This document contains a submittal list template for a construction project. The template includes a table to record required construction submittals for the project, including specification section, paragraph number, description of submittal, and whether each submittal is considered informational or requires government action. It lists submittal requirements for various specification sections relating to materials, systems, and specialties. Responsible parties for construction and design phases are identified along with instructions for completing the template and using the submittal list and review estimates to negotiate task order scopes and fees with architects and engineers. Estimated hours by discipline are to be provided for review of action submittals. The related federal contract opportunity is for housing foundation replacements at Hawaii Volcanoes National Park, solicited by the National Park Service Midwest Region under solicitation number 140P6023B0004.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

Submittal List with Review Estimate Instructions
National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21
DESIGN SERVICES (Construction Documents (CD) Phase)
Responsible Party: Design Architect/Engineer (A/E)
1Enter Park Acronym, Project Management Information System (PMIS) Number, and Project Title.
2Record construction submittal requirements. Complete Specification Section, Paragraph Number, and Description sections. Insert additional rows as required for sections containing multiple submittals.
3In Requirements section, enter X for submittal requirements where applicable. Insert additional columns as needed under Informational or Action. Refer to Specification Section 01 33 23 for clarification. (Action submittals require Government resposive action and Informational submittals do not.) Division 1 Specifications submittals are Information submittals.
4Attach black and white version to Specification Section 01 33 23 in project manual. Delete instructional note on top of page.
CONSTRUCTION SERVICES (Construction Phase)
Responsible Party: Construction Contracting Officer Representative (COR)
1Use Submittal List submitted with Final Construction Documents. Copy/paste submittal information into Submittal List with Review Estimate Template. If amendments issued, adjust submittal requirements as necessary.
2Attach this template to Architect/Engineer (A/E) Construction Services Scope of Services.
3Use Review Estimate to estimate time required for Architect/Engineer to accomplish Action submittal reviews. Enter estimated whole or partial number of hours per discipline.
4Add discipline heading column as required.
5Use total number of hours per discipline at bottom of template and apply hourly rates listed in Indefinite Delivery/Indefinite Quantity (IDIQ) contract (using appropriate option period rates) to formulate Government estimate for submittal reviews.
6Use information from this template to negotiate submittal review portion of Architect/Engineer Construction Services task order.
7Provide template to Construction Management Representative (CMR) to show submittals they are responsible for and submittals to be forwarded to the Architect/Engineer. All Informational submittals will be reviewed by Construction Management Representative.
Responsible Party: Architect/Engineer (A/E)
1Indicate level of effort required for each Action submittal review by entering number of whole or partial hours for each discipline under Architect/Engineer Review Time section.
2All Informational submittals will be reviewed by Construction Management Representative (CMR).
3Use total number of hours per discipline at bottom of template and apply hourly rates listed in Indefinite Delivery/Indefinite Quantity (IDIQ) contract (using appropriate option period rates) to formulate estimate.
4Use this estimate to negotiate submittals review portion of Architect/Engineer Construction Services portion of the task order.

&8&K01+024Submittal List with Review Estimate Instructions | National Park Service (NPS) - Denver Service Center (DSC) &8&K01+024page &P of &N

Template

Submittal List with Review Estimate Template
National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21

SUBMITTAL LIST

Park Acronym/Project Management Information System (PMIS) Number:HEHO258441, 247883, 247951
Project Title:Replace Foundations Staples, Wright, Isaac Miles
SUBMITTALREQUIREMENTS*
*Include but are not limited to (see specs)
(Indicate with X)
INFORMATIONALACTION
SPECIFICATION SECTIONPARAGRAPH NUMBERDESCRIPTIONCERTIFICATIONS OR LABORATORY TESTSREPORTS OR CALCULATIONS
OR PLANMANUFACTURER DATA
AND INSTRUCTIONSOTHERSAMPLESSHOP DRAWINGSMANUFACTURER DATA
AND INSTRUCTIONSOTHER
135131.1.JDaily Work ScheduleX
241001.02DemolitionXX
420001.1AUnit Masonry - Brick VeneerXX
420001.1AUnit Masonry - Stone VeneerX
552001.1AMetal RailingsXXXXXX
620001.03Finish Carpentry
713261.03Sheet WaterproofingXXXX
721001.3Thermal InsulationXXXXX
726161.04Under Slab Vapor RetarderXXX
731301.4Wood ShinglesXXX
792001.4Joint SealantsXXXX
921161.02Gypsum Board AssembliesXXX
901131.3Exterior PaintingXXXXX
3123231.02FillXXXXX
3216231.02SidewalksXX
3292191.02SeedingXXX
3321431.03Dampproofing and WaterproofingXXX
33000Concrete Mix DesignX
33000Concrete Reinforcing SubmittalX
33000Concrete Break StrengthsXX
521200Structural Steel SubmittalsX
Building Shoring and Lifting SubmittalXXX
61000Rough Carpentry Submittals (wood selected, hangers, etc.)X
2305291.1.AHVAC Hangers and Supports Product DataX
2305931.1.ATAB ReportX
2305931.3.ATAB Specialist QualificationsX
2305931.3.BInstrumentation InformationX
2309131.1ADuct Insulation Product DataX
2311231.1.ASteel Support Welding QualificationsX
2333001.1.AAir Duct Accessories Product DataX
2331131.1.AAir Terminal Product DataX
2381261.1.ASplit System Air Conditioners Product DataX
2205171.1.ASleeve Seal System Product DataX
2205231.1.APlumbing Valves Product DataX
2205291.1.AHangers and Supports Product DataX
2207191.1.APiping Insulation Product DataX
2211191.1.ADomestic Water Piping SpecialitesX
2213161.1.ASanitary Waste and Vent Piping Product DataX
2213191.1.ASanitary Waste Piping Specialties Product DataX
2234001.1.AWater Heater Product DataX
2234001.2.AWater Heater WarrantyX
2605001.5.APanelboard, Wiring, Switches and Surge Protection Product DataX
2605001.5.BPanelboard, Wswitches and Surge Protection Shop DrawingsX
2605001.6.AElectrical Information Closeout SubmittalsX
2605001.7.ASpare Electrical DevicesX