This is a Statement of Work (SOW) for sludge removal services at the West Lakes District Wastewater Treatment Plant located at Glacier National Park in West Glacier, Montana. The primary objective is to remove approximately 183 tons of settled sludge and inorganic materials from the main basin and an estimated volume from the winter basin. The main basin has accumulated an average sludge depth of 6.5 feet over more than 20 years of operation since 2003, interfering with operational pipes and valves. The contractor must remove all sludge using appropriate means and methods while protecting the HDPE basin liner, all wastewater treatment equipment, and facilities in place. Removed liquid materials shall be returned to the basins, while dried sludge and waste materials must be legally hauled to an approved local waste management facility outside the park with no on-site disposal permitted.

The contract is structured as a firm, fixed-price award with no progress payments permitted, and work must be completed within 210 days of contract award. All work must comply with 29 CFR 1910 and 1926 occupational safety standards, Montana DEQ regulations, and extensive park-specific requirements including wildlife protection protocols, invasive species prevention measures, visitor management, and fire prevention standards. The contractor must conduct pre-mobilization wildlife briefings, perform daily reporting, and achieve substantial and final completion inspections with punch list corrections due within 30 days. Critical requirements include secondary containment measures to prevent spills, pressure washing of all equipment at 122°F and 2,900 psi before park entry, bear-proof storage of materials and food, portable toilet facilities, and coordination with NPS staff throughout operations. Work is ideally scheduled outside peak summer months (late May through mid-September) and generally conducted Monday through Friday, 7 a.m. to 6 p.m.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Remove Sludge From West Lakes District Wastewater Treatment Plant

SCOPE OF SERVICES

REMOVE SLUDGE FROM WEST LAKES DISTRICT WASTEWATER TREATMENT PLANT

GLACIER NATIONAL PARK

UNITED STATES DEPT. OF THE INTERIOR

FINAL – 01/22/2026

0.0 TABLE OF CONTENTS

1.0 Overview & Project Description

2.0 Existing Conditions

3.0 Scope of Work

4.0 Codes & Authorities

5.0 Required Meetings, Submittals, & Closeout

6.0 Special Conditions & Requirements

7.0 Period of Performance

8.0 Attachments

1.0 OVERVIEW & PROJECT DESCRIPTION

This project will remove sludge and inorganic materials from a wastewater basin at the West Lakes District Wastewater Treatment Plant (WWTP) at Glacier National Park. The main wastewater basin, after more than 20 years in service, has an estimated 6.5 feet of settled sludge and inorganic material settled at the bottom of the basin. The sludge interferes with pipes and valves that connect the basin to the wastewater plant building.

This contract is limited to sludge removal and related activities only – the basin liner and all WWTP equipment shall remain unchanged.

All field work shall occur at the West Lakes District Wastewater Treatment Plant – 427 Barn Road, West Glacier, MT 59936. This is located just past the West Entrance Station of Glacier National Park.

A firm, fixed price contract shall include all preparation, mobilization, facilities, management, labor, equipment, materials, permitting, and other costs incurred to complete the requirement as defined under Section 3.0 Scope of Work.

Refer to Section 2.0 Existing Conditions for a description of the existing conditions for each CLIN. Refer to Section 8.0 Attachments for a list of materials and data provided by NPS.

2.0 EXISTING CONDITIONS

2.1. WLD Wastewater Treatment Plant

2.1.1. Main Basin

a. HDPE liner

b. 12’ width concrete access ramp

c. Aerated (two surface, two downdraft)

d. Decant structure

e. 2:1 side wall slope

f. 366’ x 126’ at the high water level of 9 feet

g. Approximately 2,130,000 gallons = 285,000 cubic feet capacity at high water level

h. Estimated average sludge depth of 6.5’ and TSS of 31,700 mg/L, an estimated total of 183 tons of sludge, based off measurements and calculations recorded by the wastewater plant operators in Summer 2025.

i. A small amount of sludge is removed from the basin each year, but the basin has not been thoroughly cleaned since the wastewater treatment plant opened in 2003. Expect heavy inorganic materials (trash pumped out of vault toilets) mixed in with the sludge.

2.1.2. Winter Basin

a. HDPE Liner

b. 12’ width concrete access ramp

c. Not aerated

d. Approximately 350’ x 157’ at side water level of 12’

e. 3,397,600 gallons = 454,160 cubic feet capacity

f. Estimated sludge depth of up to 2 feet above the drain in the northeast corner of the basin (on attached plans, at 3165.80 feet); due to the basin’s slope to this drain, approximately one-half of the area basin contains an amount of settled sludge.

2.1.3. Residuals Drying Basin

a. 8’ side wall depth

b. 2:1 side wall slope

c. 502,475 gallons = 67,175 cubic feet capacity at high water level

2.1.4. Estimation Note

a. Please note, these numbers are only a rough estimate and not guaranteed; the Contractor is solely responsible for determining the effort required to remove all sludge from the Main Basin and Winter Basin. Potential bidders are strongly encouraged to visit the site to verify measurements and conditions. Expect that sludge characteristics have changed between Summer 2025 and the time of work.

3.0 SCOPE OF WORK

3.1. The Contractor shall determine the appropriate means and methods to accomplish the project objectives. Inspect all existing conditions and understand the full scope of related tasks. Bring any questions or unforeseen conditions to the attention of the CO.

3.2. General

3.2.1. Complete a walkthrough with NPS wastewater and utility operators at the beginning of work. Carefully coordinate with NPS sludge removal activities to avoid interference with regular operations of the Wastewater Treatment Plant. Seek to minimize interference and disturbance to regular operations. Coordinate with NPS if any facilities must be removed or relocated, turned off, de-energized, or otherwise altered during work. Follow lockout-tagout procedures. The Contractor shall reinstate all facilities prior to the conclusion of work.

3.2.2. Protect all wastewater treatment, plant equipment and facilities in place. The Contractor shall correct accidental damage immediately at no additional cost to NPS.

3.2.3. Locate temporary equipment in a manner that does not impose excessive loads on lagoon berms or roadside berms. Do not operate equipment on the basin liner.

3.2.4. All operations shall take place within the fenced area of the Wastewater Treatment Plant.

3.3. Sludge Removal

3.3.1. Remove all sludge and other debris from the Main Basin and Winter Basin. Removed liquid materials shall be returned to the Main Basin or Winter Basin. Legally haul dried sludge and waste materials to a local waste management facility that accepts dried sludge materials (note – verify sludge acceptance criteria with the local waste management facility prior to the start of work). Ensure no spillage of sludge materials along the route. No materials shall be disposed of in the Park.

3.3.2. The Contractor shall exercise all reasonable measures to prevent the release of wastewater and sludge, including, but not limited to, using secondary containment and inspecting installation and operation of temporary pumping equipment, materials, and appurtenances. Spills shall be cleaned immediately. No sludge material, wet or dry, shall be stockpiled directly on the ground. Dried sludge shall be hauled off site immediately.

3.3.3. Do not allow waste materials to accumulate on site. Remove and transport material in a manner to prevent spillage. Any spills shall be cleaned immediately.

3.3.4. Any soil that becomes contaminated by sewage shall be immediately treated, removed, and safely stored in an area protected from animals, humans, weather or conditions that may cause leaching. Dispose of contaminated soil according to applicable Federal, State, and local laws and regulations. Workers must use appropriate PPE including disposable, impervious gloves, disposable safety suits, rubber boots, and face shield or splashguard. Workers shall thoroughly wash off after handling is complete.

3.3.5. Fully remove any temporary facilities and clean the site of any debris prior to project completion.

4.0 CODES & AUTHORITIES

4.1. All work shall be performed in accordance with the following codes. Should codes conflict, the more stringent requirement shall apply.

4.1.1. Health and Safety Codes

a. 29 CFR 1910 Occupational Safety And Health Standards

b. 29 CFR 1926 Safety And Health Regulations For Construction

c. NFPA 241 Standards For Safeguarding Construction, Alteration, And Demolition Operations

4.1.2. Montana State Codes

a. Montana DEQ Circulars, current editions

5.0 REQUIRED MEETINGS, SUBMITTALS, PAYMENTS, & CLOSEOUT

5.1. Post-Award Meeting

5.1.1. A post-award meeting will be held online with the Contractor and NPS to cover basic procedures and regulations. This meeting will include, at minimum: discussions on Park rules and regulations, wildlife management, correspondence procedures, progress meetings, lines of authority, roles and responsibilities, acceptance and rejection of work, liquidated damages, labor standards, contract modifications, accident prevention, quality control, emergency procedures, road and site constraints, environmental considerations.

5.1.2. Meeting notes will be recorded and distributed by the COR.

5.2. Submittals

5.2.1. Submit the following items prior to final closeout:

a. Contractor Daily Reports

5.3. Payments

5.3.1. The contract is a firm, fixed price. Progress payments are not permitted. The Contractor shall invoice via IPP.gov. Invoice payments and requests shall only be approved when the required closeout information is provided to NPS and all work is deemed satisfactory.

5.4. Project Closeout

5.4.1. Submittals

a. Submit all deliverables listed in Section 5.2 Submittals and make any corrections required by the CO’s review.

5.4.2. Final Cleaning

a. Prior to the Final Inspection, the Contractor shall perform a final cleaning of the project area, including removal of all tools, equipment, materials, waste, and any grease, stains, labels, or other foreign materials. The project area shall be clean and ready for use by NPS.

5.4.3. Substantial Completion, Final Inspection, and Acceptance

a. As the project is nearing completion, submit written certification that the project, or designated portion of the project, is substantially complete and ready for a Substantial Completion Inspection. After the Substantial Completion Inspection, the CO will issue a punch list for any deficiencies noted. The CO will issue a Letter of Substantial Completion.

b. At the completion of the punch list items, the Contractor shall request a Final Inspection. The CO will ensure that all work and punch list items are completed to the satisfaction of NPS.

c. All deficiencies shall be corrected within 30 days, weather permitting. The CO will issue a Letter of Acceptance when all deficiencies are corrected. If the Contractor fails to complete the work within 30 days of issuance of the punch list, the CO may correct the work with an appropriate reduction in the contract price or charge for re-inspection costs.

6.0 SPECIAL CONDITIONS & REQUIREMENTS

6.1. Wildlife Protection

6.1.1. Wildlife protection is of utmost importance. All Contractors and Subcontractors shall receive a briefing on working around wildlife, including bears, prior to the start of work. Notify the CO at least 14 days prior to the start of work to schedule this briefing. All construction personnel are required to fully understand and abide by all Park requirements, which shall be strictly enforced at all times. Failure to comply shall result in a citation and fine. A copy of Bear, Wildlife, and Sanitation Requirements While Working in Glacier National Park will be provided to the Contractor. Key points of this document include:

a. Food handling and storage

1) When not in use, food, beverages, containers, and utensils shall be kept inside of buildings, enclosed vehicles or trailers, storage sheds, or bear-proof coolers.

b. Material handling and storage

1) Mortar bags are known to attract goats, sheep, and deer. These materials shall be kept under tarps to deter wildlife.

c. Petroleum product, antifreeze, and chemical handling and storage

1) Petroleum products, antifreeze, and other chemicals are known to attract and kill wildlife. When not in use, these materials shall be kept in bear-resistant containers.

d. Equipment use, maintenance, and refueling

1) Leaky equipment shall be repaired immediately.

2) Refueling and servicing shall not occur within 100 feet of a water body.

e. Sanitation requirements, including site cleanliness, trash handling and disposal, and portable toilet requirements

1) Portable toilets must be lockable and be firmly staked into the ground to resist the force of 70 mph winds, or that of a curious grizzly bear.

2) Construction debris and trash must be disposed of in bear-proof bins or dumpsters, unless kept inside of buildings, enclosed vehicles or trailers, storage sheds, or bear-proof containers.

3) Construction debris and food waste shall not be mixed.

4) Immediately collect and contain scraps and waste.

f. Wildlife safety and potential wildlife interactions

1) All personnel shall have bear spray readily available.

2) Activities shall be suspended if a bear, wolf, mountain lion, or other aggressive, conditioned, or habituated animal comes near the construction area and creates a potential human-wildlife conflict. Notify Park Rangers immediately for resolution of the potential conflict.

3) Report wildlife sightings to the CO and COR.

6.1.2. Protect natural habitats, including nests, and ecological systems at or near the project site.

6.1.3. Protect any unknown or undiscovered threatened, endangered, or special status species. Immediately stop work and contact the CO and COR if these species are found at the site.

6.2. Natural Resource Protection

6.2.1. Air, Water, and Soil Pollution

a. Employ construction practices that minimize dust production and combustion byproducts.

b. Avoid materials that can leach toxic chemicals into the groundwater. Do not allow toxic chemicals to enter sewers or storm drains. Apply Best Management Practices, including vehicle wash-down areas, equipment storage and maintenance areas protection, and roadway sweeping related to hauling activities.

c. Air quality impacts are expected to be temporary and localized. To reduce tailpipe emissions, vehicles and equipment shall not be left idling any longer than is necessary for safety and mechanical reasons.

d. Volatile wastes shall be stored according to best industry practices and in covered containers.

e. Repair leaky equipment immediately.

1) Do not use equipment that is leaking.

2) Keep a supply of acceptable absorbent materials at the job site in the event of spills.

3) Acceptable absorbent materials are those manufactured specifically for containment and clean-up of hazardous materials.

f. Protect against erosion, contamination, and topsoil depletion.

6.2.2. Invasive Species

a. To prevent the introduction of noxious weeds to the Park, the Contractor shall thoroughly pressure wash all earth-moving and off-road vehicles and equipment with minimum 122°F water at 2,900 psi prior to entering the Park. All equipment must be free of soils, plant matter, and other debris as determined the COR. Coordinate inspections with the COR at least two business days prior to bringing equipment to the Park. Failed inspections must be corrected at the Contractor’s expense. Vehicles and equipment that are re-entering the Park do not have to be cleaned again, provided that it has not operated on a different jobsite. Coordinate with the COR.

b. All imported rocks, gravel, fill, or topsoil shall be sourced from an NPS approved weed-free source. This list is maintained by NPS. Coordinate with the COR.

6.2.3. Soundscapes

a. Minimize noise generated during construction.

6.3. Visitor Management

6.3.1. The Contractor is responsible for jobsite safety and security. The Contractor shall secure the jobsite to prevent any potential hazards to visitors and NPS staff.

6.3.2. Minimize interference with NPS operations, visitors, and traffic near the project area. Coordinate with NPS.

6.4. Contractor Access to the Park and Facilities

6.4.1. The Park does not provide lodging or campsites to Contractors. The Contractor shall not set up undesignated camps at (or near) the project site. The Contractor is responsible for finding accommodations on their own.

6.4.2. Coordinate with the COR to obtain a Commercial Vehicle Non-Recreational Entrance Pass. An Entrance Pass is required to be displayed on the dashboard of all Contractor vehicles. Come to a full stop at the Entrance Station (the Contractor shall use the “Authorized Vehicles Only” bypass lane), show the Entrance Pass to the Park Ranger at the window, and they will wave you through. Entrance Passes are of no cost to the Contractor.

a. The Entrance Pass will be valid to enter the Park at the West Entrance (in West Glacier) only.

6.5. Contractor Use of Utilities

6.5.1. There is no water, sewer, electric, or internet service available for Contractor use at the project site.

6.5.2. Cell service with most carriers should work at the project site. Cellular data usage shall be limited in the summer months.

6.5.3. The Contractor shall provide and maintain portable toilets facilities for the duration of the project. Portable toilets shall be lockable and staked into the ground to resist the force of 70 mph winds, or that of a curious grizzly bear.

6.5.4. The Contractor shall fully remove all temporary facilities prior to the final inspection.

6.5.5. Keep utility service disruptions to a minimum. If disrupting NPS owned utilities, coordinate with the CO, COR, and NPS at least two weeks in advance of any utility disruptions. Coordinate with other utility providers and follow the utility provider’s procedures if other utilities will be disrupted.

6.5.6. Accidental utility damage or disruptions shall be remedied immediately at no cost to NPS.

6.6. Contractor Use of Site

6.6.1. The Contractor shall keep the site neat and orderly at all times. Schedule regular “housekeeping” to ensure this. The site must always be free of wildlife attractants and potential hazards to NPS and visitors.

6.6.2. The Contractor shall minimize the footprint of the site.

6.6.3. The Contractor shall confine operations to within the Wastewater Treatment Plant’s fenced boundary.

6.6.4. The Contractor shall prevent undue damage to the site’s natural surroundings.

6.6.5. The Contractor shall allow for NPS occupation or visitation of the site. Keep driveways and entrances serving premises clear and available to NPS and emergency vehicles.

6.7. Vehicles, Equipment, Parking & Staging Areas

6.7.1. The Contractor shall clean vehicles and equipment to prevent the introduction of invasive species or noxious weeds into the Park, as described in Section 6.2. Natural Resource Protection above.

6.7.2. Comply with all local, state, and federal loading and hauling restrictions.

a. The railroad overpass bridge at the intersection of US-2 and Going to the Sun Road in West Glacier has as clearance of approximately 13’-6”. Verify clearance and vehicle height before taking this route. The alternate route is to take the North Fork Road to Camas Road into the Park. This route is closed in the winter months.

6.7.3. Parking and staging areas shall not obstruct emergency traffic, visitor traffic, or prevent NPS occupation or visitation of the site.

6.7.4. Do not park or operate vehicles and equipment on vegetated surfaces, unless within the defined limits of disturbance of the site. Do not damage trees or shrubs that are to remain.

6.7.5. Parking, staging, and storage is at the risk of the Contractor.

6.8. Material Handling & Waste

6.8.1. The Contractor shall handle and store materials and waste as described in Section 6.1. Wildlife Protection above.

6.8.2. The Contractor shall be present to accept any deliveries. NPS will not accept deliveries on the Contractor’s behalf.

6.8.3. All waste shall be disposed of outside of the Park in accordance with local, State, and Federal requirements.

6.9. Quality Control

6.9.1. Quality Control

a. The quality of all work shall be the responsibility of the Contractor. Inspect and test all work as needed to ensure that the highest quality of work.

6.9.2. Enforcement

a. The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the QCS or the CO.

6.10. Safety and Accident Prevention

6.10.1. Quality Assurance

a. The Contractor shall maintain a Safety and Accident Prevention Plan to identify, assess, and mitigate potential hazards associated with the project through all phases of work. The Safety and Accident Prevention Plan shall encompass detailed safety protocols, emergency response procedures, and protective measures aimed at ensuring the well-being of all Contractor and Subcontractor personnel, NPS employees, and visitors on or around the site.

b. A qualified and competent supervisor (and alternate supervisor, if applicable) shall be named to oversee and carry out the SAPP.

c. The Contractor shall ensure that all employees are physically qualified to perform their assigned duties safely. Do not allow employees to work if their abilities are impaired. Operators of all equipment shall be able to understand signs, signals, and operating instructions and be capable of operating such equipment.

6.10.2. Hazardous Spills

a. The Contractor shall incorporate preventative measures into their Safety and Accident Prevention Plan to prevent hazardous spills. Hazardous spills shall be reported to Glacier Dispatch and NPS immediately.

6.10.3. Visitor and Traffic Management

a. The Contractor shall incorporate preventative measures into their Safety and Accident Prevention Plan to prevent hazards to NPS employees and visitors at or near the jobsite.

1) The project site is located outside of public areas, but must be accessed by roads with considerable traffic in the summer and fall months.

6.10.4. Safety Measures

a. The following shall be provided by the Contactor:

1) First Aid supplies

2) PPE that meets NIOSH and MSHA standards

3) Emergency instructions, including phone numbers and reporting instructions for Glacier Dispatch and emergency medical care

4) Adequate egress at all times, following Life Safety Code NFPA 241

5) Hard hats for all employees and visitors

6) Posted signs in all designated hard hat areas

7) Hazardous spill clean-up kit

8) Fire prevention and protection equipment, as outlined in Section 6.13. Fire Prevention and Protection

b. Training

1) Provide training for first aid and hazardous material handling and storage.

2) On-site safety meetings with all personnel shall be conducted at least once per week.

c. Enforcement

1) The Contractor shall stop work on any item or feature pending satisfactory correction of any safety issue noted by any of the Contractor's staff, the subcontractor's staff, COR, or the CO.

d. Accident Reporting

1) Reportable accidents, defined as death, occupational disease, traumatic injury to Contractor's personnel, NPS employees or the public, property damage of any accident more than $100 and fires, must be reported immediately. Complete an Accident/Property Damage Report using the NPS standard Form CM-22 and forward to the CO within seven days.

6.11. Fire Prevention and Protection

6.11.1. Fire Safety

a. Observe and enforce standards of fire prevention. No open fires shall be allowed.

b. Capable and qualified person shall be in change for fire protection and prevention. Their responsibilities include locating and maintaining fire protection equipment and establishing and maintaining safe torch cutting and welding procedures.

6.11.2. Vehicles and Equipment

a. Provide one fire extinguisher on each vehicle or piece of equipment. A minimum of one fire extinguisher shall be readily available in all work areas. Extinguishers shall have a minimum UL rating of 2-A:10-B:C.

6.11.3. Hazard Control

a. Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in enclosed areas. Provide adequate ventilation during use of volatile or noxious substances.

6.11.4. Spark Arrestors

a. Equip all gasoline or diesel-powered equipment used in potential forest or grass fire locations with spark arresters approved by the U.S. Forest Service. Written determinations of areas and periods of potential fire hazard will be issued by CO. Locate internal combustion equipment so that exhausts discharge well away from combustible materials. Shut down equipment before refueling.

6.11.5. Smoking

a. Smoking inside of structures or near potentially combustible materials is prohibited. Cigarette butts shall be discarded in non-combustible containers and disposed of properly.

6.11.6. Stage 2 Fire Restrictions

a. Should the Park enter Stage 2 Fire Restrictions during the period of performance, the Contractor shall be required to obtain a Stage 2 Fire Restriction Exemption Permit from the GLAC Fire Management Office. Additional firefighting tools shall be required to be readily available during work.

b. Stage 2 Fire Restrictions prohibit the following activities, without an exemption permit:

1) Building, maintaining, attending, or using a campfire

2) Smoking, outside of an enclosed vehicle or area clear of flammable materials

3) The following acts are prohibited between 1:00 pm and 1:00 am:

1. Operation of an internal combustion engine, except for use of generators with an approved spark arrestor in an enclosed vehicle or building or area cleared of any flammable materials within three feet of the generator.

2. Welding or use of a torch with an open flame

3. Use of explosives

4) Operation of motorized vehicles off designated roads or trails.

7.0 PERIOD OF PERFORMANCE

7.1. The project shall be completed within 210 days of contract award. Coordinate the project schedule with NPS. Ideally, work shall be completed outside of the summer months of late-May to mid-September – peak demand on the wastewater plant.

7.2. Work shall generally be performed from 7 am to 6 pm, Monday to Friday. Weekends and holidays may be worked if approved at least two business days in advance by the COR and CO.

8.0 ATTACHMENTS

1.1 Project Scope of Services (this document)

1.2 WWTP Vicinity Map

1.3 GLAC_117_41097 WWTP Plans for Reference