B08_Solicitation_-_Attachment_1_-_SOW.pdf

PDF 14 MB Posted

Attached to
EFMO - Water System Rehabilitation 36569 Federal contract opportunity
Solicitation number
140P6022R0019
Issued by
Department of the Interior National Park Service Midwest Region

About this file

This document outlines requirements for a solicitation to rehabilitate water systems at various sites within the Midwest Region of the National Park Service. The solicitation number is 140P6022R0019 and seeks to address water infrastructure needs at Site 36569. Offerors are to propose solutions for upgrading or replacing pipes, pumps, treatment systems and related assets to ensure safe, reliable drinking water. Proposals are due by the end of the current fiscal year with work expected to begin in the next construction season. Pricing shall be fixed for the base period of performance with economic price adjustment terms defined for option years if exercised.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EFFIGY MOUNDS

NATIONAL MONUMENT

Iowa

WATER SYSTEM RENOVATIONS

EFMO

PMIS NO. 224112

PROJECT SPECIFICATIONS

(100% Construction Documents)

NATIONAL PARK SERVICE

MIDWEST REGION

December 2021

EFMO - 224112 00 01 07 - 1

Project Seals

PROJECT SEALS

Owner Name: National Park Service, Midwest Region Facility or Site Name: Effigy Mounds National Monument, Iowa Project Name: Water System Renovations Project or Contract Designation: PMIS No. 224112 Engineer: HDR

I hereby certify that the portion of this technical submission described below was prepared by me or under my direct supervision and that I am a duly registered Professional Engineer under the laws of the State of Iowa.

Kevin F. Newman 8-27-2021

My license renewal date is December 31, 2021

Division 01 (except 01 45 33), 31, 32, 33, 40 (except 40 71 00, 40 73 00, 40 91 10), 43, 46

Section 09 96 00, 10 14 00, 21 12 00, I hereby certify that the portion of this technical submission described below was prepared by me or under my direct supervision and that I am a duly registered Professional Engineer under the laws of the State of Iowa.

Svein K. Magnussen 8-27-2021

My license renewal date is December 31, 2021

Division 03, 05

Section 01 45 33, 04 22 00

EFMO - 224112 00 01 07 - 2

THIS PAGE INTENTIONALLY LEFT BLANK

EFMO - 224112 00 01 07 - 3

PROJECT SEALS

Owner Name: National Park Service, Midwest Region Facility or Site Name: Effigy Mounds National Monument, Iowa Project Name: Water System Renovations Project or Contract Designation: PMIS No. 224112 Engineer: HDR

I hereby certify that the portion of this technical submission described below was prepared by me or under my direct supervision and that I am a duly registered Professional Architect under the laws of the State of Iowa.

Scott P. Heaney 8-27-2021

My license renewal date is June 30, 2022

Division 04 (except 04 22 00), 06, 07, 08, 09 (except 09 96 00), 10 (except 10 14 00), 12

Section 09 96 00, 10 14 00, 21 12 00

I hereby certify that the portion of this technical submission described below was prepared by me or under my direct supervision and that I am a duly registered Professional Engineer under the laws of the State of Iowa.

Zachary J. Sachsenmaier 8-27-2021

My license renewal date is December 31, 2020

Section 21 10 00, 28 31 00

EFMO - 224112 00 01 07 - 4

EFMO - 224112 00 01 07 - 5

PROJECT SEALS

Owner Name: National Park Service, Midwest Region Facility or Site Name: Effigy Mounds National Monument, Iowa Project Name: Water System Renovations Project or Contract Designation: PMIS No. 224112 Engineer: HDR

I hereby certify that the portion of this technical submission described below was prepared by me or under my direct supervision and that I am a duly registered Professional Engineer under the laws of the State of Iowa.

Jeffrey A. Lewis 8-27-2021

Division 22, 23

I hereby certify that the portion of this technical submission described below was prepared by me or under my direct supervision and that I am a duly registered Professional Engineer under the laws of the State of Iowa.

James A. Zavadil 8-27-2021

Division 26

Section 40 71 00, 40 73 00, 40 91 10

Contracting Requirements.

It is a violation of applicable laws and regulations governing professional licensing and registration for any person, unless acting under the direction of the licensed and registered design professional(s) indicated above, to alter in any way the Specifications in this project manual.

END OF SEALS AND SIGNATURES

EFMO - 224112 00 01 07 - 6

EFMO - 224112 00 01 10 - 1

Table of Contents

TABLE OF CONTENTS

DIVISION 01 GENERAL REQUIREMENTS

01 11 00 - SUMMARY OF WORK

01 26 01 - CONTRACT MODIFICATION PROCEDURES

01 27 00 - DEFINITION OF CONTRACT LINE ITEMS

01 31 00 - PROJECT MANAGEMENT AND COORDINATION

01 32 16 - CONSTRUCTION SCHEDULE

01 32 33 - PHOTO DOCUMENTATION

01 33 23 - SUBMITTAL PROCEDURES

01 33 23A - TRANSMITTAL FORM (CM-16)

01 33 23B - SUBMITTAL LIST

01 35 13.22 - ARCHEOLOGICAL PROTECTION

01 35 23 - SAFETY REQUIREMENTS

01 40 00 - QUALITY REQUIREMENTS

01 42 00 - REFERENCE STANDARDS

01 45 33 - SPECIAL INSPECTIONS AND TESTING PROGRAM

01 50 00 - TEMPORARY FACILITIES AND CONTROLS

01 57 23 - UNDER-AN-ACRE POLLUTION PREVENTION

01 65 50 - PRODUCT DELIVERY, STORAGE, AND HANDLING

01 67 00 - PRODUCT REQUIREMENTS

01 73 20 - OPENINGS AND PENETRATIONS IN CONSTRUCTION

01 73 29 - CUTTING AND PATCHING

01 73 40 - EXECUTION

01 74 19 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 74 19A - PROJECT WASTE MANAGEMENT PLAN WORKSHEET

01 74 19B - STANDARD SOLID WASTE CONVERSIONS

01 77 00 - CLOSEOUT PROCEDURES

01 77 00A - CLOSEOUT AND OPERATION AND MAINTENANCE REQUIREMENTS

01 78 23 - OPERATION AND MAINTENANCE DATA

01 79 00 - DEMONSTRATION AND TRAINING

01 81 13 - SUSTAINABLE DESIGN REQUIREMENTS FOR NON LEED PROJECTS

01 91 14 - TOTAL BUILDING COMMISSIONING

DIVISION 03 CONCRETE

03 00 05 - CONCRETE

03 15 19 - ANCHORAGE TO CONCRETE

DIVISION 04 MASONRY

04 01 20 - MASONRY CLEANING

04 05 13 - MASONRY MORTAR AND GROUT

04 05 23 - MASONRY ACCESSORIES

04 05 50 - COLD AND HOT WEATHER MASONRY CONSTRUCTION

04 21 13 - BRICK MASONRY

04 22 00 - CONCRETE MASONRY

EFMO - 224112 00 01 10 - 2

DIVISION 05 METALS

05 41 00 - LOAD-BEARING METAL STUD SYSTEM

05 42 50 - PRE-ENGINEERED COLD FORMED TRUSSES

05 50 00 - METAL FABRICATIONS

DIVISION 06 WOOD, PLASTICS, AND COMPOSITES

06 10 00 - ROUGH CARPENTRY

DIVISION 07 THERMAL AND MOISTURE PROTECTION

07 14 00 - FLUID APPLIED WATERPROOFING

07 21 00 - BUILDING INSULATION

07 61 13 - METAL ROOFING

07 62 00 - FLASHING AND SHEET METAL

07 84 00 - FIRESTOPPING

07 92 00 - JOINT SEALANTS

DIVISION 08 OPENINGS

08 11 00 - HOLLOW METAL DOORS AND FRAMES

08 33 23 - STEEL ROLLING OVERHEAD DOORS

08 51 13 - ALUMINUM WINDOWS

08 70 00 - FINISH HARDWARE

08 81 00 - GLASS AND GLAZING

08 90 00 - LOUVERS AND VENTS

DIVISION 09 FINISHES

09 22 16 - NON-STRUCTURAL METAL FRAMING

09 29 00 - GYPSUM BOARD

09 91 10 - ARCHITECTURAL PAINTING

09 96 00 - HIGH PERFORMANCE INDUSTRIAL COATINGS

DIVISION 10 SPECIALTIES

10 14 00 - IDENTIFICATION DEVICES

10 28 13 - TOILET AND BATH ACCESSORIES

10 44 33 - FIRE PROTECTION SPECIALTIES

DIVISION 12 FURNISHINGS

12 35 53 - LABORATORY CASEWORK (METAL)

DIVISION 21 FIRE SUPPRESSION

21 10 00 - FIRE PROTECTION SYSTEMS

21 12 00 - BOLTED PANEL TYPE POTABLE WATER STORAGE TANK

EFMO - 224112 00 01 10 - 3

DIVISION 22 PLUMBING

22 05 03 - PIPE AND PIPE FITTINGS - PLUMBING SYSTEMS

22 05 23 - GENERAL-DUTY VALVES FOR PLUMBING PIPING

22 05 29 - HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

22 05 53 - IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

22 20 00 - PLUMBING FIXTURES AND EQUIPMENT

22 33 13 - INSTANTANEOUS DOMESTIC WATER HEATERS

DIVISION 23 HEATING VENTILATING AND AIR CONDITIONING

23 05 13 - COMMON MOTOR REQUIREMENTS FOR PLUMBING AND HVAC EQUIPMENT

23 05 53 - IDENTIFICATION FOR HVAC, DUCTWORK, PIPING AND HVAC EQUIPMENT

23 05 93 - HVAC SYSTEMS - BALANCING AND TESTING

23 31 00 - HVAC - DUCTWORK

23 34 00 - HVAC - FANS

23 80 00 - HVAC - EQUIPMENT

DIVISION 26 ELECTRICAL

26 05 00 - ELECTRICAL - BASIC REQUIREMENTS

26 05 19 - WIRE AND CABLE - 600 VOLT AND BELOW

26 05 26 - GROUNDING AND BONDING

26 05 33 - RACEWAYS AND BOXES

26 05 43 - ELECTRICAL - EXTERIOR UNDERGROUND

26 09 13 - ELECTRICAL METERING DEVICES

26 24 16 - PANELBOARDS

26 24 19 - MOTOR CONTROL EQUIPMENT

26 27 26 - WIRING DEVICES

26 28 00 - OVERCURRENT AND SHORT CIRCUIT PROTECTIVE DEVICES

26 28 16 - SAFETY SWITCHES

26 29 23 - VARIABLE FREQUENCY DRIVES - LOW VOLTAGE

26 41 13 - LIGHTNING PROTECTION SYSTEM

26 43 13 - LOW VOLTAGE SURGE PROTECTION DEVICES (SPD)

26 50 00 - INTERIOR AND EXTERIOR LIGHTING

DIVISION 28 ELECTRONIC SAFETY AND SECURITY

28 31 00 - FIRE ALARM SYSTEM

DIVISION 31 EARTHWORK

31 10 00 - SITE CLEARING

31 23 00 - EARTHWORK

31 23 33 - TRENCHING, BACKFILLING, AND COMPACTING FOR UTILITIES

31 25 00 - SOIL EROSION AND SEDIMENT CONTROL

DIVISION 32 EXTERIOR IMPROVEMENTS

32 12 16 - ASPHALTIC CONCRETE VEHICULAR PAVING

32 91 13 - TOPSOILING AND FINISHED GRADING

32 92 00 - SEEDING, SODDING AND LANDSCAPING

EFMO - 224112 00 01 10 - 4

DIVISION 33 UTILITIES

33 05 07 - HORIZONTAL DIRECTIONAL DRILLING

33 11 13 - WATER MAIN CONSTRUCTION

33 11 15 - WATER WELLS

DIVISION 40 PROCESS INTERCONNECTIONS

40 05 00 - PIPE AND PIPE FITTINGS - BASIC REQUIREMENTS

40 05 06 - PITLESS UNIT

40 05 07 - PIPE SUPPORT SYSTEMS

40 05 19 - PIPE - DUCTILE

40 05 23 - PIPE - STAINLESS STEEL

40 05 31 - PIPE - PLASTIC

40 05 33 - PIPE - POLYETHYLENE (HDPE)

40 05 51 - VALVES - BASIC REQUIREMENTS

40 05 61 - GATE VALVES

40 05 63 - BALL VALVES

40 42 00 - PIPE, DUCT AND EQUIPMENT INSULATION

40 71 00 - FLOW INSTRUMENTATION

40 73 00 - PRESSURE INSTRUMENTATION

40 91 10 - PRIMARY METERS AND TRANSMITTERS

DIVISION 43 PROCESS GAS AND LIQUID HANDLING, PURIFICATION AND STORAGE

EQUIPMENT

43 21 00 - PUMPING EQUIPMENT - BASIC REQUIREMENTS

43 23 90 - PUMPING EQUIPMENT - POTABLE WATER PUMPING SYSTEM

43 24 26 - PUMPING EQUIPMENT - SUBMERSIBLE VERTICAL TURBINE

DIVISION 46 WATER AND WASTEWATER EQUIPMENT

46 33 11 - CHEMICAL FEED - LIQUID SYSTEMS

APPENDICES

APPENDIX A - GEOTECHNICAL REPORT

GENERAL REQUIREMENTS

EFMO - 224112 01 11 00 - 1

SUMMARY OF WORK

2021/12/30

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Work Restrictions.

9. Special Construction Requirements.

10. Soils Investigation Report.

11. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Effigy Mounds National Monument, located 10 miles south of Harpers Ferry, IA.

B. The Work consists of the following:

1. The Work includes water system renovations including but not limited to a new water system building, a new groundwater source well, and replacement of the potable water distribution piping. The water system building includes a water storage tank, potable water pumping systems, fire protection pumping systems, disinfectant chemical feed and building ancillary systems.

C. Project will be constructed under a single prime contract.

1.3 WORK PHASES

A. The Work shall be conducted in two phases in the following order, with each phase substantially complete before beginning the next phase:

1. Phase One: The new well shall be constructed and temporarily connected to the existing potable water supply system. The existing disinfectant chemical feed unit shall be temporarily reconnected to the new well. After the new well and chemical feed systems are online, the existing well shall be abandoned to allow construction of the water system building to proceed. Work of this phase shall be substantially complete within 120 days after the Notice to Proceed.

EFMO - 224112 01 11 00 - 2

2. Phase Two: The remaining Work shall be substantially complete and ready for occupancy at time of Substantial Completion.

1.4 CONTRACTOR USE OF SITE

A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.

B. Storage of Materials: Confine storage of materials to paved areas adjacent to the Maintenance Building.

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Construction Camp: Establishment of a camp within the park will not be permitted.

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

1.5 PUBLIC USE OF SITE

A. The building will be closed to the public during construction.

EFMO - 224112 01 11 00 - 3

1.6 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings:

1. Partial Government Occupancy: Government will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).

B. New Buildings:

1. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of building, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the entire project.

a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government occupancy.

b. Obtain a Certificate of Occupancy from the NPS before Government occupancy.

c. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.

d. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.

1.7 CONDUCT OF OPERATIONS

A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

EFMO - 224112 01 11 00 - 4

1.8 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: subject to Contracting Officer approval.

2. Early Morning Hours: work before 7:00 a.m. requires Contracting Officer approval.

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without written permission.

3. Hours for Utility Shutdowns: subject to Contracting Officer approval.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.

1.9 SPECIAL CONSTRUCTION REQUIREMENTS

A. Archaeological Monitoring: An NPS archaeologist shall monitor all excavation activities. The contractor shall coordinate proposed excavation times with the Contracting Officer. Excavation shall not take place without prior approval of the Contracting Officer or when the Archaeologist is not present.

1.10 SOILS INVESTIGATION REPORT

A. A soils investigation report entitled Geotechnical Exploration, Water Treatment Plant Building, Effigy Mounds National Monument Visitors Center, Marquette/Harpers Ferry, Iowa, July 30, 2020 has been prepared by Allender Butzke Engineers, Inc.

B. A copy of the report is available to all plan holders with this package.

C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

EFMO - 224112 01 11 00 - 5

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 01 11 00

EFMO - 224112 01 26 01 - 1

CONTRACT MODIFICATION PROCEDURES

2020/09/30

SECTION 01 26 01 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead:

attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

EFMO - 224112 01 26 01 - 2

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1) Social Security

2) Medicare

3) Workers Compensation Policy and company calculation to be made available.

EFMO - 224112 01 26 01 - 3

4) FUTA Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA Cap Rate and percentage to be proportionally allocated over one year.

6) Union agreement costs Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. This covers the loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

EFMO - 224112 01 26 01 - 4

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.

Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact A received with the proposal by the date shown within the Request for Proposal letter.

failure to submit within the specified time frame will be construed as the

Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work. Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for miscellaneous tools and equipment in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

EFMO - 224112 01 26 01 - 5

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.

Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead 10% Profit 7.50%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

EFMO - 224112 01 26 01 - 6

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 01 26 01

EFMO - 224112 01 27 00 - 1

DEFINITION OF CONTRACT LINE ITEMS

2020/09/30

SECTION 01 27 00 - DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No.0001: Water System Rehabilitation

1. This item consists of all work required by the plans and specification to complete the renovations to the Effigy Mounds Water System.

2. No separate measurement will be made for payment of the lump sum.

3. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

EFMO - 224112 01 31 00 - 1

PROJECT MANAGEMENT AND COORDINATION

2020/09/30

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination.

3. Submittals

4. Coordination Drawings.

5. Requests for Information (RFIs).

6. NPS/DSC SharePoint Project Website.

7. Project meetings.

8. Environmental Coordination.

9. Permits

B. Related Requirements:

1. Section 01 32 16 struction Schedule construction schedule.

2. Section 01 73 40 field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00

4. Section 01 91 14 Total Building Commissioning

1.2 DEFINITIONS

A. Agency with Jurisdiction

B. Construction Permits Contractor Provided

C. Government Furnished Permits

EFMO - 224112 01 31 00 - 2

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Permit requirements.

7. Pre-installation conferences.

8. Project closeout activities.

9. Commissioning activities.

1.4 SUBMITTALS

A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

EFMO - 224112 01 31 00 - 3

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7.

the Contactor and all subcontractors.

8. Waste Management Plan.

9. Quality Control Plan.

10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).

11. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit.

b. The Agency(ies) with Jurisdiction issuing the permit.

c. Information required from the Government to complete the permit application.

B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.

Work shall not commence until written Notice to Proceed has been issued.

1.5 REQUESTS FOR INFORMATION (RFIS)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.

1. CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

EFMO - 224112 01 31 00 - 4

C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:

1. Enter the general information at the top of the form.

2.

drop-

3. Enter the details of the question and attach related documents.

4.

D. Contracting Officer s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.6 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Jobsite Safety.

4. Resolution of comments on required Division 01 documents.

5. Coordination of Subcontractors.

6. Labor law application.

7. Modifications.

8. Payments to Contractor.

9. Payroll reports.

10. Contract time.

11. Liquidated damages.

12. Contractor Performance Evaluation.

13. Display of Hotline posters.

14. Notice to proceed.

15. Correspondence procedures.

16. Acceptance/rejection of work.

17. Progress meetings.

EFMO - 224112 01 31 00 - 5

18. Submittal procedures.

19. NPS Final Accessibility Inspection.

20. Environmental requirements.

21. Permit requirements.

22. As-constructed drawings/operation and maintenance (O&M) manuals.

23. Saturday, Sunday, holiday and night work.

24. Reference materials.

25. Value engineering.

B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.

All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections,

h. Construction Schedule update (provide updated CPM).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

k. Permit requirements.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

EFMO - 224112 01 31 00 - 6

f. Deliveries.

g. Submittals.

h. Review of mockups.

i. Possible conflicts.

j. Compatibility requirements.

k. Time schedules.

l. Weather limitations.

m. Manufacturer's written instructions.

n. Warranty requirements.

o. Compatibility of materials.

p. Acceptability of substrates.

q. Temporary facilities and controls.

r. Space and access limitations.

s. Regulations of agency(ies) with jurisdiction.

t. Testing and inspecting requirements.

u. Installation procedures.

v. Coordination with other work.

w. Required performance results.

x. Protection of adjacent work.

y. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

1.7 ENVIRONMENTAL COORDINATION

A. -site party responsible for overseeing the for environmental protection.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of the Waste Management Plan(WMP).

c. Implementation of the Indoor Air Quality (IAQ) Management Plan.

d. Implementation of the Storm Water Pollution Prevention Plan(SWPPP).

e. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.

f. Training for Contractor personnel in accordance with their position requirements.

g. Monitoring and documentation of environmental procedures.

EFMO - 224112 01 31 00 - 7

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements.

2. Regulatory Requirements.

3. Indoor Air Quality (IAQ) Management.

4. Noise & Acoustics Management.

5. Temporary Storm Water Pollution Prevention Environmental Management.

6. Construction Waste Management.

C.

for workers performing work on the project site. Training shall include the following:

1. Overview of environmental issues related to the building industry.

2. Overview of environmental issues related to the Project.

3. Review of site specific procedures and management plans:

a. Construction Waste Management.

b. Noise & Acoustics Management.

c. Temporary Storm Water Pollution Prevention.

4. Pollution Prevention (P2) practices: Submit evidence of P2 training and participation in P2 programs.

5. Compliance with environmental regulations: As specified in Regulatory Requirements.

Submit Contractor 40 CFR employee training records upon request of Contracting Officer.

D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Storm Water Pollution Prevention Plan.

1.8 PERMITS

A. General:

1. Permits and Responsibilities: The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a resul Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the work.

2. For the purpose of this contract the Contractor will not be considered an agent of the Government. Therefore the Contractor will comply with the appropriate Federal, State and local laws.

EFMO - 224112 01 31 00 - 8

B.

listed below were negotiated and agreed to by the Government. The terms and provisions of these permits shall be adhered to for the duration specified in each permit.

1. Approval will be obtained from the State of Iowa, Department of Natural Resources, to construct the water system improvements.

C. Potential Permits: The permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist the contractor in determining which permits wi means and methods. The list shall not be considered complete, as it is the responsibility of the contractor to determine means and methods, and obtain the required permits. It is the responsibility of the Contractor to obtain all permits required to legally conduct the work.

1. Electrical Utility Hookup National Park Service

2. Sewer Hookup National Park Service

3. New Water Meter National Park Service

4. Construction trailer, Utilities hookup permit National Park Service

5. Street Closure National Park Service

6. Stormwater Pollution Prevention Permit Iowa Department of Natural Resources

7. Dewatering Permit Iowa Department of Natural Resources

D. Coordination with Agency(ies) with Jurisdiction Issuing Permits

1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying the work: Coordinate meetings, reporting requirements, inspections, or any other requirements.

E. Administrative Procedures:

1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts and to ensure orderly execution of the Work.

2. Supply all needed information to Agency(ies) with Jurisdiction issuing permits, pay any provisions.

3. Upload permits to the NPS/DSC SharePoint project website when the permits are obtained.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 01 31 00

EFMO - 224112 01 32 16 - 1

CONSTRUCTION SCHEDULE

2020/09/30

SECTION 01 32 16 - CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section consists of Construction Schedule requirements including but not limited to the following:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.

C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Float: The measure of leeway in starting and completing an activity.

1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.

EFMO - 224112 01 32 16 - 2

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.

G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.3 SUBMITTALS

A. Electronic Copies: All schedules and reports submitted shall be provided in the native electronic file format. It is the intent of the Government to limit the number of printed reports to only those reports determined by the project team to be essential.

B. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.

C. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit two…