B08_Attachment_No__3_Bid_Schedule.pdf
PDF 112 KB Posted
- Attached to
- CAHTO PEAK ROAD IMPROVEMENT PHASE 2 Federal contract opportunity
- Solicitation number
- 140L1225Q0027
About this file
This document is a Price Schedule for the Cahto Peak Road Improvements Phase 2 project. The price schedule contains 19 line items across multiple treatment sites, including work such as inslope ditches, road grading, rock armoring for culvert inlets/outlets, 18" CMP (Corrugated Metal Pipe) installations, and rolling dips. The line items are structured as lump sum pricing for specific treatment sites (Sites 1-5), with two additional additive items: a general grading prescription along 125 feet of road and additional rolling dips. Each treatment site involves multiple components of road and drainage infrastructure improvement, with a quantity of 1 for each lump sum item. The price schedule is designed to allow potential contractors to provide unit costs for each specific treatment and infrastructure enhancement task within the project scope.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SITE_VISIT_SIGN_IN_SHEET_7_7_2025_0001.pdf | ||
| REVISED_SOW_Cahto_Peak_Rd_Ph2_7_23_2025_0001.pdf | ||
| Sol_140L1225Q0027_Amd_0001.pdf | ||
| CAHTO_PEAK_ROAD_IMPROVEMENTS_PHASE_2_Q_A_0001.pdf | ||
| B08_Attachment_No__1_Construction_SOW_Cahto_Peak_Rd_Ph2.pdf | ||
| Sol_140L1225Q0027.pdf | ||
| B08_Attachment_No__2_SAM_WD.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule – Cahto Peak Road Improvements Phase 2
Item Description of Work Quantity Unit Unit Cost Cost
1 Treatment Site 1.a - Inslope Ditch 1 Lump Sum
2 Treatment Site 1.b - Road Grading 1 Lump Sum
3 Treatment Site 1.c - Rock Armoring Culvert Inlet 1 Lump Sum
4 Treatment Site 2.a - Inslope Ditch 1 Lump Sum
Treatment Site 2.b - Road Grading 1 Lump Sum
6 Treatment Site 3.a – 18” CMP 1 Lump Sum
7 Treatment Site 3.b – Rock Armor Inlet/Outlet 1 Lump Sum
8 Treatment Site 3.c – Rolling Dip 1 Lump Sum
9 Treatment Site 3.d – Road Grading 1 Lump Sum
10 Treatment Site 4.a – 18” CMP 1 Lump Sum
11 Treatment Site 4.b – Rock Armor Inlet/Outlet 1 Lump Sum
12 Treatment Site 4.c – Rolling Dip 1 Lump Sum
13 Treatment Site 4.d – Road Grading 1 Lump Sum
14 Treatment Site 5.a – 18” CMP 1 Lump Sum
15 Treatment Site 5.b – Rock Armor Inlet/Outlet 1 Lump Sum
16 Treatment Site 5.c – Rolling Dip 1 Lump Sum
17 Treatment Site 5.d – Road Grading 1 Lump Sum
18 Additive Item A – General Grading Prescription along 125-feet of Road 1 EA (125 LF)
19 Additive Item B – Additional Rolling Dips 1 EA