B08 Contract Price Schedule.pdf

PDF 152 KB Posted

Attached to
Rehabilitate Housing Quarters at Lake Mead Nationa
Solicitation number
140P8121Q0008
Issued by

View the file

Other files

File Type Posted
Sol_140P8121Q0008_Amd_0001.pdf PDF
B09 Questions and Answers_0001.pdf PDF
Sol_140P8121Q0008.pdf PDF
B08 Invoice Payment Request.docx DOCX document
B08 Release of Claims.pdf PDF
B03 General Decision.pdf PDF
A04 Scope of Work Qtrs 202 and 203.pdf PDF
A06 Pictures Cottonwood Cove 202 and 203.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price Schedule

CLIN CLIN Description

QTY Total ($) 1 (Quarters 202) All labor, equipment & materials for -

Flooring

1 EA

2 (Quarters 202) All labor, equipment & materials for - Baseboards

1 EA

3 (Quarters 202) All labor, equipment & materials for - Interior Walls and Ceiling

1 EA

4 (Quarters 203) All labor, equipment & materials for - Flooring

1 EA

5 (Quarters 203) All labor, equipment & materials for - Baseboards

1 EA

6 (Quarters 203) All labor, equipment & materials for – Interior Walls

1 EA

7 (Quarters 203) All labor, equipment & materials for – Fire Sprinkler System

1 EA

8 (Quarters 203) All labor, equipment & materials for – Ceiling/Swamp Cooler Vent

1 EA

9 (Quarters 203) All labor, equipment & materials for – Swamp Cooler Unit

1 EA

10 (Quarters 203) All labor, equipment & materials for – Kitchen Counter Tops

1 EA

11 (Quarters 203) All labor, equipment & materials for – Kitchen Sink/Faucet

1 EA

12 (Quarters 203) All labor, equipment & materials for – Kitchen Light

1 EA

13 (Quarters 203) All labor, equipment & materials for – Mixing valves in Laundry Room

1 EA

14 (Quarters 203) All labor, equipment & materials for – Replace Interior Doors

1 EA

15 (Quarters 203) All labor, equipment & materials for – Closet Doors

1 EA

16 (Quarters 203) All labor, equipment & materials for – HVAC Filter Return Vent

1 EA

17 (Quarters 203) All labor, equipment & materials for – Exterior Door of Kitchen

Price Schedule

18 (Quarters 203) All labor, equipment & materials for – Windows

1 EA

19 (Quarters 203) All labor, equipment & materials for – Electrical Panel

1 EA

20 (Quarters 203) All labor, equipment & materials for – Outlet GFCI and Light Switches

1 EA

21 (Quarters 203) All labor, equipment & materials for – Exterior Door to Backyard

1 EA

22 (Quarters 203) All labor, equipment & materials for – Shower/bathtub

1 EA

23 (Quarters 203) All labor, equipment & materials for – Bathroom Faucets, Drains, Mirrors, Light fixture and Countertops

Total CLINs 1-23

24 (Quarters 203) OPTION LINE A: All labor, equipment & materials for – Carport Storage Doors

1 EA

25 (Quarters 203) OPTION LINE B: All labor, equipment & materials for – Adding Shower into Master Bathroom

1 EA

26 (Quarters 203) OPTION LINE C: All labor, equipment & materials for – Front Yard Landscape

1 EA

27 (Quarters 203) OPTION LINE D: All labor, equipment & materials for – Concrete Patio

1 EA

28 (Quarters 203) OPTION LINE E: All labor, equipment & materials for – Ceiling Fans

1 EA

Total CLINs 1-28 $

This is a firm fixed price requirement. All costs associated to perform the work in accordance to the Statement of Work shall be included. It is anticipated that award will be made as a lump sum.

For price evaluation purposes, price reasonableness will be based on the total sum of CLIN's 1‐23 plus the option line CLINs 24-28. The option lines may be exercised at time of award. However, this does not obligate the Government to exercise the option line items.

Total ($)
QTY
CLIN Description
CLIN
1 EA
(Quarters 202) All labor, equipment & materials for - Flooring
1
1 EA
(Quarters 202) All labor, equipment & materials for - Baseboards
2
1 EA
(Quarters 202) All labor, equipment & materials for - Interior Walls and Ceiling
3
1 EA
(Quarters 203) All labor, equipment & materials for - Flooring
4
1 EA
(Quarters 203) All labor, equipment & materials for - Baseboards
5
1 EA
(Quarters 203) All labor, equipment & materials for – Interior Walls
6
1 EA
(Quarters 203) All labor, equipment & materials for – Fire Sprinkler System
7
1 EA
(Quarters 203) All labor, equipment & materials for – Ceiling/Swamp Cooler Vent
8
1 EA
(Quarters 203) All labor, equipment & materials for – Swamp Cooler Unit
9
1 EA
(Quarters 203) All labor, equipment & materials for – Kitchen Counter Tops
10
1 EA
(Quarters 203) All labor, equipment & materials for – Kitchen Sink/Faucet
11
1 EA
(Quarters 203) All labor, equipment & materials for – Kitchen Light
12
1 EA
(Quarters 203) All labor, equipment & materials for – Mixing valves in Laundry Room
13
1 EA
(Quarters 203) All labor, equipment & materials for – Replace Interior Doors
14
1 EA
(Quarters 203) All labor, equipment & materials for – Closet Doors
15
1 EA
(Quarters 203) All labor, equipment & materials for – HVAC Filter Return Vent
16
1 EA
(Quarters 203) All labor, equipment & materials for – Exterior Door of Kitchen
17
1 EA
(Quarters 203) All labor, equipment & materials for – Windows
18
1 EA
(Quarters 203) All labor, equipment & materials for – Electrical Panel
19
1 EA
(Quarters 203) All labor, equipment & materials for – Outlet GFCI and Light Switches
20
1 EA
(Quarters 203) All labor, equipment & materials for – Exterior Door to Backyard
21
1 EA
(Quarters 203) All labor, equipment & materials for – Shower/bathtub
22
1 EA
(Quarters 203) All labor, equipment & materials for – Bathroom Faucets, Drains, Mirrors, Light fixture and Countertops
23
$
Total CLINs 1-23
1 EA
(Quarters 203) OPTION LINE A: All labor, equipment & materials for – Carport Storage Doors
24
1 EA
(Quarters 203) OPTION LINE B: All labor, equipment & materials for – Adding Shower into Master Bathroom
25
1 EA
(Quarters 203) OPTION LINE C: All labor, equipment & materials for – Front Yard Landscape
26
1 EA
(Quarters 203) OPTION LINE D: All labor, equipment & materials for – Concrete Patio
27
1 EA
(Quarters 203) OPTION LINE E: All labor, equipment & materials for – Ceiling Fans
28
$
Total CLINs 1-28
This is a firm fixed price requirement. All costs associated to perform the work in accordance to the Statement of Work shall be included. It is anticipated that award will be made as a lump sum.
For price evaluation purposes, price reasonableness will be based on the total sum of CLIN's 1‐23 plus the option line CLINs 24-28. The option lines may be exercised at time of award. However, this does not obligate the Government to exercise the option line items.

File details come from the government source that posted it. Updated .