of award to assist the CO in the day-to-day on-site administration of the contract requirements. The responsibilities of the COR include, but are not limited to;
a) Determining the compliance and adequacy of performance by the Contractor in accordance with the terms and conditions of this contract;
b) Requesting removal of unsuitable contractor employees;
c) Ensuring adequacy of schedule and Quality Control Plan, including changes;
d) Ordering re-performance of unacceptable work or performance by other mean, etc.
3) Point-of-Contact (POC): The POC will be used if an official certified COR cannot be designated at the time of award. The POC will not be designated in writing and will assist the CO in the day-to-day on-site administration of the contract requirements.
PART III: GOVERNMENT FURNISHED DATA AND MATERIALS
I. The Government will provide the following documents via email or AE FTP website.
| General Document(s) |
| Media Type |
| Dated |
| ExternalUse_NCR Regional Office Photo Metadata Guide |
| 2021 |
| NCR Regional Office Universal Design Guide |
| 2021 |
PART IV: SPECIFIC TASKS
I. SCOPE OF SERVICES
The contractor shall coordinate the work of all trades related to the successful completion of the work of this project. The contractor shall not proceed with aspects of this work that require completion of other trades until all such work of other trades are completed. The order in which information is presented in this document is not meant to imply sequence in the field, rather it is the contractor’s responsibility to determine the sequenceing and present it to the Government in a schedule format that shall be reviewed by the Contracting Officer’s Representative (COR) assigned to this job and approved by the Contracting Officer.
1) Mobilization
a) The Contractor shall develop and submit a Work Plan to NPS for review and acceptance prior to the start of work
i) The Work Plan must address the following:
(1) Demonstrate an understanding of all project goals and objectives for the conservation of the bronze and granite elements at the Gompers and Burke Memorials.
(2) Demonstrate an understanding of all project goals and objectives for the heritage documentation of the Gompers and Burke Memorials.
(3) Describe the tools and methology that will be used to complete the project goals and objectives.
(4) Describe how the historic materials will be protected during the project.
(5) Provide detailed written treatment recommendations including methods and materials to address the following tasks:
(a) Bronze conservation including cleaning, spot patination, and hot and cold waxing
(i) COR shall review the method of cleaning and the optimal level of cleaning in order to produce an even and consistent surface for the wax application and will be approved by the CO if determined acceptable by the COR.
(ii) At the time of the Government’s assessment, there were no visible cracks, losses, broken elements, or mechanical failures around attachment points. If onsite conditions assessment determines that there is additional damage, repair or missing element replacement may be necessary. If such damage is apparent, please inform COR and CO of conditions and provide a conditional work plan with treatment recommendations for review and approval.
(b) Masonry cleaning, taking into account various types of surface staining and the polished granite surface on the base of Gompers.
(c) Masonry restoration including the sensitive removal of failing mortar and lead joints and repointing and refilling with lead where appropriate. The Contractor shall review the current conditions and shall propose method or methods to ensure that the joints of the Gompers and Burke Statues are watertight.
(6) Schedule, sequence and coordination.
(7) Submittals and Mock-ups.
b) The Contractor shall participate in an initial site meeting with the NPS to discuss:
i) Approved Work Plan.
ii) Site access.
iii) During the period of work, erect, maintain and remove scaffolding (or other form of access) to ensure that there is no damage to the stone or bronze elements and ensuring that scaffolding is properly erected for work to be complete.
iv) Perform a condition assessment including digital photographs after scaffolding or access has been erected to document the existing conditions, to ensure all conditions are addressed, and to provide detailed treatment recommendations. Once access is secured, perform a detailed survey of the bronze to determine if there are cracks, material losses, and/or missing elements of the bronze statues. At the time of the Government’s assessment, there were no visible cracks, losses, broken elements, or mechanical failures around attachment points.
2) Bronze Conservation – Gompers Statue and Burke Statue
a) Gompers Statue: The existing condition of the Gompers and Burke statues is that of an unmaintained urban bronze statue with areas where there is no longer wax coating existing. This is typical of a large bronze statue that has been minimally maintained. There do not appear to be any visible cracks, losses, or missing elements from the bronze statues. The assessment was performed from the ground and did not involve the use of a lift to access the bronze in entirety. The following is a list of accepted procedures identified by the Government after its own initial assessment. Substitutions will be accepted if they are submitted to the COR for review and accepted by the Contracting Officer.
b) Tasks and Accepted Procedures: It is the responsibility of the contractor to achieve general and detailed bronze cleaning, chemical patination (if determined necessary upon further inspection of the bronze surfaces), and the application of both hot and cold wax coatings to the bronze statues. The Contractor shall be responsible for any missing elements that are visible during the site visit. If there is a crack that CANNOT be reasonably be addressed then the Contractor shall submit an RFI (to include time and cost impact) to the COR for review and the acceptance/rejection of the Contracting Officer. All cleaning shall be undertaken through the mildest and least abrasive method.
i) Clean all bronze with a non-ionic detergent solution such as Igepal or Orvus WA Paste, or approved equal and hose pressurized water. Remove dirt, organic material, and loose corrosion with the detergent solution and natural bristle brushes.
ii) Water washing: Wash the surface of the bronzes with low to medium jet pressure, 200-800 psi at 4-6 gpm using a 45 degree fan type nozzle for water soluble dirt and chemical compounds. Optimal water pressure should be determined during preparation of cleaning samples. If loose corrosion and existing wax is not removed through low-pressure water washing then high pressure washing between 3000-4000 psi can be used with a 25 degree nozzle and a stand off distance of 8” to 10” between wand and bronze surface. Delicate areas of the bronze should be cleaned at lower pressures, with a 45-degree nozzle and at increased distances.
iii) Assess water intrusion issues for the bronze statue and repair bronze as needed. Undertake brazing repairs and possible epoxy repairs.
iv) Complete spot-patination sample, patination formula shall be deterimined with COR and Technical Experts. Contractor shall apply an appropriate matching chemical patina to visually minimize patina loss and integrate uneven surfaces to blend together as a whole statue. Review historic photographs to determine the artists original intent for the patina coloration.
v) Apply an outdoor grade designed wax to be used on bronze statues to ensure a long lasting coating. Outdoor Sculpture Wax (Museum Services Corporation), or approved equal may be used. Make sure bronze is free from dust and debris. Wash lightly if necessary. Heat surface with propane torches until wax flows. Apply a coat of hot wax wax over the entire surface, ensuring that wax does not become too thick. Allow it to fully cool. Apply a second coat of hot wax. Once cool, apply one coat of cold paste wax; allow it to dry, lightly buff with soft bristle, horsehair type brushes, and lint-free cotton cloths.
3) Masonry Cleaning: Gompers and Burke
a) Requirements: The Contractor shall clean the granite masonry at the Gompers and Burke statue bases. The masonry cleaning includes the statue bases only and not the cast stone plaza and steps at the Gompers statue.
b) Tasks and Accepted Procedures: The Contractor shall clean all the granite masonry at the Gompers and Burke statues. Because various types of soiling and staining are present, NPS anticipates that more than one cleaning method may be required and shall be included as part of th offerors proposal. General cleaning, to be applied overall, and stain specific cleaning, to be applied locally, are both required as part of this SOW. The range of soiling /staining that the Contractor shall include, but not limited to: atmospheric and biological soiling, carbon soiling, sharpie maker in the inscription on the Burke plinth, and oily stains. Note that the Gompers statue base is a polished stone, only products safe to be used on polished stone shall be accepted.
c) Environmental Requirements: The Contractor will not execute any work in this Section when the air and surface temperatures are outside the operating range of 40 degrees F and rising or less than 90 degrees F and falling. Do not work when rain, snow, or temperatures below freezing are expected within 24 hours
d) Masonry Cleaning Requirements: For cleaning of all granite.
i) The cleaning systems and methods employed shall not damage, etch, burn, bleach, scour, abrade, streak or discolor any masonry surface.
ii) Use only those cleaning methods and materials indicated for each type of masonry/soiling/oily staining and location. Cleaning materials and methods must be addressed in the work plan to be reviewed by the COR and approved by the CO.
iii) No wire brushes or scrapers shall be used. For chemical cleaning, use only brushes that are resistant to chemical cleaners.
iv) Perform each cleaning method indicated in a manner that results in uniform coverage of all surfaces, including corners and interstices, and that produces an even effect without streaking or damaging masonry surfaces.
v) Apply cleaning materials in strict compliance with the anufacturer’s written instructions and as specified.
vi) Rinsing shall commence at the bottom of a given wall and proceeed upward, unless specified otherwise. The mechanic shall operate the pressure washer wand in steady, even passes and maintain a consistent distance of 12-18” feet from the fountain, using a 45 degree tip.
vii) Contractor shall flush heated water through the system for at least one minute prior to rinsing, so that no iron deposits from within the boiler are deposited on the memorial.
viii) Brushes shall be nylon or natural bristle without metal ferrules. Scrapers shall be plastic only, use no metal. Picks shall be wood, no metal shall be used.
ix) Water shall be clean, potable water. Run all hose attachments for minimum 5 minutes to minimize iron deposits prior to use. Water shall be run through both a 20 micro paper and 5 micron charcoal in-line filter before use. Change filters as needed according to manufacturer’s recommendations.
4) Masonry Restoration- Gompers and Burke Statues
a) Tasks and Accepted Procedures: The Contractor shall review the current conditions and shall propose method or methods to ensure that the joints of the Gompers and Burke Statues are watertight. The range of conditions to be treated is expected to include the following: Please note that the Gompers statue base stone-to-stone joints are all mortar, the statue joints are lead joints. For the Burke statue, the plinth is a mix of mortar and lead wool.
i) Rake out mortar joints at the Gompers Statue. Mortar that remains in stone-to-stone joints is significantly deteriorated, compromised, failed, or entirely absent. All joints within the contract limits shall be carefully raked of mortar to the greatest depth possible. Mortar may be removed through a combination of hand and power tools, if the safe use of power tools can be successfully demonstrated through an approved pre-construction mock-up.
ii) Repoint stone-to-stone joints. All stone-to-stone joints shall be repointed with mortar to prevent water ingress. Note: Stone-to-bronze joints shall not be pointed with mortar and shall be discussed on a case-by-case basis with the NPS Historic Architect and/or Architectural Conservator. Mortar shall be installed in a minimum of two lifts. The mortar may be a type “N”. Exact pointing protocol shall be determine on-site through the mock-up process in consultation with NAMA’s Architectural Conservator and/or Historic Architect. It is critical that proper environmental conditions be in place at the time mortar is installed, and shall be maintained for the duration of the curing process.
iii) Install lead wool/lead sheet joints in between granite stone to stone joints in the Burke statue and in between the bronze to bronze joints in the Gompers statue.
5) Heritage Documentation – Gompers and Burke Statues Requirements: The Contractor shall document the Gompers and Burke Monuments after conservation work has been completed using high-resolution photography.
a) Photographs: Photographic record of the monuments to consist of: monuments and sites, all elevations, significant details and structural elements, and physical evidence of monuments’ evolution/repairs.
i) Uncompressed, lossless TIFF format with a resolution of at least 300 dpi (dots per inch) digital computer print shall be acceptable in color or black/white as appropriate. All reproductions of historic photographs shall be of the highest resolution practicable to convey essential information. Photo numbering system should comply with the NCR Preservation Services Program photo metadata standards and will be supplied to the contractor at project start.
ii) Within the report, all photographs shall be clearly organized, identified, labeled and dated. Photographs/images shall be numbered and captioned with all known dates and relevant information, i.e. photographer and description of image. Photographs/images shall be properly referenced and credited with release when required.
II. ADDITIONAL CONTRACT PERFORMANCE REQUIREMENTS AND NOTIFICATIONS
1) The project is located in an area of high visibility, high pedestrian traffic, and high vehicular traffic. Extreme care shall be exercised to protect vehicles, pedestrians, the sculptures and adjacent natural resources at all times.
2) All on-site work must be coordinated with the COR and park Point of Contact a minimum of 48 hours in advance.
3) Any discovery made during the execution of the work that has the potential of creating a life safety issue either to the public, park staff or any employee of the Contractor shall be corrected and brought to the attention of the COR and Contracting Officer (CO) immediately and followed up in writing.
4) No work shall be done when environmental factors are outside of the manufacturer’s recommendations.
5) The Contractor is responsible for protecting existing adjacent materials during the execution of the work. Provide all necessary protection and work procedures to avoid damage to existing material assemblies not a part of the work of this Section.
6) The Contractor must provide barriers in the form of 6’ temporary perimeter security fencing panels (without barbed wire at the top) to prevent public entry into the area while work is being performed or any equipment is in place. All barricading shall be approved by the COR prior to installation.
7) No restroom facilities or potable water are available on sites. Onsite installation of portable toilets is not allowed.
8) Parking pass(es) for work vehicles can be provided for work vehicles only, but vehicles cannot be parked on turf or historic pavements in the parks and they are subject to all DC parking and roadway laws even with a pass. The contractor will be responsible for any permitting costs association with DDOT right of way parking during project work if necessary.
9) There is no overnight storage of supplies or materials on-site with the exception of scaffolding or a lift as needed.
10) The contractor shall be responsible for all damages to persons or property that occurs as result of the contractor’s fault or negligence. The Contractor shall take proper safety and health precautions to protect work, workers, the public and property of others.
11) All trash and debris must be removed at the end of each day and must be in accordance with local, state and federal regulations.
12) Contractor must have adequate liability insurance in accordance with contact clauses and up to date contractor’s license, and certified applicator qualifications to perform all work stated herein.
13) Submit to COR signed copies of the following written warranties against defective materials and workmanship for a period of one year following the date of completion.
III. DELIVERABLES
Assessment Report and Completion Report: Upon mobilization and access to the sites, the Contractor shall complete an initial Condition Assessment of the Gompers Statue and the Burke Statue. The condition assessment shall include digital photographs to document the existing conditions to ensure all conditions are addressed, and to provide detailed treatment recommendations. A detailed survey of the bronze to determine if there are cracks, material losses, and/or missing elements of the bronze statues shall also be documented. The Contractor shall provide a detailed written condition assessment report.
Upon successful completion of the Work, the Contractor shall submit a completion report. The completion report shall describe the work performed in narrative format. The report will include sufficient, high-resolution images to document the condition of the monument before, during, and after treatment.
| Deliverable |
| Deliverable Description |
| Condition Assessment Report for Gompers and Burke Monuments |
| Report of a detailed survey of the bronze elements of both monuments before any conservation work begins, documenting found conditions with digital photography and determining if there are cracks, material losses, and/or missing elements from either statue. Report should provide treatment recommendations for any additional found conditions that should be addressed in the conservation treatment for conditional review and approval by the COR and CO. |
| Conservation of Gompers and Burke Monuments |
| Both monuments are conserved and made to be watertight: |
- Bronze elements are cleaned, repaired as necessary, chemical patination spot applied as necessary, missing elements replaced as necessary, and hot and cold wax applied to all bronze surfaces.
- Stone masonry is cleaned and all joints, stone-to-stone or stone-to-bronze, repointed or filled with lead wool or sheets as appropriate.
| Documentation of Gompers and Burke Monuments |
| High level heritage documentation of each monument after conservation treatments have been finalized. Documentation should include high-resolution digital photography (minimum 300 dpi in TIFF format), laser scanning and photogrammetry, and measured drawings. |
| Treatment Report for Gompers and Burke Monuments |
| Report of all conservation work performed on the monuments including all stone and bronze treatments. A section with details on heritage documentation methods and products should be included as well. |
IV. CODES, REGULATIONS AND STANDARDS
All work shall conform to the latest edition of the International Existing Building Code (IEBC), International Building Code (IBC), and family of International Codes. Work shall conform to Life Safety Code and the requirements of the ADA American with Disabilities Act – 28 CFR Part 36. All work shall conform to all local codes and regulations that govern this type of work.
All work shall utilize The Secretary of the Interior’s Standards for Rehabilitation and Guidelines for Rehabilitating Historic Buildings (The Secretary of the Interior’s Standards—Technical Preservation Services, National Park Service (nps.gov) and the American Institute for Conservation of Historic and Artistic Works or Art “Code of Ethics.( Code of Ethics and Guidelines for Practice (culturalheritage.org)” To be eligible for the project award, contractor shall be a Professional Associate of the American Institute for Conservation of Historic and Artistic Works.
V. 508 COMPLIANCE AND DOCUMENT ACCESSIBILITY
1) Final digital documents must meet Section 508 accessibility compliance standards. Section 508 of the Rehabilitation Act of 1973, codified at section 29 USC 794d, as amended, ensures those with disabilities have equal access to government information as contained on information and communications technology (ICT), and thereby to the government employment, programs, and services to which all citizens are entitled.
2) At a minimum, digital documents must comply with the most current version of Section 508 of the Rehabilitation Act as amended. In addition, the DOI and its bureaus strive to meet Levels A and AA of the Web Content Accessibility Guidelines (WCAG) 2.1. and PDF/UA-1 accessibility guidelines.
3) Contractor shall test any final digital documents and a provide a record of passing report (without error) with each final file. For PDFs, use the built-in Adobe accessibility checker. NPS will check all documents for accessibility prior to approving payment.
4) Final documents should include, at a minimum:
a) Document Metadata (including title and language)
b) Proper Tag Structure (use styles for headings, text, lists, table content, and all parts of your document. Do not format “by hand” or with carriage returns and tabs.)
c) Include at least one level 1 heading (H1)
d) Descriptive Alternate Text for Images, figures, and maps (Not mere reproduction of figure captions, unless appropriate)
e) Proper Read Order (particularly important when the layout has multiple columns, side-bars, call-outs, etc.)
f) Descriptive Hyperlinks
i) For tables:
ii) Add tables using table element.
iii) Use one or more table row elements (TR) which define each row of table cells as immediate children of the table element.
iv) Use one or more table header elements (TH) or table data elements (TD) as the immediate children of each table row element.
5) Guidance on creating 508 accessible content from the General Services Administration (GSA) can be found at: https://www.section508.gov/create/
VI. SUBMITTALS AND MOCK-UPS
1) Prior to performing mock-ups or executing work, the contractor shall provide the following submittals for review by the COR and approval by the CO.
a) Develop a Work Plan for NPS to review prior to start of work.
i) The Work Plan must address the following:
(1) Demonstrate an understanding of all project goals and objectives for the conservation of the bronze and masonry elements at the Gompers and Burke statues.
(2) Describe the tools and methology that will be used to complete the project goals and objectives.
(3) Describe how the historic materials will be protected during the project.
(4) Conditions Assessment Report. At the time of the Government’s assessment, there were no visible cracks, losses, broken elements, or mechanical failures around attachment points. If onsite conditions assessment determines that there is additional damage, repair or missing element replacement may be necessary. Provide a conditional work plan for missing element replacement or damage with treatment recommendations for review and approval by the COR and CO.
ii) Schedule, sequence and coordination. Provide a project schedule in Gantt chart format that demonstrates how the Contractor shall successfully complete this project within the prescribed period of performance.
iii) Submittals and Mock-ups.
b) Erect, maintain and remove scaffolding (or access) to ensure that there is no damage to the stone or bronze elements and ensuring that scaffolding is properly erected for work to be complete.
c) Product Data: Submit manufacturer’s Technical Data Sheet (TDS) and Safety Data Sheet (SDS), installation instructions, use limitations, and recommendations for each material to be used.
d) Samples: Submit physical samples of the following materials for COR to review and submit for approval to the CO prior to installation:
i) Mortar for the Gompers Statue Base
ii) Lead Wool/Lead Sheet for Gompers statue and Burke statue
e) Mock-ups: Prior to the start of any work under each item in the section, the contractor shall prepare the following mock-ups and demonstrations of all masonry restoration procedures for COR review and CO approval. The Contractor shall use the materials and methods specified for the work and prepare samples under conditions that reflect actual working conditions.
i) The following represents the minimum list of mock-ups to be performed:
(1) Stone cleaning, general: 4’ x 4’
(2) Stone cleaning, oily stains
(3) Stone repointing, 3 linear feet
(4) Lead Joints, 1 linear feet
(5) Bronze cleaning, general: 1’ x 1’
(6) Bronze spot patination
(7) Bronze hot waxing
ii) Each mock-up shall be prepared in a representative location, selected and approved in consultation with the COR as listed under each item (see under each item for specific directions on mock-up and demonstration requirements).
iii) Samples shall demonstrate technique and quality of workmanship, and will be the basis of acceptance for actual work to be performed.
iv) No work shall proceed without the COR’s review of the mock-up and recommendation of acceptane to the CO.
v) If samples are not approved by the NPS, the Contractor shall provide additional samples as requested. For example, the first time the contractor submits a required submittal, the government has 14 days to review, reject, or approved. The contractor shall resubmit rejected and or approved submittles /with notes within 7 days. The government shall be allotted a minimum of 7 days to review, reject, or approve any submittals that required resubmittal.
vi) Upon acceptance, all mock-ups shall serve as standards for acceptable technique, appearance and material quality for masonry cleaning and restoration.
VII. GENERAL PLACE OF PERFORMANCE AND HOURS OF OPERATION
This project will complete a restoration of the Gompers Statue and Burke Statue, located in Washington, DC.
All work must be performed between the hours of 7:00 AM to 4:00 PM, Eastern Time, Monday through Friday.
The area is open to staff and park vehicles.
No work shall occur on the following Federal Holidays:
New Year’s Day – January 1st Martin Luther King Junior’s Birthday – Third Monday in January President’s Day – Third Monday in February Memorial Day – Last Monday in May Juneteenth – June 19th Independence Day – July 4th Labor Day – First Monday in September Columbus Day – Second Monday in October Veteran’s Day – November 11th Thanksgiving Day – Fourth Thursday in November Christmas Day – December 25th
Note - if any of the holidays stated above fall on a Saturday, the Friday before the actual day is the official day the Government takes for the holiday. If the holiday falls on a Sunday, the Monday after the actual day is the official day the Government takes for the holiday. These dates do not account for any other days or shorten days that may be added prior to any of the holidays mentioned above that may be added at the discretion of any Presidential Administration and implemented by the DOI.
VIII. SCHEDULE
1) It is anticipated that this work will take approximately 120 days to complete after the issuance of the Notice to Proceed.
2) Work shall be performed on a daily basis, without interruption, from the start of testing through project completion, unless weather conditions prohibit the performance of work, or unless directed otherwise by the CO.
IX. SAFETY
During the execution of this contract, the Contractor must conform to the rules and regulations, as amended and as set forth by:
· 29 CFR 1910 – OSHA General Industry Regulations & Standards
· 29 CFR 1926 – OSHA Construction Industry Regulations & Standards
· US Army Corps of Engineers “Safety and Health Requirements” Manual No. 385-1-1 (free online https://www.publications.usace.army.mil/USACE-Publications/Engineer-Manuals/ )
· National Park Service Occupational Safety and Health Program – Reference Manual 50B - Reference Manual 50B: NPS Occupational Safety and Health Program
General Requirements:
· Work area shall always be maintained in a clean and safe condition.
· All personnel providing service on-site shall have pictured identification and uniform displaying the name of the company (if appliable).
· All on-site vehicles shall also be marked with the company name (if applicable).
· Use of barricades, ropes, signs, or audible signals is required, and the contractor must take all necessary precautions for the protection of the work, property, and safety of the public.
· Any accident or incident, regarding the work under this contract, shall be reported immediately, in writing, to the Contracting Officer.
· Smoking of any kind shall not be permitted on premises. The COR/POC may authorize the use of a designated smoking if requested.
Working in a Federal building or Federally controlled indoor workspaces:
In order to take steps to prevent the spread of COVID-19 and to protect the health and safety of all Federal employees, onsite contractors, visitors to Federal buildings or Federally controlled indoor workspaces, and other individuals interacting with the Federal workforce, employees under the subject contract who are required to work on site in Federal buildings or Federally controlled indoor worksites must comply with requirements located at https://www.saferfederalworkforce.gov/overview/
X. LANDSCAPE PRESERVATION
1) The contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.
2) Operation shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto.