Summary: Project Specifications for Badlands National Park Propane Distribution System Rehabilitation
This is a project specifications document for the rehabilitation of propane distribution lines at Badlands National Park's Administration/Housing Area near Interior, South Dakota (PMIS 171379, Drawing No. 80122). The work consists of removing existing propane piping and installing approximately 3,080 linear feet of new propane distribution piping, 1,980 linear feet of propane service piping (including 330 linear feet via horizontal directional drilling), shutoff valves, and cleaning two culverts. The project also includes 560 cubic yards of channel excavation for drainage improvement and construction of a 285 cubic yard earthen berm to mitigate flooding issues along Ben Reifel Road caused by Cedar Pass East Drainage aggradation. The contract is a single lump-sum item with a 90-calendar-day completion period from Notice to Proceed, with all work inclusive of supply lead times, material deliveries, decommissioning, installation, and final commissioning.
The National Park Service issued this specifications document on May 16, 2025, containing comprehensive technical requirements across multiple divisions including general requirements, demolition, earthwork, exterior improvements, utilities, and miscellaneous services. Key requirements include site-specific accident prevention planning, paleontological monitoring during excavation (with government-provided monitors), temporary erosion and sediment control compliance with EPA NPDES standards and South Dakota DOT requirements, protection of cultural resources and existing utilities, contractor-provided temporary facilities, noise limitations (70-80 dB(A) at 50 feet), weekly safety meetings, photographic documentation of existing conditions and progress, and restoration of damaged areas at no cost to the government. Contractors must submit detailed preconstruction submittals including construction schedules, safety plans, subcontractor lists, waste management plans, storm water pollution prevention plans, and lists of required construction permits within specified timeframes prior to Notice to Proceed issuance.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_Solicitation_Amendment_2_attach_1_Questions_and_Answers__0002.pdf | ||
| Sol_140P6326B0003_Amd_0002.pdf | ||
| Sol_140P6326B0003_Amd_0001.pdf | ||
| B08_Solicitation_attach_2_Drawings.pdf | ||
| B08_Solicitation_attach_3_submittal_list.pdf | ||
| B08_Solicitation_attach_4_WD.PDF | ||
| Sol_140P6326B0003.pdf | ||
| B08_Solicitation_attach_5_Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BADL 171379
Page | 1
BADLANDS NATIONAL PARK
ADMINISTRATION/HOUSING AREA
REHABILITATE PROPANE DISTRIBUTION LINES
PMIS 171379
Drawing No: 80122
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
MAY 16, 2025
5/16/2025 5/16/25
Page | 2
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
Section 01 10 00 - Division 01 Short Form General Requirements Section 01 35 13.23 – Paleontological Protection Section 01 57 13 – Temporary Erosion and Sedimentation Control
DIVISION 02 – DEMOLITION
Section 02 41 00 – Demolition
DIVISION 31 – EARTHWORK
Section 31 10 00 – Site Clearing Section 31 22 00 – Grading Section 31 23 16.13 – Trenching Section 31 23 23 – Fill
DIVISION 32 – EXTERIOR IMPROVEMENTS
Section 32 11 20 – Subbase and Aggregate Base Courses Section 32 12 16 – Asphalt Paving Section 32 13 13 – Concrete Paving Section 32 91 19 – Landscape Grading Section 32 92 19 – Seeding
DIVISION 33 – UTILITIES
Section 33 05 07.13 – Utility Directional Drilling Section 33 52 16 – Gas Hydrocarbon Piping
Page | 3
SECTION 01 10 00
DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: The existing propane distribution system in the administration/housing area is aging and due for replacement. The goal of the project is to replace the existing piping with materials that will provide greater longevity and new valve placement with greater isolation capabilities.
Additionally, aggradation of the Cedar Pass East Drainage causes flooding along Ben Reifel
Road. The goal of this project is also to construct improvements to help mitigate these flooding issues.
1.2 Work Covered by the Contract Documents:
A. Project Location: The project is located in the administration/housing area near the Ben Reifel
Visitor Center within Badlands National Park near Interior, SD.
B. Work consists of: Removal of existing propane piping and construction of approximately
3,080 LF of new propane distribution piping, 1,980 LF of propane service piping, 330 LF of which shall be installed by horizontal directional drilling, shutoff valves, cleanout of two culverts, 560 CY of channel excavation to be hauled to a park-provided soil waste disposal site, and 285 CY of haul-on material for construction of an earthen berm.
C. All work will be performed under a single contract.
D. Period of performance: Work shall be completed within 90 calendar days of the start date provided on the Notice to Proceed.
a. Clarification: The Notice to Proceed will be issued with a period of performance that is all inclusive of supply lead times, material deliveries, decommissioning, installation, anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to Proceed. If there are weather related environmental factors affecting the construction period where unexpected adverse weather conditions may delay progress, the Contracting Officer will work the Contractor to adjust the Period of Performance at no additional cost to the Government.
1.3 Existing Condition Protections:
A. Preservation of Historical and Archeological Fabric:
i. The Historic and Archeological Data Preservation Act of 1974, provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
Page | 4
ii. IF, in connection with operations under this contract, the Contractor, subcontractors, or employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the discovery and notify the
Contracting Officer immediately, when safe to do so, and follow up in writing within 2 days, giving the location and nature of the findings. No objects of cultural resource value may be removed. Contracting Officer will contact other entities as required.
iii. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with Changes clause.
iv. The Contractor will be responsible for protecting the cultural resources within and adjacent to the project area from damage. In addition, the Contractor will be liable for all damage to the cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting
Officer or their representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
v. The Contractor agrees to include this language within all subcontracts.
B. Protection of Landscaping and Surrounding Structures: All Ground Disturbance at this project shall have oversite by an Owner provided Archeologist. Coordinate schedules as required.
The Contractor shall take all necessary measures to provide protection for all trees, fencing, walks and other landscape features and surrounding structures near the work site as noted with the contract. Any such surrounding features damaged, scarred or broken as a result of the Contractor’s operations at the site outside of agreed upon documented extents, shall be treated, repaired or replaced in kind to the satisfaction of the Contracting Officer at no additional expense to the Government.
C. Paleontological Protection: This project shall have Government-provided paleontological monitoring (by park staff) during excavation. The Contractor shall coordinate with the
Contracting Officer’s Representative (COR) to ensure a government-provided paleontological monitor is present on site at all times during earthwork operations. See the Paleontological
Protection specification for additional information.
ITEM 2 – PROTECTING EXISTING UTILITIES
2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative
(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.
2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.
Page | 5
2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:
A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.
B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR. The existing propane distribution system in the affected construction area will be shut down for the duration of construction. The park shall provide temporary propane hookups at each building as necessary during construction. All work involved with temporary propane hookups shall be the park’s responsibility.
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park
Service, and applicable park rules and regulations prescribed by the Park Superintendent.
https://www.nps.gov/badl/learn/management/superintendent-s-compendium.htm
A. Communications: Contractor shall provide the Contracting Officer and COR with methods of communications including land and/or cell phone numbers (note some areas of work have limited service coverage), email and in case of emergency 24-hour contact options for duration of time operations.
B. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting
Officer.
C. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
D. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.
3.2 On-site work hours: Work shall be generally performed during normal business working hours of
8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.
A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.
The following Federal holidays are observed by the National Park Service:
New Year Day
Martin Luther King, Jr’s Birthday
Washington’s Birthday
Memorial Day https://www.nps.gov/badl/learn/management/superintendent-s-compendium.htm
Page | 6
Juneteenth National Independence Day
Independence Day
Labor Day
Columbus Day
Veterans Day
Thanksgiving Day
Christmas Day
B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding
Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal
Holidays (opm.gov).
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
C. Do Not disturb site outside of noted disturbance area, including earthwork and clearing of vegetation, to:
1. 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter
2. 15 feet beyond primary roadway curbs and main utility branch trenches
3. 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas to limit compaction in the constructed area.
D. Utilities
1. General: Cost or use charges for temporary facilities shall be included in the Contract Sum as required.
2. Water Service: Water from existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.
3. Electric Power Service: Electric power from existing system is not available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.
https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022
Page | 7
4. Waste Operation:
a. Toilets: Contractor must provide toilets for contractor personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan.
b. Waste Removal / Recycling: Contractor is responsible for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site. Locate as shown on site plan or coordinated with COR.
E. Security and Protection facilities:
1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.
Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.
3. Tree and Plant Protection: Provide Tree Protection fence at drip line of trees impacted in construction area. Coordinate with COR. Restore damaged areas to original condition, repairing or replacing damaged trees and plants, at no additional expense to the Government.
b. Provide temporary barriers to protect existing trees and plants and root zones.
c. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer Representative and remove agreed-on roots and branches that interfere with construction.
d. Do not fasten ropes, cables, or guys to trees.
e. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.
5. Temporary Enclosures: N/A
6. Site Enclosure Fence: N/A
7. Hot Work Permit: Submit HW-1 Hot work permit form and receive approval from COR prior to Hot work activities commencing on site.
3.4 Storage - Staging Areas:
A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. Specific storage units shall be provided by the contractor and exact location
Page | 8 within staging area may be discussed at the preconstruction briefing. All storage units provided by the contractor shall be in a clean and acceptable condition to the COR. Security of the materials and equipment on site is the Contractor’s responsibility. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site and impact to park visitors (avoid high use times.)
3.5 Preservation of Natural Features: N/A.
3.6 Hauling Restrictions: Contractor shall verify and be responsible for the path accessing the site and obtaining / maintaining all local, state and federal permits/licenses associated with hauling/road requirements and dumping of materials associated with the project.
3.7 Housekeeping:
A. Keep project neat, orderly, and in a safe condition at all times.
1. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters
2. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.
3.8 Occupancy Requirements for Buildings:
A. Existing Buildings:
1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO or COR.
b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
B. New /Existing Buildings Unoccupied:
1. Contractor shall be responsible for and protect the entire facility and construction site from notice to proceed through final acceptance.
2. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of building, Page | 9 provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the entire project.
a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government acceptance.
b. Obtain a Certificate of Occupancy from the NPS before Government occupancy.
c. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed.
On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.
d. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.
3.9 Photo Documentation:
A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted preferably electronically by email or optional via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.
B. Existing Condition Images:
1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
C. Construction Progress Images:
1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
D. Completion Images:
1. Document all completed work within scope of work.
2. Maintain organized index for photos with date, description, etc..
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
3.10 Fire and Life Safety:
A. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the
Page | 10 worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.
B. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
C. Store and handle hazardous materials in accordance with manufacturers and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the CO, COR, and park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.11 Noise and Acoustics Management
A. Contractor shall not have personal radios or other media sources and they shall not be broadcast within NPS property.
B. Noise Control: Perform propane piping removal and construction operations to minimize noise.
Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer or COR.
C. Repetitive and/or intermittent, high-level noise: Permitted only during Daytime.
1. Do not exceed the following dB(A) limitations at 50 feet:
Sound Level in dB(A) Time Duration of Impact Noise
70 More than 12 minutes in any hour
80 More than 3 minutes in any hour
2. Maximum permissible construction equipment noise levels at 50 feet:
EARTHMOVING dB(A) MATERIALS HANDLING dB(A)
Compressors 75 Pneumatic Tools 80
Pumps 75 Saws 75
Generators 75 Vibrators 75
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.
Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.
Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed.
https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926
Page | 11
ITEM 6 - ABBREVIATIONS
6.1 The list of abbreviations, standards and organizations which may be used in/referred within the
Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS
Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm
ITEM 7 - ACCIDENT PREVENTION
7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.
7.2 Submittals:
A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name and qualifications of responsible supervisor to carry out the program.
2. First aid and rescue procedures.
3. Training, both initial and continuing.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National
Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample
JHA template may be provided upon request.
5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
6. Contractor to identify nearest location of medical facility for emergencies
7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.
8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.
B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute
"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.
7.3 Qualification of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
https://www.nps.gov/orgs/1671/do-business-with-us.htm
Page | 12
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.
7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA
29CFR 1926 Subpart E.
B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
C. All PPE will be serviceable at all times. At a minimum, maintain four sets of PPE including hard hats and all other Accident Prevention Plan required equipment.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park
Service Emergency Dispatch.
ITEM 8 - PRECONSTRUCTION CONFERENCE
8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.
Page | 13
ITEM 9 - SUBMITTALS
9.1 General Contracting Submittal Procedures:
A. General: Prepare and submit submittals required by individual Technical Specification
Sections. Types of submittals are indicated in individual specific sections.
1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using
National Park Service form CM-16 form. The form will be provided by the Contracting
Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR
B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.
C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items are to be submitted prior to the
Preconstruction Conference or as specified at the CO’s discretion. The timeline for the documents to be submitted will be addressed at the pre-construction conference for those items that were not received and approved prior. Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed.
Work shall not commence until written Notice to Proceed has been issued. Contracting
Officer will notify Contractor of tentative date for the Pre-Construction Conference:
1. Letter designating Project Superintendent.
2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention (Safety) Plan (see section 7 of this document).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
7. Quality Control Plan.
8. Waste Management Plan.
9. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP) Submitted to South
Dakota Department of Agriculture and Natural Resources.
10. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit.
b. The Agency(ies) with Jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
9.2 Project Submittal Process (Shop Drawings, Product Data, and Samples): Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical specification or attached at the end of this document.
A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation
Page | 14 details and locations.
1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.
B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.
1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.
C. Samples: Submit 2 color samples 4” x 6” minimum in size for all product color selections.
Paint samples shall be actual paint finish drawdown for all project colors.
1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.
D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).
E. After approving submittals, Contracting Officer and/or COR will return one copy to the
Contractor. If submittals are not approved, Contracting Officer will return all copies to
Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: All brand names noted are subject to ‘or equal’ products. If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.
A. For each item proposed as an “approved equal,” submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
Describe availability of maintenance service, and state source of replacement materials.
B. A request for approval constitutes a representation that General Contractor:
1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.
2. Will meet or exceed warranties for the proposed item specified.
Page | 15
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the
Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.
9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.
Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of
Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.
ITEM 10 – TEMPORARY SERVICES
10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this
Contract.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.
Page | 16
11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting
Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.
B. If the work is not determined to be complete following the final inspection, the Contracting
Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the
CO.
D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.
E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
F. Disposition of any permits and warranties required by the specifications in this section.
11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of
Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.
B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.
C. Information shall include operation and maintenance manuals for each warranted product.
ITEM 12 - DEFINITION OF CONTRACT LINE ITEMS
12.1 Summary
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut off points where one item ends and another begins.
Page | 17
B. If no contract line item exists for a portion of the work, include the costs in a related item.
12.2 List of Contract Line Items
A. Contract Line Item No. 0001: Rehab Propane Distribution Lines
1. This item consists of removal and construction of propane distribution lines and earthwork for drainage improvements as indicated on the drawings.
2. Payment will be made per the contract after completion and acceptance.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXCUTION (NOT USED)
END OF SECTION
BADL 171379 013513.23-1 Paleontological Protection
SECTION 01 35 13.23
PALEONTOLOGICAL PROTECTION
PART 1 - GENERAL
1.1 SUMMARY
A. The work in this section consists of protecting paleontological resources contained in bedrock deposits.
1.2 DEFINITIONS
A. Paleontological Resources: Paleontological resources are physical evidences of past animal life. Paleontological resources represent prehistoric time periods. They are found above and below ground and under water.
B. Paleontologically Sensitive Areas: Areas containing bedrock from the
Eocene/Oligocene White River Group which is fossil-rich in nature.
C. Paleontological Monitor: The park will provide qualified individuals designated to oversee construction activities that could disturb paleontological resources. The Contractor shall coordinate with the Contracting Officer/COR for monitoring.
D. Paleontological Resources Preservation Act P.L. 111-11- March 30, 2009 defines paleontological resources as any fossilized remains, traces, or imprints of organisms, preserved in or on the earth’s crust, that are of paleontological interest, and that provide information about the history of life on earth.
E. Bedrock: Solid rock underlying loose deposits such as soil or alluvium. All bedrock preserved in Badlands National Park is fossil-rich.
1.3 SUBMITTALS
A. Daily Work Schedule; Submit a Daily Work Schedule detailing construction work in paleontologically sensitive areas. Submit to Contracting Officer/COR 2 days before start of ground disturbing site work.
1.4 QUALITY ASSURANCE
A. At least one week before on-site work begins, Contractor shall meet with Contracting Officer/COR and Paleontological Monitor to discuss Daily Work Schedule and equipment and special methods to be used in paleontologically sensitive areas. Contractor shall ensure that approved Daily Work Schedule is followed throughout construction.
BADL 171379 013513.23-2 Paleontological Protection
PART 2 - PRODUCTS
2.1 DAILY WORK SCHEDULE
A. A Daily Work Schedule is required for all work occurring within paleontologically sensitive areas. Include all work that is to occur within the area and key the schedule to the drawings to include the following:
1. Starting and ending dates of ground-disturbing construction.
2. Locations of temporary facilities, such as barriers, field offices, staging areas, sanitary facilities, and haul and access roads.
3. Types of construction, such as clearing, topsoil stripping, structure or trench excavation, landscaping, and post construction clean-up.
4. Methods and equipment used for each type of construction.
5. Plan for alternative work in the event of temporary work stoppages at each paleontologically sensitive area.
PART 3 - EXECUTION
3.1 PALEONTOLOGICAL INVESTIGATION BY PARK PERSONNEL
A. All monitoring will be completed by qualified paleontological monitor provided by the park. A salvage collection permit for paleontology, signed by the park superintendent will be drafted for all paleontological monitors. All fossils that are collected will be evaluated by the park paleontologist and shall be prepared, curated and recorded in the NPS ICMS database.
3.2 OBSERVATION
A. Paleontological Monitor will observe all ground-disturbing site work. The monitor will keep a daily log and will record all associated data when collecting a fossil. Photographs will be taken of work areas, all fossils collected and associated stratigraphy.
3.3 DISCOVERY OF RESOURCES
A. If Paleontological Monitor discovers resources, immediate change of work to a non-excavation activities may be required to allow Monitor to identify and document resources and, if necessary, develop an appropriate mitigation plan. While Paleontological Monitor is documenting resources in sensitive areas, Contractor shall cease all excavation work which requires a paleontological monitor.
B. If resources are discovered while Paleontological Monitor is absent, stop work in the vicinity immediately and report the discovery to the Contracting Officer/COR.
BADL 171379 013513.23-3 Paleontological Protection
3.4 WORK STOPPAGE
A. The Contractor shall plan, schedule, and execute the work to prevent stoppages at one area from stopping all work at the construction site
BADL 171379 015713 - 1 Temporary Erosion and Sediment Control
SECTION 015713
TEMPORARY EROSION AND SEDIMENT CONTROL
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Prevention of erosion due to construction activities.
B. Prevention of sedimentation of waterways, open drainage ways, and storm and sanitary sewers due to construction activities.
C. Restoration of areas eroded due to insufficient preventive measures.
1.02 RELATED REQUIREMENTS
A. Section 311000 - Site Clearing: Limits on clearing; disposition of vegetative clearing debris.
B. Section 312200 - Grading: Temporary and permanent grade changes for erosion control.
C. Section 321500 - Aggregate Surfacing: Temporary and permanent roadways.
D. Section 329219 - Seeding: Permanent turf for erosion control.
1.03 PERFORMANCE REQUIREMENTS
A. Comply with requirements of EPA (NPDES) for erosion and sedimentation control, as specified by the NPDES, for Phases I and II, and in compliance with requirements of Construction General Permit (CGP).
B. Also comply with all more stringent requirements of State of South Dakota DOT Erosion and Sedimentation Control Manual.
C. Develop and follow an Erosion and Sedimentation Prevention Plan and submit periodic inspection reports.
D. Do not begin clearing, grading, or other work involving disturbance of ground surface cover until applicable permits have been obtained; furnish all documentation required to obtain applicable permits.
1. Obtain and pay for permits and provide security required by authority having jurisdiction.
E. Timing: Put preventive measures in place as soon as possible after disturbance of surface cover and before precipitation occurs.
F. Erosion On Site: Minimize wind, water, and vehicular erosion of soil on project site due to construction activities for this project.
1. Control movement of sediment and soil from temporary stockpiles of soil.
2. Prevent development of ruts due to equipment and vehicular traffic.
3. If erosion occurs due to non-compliance with these requirements, restore eroded areas at no cost to Owner.
G. Erosion Off Site: Prevent erosion of soil and deposition of sediment on other properties caused by water leaving the project site due to construction activities for this project.
1. Prevent windblown soil from leaving the project site.
2. Prevent tracking of mud onto public roads outside site.
3. Prevent mud and sediment from flowing onto sidewalks and pavements.
4. If erosion occurs due to non-compliance with these requirements, restore eroded areas at no cost to Owner.
H. Sedimentation of Waterways On Site: Prevent sedimentation of waterways on the project site, including rivers, streams, lakes, ponds, open drainage ways, storm sewers, and sanitary sewers.
1. If sedimentation occurs, install or correct preventive measures immediately at no cost to
Owner; remove deposited sediments; comply with requirements of authorities having jurisdiction.
2. If sediment basins are used as temporary preventive measures, pump dry and remove deposited sediment after each storm.
BADL 171379 015713 - 2 Temporary Erosion and Sediment
I. Sedimentation of Waterways Off Site: Prevent sedimentation of waterways off the project site, including rivers, streams, lakes, ponds, open drainage ways, storm sewers, and sanitary sewers.
1. If sedimentation occurs, install or correct preventive measures immediately at no cost to
Owner; remove deposited sediments; comply with requirements of authorities having jurisdiction.
J. Open Water: Prevent standing water that could become stagnant.
K. Maintenance: Maintain temporary preventive measures until permanent measures have been established.
1.04 SUBMITTALS
A. Erosion and Sedimentation Control Plan:
1. Obtain the approval of the Plan by authorities having jurisdiction.
B. Inspection Reports: Submit report of each inspection; identify each preventive measure, indicate condition, and specify maintenance or repair required and accomplished.
PART 2 PRODUCTS
2.01 MATERIALS
A. Erosion Control Blankets:
1. Erosion control blankets shall be composed of 100% all natural fibers made of jute, coir, or excelsior. No straw or hay is acceptable. Netting for blankets shall be double-netted and shall have a top and bottom net made of biodegradable material, not photodegradable material. Stitching that binds the fibers to the net shall be 100% biodegradable.
Anchors/staples shall be 100% biodegradable.
2. Minimum matting properties:
a. Stitch Spacing: 2 in. on center
b. Unit Weight: 8.0 oz/yd
c. Tensile Strength (MD): 190 lb/ft
d. Tensile Strength (TD): 150 lb/ft
e. Coverage: 15% open
f. Longevity: 12 months
B. Silt Fence Fabric: Polypropylene geotextile resistant to common soil chemicals, mildew, and insects; non-biodegradable; in longest lengths possible; fabric including seams with the following minimum average roll lengths:
1. Average Opening Size: 30 U.S. Std. Sieve, maximum, when tested in accordance with
ASTM D4751.
2. Permittivity: 0.05 sec^-1, minimum, when tested in accordance with ASTM
D4491/D4491M.
3. Ultraviolet Resistance: Retaining at least 70 percent of tensile strength, when tested in accordance with ASTM D4355/D4355M after 500 hours exposure.
4. Tensile Strength: 100 pounds-force, minimum, in cross-machine direction; 124 pounds-force, minimum, in machine direction; when tested in accordance with ASTM D4632/D4632M.
5. Elongation: 15 to 30 percent, when tested in accordance with ASTM D4632/D4632M.
6. Tear Strength: 55 pounds-force, minimum, when tested in accordance with ASTM
D4533/D4533M.
7. Color: Manufacturer's standard, with embedment and fastener lines preprinted.
C. Silt Fence Posts: One of the following, minimum 5 feet long:
1. Steel U- or T-section, with minimum mass of 1.33 pound per linear foot.
BADL 171379 015713 - 3 Temporary Erosion and Sediment
PART 3 EXECUTION
3.01 EXAMINATION
A. Examine site and identify existing features that contribute to erosion resistance; maintain such existing features to greatest extent possible.
3.02 PREPARATION
A. Schedule work so that soil surfaces are left exposed for the minimum amount of time.
3.03 SCOPE OF PREVENTIVE MEASURES
A. In all cases, if permanent erosion resistant measures have been installed temporary preventive measures are not required.
B. Construction Entrances: Traffic-bearing aggregate surface.
1. Width: See plan.
2. Length: See plan.
3. Provide at each construction entrance from public right-of-way.
4. Where necessary to prevent tracking of mud onto right-of-way, provide wheel washing area out of direct traffic lane, with drain into sediment trap or basin.
C. Linear Sediment Barriers: Made…