B08_Solicitation_-_Att_2_-_Specifications_-_Division_1.docx
DOCX document 2 MB Posted
- Attached to
- STGE - GTT Retaining Wall Rehab
- Solicitation number
- 140P6026Q0049
About this file
This is a Project Specifications document for the Green Tree Tavern Retaining Wall Rehabilitation at Sainte Genevieve National Historical Park in Missouri, issued by the National Park Service. The project involves the deconstruction, rehabilitation, and reconstruction of a historic limestone retaining wall built in 1803, located on the Green Tree Tavern property within the National Historic Landmark District. The wall measures approximately 90 linear feet in length, 4 feet in height, and 1.5 feet in thickness, with approximately 90 linear feet requiring reconstruction due to deferred maintenance. The contractor must hand-dismantle the wall, label and clean each stone, salvage usable historic flagstone, and reconstruct using NHL 3.5 lime mortar (1-part lime to 2.5-part sand) to ensure moisture permeability and structural strength. All work must be performed without mechanical excavation equipment, with hand tools only, to protect the adjacent historic building and archaeological resources. The project includes hand-excavation and shoring of fill material behind the structure, implementation of traffic control measures along St. Marys Road, installation of drainage infrastructure with washed limestone aggregate and perforated HDPE draintile, and topsoil restoration with turfgrass sod.
The contract requires completion within 180 calendar days from Notice to Proceed and mandates numerous submittals including a shoring plan, traffic control plan, construction schedule, accident prevention plan, temporary storm water pollution prevention plan, and historic preservation treatment plan, all requiring approval prior to mobilization. An archaeologist from the Midwest Archeological Center will monitor ground disturbance throughout the project. Work is restricted to normal business hours (8 a.m. to 4 p.m., Monday through Friday) with prior approval required for any deviation, and the contractor must provide comprehensive photo documentation before, during, and after each phase of work. Additional requirements include coordination with utilities, protection of existing landscaping and structures, waste management and recycling, provision of sanitary facilities, adherence to noise limitations (70 dB(A) maximum more than 12 minutes per hour at 50 feet), and compliance with OSHA safety standards and NPS regulations. The single contract line item (001) covers Stone Wall Rehabilitation with payment based on percentage of completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B12_MISC_Addendum_0002.pdf | ||
| Sol_140P6026Q0049_Amd_0002.pdf | ||
| B12_MISC_QA_Document_0002.docx | DOCX document | |
| B11_MISC_Site_Visit_attendance_0001.pdf | ||
| Sol_140P6026Q0049_Amd_0001.pdf | ||
| B08_Solicitation_-_Att_4_-_Construction_Wage_Determination.pdf | ||
| B08_Solicitation_-_Att_1_-_Specifications.docx | DOCX document | |
| B08_Solicitation_-_Att_3_-_Submittal_List.xls | XLS spreadsheet | |
| Sol_140P6026Q0049.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ste. Genevieve National Historical Park 339 St. Marys Rd, Sainte Genevieve Missouri, 63670
Green Tree Tavern Retaining Wall Rehabilitation
PMIS 351091
Drawing No: N/A
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
2026-02-20
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
Section 01 10 00 - Division 01 Short Form General Requirements
DIVISION 04 – STONE WALL REHABILITATION
Section 04 01 40.62 - Stone Rehabilitation
PHOTOS/MAP – APPENDIX A
SECTION 01 10 00
DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: The Green Tree Tavern is a historic home located within the National Historic Landmark District in Sainte Genevieve, Missouri. On the property stands a historic limestone wall, built in 1803, that is in disrepair. The total wall length is approximately 140 LF in length, 4 ft tall and 1.5 ft in depth. 90 LF of the wall is in need of reconstruction due to years of deferred maintenance. Comment by Bentley, Thomas L: Clarify if all 140 feet is being dismantled and reconstructed or only 90-feet. Knowing the full length means the section on other side of steps, but may be a bit confusing to a contractor reading 140' and 90' to understand. Additionally, wall depth/thickness noted 12" here but 1.5' in 1.2A.1. Edit which thickness you want to cite and have the same language for both.
1.2 Work Covered by the Contract Documents:
A. Project Location: 244 St. Marys Rd, Ste. Genevieve MO 63670
1. Work consists of: The Green Tree Tavern Retaining Wall Reconstruction project entails the careful deconstruction and reconstruction of a historic mortared limestone retaining wall located on the Green Tree Tavern property. The wall currently exhibits a slight outward lean along its length until it connects to the concrete steps, necessitating this rehabilitation effort. The wall, approximately 90 linear feet long, 4 feet high, and 1.5 feet thick, sits roughly 10 feet from the historic Green Tree Tavern structure and adjacent to St. Marys Road. The contractor will dismantle the wall by hand, label and clean each stone, and salvage usable historic flagstone for reuse. Reconstruction will utilize NHL 3.5 lime mortar (1-part lime to 2.5-part sand) to ensure moisture permeability and structural strength. See specification section 04 01 40.62 within this scope document for further detail. Comment by Bentley, Thomas L: Is 'flagstone' the right term? Probably is, but to my experience that is the thin material you put down as a patio. I would categorize this wall as 'fieldstone', but use what is the conventional nomenclature in your area.
2.
Fill material between the structure and wall will be hand-excavated and shored, along the length of the wall to protect the building. No mechanical excavation equipment shall be allowed. The project will include traffic control measures to maintain access along St. Marys Road and shall incorporate rock/chat backfill to improve drainage and capillary pressure behind the wall to extend the wall’s lifespan. The park will provide an archeologist from the Midwest Archeological Center (MWAC) who will be present to monitor ground disturbance and conduct test digs as needed. The Contractor shall coordinate with the CO/COR to provide sufficient lead time ahead of work requiring travel by MWAC to be present.
| Shoring: | Comment by Newman-Johnson, Anderson R: I feel that all of these sections could be reorganized to look better. I am having trouble categorizing the work in my head that would make sense for the project. | Comment by Bentley, Thomas L: This comment was prior to our discussion on Apr 13, so presume better clarity in how this reads now, correct? |
| · Contractor shall hand dig and excavate soil from behind the retaining wall to prevent additional soil from slumping and undermining the front porch. No power tools or equipment are to be used for excavation as their impacts and vibrations pose a risk to stability. | Comment by Newman-Johnson, Anderson R: Removing language that specifically calls out the "6-8 ft section" idea and including a blurb about shoring the Green Tree Tavern Porch prior to excavation. |
· The front porch of the Green Tree Tavern shall be supported by cribbing/shoring for the duration of the project.
· Contractor shall submit a shoring plan as a submittal for written COR approval, detailing these parameters. The Contractor shall employ approved measures and seek further approval from the COR if conditions warrant any modification or addition of shoring measures.
Traffic Control:
· Traffic control shall include advanced notification signage at 300 and 100 feet distances preceding the work area in both directions. Signage to be sawhorse mounted and meeting MUTCD standards for color, size, shape, and text.
· As no drive lane closures are required or allowed to perform the work, a contracted flagman crew is not required for the project. Any temporary stopping of Contractor vehicles on the road to load or offload must be limited to a tolerance approved by the COR in writing and have sufficient dedicated workers actively directing traffic during the time the Contractor vehicle is occupying the traffic lane.
· Traffic control at a minimum shall consist of a dedicated employee monitoring traffic at a minimum while work is being led in direct proximity to the road.
· Traffic control may consist, but is not limited to; Traffic Cones, hi-visibility fencing or other as proposed by contractor and approved by the COR.
· Contractor shall submit a traffic control plan to the CO/COR for review and written approval prior to starting work.
Documentation:
· Contractor shall submit before and after photos for each section of the stone wall on a physical memory device (SD card or Compact Disc) to the COR prior to project close out
· Photos to be Submitted
· Well before deconstruction with stones labeled/mapped.
· Wall after deconstruction with stones labeled/mapped.
· Wall after construction with stones labeled/mapped demonstrating an accurate restoration.
· Photos must show each stone numbered and confirm stones are placed back in their original location after reconstruction.
· Conduct additional photo documentation in accordance with part 3.9 below.
Comment by Newman-Johnson, Anderson R: Maybe include a subsection specifically about backfilling and drainage?
Reconstruction:
· Contractor shall number each stone before deconstruction to ensure accurate placement during reconstruction. The contractor shall submit a removal and resetting plan to be approved by CO/COR prior to work.
· Contractors shall carefully remove old mortar using hand tools and brushes only.
· Stones shall be cleaned and the wall reconstructed in the same order, ensuring the wall is plumbed and level. Comment by Bentley, Thomas L: What do you intend to call for on this. Calling for 1/8" batter would contradict a plumb wall. Are we stating 'correcting the existing displacement and lean to the wall'?
· The existing stones are of a size and density providing the expectation that re-use should be 100-percent and no new stones are necessary.
Drainage:
- The Contractor shall provide a drainage layer of washed aggregate (1” limestone) behind the retaining wall which shall be wrapped on the bottom, back, and top of excavation with non-woven geosynthetic fabric in order to prevent sediment migration.
- The drainage layer shall extend to within 8-inches of the top of wall, wrapping the geosynthetic fabric and tuck against stone to fully encapsulate the drainage aggregate, and receive 6-inches of topsoil with new turfgrass sod over the top to fully restore the lawn.
- The Contractor shall provide a 4-inch fabric wrapped perforated HDPE draintile within the bottom 6-inches of the drainage layer and route to a maximum of two locations through the wall in order to sufficiently provide a slope of the draintile between 1% minimum and 2% maximum.
- The perforation through the stone wall for daylighting drainage shall be a maximum 2” PVC piping at a location proposed by the Contractor and approved by the COR. The Contractor shall provide reducer couplers concealed within the drainage layer behind the wall to reduce the diameter from 4-inch to 2-inch. The priority shall be for the Contractor to determine location(s) which are as discreated as possible, placing the outfall at the base of the wall at the adjacent turfgrass level, utilizing the voids/mortar jointing between irregular shaped stones. Cutting or modifying stone shall not be allowed unless demonstrated as the sole option which the COR approves in writing.
B. All work will be performed under a single contract.
C. Period of performance: Work shall be completed within 180 calendar days of the start date provided on the Notice to Proceed.
a. Clarification: The Notice to Proceed will be issued with a period of performance that is all inclusive of supply lead times, material deliveries, decommissioning, installation, anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to Proceed. If weather impacts project beyond typical average weather patterns, contractor shall provide documentation in request for additional days.
1.3 Existing Condition Protections:
A. Preservation of Historical and Archeological Fabric:
i. The Historic and Archeological Data Preservation Act of 1974 provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
ii. IF, in connection with operations under this contract, the Contractor, subcontractors, or employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological remains or data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts not specifically noted within the contract. The Contractor shall immediately suspend all operations in the vicinity and continue work in other areas outside a 50 foot radius of discovery and notify the Contracting Officer immediately. When safe to do so, follow up in writing with photographs within 2 days, giving the location and nature of the findings. No objects of cultural resource value may be removed. Contracting Officer will contact other entities as required.
iii. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with Changes clause.
iv. The Contractor will be responsible for protecting the cultural resources within and adjacent to the project area from damage. In addition, the Contractor will be liable for all damage to the cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or their representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
v. The Contractor agrees to include this language within all subcontracts.
The structure involved in the work of this Contract is a designated historic structure listed in the National Register of Historic Places. Every precaution shall be taken by the Contractor to prevent damage to existing historical materials, structural components of the building and to the surrounding area. Should any damage be incurred as a result of the Contractor’s operations at the site, it shall be repaired, or the damaged materials replaced in kind by the Contractor to the satisfaction of the Contracting Officer at no additional expense to the Government.
Protection of Landscaping and Surrounding Structures: All Ground Disturbance at this project shall have oversite by an Owner provided Archeologist. Coordinate schedules as required. The Contractor shall take all necessary measures to provide protection for all trees, fencing, walks and other landscape features and surrounding structures near the work site as noted with the contract. Any such surrounding features damaged, scarred or broken as a result of the Contractor’s operations at the site outside of agreed upon documented extents, shall be treated, repaired or replaced in kind to the satisfaction of the Contracting Officer at no additional expense to the Government.
ITEM 2 – PROTECTING EXISTING UTILITIES
2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative (COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.
2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.
2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:
A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.
B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent. https://home.nps.gov/stge/learn/management/superintendent-s-compendium.htm
A. Communications: Contractor shall provide the Contracting Officer and COR with methods of communications including land and/or cell phone numbers (note some areas of work have limited service coverage), email and in case of emergency 24-hour contact options for duration of time operations.
B. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
C. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
D. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public. Contractor cannot work on site during the dates of May 28th - June 1st for the A250th celebration. Contractor is to have worksite secured and cleaned up before the May 28th date and approved by COR
3.2 On-site work hours: Work shall be generally performed during normal business working hours of 8am - 4pm., Monday through Friday, except when otherwise indicated. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.
The following Federal holidays are observed by the National Park Service:
New Year’s Day Inauguration Day Martin Luther King, Jr’s Birthday Washington’s Birthday Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day
· Note: Any of the above holidays falling on a Saturday will be observed on the preceding Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays (opm.gov).
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
C. Do Not disturb site outside of noted disturbance area, including earthwork, and clearing of vegetation, to:
10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter 15 feet beyond primary roadway curbs and main utility branch trenches 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas to limit compaction in the constructed area.
Contractor shall provide appropriate matts for equipment on turf areas to reduce soil compaction. Contractor shall remediate soil compaction as directed to do so by the CO/COR.
D. Utilities
1. General: Cost or use charges for temporary facilities shall be included in the Contract Sum as required.
2. Water Service: Water from existing water system is not available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.
3. Electric Power Service: Electric power from existing system is not available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.
4. Sanitary Operations:
a. Toilets: Contractor must provide toilets for contractor personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan.
E. Security and Protection facilities:
1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area. Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.
Vegetation and Wetland Protection: Coordinate with COR to construct protection fence at drip line of any vegetation or wetlands impacted within construction and grading limits. Any damaged vegetation or wetlands are to be restored to original conditions via replacement at no additional expense to the Government. Protection fence to be a temporary barrier, meeting the following requirements: High-density plastic, extruded and stretched polyethylene fabric with 2 inch (50mm) maximum opening pattern, highly visible orange color, 48 inches (1220mm) high, supported by tubular or T-shape galvanized steel posts spaced not more than 96 inches (2440mm) apart. Coordinate with COR prior to ANY vegetation or wetland removals. Consult with COR for any unplanned removals required for vegetation that interferes with construction. Carefully supervise excavating, grading, filling, and other construction operations near vegetation to prevent damage.
3. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.
4. Temporary Enclosures: Provide and maintain temporary enclosures such as snow fence as required for protection of construction in progress and from access by visitors or staff, other construction operations, and similar activities.
5. Hot Work Permit: Not Required
3.4 Storage - Staging Areas:
A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. Specific storage units shall be provided by the contractor and exact location within staging area shown in appendix A below may be discussed at the preconstruction briefing. All storage units provided by the contractor shall be in a clean and acceptable condition to the COR. Security of the materials and equipment on site is the Contractor’s responsibility.
3.5 Preservation of Natural Features: Contractor is to ensure that all grounds/landscapes are protected from equipment/contractor use.
3.6 Hauling Restrictions: Contractor shall verify and be responsible for the path accessing the site and obtaining / maintaining all local, state and federal permits/licenses associated with hauling/road requirements and dumping of materials associated with the project.
3.7 Waste Removal, Recycling, and General Housekeeping:
A. Keep project site in a neat, orderly, and safe condition at all times.
1. Contractor is responsible for providing dumpsters for waste and recycling and for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site. Coordinate with COR for approved dumpster locations prior to commencing construction.
2. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters.
3. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to the extent possible during this project, recycling material as much as possible within local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.
4. For all waste and recycling removals offsite, contractors shall provide estimates and/or tickets to quantify material weights and report back to the park, submit to COR for review and record filing.
3.8 Occupancy Requirements for Buildings:
A. Existing Buildings:
1. N/A
B. New /Existing Buildings Unoccupied:
N/A
3.9 Photo Documentation:
A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted preferably electronically by email or optional via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.
B. Existing Condition Images:
1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
C. Construction Progress Images:
1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
D. Completion Images:
1. Document all completed work within scope of work.
2. Maintain organized index for photos with date, description, etc..
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
3.10 Fire and Life Safety:
A. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.
B. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
C. Store and handle hazardous materials in accordance with manufacturers and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the CO, COR, and park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.11 Noise and Acoustics Management
Contractor shall not have personal radios or other media sources and they shall not be broadcast within NPS property.
Noise Control: Perform operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer or COR.
Repetitive and/or intermittent, high-level noise: Permitted only during Daytime.
Do not exceed the following dB(A) limitations at 50 feet: 70 dB(A) More than 12 minutes in any hour, 80 dB(A) More than 3 minutes in any hour. 2. Maximum permissible construction equipment noise levels at 50 feet: Compressors 75 dB(A), Pneumatic Tools 80 dB(A), Pumps 75 dB(A), Saws 75 dB(A), Generators 75dB(A), Vibrators 75 dB(A) 3. Ambient Noise maximum noise levels (dB) for receiving noise area at property line shall be as follows. Residential receiving area: Daytime 65 dB Nighttime 45 dB. Commercial/Industrial receiving area: Daytime: 67 dB Nighttime: 65 dB
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract. Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids. Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed.
ITEM 6 - ABBREVIATIONS
6.1 The list of abbreviations, standards and organizations which may be used in/referred within the Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm
ITEM 7 - ACCIDENT PREVENTION
7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.
7.2 Submittals:
A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name and qualifications of responsible supervisor to carry out the program.
2. First aid and rescue procedures.
3. Training, both initial and continuing.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample JHA template may be provided upon request.
5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
6. Contractor to identify nearest location of medical facility for emergencies
7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.
8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.
B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.
7.3 Qualification of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.
7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA 29CFR 1926 Subpart E.
B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
C. All PPE will be serviceable at all times. At a minimum, maintain 2 sets of PPE including hard hats and all other Accident Prevention Plan required equipment.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park Service Emergency Dispatch.
ITEM 8 - PRECONSTRUCTION CONFERENCE
8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.
ITEM 9 - SUBMITTALS
9.1 General Contracting Submittal Procedures:
A. General: Prepare and submit submittals required by individual Technical Specification Sections. Types of submittals are indicated in individual specific sections.
1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using National Park Service form CM-16 form. The form will be provided by the Contracting Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR
B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.
C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items are to be submitted prior to the Preconstruction Conference or as specified at the CO’s discretion. The timeline for the documents to be submitted will be addressed at the pre-construction conference for those items that were not received and approved prior. Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed. Work shall not commence until written Notice to Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference:
1. Letter designating Project Superintendent.
2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention (Safety) Plan (see section 7 of this document).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
7. Quality Control Plan.
8. Waste Management Plan. REQUIRED for this project.
9. Temporary Storm Water Pollution Prevention Plan (SWPPP or UPPP) Submitted to AHJ (Authority Having Jurisdiction). REQUIRED for this project
10. Historic Preservation Treatment Plan Submitted to AHJ (Authority Having Jurisdiction). REQUIRED for this project
a. The Agency(ies) with Jurisdiction issuing the permit.
b. Information required from the Government to complete the permit application.
11. Shoring Plan to be approved by COR/CO before mobilization.
12. Traffic Control plan to be approved by COR/CO before mobilization.
13. Photo Documentation submitted to COR/CO for each project milestone.
9.2 Project Submittal Process (Shop Drawings, Product Data, and Samples): Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical specification or attached at the end of this document.
A. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.
1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.
B. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).
C. After approving submittals, Contracting Officer and/or COR will return one copy to the Contractor. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: All brand names noted are subject to ‘or equal’ products. If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.
A. For each item proposed as an “approved equal,” submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.
B. A request for approval constitutes a representation that General Contractor:
1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.
2. Will meet or exceed warranties for the proposed item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.
9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents. Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.
ITEM 10 – TEMPORARY SERVICES
10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.
11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.
B. If the work is not determined to be complete following the final inspection, the Contracting Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the CO.
D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.
E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
F. Disposition of any permits and warranties required by the specifications in this section.
11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.
ITEM 12 - DEFINITION OF CONTRACT LINE ITEMS
12.1 Summary
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut off points where one item ends, and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
12.2 List of Contract Line Items
Contract Line-Item No.001 STONE WALL REHABILITATION This item consists of Stone Wall Rehabilitation.
Payment will be made per the contract and percentage of completion level.
END OF SECTION
Appendix A Project Photos/Map Project Map
Street View
(Red outline = Staging location, Pink outline = Work area)
Div. 1 V. 2023-11-11 Page | 1 image1.wmf image2.jpeg image3.jpeg image4.jpeg
File details come from the government source that posted it. Updated .