B08_Attch_12_BaselineScheduleReviewChecklist.docx

DOCX document 31 KB Posted

Attached to
LIBI 241430 - Replace Dilapidated Visitor Center F Federal contract opportunity
Solicitation number
140P2024R0111
Issued by
Department of the Interior National Park Service National Office

About this file

This document is a Baseline Schedule Review Checklist Form used by the National Park Service (NPS) - Denver Service Center (DSC) to evaluate an initial project schedule submitted before the pre-construction conference. The checklist covers general requirements such as verifying contract dates, including procurement and construction activities, identifying the critical path, and incorporating contract constraints. It also lists optional requirements for more complex, longer duration, or phased projects, such as activity numbering, resource loading, and accounting for special circumstances. The related federal contract opportunity is for the replacement of a dilapidated visitor center facility at the Little Bighorn Battlefield National Monument, solicited by the Department of the Interior National Park Service National Office.

View the file

Other files for this federal contract opportunity

Other files attached to LIBI 241430 - Replace Dilapidated Visitor Center F, newest first.
File Type Posted
Sol_140P2024R0111_Amd_0002.pdf PDF
B09_Amendment_2_SF30_5-31-24_0002.pdf PDF
B09_Amendment_2_Questions_5-31-24_0002.pdf PDF
B09_Amendment_1_Questions_5-24-24_0001.pdf PDF
B09_Amendment_1_SF30_5-24-24_0001.pdf PDF
Sol_140P2024R0111_Amd_0001.pdf PDF
B08_Attch_4_HAZMAT_Rpt_1-10-23.pdf PDF
B11_PreProposal_Conf_Slides_LIBI_241430_5-7-24_Final.pptx PPTX presentation
B08_Attch_9_General_Ref.doc DOC document
B08_Attch_10_LmtOnSubconRpt.xlsx XLSX spreadsheet
B08_Attch_3_Wage_Determination_MT20240056_1-5-24.pdf PDF
B08_Attch_6_Project_Experience_Form.docx DOCX document
B08_Attch_1_Specifications_4-30-24.pdf PDF
B08_Attch_2_Drawings_4-30-24.pdf PDF
B11_Preproposal_Conference_Sign_In_Sheet_5-7-24_(2).pdf PDF
B08_Attch_8_Bid_Bond.pdf PDF
B08_LIBI_241430_Sol_140P2024R0111_5-7-24.pdf PDF
B08_Attch_5_Geotech_Rpt_2-8-23.pdf PDF
Sol_140P2024R0111.pdf PDF
B08_Attch_11_Construction_Contract_Administration.docx DOCX document
B08_Attch_7_Past_Perf_Quest.docx DOCX document
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Baseline Schedule Review Checklist Form National Park Service (NPS) - Denver Service Center (DSC) | 10-22-18 General ☐ Draft Baseline Schedule submitted before Pre-Construction Conference.

Initial Schedule - Basic Requirements

☐Check dates of Award, Notice to Proceed, Substantial Completion(s-if there are multiple beneficial occupancies), and Project Completion with contract. Completion Date is the contract completion date, not an earlier date.
☐Include in Project Schedule: Procurement and Construction activities including mobilization; submittals; and fabrication and delivery of key and long-lead procurement items.
☐Schedules containing items of work currently underway or design progress and milestones shall be up to date and correct. Check milestones against contract.
☐Activities shall have at least one predecessor and one successor except Notice to Proceed and Project Completion.
☐Include a Critical Path.
☐Include concise description of work represented by activity (48-character maximum).
☐Activity duration shall be in whole working days, 15-work day maximum. (Exceptions include mobilization, shop drawings and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing times).
☐Include and coordinate work by Contractor and Subcontractor.
☐Show sequence and interdependence of activities for complete performance of work.
☐Show a coordinated work plan with logical sequence.
☐Assign realistic duration to each activity, considering scope and resource loading.
☐Start activities on a work day, not a holiday or weekend.
☐Incorporate contract constraints into schedule such as seasonal shutdown, blackout non-work dates, holidays, and breaks in schedule where work is not performed.
☐Compare to Schedule of Values to ensure that progress and monthly billings can be tracked with relative ease. Consider what will happen if there is delay or work done out of sequence? Can progress still be followed without a degree in scheduling? Does presented schedule work with CLINs (contract line item numbers)?
☐Account for “normal” bad weather in schedule. Normal bad weather information is available, so this number should not be a swag.
☐Start-up and testing shall have a duration of at least 10 days, depending on what is being tested.
☐Activities can include Mobilization but not General Conditions and Overhead Profit. There may be multiple mobilizations.
☐Review schedule for frontloaded or unreasonably scheduled high cost items to allow for higher billing during early stages of project. A schedule is a work plan and if the plan makes sense, costs will follow. But at the beginning of the job, if there is a particularly high cost not associated with long lead items, it could indicate an attempt to obtain a lot of money up front to fund a job and this can lead to problems later.

Initial Schedule - Optional Requirements Depending on Complexity, Duration, Cost and/or Phasing

☐Identify activities numerically (5-digit maximum) in 10-digit increments.
☐Limit one activity to one work trade.
☐Resource load each activity by labor category and equipment type.
☐If applicable, account for special circumstances in the Schedule-Traffic Control and/or Coordination activities and avoid double-charging. Include in schedule if critical to project.
☐Include milestones. At a minimum, include Notice to Proceed, Substantial Completion, and milestones identified in Division 01 Specifications and by Project Manager (PM) and/or Contracting Officer Representative (COR).
NPS DSC Baseline Schedule Review Checklist Form, 10-22-18page 1 of 2