This is a Project Manual for the USFWS Flint Hills Visitor Center/Headquarters Building Residing and Reroofing Project in Hartford, Kansas, issued by the United States Fish and Wildlife Service, Division of Engineering, Midwest Region on May 10, 2026.
The project encompasses a comprehensive renovation of the exterior building envelope including removal and replacement of vertical wood siding with fiber-cement (Hardie Board) siding and batten strips, installation of new horizontal sliding wood-clad windows to match existing rough openings, replacement of roof shingles with a 24-gauge metal roofing system with concealed fasteners, replacement of wood fascia and soffit with 24-gauge metal panels, removal and installation of new 6-inch K-style gutters and downspouts, installation of new window and door trim with fiber-cement materials, exterior painting of doors and trim, snow guard installation, and creation of an 18-inch decorative rock border around the building base. Two bid additive options are included: Additive #1 offers vertical metal siding as an alternative to fiber-cement siding with manufacturer color selection; Additive #2 includes heavy-duty gutter guards on all new gutters. The work is performed on a firm fixed price lump sum basis with all work items not specifically called out considered incidental with no direct compensation. Contractors must provide temporary facilities including at minimum one toilet facility, maintain project schedules with activities no longer than 20 days, submit detailed submittals including product data and shop drawings, comply with OSHA and environmental regulations including VOC content restrictions, and maintain a one-year warranty period with replacement of defective work at no cost to the Government.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USFWS Flint Hills Visitor Center/HQ
Residing/Reroofing Project
Hartford, Kansas
PROJECT MANUAL
United States Department of the Interior Fish and Wildlife Service Division of Engineering
Midwest Region, Bloomington, MN 55437-1458
May 10, 2026
Flint Hills National Wildlife Refuge Office Building Reroofing and Residing
000110 - 1 Table of Contents
SECTION 000110
TABLE OF CONTENTS
PROCUREMENT AND CONTRACTING REQUIREMENTS
1.01 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS
A. 000110 - Table of Contents
SPECIFICATIONS
2.01 DIVISION 01 -- GENERAL REQUIREMENTS
A. 011000 - Summary of the Work B. 012900 - Payment Procedures C. 013000 - Submittals D. 013100 - Project Coordination E. 013200 - Construction Progress Documentation F. 014000 - Quality Requirements G. 014200 - Definitions and Standards H. 015000 - Temporary Facilities and Controls I. 016000 - Product Requirements J. 016116 - Volatile Organic Compound (VOC) Content Restrictions K. 017419 - Construction Waste Management and Disposal L. 017700 - Project
2.02 DIVISION 02 -- EXISTING CONDITIONS
A. 024100 - Demolition
2.03 DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES
A. 061000 - Rough Carpentry B. 061219 - Structural Insulated Panels
2.04 DIVISION 07 -- THERMAL AND MOISTURE PROTECTION
A. 070150.19 - Preparation for Re-Roofing B. 072500 - Weather Barriers C. 074113 - Metal Roof Panels D. 074213 - Metal Wall Panels E. 074646 - Fiber-Cement Siding F. 076200 - Sheet Metal Flashing and Trim G. 077200 - Roof Accessories H. 079200 - Joint Sealants
2.05 DIVISION 08 -- OPENINGS
A. 085200 - Wood Windows B. 088000 - Glazing C. 088723 - Safety and Security Films
2.06 DIVISION 09 -- FINISHES
A. 099113 - Exterior Painting
2.07 DIVISION 32 -- EXTERIOR IMPROVEMENTS
A. 329400 - Planting Accessories
011000 - 1 SUMMARY OF THE WORK
PART 1 - GENERAL
SECTION 011000
SUMMARY OF THE WORK
1.01 PROJECT TITLE: FLINT HILLS NATIONAL WILDLIFE REFUGE OFFICE/VISITOR CENTER
RESIDING/REROOFING
1.02 WORK UNDER THESE SPECIFICATIONS
A. The Contractor shall furnish all materials, labor, equipment, and supervision required for the work described below and within the construction documents. The work includes, but is not limited to, project mobilization and demobilization, project management and oversight, demolition and construction of the items described below, quality control, cleanup, and the removal of all debris and waste generated during the performance of the work.
B. Base Bid: Flint Hills National Wildlife Refuge Residing and Reroofing Project
1. Siding: The work includes the removal of all existing vertical wood siding and batten strips from the Visitor Center/Headquarters Building. This includes, but is not limited to, the removal of cedar/plywood siding, batten strips, trim, wood soffits and fascia, J-channels and any metal flashing beneath the siding. The contractor shall also inspect the structural insulated panels underneath the siding for any water damage or rot. If damage or rot is found then a report of damage will be given to the Government for review and planning.
After all existing materials are removed, replace them with new furring strips, metal flashing, and fiber-cement/Hardie Board siding and batten strips.
a. Note: The thickness of the furring strips on the Visitor Center/Headquarters Building may need to be adjusted to account for the new fiber-cement siding and trim, ensuring that the existing doors, those that are to remain in place, do not extend any farther past the new Hardie siding and trim than they currently extend past the existing siding. The furring-strip thickness and rigid-insulation thickness shall be adjusted as necessary to position the new siding in the same relationship to the window and door frames as the existing building siding.
2. Windows: The work includes the removal of all existing horizontal sliding wood windows and the installation of new horizontal sliding wood-clad windows of the same size. The contractor shall ensure that all replacement windows match the existing rough-opening dimensions, maintain the original operating configuration, and integrate seamlessly with adjacent building finishes. Contractor shall ensure proper weatherproofing, insulation, and overall continuity of the building envelope.
3. Window/Door Trim: This work shall also include fiber cement trim around all windows and doors under the fascia and down all corners of the building. In order for the trim to be uniform and flush or slightly passed the face of the window frames a wood sub trim/furring trim shall be required before the fiber cement trim is applied. All trims shall be caulked and painted when completed. The width of the trim between the windows may have to vary so it extends the full width between the windows.
4. Roof: Remove the GAF fiberglass three-tab shingles and the 30-pound felt paper. After the shingles and felt paper have been removed, inspect the existing plywood to ensure it is flat and free of leaks. Once the plywood has been inspected and verified to be acceptable, install the underlayment, furring strips/purlins, 24-gauge metal roofing system with concealed fasteners, as well as matching flashing and trim. Snow Guards shall also be installed as specified on drawings.
5. Soffit/Fascia: Work includes the demolition and removal of all existing wood fascia and soffit materials from the designated structures. Following removal, the contractor shall furnish and install new 24-gauge metal fascia and soffit panels, complete with all required trims, closures, and fasteners to ensure a weather-tight and structurally secure installation.
011000 - 2 SUMMARY OF THE WORK
6. Gutters/Downspouts: Work includes the removal and disposal of all existing gutters, downspouts, hangers, and associated hardware. Following demolition, the contractor shall furnish and install new 6-inch K-style gutters and matching downspouts, complete with all required brackets, fasteners, sealants, and accessories to ensure a structurally sound and weather-tight installation.
7. Landscaping: Work includes the excavation and removal of soil, vegetation, and debris necessary to create a continuous 18-inch-wide border around the base of the building.
The contractor shall furnish and install an 18-inch decorative rock border using clean, uniformly graded stone placed over a weed barrier fabric. All edges shall be neatly defined with aluminum edging, and the installation shall ensure proper drainage away from the structure.
8. Paint: Painting includes the preparation and repainting of all existing doors, door frames, and fiber-cement siding and trim. The contractor shall clean, sand, and prime all surfaces as required to ensure proper adhesion of the new coating system. Following preparation, apply the specified paint system to achieve uniform color and coverage across all components. The work shall also include any necessary touch-ups to ensure a complete, consistent, and professionally finished appearance.
C. Bid Additive #1: Vertical Metal Siding Installation
1. All work previously specified for the Visitor Center/Headquarters Building shall remain the same, except that the siding shall be vertical metal siding with a profile similar to the existing, rather than fiber-cement ‘Hardie Board’ siding and batten strips. Additionally, instead of paint, the Government shall select the color from the manufacturer’s expanded color range
D. Bid Additive #2: Gutters guards
1. All work previously specified for the Visitor Center/Headquarters Building shall remain the same, with exception to furnishing and installing heavy-duty gutter guards on all new gutters specified in the base bid. The contractor shall provide a compatible guard system designed to prevent debris accumulation while maintaining proper water flow. Installation shall include all necessary fasteners, accessories, and coordination with the new gutter and downspout system to ensure secure attachment and long-term performance.
E. All work items that are not specifically called out are considered incidental and no direct compensation will be provided. This work shall be performed on a firm fixed price lump sum basis.
1.03 LOCATION AND INSPECTION OF SITE
A. The work site is located at the Flint Hills National Wildlife Refuge in Hartford, KS. See cover sheet for project location. The address for the Refuge Visitor Center is: 530 W Maple Ave, Hartford, KS 66854. The Refuge Manager may be contacted for further information concerning the project location by telephone at (406) 464-5181.
1. The project site is available for inspection Monday through Friday: 8:00 AM to 4:00 PM
EST except Federal Holidays.
B. All prospective bidders, contractors, subcontractors, and related persons are encouraged to visit the site of the proposed Work and to assess the location and extent of the Work prior to submitting bids/quotes. Persons may inspect the site by contacting the Refuge Manager for an appointment.
1.04 DRAWINGS AND SPECIFICATIONS FOR CONSTRUCTION
A. The successful bidder will be provided, upon request, one digital copy of the construction drawings and specifications in .pdf format via email. These files will be provided at no additional cost to the successful bidder.
1. Government's Digital Data Files: Electronic digital data files of the Contract Drawings will not be provided by the Government for Contractor's use in preparing submittals.
011000 - 3 SUMMARY OF THE WORK
B. Construction drawings are drawn on a 22” x 34” standard “D” size sheet at 100%. When plotting drawings at different percentages bar scales on drawings shall be used for measuring.
C. Exact location of all affected utilities will be the responsibility of the contractor. Drawings may not completely show all utilities. Site verification is required in addition to contacting any local authorities and utility companies to determine exact locations of utilities.
1.05 WORK NOT INCLUDED IN THIS CONTRACT
A. All items indicated “NIC” on the drawings or in the specifications are items not included in this contract.
B. Work to be performed under other contracts and not included as a part of this contract is generally shown as “By Others” on the Contract Documents.
1.06 ITEMS PROVIDED BY THE GOVERNMENT
A. Work to be accomplished by the Government or manufactured items to be provided by the Government are generally shown as “By Government” on the Contract Documents.
1.07 TEMPORARY FACILITIES
A. Maintain and restore all government roads, service areas, landscaping, and utilities used to pre-construction condition.
B. Temporary Toilet Facilities: Contractor shall provide, pay for, and maintain, at a minimum, one temporary toilet facility and enclosure for the duration of the project. Provide at time of project mobilization. Maintain daily in clean and sanitary conditions.
1.08 SITE ACCESS AND RIGHT OF WAY
A. The construction access limits on Government property will be established by the Government and provided to the Contractor at the preconstruction meeting. The Contractor shall be responsible for complying with these limits and governing all work accordingly.
B. Provide and maintain access to fire hydrants, free of obstructions.
C. The Contractor is reminded all materials, items, and equipment stored on Government property for the duration of the work is at the Contractors own risk. The Government is not responsible for lost, stolen, or damaged property.
D. All bidders are reminded that they are responsible for contacting the local entity such as township, county, or state having jurisdiction in the project vicinity to insure bidders are aware of any requirements of the local entity. These requirements are between the entity and the bidder. Load limits and other restrictions shall be obeyed.
E. Work scheduled on Saturdays, Sundays, Federal Holidays or other than normal working hours shall be approved in advance by the Government Contracting Officer.
1.09 SAFETY - IN ADDITION TO FAR 52.236-13 ACCIDENT PREVENTION
A. The Contractor shall fill out and submit the “Preconstruction Safety Checklist” to the
Government Contracting Officer prior to beginning construction. A copy of this document is included in the specifications.
B. The Contractor shall designate a safety officer to ensure a safe work site. The safety officer shall perform daily work site inspections to assure compliance with all safety regulations and standards.
C. The Contractor’s Safety Plan shall be available on-site. The Contractor shall provide Safety Data Sheets (SDS) for all hazardous materials brought on-site. SDS shall be made available in a conspicuous location.
D. All equipment and work activities shall comply with OSHA Regulations and all accidents incidental to work performed under this contract shall be reported in accordance with OSHA reporting requirements. Additionally a copy of the accident report shall be provided to the Government Contracting Officer.
011000 - 4 SUMMARY OF THE WORK
E. The Contractor shall provide and install barricades, signs, or other warning devices to delineate the construction area.
F. Provide at least one non-freezing type fire extinguisher of the appropriate class for each group of workers performing flammable procedures on the construction site.
G. Provide and maintain on the construction site a basic first aid kit for the workers to use.
1. Provide first aid supply commensurate with size of project with items necessary for first aid treatment of all injuries. The first aid kit shall include items identified on SDS (see paragraph C of this section) in applicable locations.
2. Advise all workers of the location of first aid supplies.
3. Post telephone numbers of nearest hospital or ambulance service and fire station in conspicuous location. Advise all workers of location of telephone numbers.
H. Provide necessary Personnel Protective Equipment (PPE) as identified by SDS and OSHA regulations.
I. Provide documentation workers have been trained in the use of PPE prior to individual use.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION
012900 - 1 PAYMENT PROCEDURES
1.01 SECTION INCLUDES
SECTION 012900
PAYMENT PROCEDURES
A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.
1.02 DEFINITIONS
A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract
Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.
1.03 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.
B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section. Further breakdown each line item to include materials, labor, and equipment.
1. Identification: Include the following Project identification on the schedule of values:
a. Project name and location.
b. Owner's name.
c. Owner's Project number.
d. Contractor's name and address.
e. Date of submittal.
2. Overhead Costs, Proportional Distribution: Include total cost and proportionate share of general overhead and profit for each line item.
1.04 APPLICATIONS FOR PAYMENT
A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments, as certified by Government and paid for by Government.
B. Payment Application Times: Submit Application for Payment to Government monthly.
C. Application for Payment Forms: Use form approved by Government as form for Applications for
Payment.
D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Government will return incomplete applications without action.
1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.
2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.
3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.
E. Transmittal: Submit signed and notarized original copies of each Application for Payment to Government via email. One copy shall include waivers of lien and similar attachments if required.
F. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:
1. List of subcontractors.
2. Schedule of values.
3. Copies of permits, if required.
012900 - 2 PAYMENT PROCEDURES
4. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.
G. Application for Payment at Substantial Completion: After Contracting Officer issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
2. This application shall reflect Certificate(s) of Substantial Completion issued previously for
Government occupancy of designated portions of the Work.
H. Final Payment Application: After completing Project closeout requirements, submit final
Application for Payment with releases and supporting documentation not previously submitted and accepted, including but not limited, to the following:
1. Evidence of completion of Project closeout requirements.
2. Certification of completion of final punch list items.
3. Updated final statement, accounting for final changes to the Contract Sum.
4. Waivers and releases.
5. Waivers and releases.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
013000 - 1 SUBMITTALS
1.01 GENERAL
SECTION 013000
SUBMITTALS
A. Refer to the technical specifications for all submittals required.
B. Contractor shall coordinate submittal review with construction schedule.
1. Review Time: Government response and return of submittal in .pdf format to Contractor within 10 business days of receipt.
C. When specifically requested by the Contracting Officer, Contracting Officers Representative, or the Government’s on-site observer, the Contractor shall provide paper copies of approved submittals, manufacturer’s written installation instructions, and/or recommendations for review and approval prior to accomplishing equipment installation.
1.02 SUBMITTALS
A. The Contractor shall provide a “Standard Submittal Form” for submittals provided to the
Government. A copy of the form is provided in the specifications. Upon request, one digital copy of the form in .doc format will be provided via email.
B. The Contractor shall provide digital .pdf copies of all submittals via an online project web site to the Government except for items noted otherwise in the specifications. The Contractor shall submit material samples via mail. Submitted material samples will become the property of the Government and will not be returned to the Contractor.
1. Electronic Submittals: Assemble complete submittal package into a single indexed file.
2. File name shall use specification section number followed by a decimal point, then a sequential number, followed by a title (e.g., 061000.01 Concrete). Resubmittals shall include an alphabetic suffix after another decimal point (e.g., 061000.01A Concrete).
C. The approval of submittals shall not relieve the Contractor to comply with the terms and conditions of the Contract Drawings, Specifications, and Manufacturer’s Installation Instructions. The Contractor shall be responsible to determine correct dimension, design, connection, detail and satisfactory construction of all Work.
D. The approval of submittals does not constitute acceptance of a change order by the Government. Contract change orders shall be submitted to the Government Contracting Officer following the modification/change order procedures in Section 013100 Project Coordination.
E. The Contractor shall provide and maintain in proper order and in good, clean condition, at the project site, a copy of approved submittals.
1.03 PROJECT WEB SITE
A. Contractor shall provide, administer, pay for, and use Project Web site for purposes of hosting and managing project communication and documentation until Final Completion. Project Web site shall include the following functions:
1. Project directory.
2. Project correspondence.
3. Meeting minutes.
4. RFI forms and logs.
5. Photo documentation.
6. Submittals forms and logs.
7. Reminder and tracking functions.
8. Daily inspection reports.
B. Provide up to three Project Web Site user licenses for use by the Government.
C. On completion of Project, provide one complete archive copy of the Project Web site to the
Government.
013000 - 2 SUBMITTALS
D. Provide one of the following Project Web site software packages by the following under their current published licensing agreements:
1. Procore
2. Project Teams.
3. Submittal Exchange.
4. Or an approved equal.
1.04 PROJECT SCHEDULE
A. Contractor shall provide as required by Federal Acquisition Regulation (FAR) clauses. *
1.05 PRICE BREAKDOWN - LUMP SUM ITEMS
A. Contractor shall provide as required by FAR clauses. *
2.01 SUBMITTAL OF PROGRESS PAYMENT CERTIFICATE
A. Contractor shall provide as required by FAR clauses. *
2.02 GUARANTEES, WARRANTIES AND CERTIFICATES
A. Refer to Section 017700 Project Closeout.
2.03 OPERATING AND MAINTENANCE INSTRUCTION
A. Refer to Section 017000 Execution and Closeout Requirements.
2.04 DELIVERY TICKETS
A. The Contractor shall submit to the Government via the submittal process in digital .pdf format a copy of each delivery ticket for all material delivered to the construction site.
B. The delivery ticket shall show brand name, catalog number, and number of items received.
2.05 WASTE MANIFESTS
A. The Contractor shall submit to the Government via the submittal process copies of all waste manifests.
B. Manifests shall state type of waste (i.e., construction debris, hazardous asbestos, etc.), location of disposal, landfill designation, EPA registration of landfill, and EPA registration for transportation of any hazardous wastes.
PART 2 -PRODUCTS - NOT APPLICABLE
PART 3 - EXECUTION (NOT APPLICABLE)
3.01 * THE APPLICABLE FAR CLAUSES WILL BE PROVIDED TO THE RESULTANT
CONTRACTOR AT THE PRE-CONSTRUCTION CONFERENCE.
013100 - 1 PROJECT COORDINATION
1.01 JOBSITE ADMINISTRATION
SECTION 013100
PROJECT COORDINATION
A. Superintendence, Subcontract Administration, Quality Assurance, Quality Control, and Construction Inspection are the responsibility of the Contractor.
B. Final decisions relative to items of conflict shall be made by the Contracting Officer.
C. The Government shall have the authority to temporarily suspend the Work for such time as necessary because of the failure on the part of the Contractor to perform any of the provisions of the Contract. No extension of contract performance time will be permitted until the Government determines that the deficiencies in performance, which caused the temporary suspension, have been corrected.
D. The Contractor shall have responsible superintendence on site during all project operations.
The Contractor shall submit to the Government in writing a project superintendence plan.
Changes to the superintendence plan shall be approved by the Government three business days prior to implementation.
E. The Contractor shall notify the Contracting Officer in writing at least ten (10) days prior to the anticipated date of completion of all Work specified herein. Upon completion of the Work, the Contracting Officer, or their designee, shall proceed with the final inspection which shall be completed as promptly as practicable. The time required for such inspection and for performing any corrective Work shall be included in the contract performance time.
1.02 MODIFICATION/CHANGE ORDER PROCEDURES
A. In the event of the need for a Change Order, the Contractor will receive a letter requesting a price quote for proposed changes to the Contract.
B. The Contractor shall not perform work outside of the contract documents without written approval from the Contracting Officer. All expenses of Work performed outside of the contract documents without prior approval will be the responsibility of the contractor.
C. For evaluation purposes, the Contractor's quote shall be broken down to show the costs of labor, materials, and equipment for each proposed category of Work included with the change, along with the total cost for Contractor's overhead, profit, and bond for the proposed changes.
D. All Contract time extensions required as a result of a proposed change must be justified and supported in detail at the time of the proposal.
1.03 REQUESTS FOR INTERPRETATION PROCUDURES (RFI'S)
A. Definition: A request seeking one of the following:
1. An interpretation, amplification, or clarification of some requirement of Contract Documents arising from inability to determine from them the exact material, process, or system to be installed or when an item of work is described differently at more than one place in the Contract Documents.
2. A resolution to an issue which has arisen due to field conditions and affects design intent.
B. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of the
Contract Documents.
1. Prepare a separate RFI for each specific item.
a. Review, coordinate, and comment on requests originating with subcontractors and/or materials suppliers.
b. Do not forward requests which solely require internal coordination between subcontractors.
C. Submission: Submit all RFI's in .pdf format via project website.
013100 - 2 PROJECT COORDINATION
D. Content: Include identifiers necessary for tracking the status of each RFI, and information necessary to provide an actionable response.
1. Official project name and contract number.
2. Owner's and contractor's name and contact information.
3. Discrete and consecutive RFI number, and descriptive subject/title.
4. Issue date.
5. Reference to particular Contract Document(s) requiring additional information/interpretation. Identify pertinent drawing and detail number and/or specification section number, title, and paragraph(s).
6. Annotations: Field dimensions and/or description of conditions which have engendered the request.
E. Attachments: Include sketches, coordination drawings, descriptions, photos, submittals, and other information necessary to substantiate the reason for the request.
F. Review Time: Government shall respond and return RFI's in .pdf format via project website to Contractor within ten business days of receipt.
1. Response period may be shortened or lengthened for specific items, subject to mutual agreement, and recorded in a timely manner in progress meeting minutes.
2. Response period may be shortened or lengthened for specific items, subject to mutual agreement, and recorded in a timely manner in progress meeting minutes.
G. Responses: Content of answered RFIs will not constitute in any manner a directive or authorization to perform extra work or delay the project. If in Contractor's belief it is likely to lead to a change to Contract Sum or Contract Time, promptly contact the Government Contracting Officer.
1. The Contractor shall not perform work outside of the contract documents without written approval from the Contracting Officer. All expenses of Work performed outside of the contract documents without prior approval will be the responsibility of the contractor.
2. Response may include a request for additional information, in which case the original RFI will be deemed as having been answered, and an amended one is to be issued forthwith.
3. Upon receipt of a response, promptly review and distribute to all affected parties.
1.04 PRECONSTRUCTION CONFERENCE
A. Soon after award of the Contract and prior to commencing construction, the Contractor shall attend a preconstruction conference with representatives of the Government at the project location. Timely notification of the meeting will be given to the Contractor. Time, date, and place of the conference will be determined by the Contracting Officer. Requirements pertaining to contract administration, construction operations, project superintendence, and the project schedule will be discussed. The project schedule shall be in accordance with Section 013000 Submittals. The preconstruction safety checklist and project schedule shall be submitted for review during this conference.
1.05 PROGRESS MEETINGS
A. Weekly project meetings will be conducted by the Contractor with representatives of the
Government at the project site and by a web based voice, video, chat, and data sharing application for the purpose of coordinating, expediting, and assessing the work progress. Dates and times will be determined at the Preconstruction Conference.
B. The Contractor shall provide reports of progress on the project, discuss the work schedule for the coming period, and present all conflicts, discrepancies or other difficulties for resolution. A record of discussions, decisions, and meeting minutes will be prepared by the Contractor and distributed via the project website.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
Residing
CONSTRUCTION PROGRESS
DOCUMENTATION 013200 - 1
SECTION 013200
CONSTRUCTION PROGRESS DOCUMENTATION
1.01 SECTION INCLUDES
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Contractor's construction schedule.
2. Daily construction reports.
3. Site condition reports.
4. Unusual event reports.
1.02 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction Project. Activities included in a construction schedule consume time and resources.
1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
C. Event: The starting or ending point of an activity.
1.03 SUBMITTALS
A. Format for Submittals: Submit in .pdf format via project website.
B. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.
1. Submit a working digital copy of schedule labeled to comply with requirements for submittals.
C. Daily Construction Reports: Submit next business day.
D. Site Condition Reports: Submit at time of discovery of differing conditions.
E. Unusual Event Reports: Submit at time of unusual event.
1.04 COORDINATION
A. Coordinate each construction activity in the network with other activities, and schedule them in proper sequence.
1.05 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Computer Scheduling Software: Prepare schedules using current version of a program that has been developed specifically to manage construction schedules.
B. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion.
1. Contract completion date shall not be changed by submission of a schedule that shows a late completion date, unless specifically authorized by Change Order.
C. Activities: Comply with the following:
1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Contracting Officer.
2. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for Government's administrative procedures necessary for certification of Substantial Completion.
Residing
DOCUMENTATION 013200 - 2
3. Final Completion: Indicate completion in advance of date established for Final Completion, and allow time for Government's administrative procedures necessary for certification of Final Completion. Include not more than 30 days for completion of punch list items and Final Completion.
D. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities.
1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
2. As the Work progresses, indicate Final Completion percentage for each activity.
1.06 GANTT-CHART SCHEDULE REQUIREMENTS
A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal, Gantt-chart-type, Contractor's Construction Schedule within 30 days of date established for the Notice to Proceed.
B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line.
1.07 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:
1. List of subcontractors at Project site.
2. List of separate contractors at Project site.
3. Approximate count of personnel at Project site.
4. Equipment at Project site.
5. Material deliveries.
6. High and low temperatures and general weather conditions, including presence of rain or snow.
7. Testing and inspection.
8. Accidents.
9. Meetings and significant decisions.
10. Unusual events.
11. Stoppages, delays, shortages, and losses.
12. Meter readings and similar recordings.
13. Emergency procedures.
14. Orders and requests of authorities having jurisdiction.
15. Change Orders received and implemented.
16. Construction Change Directives received and implemented.
17. Services connected and disconnected.
18. Equipment or system tests and startups.
19. Partial completions and occupancies.
20. Substantial Completions authorized.
B. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.
C. Unusual Event Reports: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report. List chain of events, persons participating, responses by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise Owner in advance when these events are known or predictable.
1. Submit unusual event reports directly to Government within one day of an occurrence.
Distribute copies of report to parties affected by the occurrence.
Residing
DOCUMENTATION 013200 - 3
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
014000 - 1 QUALITY REQUIREMENTS
PART 1 GENERAL
SECTION 014000
QUALITY REQUIREMENTS
A. Quality assurance submittals.
B. Mock-ups.
C. Control of installation.
D. Tolerances.
1.02 SUBMITTALS
A. Design Data: Submit for Government's knowledge as contract administrator for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents, or for Government's information.
B. Certificates: When specified, submit certification by the manufacturer and Contractor or installation/application subcontractor to Government, in quantities specified for Product Data.
1. Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.
2. Certificates may be recent or previous test results on material or product, but must be acceptable to Government.
C. Manufacturer's Instructions: When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, for the Government's information. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.
D. Erection Drawings: Submit drawings for Government's benefit as contract administrator or for Government.
1. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.
2. Data indicating inappropriate or unacceptable Work may be subject to action by
Government.
1.03 REFERENCES AND STANDARDS
A. For products and workmanship specified by reference to a document or documents not included in the Project Manual, also referred to as reference standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.
B. Conform to reference standard of date of issue current on date of Contract Documents, except where a specific date is established by applicable code.
C. Obtain copies of standards where required by product specification sections.
D. Should specified reference standards conflict with Contract Documents, request clarification from Government before proceeding.
E. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of Government shall be altered from the Contract Documents by mention or inference otherwise in any reference document.
1.04 TESTING AND INSPECTION AGENIES AND SERVICES
A. Contractor shall employ and pay for services of an independent testing agency to perform all specified testing including special inspections.
B. Employment of agency in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.
014000 - 2 QUALITY REQUIREMENTS
C. Contractor Employed Agency: Testing agency: Comply with requirements reference in each section.
1.05 DELEGATED DESIGN SERVICES
A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.
1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Contracting Officer.
B. Delegated Design Services Statement: Submit a statement signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional, indicating that the products and systems are in compliance with performance and design criteria indicated. Include list of codes, loads, and other factors used in performing these services.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.01 CONTROL OF INSTALLATION
A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality.
B. Comply with manufacturers' instructions, including each step in sequence.
C. Should manufacturers' instructions conflict with Contract Documents, request clarification from
Government before proceeding.
D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.
E. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.
F. Have Work performed by persons qualified to produce required and specified quality.
G. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.
H. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement.
3.02 MOCK-UPS
A. Assemble and erect specified items with specified attachment and anchorage devices, flashings, seals, and finishes.
B. Accepted mock-ups shall be a comparison standard for the remaining Work.
3.03 TOLERANCES
A. Monitor fabrication and installation tolerance control of products to produce acceptable Work.
Do not permit tolerances to accumulate.
B. Comply with manufacturers' tolerances. Should manufacturers' tolerances conflict with Contract Documents, request clarification from Government before proceeding.
C. Adjust products to appropriate dimensions; position before securing products in place.
3.04 DEFECT ASSESSMENT
A. Replace Work or portions of the Work not conforming to specified requirements.
B. If, in the opinion of Government, it is not practical to remove and replace the Work, Government will direct an appropriate remedy or adjust payment.
014000 - 3 QUALITY REQUIREMENTS
014200 - 1 DEFINITIONS AND STANDARDS
SECTION 014200
DEFINITIONS AND STANDARDS
DEFINITIONS AND STANDARDS
1.01 1.1 REGULATORY REQUIREMENTS
A. All work shall be accomplished in strict accordance with OSHA and all other regulations, codes, and laws in effect at the time the work is performed for the location where it is to be performed.
B. All completed construction shall comply with OSHA, NFPA, Architectural Barriers Act (ABA), Americans with Disabilities Act (ADA), and local codes and regulations.
1.02 MEANS AND METHODS
A. Means and methods used in the performance of this Contract must be in accordance with all applicable Federal Acquisition Regulations in addition to OSHA regulations, 29 Code of Federal Regulations, acceptable industry practices as recognized by societies, associations, building codes, manufacturers’ specifications, and any applicable state safety and health requirements.
1.03 PERMITS
A. All permits required to support construction activities shall be obtained and paid for by the
Contractor.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
015000 - 1 Temporary Facilities and Controls
A. Temporary utilities.
SECTION 015000
TEMPORARY FACILITIES AND CONTROLS
B. Temporary telecommunications services.
C. Temporary sanitary facilities.
D. Temporary Controls: Barriers.
E. Security requirements.
F. Vehicular access and parking.
G. Waste removal facilities and services.
1.02 RELATED REQUIREMENTS
A. Section 015100 - Temporary Utilities.
B. Section 015500 - Vehicular Access and Parking.
1.03 TEMPORARY UTILITIES - SEE SECTION 015100
A. Maintain and restore all government roads, service areas, landscaping, and utilities used to pre-construction condition.
B. Sanitary Sewer Service: Sanitary sewer service through the Government's existing sewer system will not be available for Contractor's use.
C. Water Service from existing Visitor Center/Headquarters Building: Water from the
Government's existing water system is available for use without metering and without payment of use chargers. Provide connections and extensions of service as required for construction operations. Government makes no warranty to serviceability of water service provided to the Contractor for use.
D. Electric Power Service from existing Visitor Center/Headquarters Building: Electric power from the government's existing electric system is available for use without metering and without payment of use chargers for general lighting and equipment. Contractor shall provide temporary power for equipment that requires in excess of 20 amps of electricity and for temporary electric space heating. Contractor shall provide connections and extensions of service as required for construction operations. Government makes no warranty to serviceability of electrical service provided to Contractor for use.
E. Natural Gas Service: Natural gas from Government's existing natural gas service will not be available for Contractor's use.
F. Contractor shall provide and pay for all utilities not described above.
1.04 TELECOMMUNICATIONS SERVICES
A. Provide, maintain, and pay for telecommunications services to field office at time of project mobilization.
B. Telecommunications services shall include:
1. At a minimum, one cellular telephone.
1.05 TEMPORARY SANITARY FACILITIES
A. Provide and maintain required facilities and enclosures. Provide at time of project mobilization.
B. Maintain daily in clean and sanitary condition.
1.06 BARRIERS
A. Provide barriers to prevent unauthorized entry to construction areas, to prevent access to areas that could be hazardous to workers or the public, to allow for owner's use of site and to protect
015000 - 2 Temporary Facilities and Controls existing facilities and adjacent properties from damage from construction operations and demolition.
B. Provide barricades and covered walkways required by governing authorities for public rights-of-way and for public access to existing building.
C. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.
1.07 SECURITY - SEE SECTION 013553
A. Provide security and facilities to protect Work, existing facilities, and Government's operations from unauthorized entry, vandalism, or theft.
1.08 VEHICULAR ACCESS AND PARKING - SEE SECTION 015500
A. Coordinate access and haul routes with governing authorities and Government.
B. Provide and maintain access to fire hydrants, free of obstructions.
C. Provide means of removing mud from vehicle wheels before entering streets.
D. Provide temporary parking areas to accommodate construction personnel. When site space is not adequate, provide additional off-site parking.
1.09 WASTE REMOVAL
A. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition.
B. Provide containers with lids. Remove trash from site periodically.
C. If materials to be recycled or re-used on the project must be stored on-site, provide suitable non-combustible containers; locate containers holding flammable material outside the structure unless otherwise approved by the authorities having jurisdiction.
D. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
016000 - 1 Product Requirements
SECTION 016000
PRODUCT REQUIREMENTS
A. General product requirements.
B. Transportation, handling, storage and protection.
C. Product option requirements.
1.02 RELATED REQUIREMENTS
A. Section 016116 - Volatile Organic Compound (VOC) Content Restrictions: Requirements for
VOC-restricted product categories.
B. Section 017419 - Construction Waste Management and Disposal: Waste disposal requirements potentially affecting product selection, packaging and substitutions.
1.03 SUBMITTALS
A. Product Data Submittals: Submit manufacturer's standard published data. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information specific to this Project.
B. Shop Drawing Submittals: Prepared specifically for this Project; indicate utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
C. Sample Submittals: Illustrate functional and aesthetic characteristics of the product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.
1. For selection from standard finishes, submit samples of the full range of the manufacturer's standard colors, textures, and patterns.
PART 2 PRODUCTS
2.01 NEW PRODUCTS
A. Provide new products unless specifically required or permitted by Contract Documents.
B. Use of products having any of the following characteristics is not permitted:
1. Made outside the United States, its territories, Canada, or Mexico.
2. Made using or containing CFC's or HCFC's.
3. Made of wood from newly cut old growth timber.
4. Containing lead, cadmium, or asbestos.
C. Where other criteria are met, Contractor shall give preference to products that:
1. If used on interior, have lower emissions, as defined in Section 016116.
2. If wet-applied, have lower VOC content, as defined in Section 016116.
2.02 PRODUCT OPTIONS
A. Products Specified by Reference Standards or by Description Only: Use any product meeting those standards or description.
B. Products Specified by Naming One or More Manufacturers: Use a product of one of the manufacturers named and meeting specifications, no options or substitutions allowed.
C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions:
Submit a request for substitution for any manufacturer not named.
PART 3 EXECUTION
3.01 SUBSTITUTION LIMITATIONS
A. See Section 013000 Submittals for product substitution procedures.
016000 - 2 Product Requirements
3.02 TRANSPORTATION AND HANDLING
A. Package products for shipment in manner to prevent damage; for equipment, package to avoid loss of factory calibration.
B. If special precautions are required, attach instructions prominently and legibly on outside of packaging.
C. Coordinate schedule of product delivery to designated prepared areas in order to minimize site storage time and potential damage to stored materials.
D. Transport and handle products in accordance with manufacturer's instructions.
E. Transport materials in covered trucks to prevent contamination of product and littering of surrounding areas.
F. Promptly inspect shipments to ensure that products comply with requirements, quantities are correct, and products are undamaged.
G. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage, and to minimize handling.
H. Arrange for the return of packing materials, such as wood pallets, where economically feasible.
3.03 STORAGE AND PROTECTION
A. Designate receiving/storage areas for incoming products so that they are delivered according to installation schedule and placed convenient to work area in order to minimize waste due to excessive materials handling and misapplication. See Section 017419.
B. Store and protect products…