Price Schedule Summary: Flint Hills National Wildlife Refuge Residing and Reroofing Project

This is a Price Schedule template for the Flint Hills National Wildlife Refuge Residing and Reroofing Project. Offerors must provide pricing for six base line items: (1) removal and replacement of vertical wood siding, batten strips, cedar/plywood trim, wood soffits, fascia, and metal flashing with new furring strips, rigid insulation, building wrap, and fiber cement/Hardie Board siding; (2) fiber cement trim installation around all windows, doors, fascia, and building corners with caulking and painting; (3) roof replacement including removal of existing GAF Fiberglass 3 Tab shingles and 30# felt paper, plywood inspection, installation of underlayment, metal roof system with concealed fasteners, hurricane ties, flashing, and replacement of wood soffit and fascia with 24-gauge metal panels and 6" K-style gutters; (4) demolition and replacement of all existing windows with new wood-clad horizontal sliding windows, bug screens, and interior sills and trim; (5) installation of a 24-inch rock barrier with landscape fabric, weed barriers, borders, and gravel/rock around the building perimeter; and (6) painting of new siding, fiber cement trim, soffit, and fascia. The schedule also includes two optional line items: vertical metal siding installation and gutter guard installation. Offerors must complete all fields including Name of Offeror, SAM UEI Number, and CAGE Code, and provide a Total Contract Amount and Total Contract Amount with Options.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRICE SCHEDULE

Name of Offeror or Contractor: ___________________________________

SAM UEI NUMBER: ____________________________________________

CAGE CODE: __________________________________________________

Flint Hills National Wildlife Refuge Residing and Reroofing Project

1. Siding: Siding: The work includes removal of all existing vertical wood siding and batten strips from the Building Maintenance shop. This includes but is not limited to removal of the siding, batten strips, cedar/plywood trim, wood soffits and fascia, and any metal flashing under the siding. Also remove the building wrap and all damaged insulation underneath the side. After all existing materials are removed, replace them with new furring strips, rigid insulation, building wrap, metal flashing and fiber cement/Hardie Board siding and batten strips.

a. Note: Note: The thickness of the furring strips and rigid insulation on the Office Building/Visitor Center may have to be adjusted to account for the new fiber cement siding thickness and trim so that the existing doors and windows that are to remain in place will not extend out any further past the new Hardie siding and trim then they currently extend past the existing siding. The furring strip thickness and rigid insulation thickness shall be adjusted to account for any adjustment that have to be made to bring the new lap siding to the same location in relation to the window and door frames as the existing building siding.

LINE ITEM 1 PRICING: __________________________________________________________

2. This work shall also include fiber cement trim around all windows, doors under the fascia and down all corners of the building. For the trim to be uniform and flush or slightly passed the face of the window frames a wood sub trim/furring trim shall be required before the fiber cement trim is applied. All trims shall be caulked and painted when completed. The width of the trim between the windows may have to vary so it extends the full width between the windows.

LINE ITEM 2 PRICING: __________________________________________________________

3. Roof: Remove GAF Fiberglass 3 Tab shingles and 30# felt paper. Once the shingles and felt paper are removed, inspect the existing plywood to ensure they are flat and leak-free. Once plywood is inspected and verified to work then install underlayment, furring strips/purlins, 24-gauge metal roof system with concealed fasteners, hurricane ties, and flashing and trims. Existing wood soffit and fascia will also be replaced with 24-gauge metal fascia and soffit panels. Existing gutters will be removed and replaced with new 6" K-style gutters.

LINE ITEM 3 PRICING: __________________________________________________________

4. Windows: All existing windows will be demolished and replaced with new wood-clad horizontal sliding windows with bug screen, and new interior sills and trim will also be installed.

LINE ITEM 4 PRICING: __________________________________________________________

5. Landscaping: A new 24" rock barrier will be installed all around the building with a landscape fabric, weed barriers, boarders, and filled with gravel/rock.

LINE ITEM 5 PRICING: __________________________________________________________

6. Paint: This painting work includes all the new siding, and fiber cement trim, soffit and fascia.

LINE ITEM 6 PRICING: __________________________________________________________

-- OPTION LINE ITEMS --

Option 1 -- Install Vertical metal siding

LINE ITEM 1 PRICING: __________________________________________________________

Option 2 -- Install gutter guard

LINE ITEM 1 PRICING: __________________________________________________________

TOTAL CONTRACT AMOUNT $ __________________________________

TOTAL CONTRACT AMOUNT + OPTIONS $ __________________________________