REVISED_SOW_Cahto_Peak_Rd_Ph2_7_23_2025_0001.pdf

PDF 3 MB Posted

Attached to
CAHTO PEAK ROAD IMPROVEMENT PHASE 2
Solicitation number
140L1225Q0027
Issued by

About this file

This is a Revised Statement of Work (SOW) for the Cahto Peak Road Improvements Phase 2 project for the Bureau of Land Management (BLM) Arcata Field Office in Mendocino County, California. The project involves road-related construction services along approximately 5 miles of rural dirt and aggregate surface road, with specific tasks including installing 3 new 18" Corrugated Metal Pipe (CMP) culverts, upgrading associated ditches and surface drainage conditions, and implementing road grading improvements.

The project's key objectives are to reduce road maintenance burden, improve stormwater drainage, and enhance vehicle accessibility to private and public lands, including hunting areas, timber harvest plan regions, and critical infrastructure communication towers. The work includes constructing an 800-foot inslope ditch, a 300-foot rock armored ditch, installing three 18" Aluminized 12-gauge CMP cross drain culverts with accompanying rolling dips, and grading approximately 4.7 miles of aggregate road surface. The period of performance is 60 calendar days, beginning within 7 days of Notice to Proceed, with all work to be completed by October 31, 2025. The project will follow Pacific Watershed Associates roadwork specifications and requires careful erosion control, environmental protection, and drainage management.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION C, UNIFORM CONTRACT FORMAT (UCF)

DESCRIPTION / SPECIFICATION / STATEMENT OF WORK (SOW)

SOW Page i

REVISED STATEMENT OF WORK (SOW)

7 / 23 / 2025

PROJECT TITLE:

Cahto Peak Road Improvements Phase 2

Table of Contents SOW 1.0 Background on the Government’s Requirement

SOW 2.0 General Scope of Work

REQUIRED TREATMENT SITES:

General Specifications:

Place of Performance

Period of Performance

SOW 3.0 Overall Objective(s)

SOW 4.0 Specific Tasks

SOW 5.0 Delivery / Performance Schedule

SOW 6.0 Government-Furnished Property, Materials, Services

SOW 7.0 Security and Administrative Matters

SOW 8.0 Technical Exhibits and Definitions

EXHIBIT 1: MAPS OF PROJECT AREA AND TREATMENT SITE LOCATIONS .. 16

EXHIBIT 2: TECHNICAL EVALUATION FACTORS

EXHIBIT 3: PWA HANDBOOK SPECIFICATIONS

END OF SOW

Amendment No. 001

SOW Page 1

SOW 1.0 Background on the Government’s Requirement

The Bureau of Land Management (BLM) Arcata Field Office requires roads-related construction services to Cahto Peak Road in Mendocino County near the community of

Laytonville (see Figure 1). The project will install 3 new 18” CMP culverts and upgrade associated ditches and surface drainage conditions along ~5 miles of rural dirt and aggregate surface road. Cahto Peak Road provides access to private lands, public lands including hunting and timber harvest plan areas, as well as critical infrastructure interagency communication towers serviced by PG&E and telecommunications companies. The intent of this project is to reduce the maintenance burden by addressing drainage issues which could lead to road closures and threats to health and human safety.

SOW 2.0 General Scope of Work

Services include the construction of an inboard ditch along 800 feet, a rock armored ditch along 300 feet, installation of three 18” Aluminized 12-gauge CMP cross drain culverts plus three accompanying rolling dips, and a general grading prescription for the remaining ~4.7 miles of aggregate surface on Cahto Peak Road. The site locations are shown on the maps in Figure 2 and the table below lists the general scope of work entailed for each site. Culvert installation sites will be accompanied by installation of rolling dips and rock armoring on the approaches. Rock armoring of the culvert approaches shall use 6-12” angular drain rock in an 18” thick vee-shaped wingwall formation, 4 feet in length and of varying height depending on road and inboard ditch conditions. BLM will stake out the exact locations AND MARK ANY BURIED

UTILITIES prior to the Notice to Proceed. Specifications for rolling dips are provided in

EXHIBIT 3: PWA HANDBOOK SPECIFICATIONS and the Contractor will be required to adhere to these in order to provide all season vehicle passage. HEAVY EQUIPMENT

CAN BE STORED OVERNIGHT AT THE TOP OF CAHTO PEAK BEHIND

GATED BLM LAND OR CONTRACTOR CAN CHAIN EQUIPMENT UP AT ANY

OF THE ADJACENT PULLOUTS/WIDE SHOULDERS. BLM’S EASEMENT

EXTENDS 30 FEET FROM CENTERLINE.

SOW Page 2

REQUIRED TREATMENT SITES:

Site # Milepost Treatment

1 0.7 – 0.9 800 LF inslope ditch and one (1) culvert inlet armoring

• Cut an inslope ditch, 2 ft wide x 18 in deep approximately 800 feet in length along the south side of

Cahto Peak Road. BLM will stake out for Contractor.

• Scarify NO SCARIFICATION DUE TO PRESENCE OF LANDSCAPE FABRIC. Add rock, reshape, compact, and grade the 800 ft of road surface: Contractor will make efforts to salvage existing rock on the road tread and incorporate an additional 6” of 3” Road Base. Treated segment will then be graded and compacted to direct drainage to the existing culvert.

• Install rock armor along one (1) culvert inlet: 4’ long x 18” deep x variable height vee-shaped wingwall configuration on inlet and outlet of existing culvert to prevent depositional erosion and undermining of pipe.

2 0.9 – 1.1 300 LF rock armored inslope ditch

• Cut inslope ditch, excavate 36 in wide x 30 in deep, backfill with 3” to 6” ballast/drain rock, finished dimensions of 2 ft wide x 18 in deep x 300 feet in length. BLM will stake out for Contractor.

• Add rock, reshape, and grade the 300 ft of road surface.: Contractor will make efforts to salvage existing rock on the road tread and incorporate an additional 6” of 3” Road Base. Treated segment will then be graded and compacted to direct drainage to the existing culvert.

3 1.2 One (1) new culvert 18” diameter and Rolling Dip

• Scarify road surface, excavate, install 18” Aluminized 12 gauge CMP, 45° skew from road, minimum 3% slope to outlet. Estimated pipe length 32’ 3/8”. BLM will stake exact position of culvert. TIE CULVERT OUTLET TO THE EXISTING SHELF 5’ BELOW ROAD SURFACE

ON THE NORTH SIDE OF ROAD.

• Install rock armor along culvert inlet and outlet: 4’ long x 18” deep x variable height vee-shaped wingwall configuration on inlet and outlet of existing culvert to prevent depositional erosion and undermining of pipe.

SOW Page 3

• Install one ~80 ft long rock armored rolling dip. BLM to stake out position.

Install and compact 3” Road Base 110’ x 20’ through rolling dip and culvert cross drain area.

Site # Milepost Treatment

4 1.3 One (1) new culvert 18” diameter and Rolling Dip

• Scarify road surface, excavate, install 18” Aluminized 12 gauge CMP, 45° skew from road, minimum 3% slope to outlet. Estimated pipe length 32’ 3/8”. BLM will stake exact position of culvert. TIE CULVERT OUTLET TO THE EXISTING SHELF 5’ BELOW ROAD SURFACE

ON THE NORTH SIDE OF ROAD.

• Install rock armor along culvert inlet and outlet: 4’ long x 18” deep x variable height vee-shaped wingwall configuration on inlet and outlet of existing culvert to prevent depositional erosion and undermining of pipe.

• Install one ~80 ft long rock armored rolling dip. BLM to stake out position.

• Install and compact 3” Road Base 110’ x 20’ through rolling dip and culvert cross drain area.

5 1.4 One (1) new culvert 18” diameter and Rolling Dip

• Scarify road surface, excavate, install 18” Aluminized 12 gauge CMP, 45° skew from road, minimum 3% slope to outlet. Estimated pipe length 32’ 3/8”. BLM will stake exact position of culvert. TIE CULVERT OUTLET TO THE EXISTING SHELF 5’ BELOW ROAD SURFACE

ON THE NORTH SIDE OF ROAD.

• Install rock armor along culvert inlet and outlet: 4’ long x 18” deep x variable height vee-shaped wingwall configuration on inlet and outlet of existing culvert to prevent depositional erosion and undermining of pipe.

• Install one ~80 ft long rock armored rolling dip. BLM to stake out position.4

• Install and compact 3” Road Base 110’ x 20’ through rolling dip and culvert cross drain area.

6 (alt) 1.4 - 5.1 Road Grading 4.7 miles

Scarify, reshape, and grade existing aggregate road surface to promote stormwater drainage to existing culverts. C

SOW Page 4

General Specifications:

• New culverts shall be 12 gauge, aluminized, Type 2, 18” corrugated metal pipe for all culvert sites.

• Culvert coupling bands shall be made of the same material as the culvert.

• Culverts shall be set into prepared native material free of visible organic debris and rock particles >3”. Water used to achieve compaction shall be supplied by the contractor. Compaction shall conform to requitements in EXHIBIT 3: PWA

HANDBOOK SPECIFICATIONS.

• Contractor shall remove any brush cleared from the site.

• Contractor shall provide sufficient water to achieve compaction at all treatment sites.

• Ballast rock and 3” base rock shall be angular, crushed particles. Substitutions may be proposed for road base materials to meet the 3” base rock objective of providing a durable all-season running surface.

• Ballast rock shall be 3” max and shall be placed through the axis of the rolling dip and then surfaced with 3” base or suitable substitute along the entire disturbed length.

• Rolling Dip: Assume a 20-foot wide, 80-foot long, 6-inch thick course of 3” base, and one full dump truck load (8 yards) of 3” ballast rock placed in the center.

Install in accordance with the standard typical drawings (EXHIBIT 3: PWA

HANDBOOK SPECIFICATIONS).

Local Quarries for rock material supplies:

• Northern Aggregates in Willits, CA

Place of Performance Work will be performed along Cahto Peak Road, located approximately 6 miles SW of the community of Laytonville, California in Mendocino County. map is provided showing the treatment locations.

For orientation purposes, Treatment Site # 1 is located at the following coordinates:

Latitude: 39.6746530°

Longitude: -123.5267360°

Period of Performance The period of performance shall begin within 7 days of Notice to Proceed (NTP) and must be completed within 60 days. All work shall be done with suitable moisture conditions for achieving compaction. All work shall be completed no later than October

31, 2025.

SOW Page 5

Rock materials for Tasks 1- 5:

Table 1. Estimates of rock material required for Treatment Sites 1-5.

Material Quantities Total (All Tasks) Volume (CY) Volume (tons)

3" Base Rock 634.0 1142 6-12" Angular Rock 16.0 29 3" Ballast Rock 113.0 204

Treatment Site Location Dimensions Volume (CY) Volume (tons)

Treatment Site 1 3" Base Rock 800'x20'x6" 297.0 535.00 Vee-shaped inlet 6-12" Angular 2 x 4'x4'x18" 2.0 3.6 Vee-shaped outlet 6-12" Angular 2 x 4'x4'x18" 2.0 3.6 Treatment Site 2 3" Base Rock 300' x 20' x 6" 112.00 201.6 Rock Armor Ditch 3-6” Ballast 300' x 96" x 12" 89.0 160.2 Treatment Site 3 3" Base Rock 200' x 20' x 6" 75.0 135.0 Rolling Dip 3" Ballast Rock 8.0 14.4 Vee-shaped inlet 6-12" Angular 2 x 4'x4'x18" 2.0 3.6 Vee-shaped outlet 6-12" Angular 2 x 4'x4'x18" 2.0 3.6 Treatment Site 4 3" Base Rock 200' x 20' x 6" 75.0 135.0 Rolling Dip 3" Ballast Rock 8.0 14.4 Vee-shaped inlet 6-12" Angular 2 x 4'x4'x18" 2.0 3.6 Vee-shaped outlet 6-12" Angular 2 x 4'x4'x18" 2.0 3.6 Treatment Site 5 3" Base Rock 200' x 20' x 6" 75.0 135.0 Rolling Dip 3" Ballast Rock 8.0 14.4 Vee-shaped inlet 6-12" Angular 2 x 4'x4'x18" 2.0 3.6 Vee-shaped outlet 6-12" Angular 2 x 4'x4'x18" 2.0 3.6

Any excess rock shall be used to enhance the reshaping and grading of remaining road described in Additive Item.

SOW Page 6

Quality Assurance and Control.

The Contractor shall follow QA/QC guidelines in the California Department of

Transportation (CalTrans) Construction Manual, Chapter 4, Section 26 related to application and compaction of aggregate base materials. Specifically, the following guidelines shall be followed:

• Ensure that the aggregate base is spread on the subgrade without significant segregation. Normally you would verify this through observation, but if problems persist, support your observations with a sieve analysis. If segregation is taking place, it can sometimes be avoided by wetting the material before it is hauled to the job or before spreading operations start.

Watering and compacting go hand in hand. It is important that the proper amount of water is evenly distributed in the aggregate at the time of compaction.

• Sample the aggregate base at the time it is deposited on the roadbed. Observe delivered aggregate base to ensure that it is clean of debris and other harmful materials.

• Observe the compacting operation to ensure that the material forms a uniformly firm, stable base.

• Measure the thickness of the completed aggregate base. Use your judgment to determine the number of measurements necessary. The minimum acceptable thickness equals the planned thickness minus the sum of the specified tolerance for high subgrade and the specified tolerance for low-finished aggregate base surface.

No testing, as outlined in the CalTrans Construction Manual Section 26, shall be required. The BLM reserves the right to conduct independent testing to verify suitability of materials and application procedures. The Contractor will not be responsible for any independent testing costs. Government reserves the right to complete, finalize, and approve any quality assurance.

Environmental Controls:

The presence of archaeological resources, sensitive soils and private lands within the project area requires that all vehicles and equipment operate on the existing roadway. No work shall occur if moisture conditions are sufficient to cause rutting or pumping of sediment on the road surface.

SOW Page 7

Site Use Plan:

All vehicle and equipment use shall be restricted to the existing roadway. Existing pull-outs may be used for equipment staging and materials storage. Other sites may be utilized for staging, storage, or disposal of excess soils subject to the Contracting Officer or their representative’s approval. At the conclusion of work, all storage and staging areas shall be restored to a free-draining condition. All excess soils will be groomed to match existing topography as feasible. No hazardous materials or fuels shall be stored within

150 feet of a watercourse.

Contractor shall provide for public access through the work site with no more than a five-minute delay. Contractor shall provide signage warning vehicles of the road work.

Traffic Control:

Contractor shall provide traffic control and manage road closures. Road closures shall be kept to a minimum, only as required for the culvert removal and installation. Closures shall not last more than 4 hours at a time and only during weekdays. Post notification signs at least 24 hours prior to road closures in clear view at the bottom of the road and top of the road. Limit the sections of the road that are closed to only the areas immediately adjacent to the work. Plan for designated areas for vehicles to turn around.

Road access shall be re-established by the end of the workday.

Water Diversion:

If water is still running in the streams at the time of construction, the contractor shall divert water around the work area and back into the stream prior to working in the stream channel. Provide temporary bypass piping and cofferdams at the inlet.

SOW 3.0 Overall Objective(s)

The objective of this work is to improve road stormwater drainage which will reduce maintenance costs and safeguard health and human safety by improving vehicle accessibility to private and public lands including critical infrastructure communication towers. Public Lands accessible by Cahto Peak Road are used for hunting and camping.

Upcoming timber harvest plans in this area require safe roads for logging trucks.

SOW Page 8

SOW 4.0 Specific Tasks

See the Treatment Site Map, Figure 2 located in EXHIBIT 1: MAPS OF PROJECT

AREA AND TREATMENT SITE LOCATIONS

Task 1: Treatment Site #1 - 800 LF inslope ditch and one (1) culvert inlet armoring

a. Cut an inslope ditch, 2 ft wide x 18 in deep approximately 800 feet in length along the south side of Cahto Peak Road. BLM will stake out for Contractor.

b. Scarify, add rock, reshape, compact, and grade the 800 ft of road surface.

Contractor will make efforts to salvage existing rock on the road tread and incorporate an additional 6” of 3” Road Base. Treated segment will then be graded and compacted to direct drainage to the existing culvert.

c. Install rock armor along culvert inlet: 4’ long x 18” deep x variable height vee-shaped wingwall configuration on inlet and outlet of existing culvert to prevent depositional erosion and undermining of pipe.

Task 2: Treatment Site #2 - 300 LF rock armored inslope ditch

a. Cut inslope ditch, excavate 36 in wide x 30 in deep, backfill with 3-6” ballast/drain rock, finished dimensions of 2 ft wide x 18 in deep x 300 feet in length. BLM will stake out for Contractor.

b. Add rock, reshape, and grade the 300 ft of road surface.

Contractor will make efforts to salvage existing rock on the road tread and incorporate an additional 6” of 3” Road Base. Treated segment will then be graded and compacted to direct drainage to the existing culvert.

Task 3: Treatment Site #3 - One (1) new culvert 18” diameter and Rolling Dip

a. Scarify road surface, excavate, install 18” Aluminized 12 gauge CMP, 45° skew from road, minimum 3% slope to outlet. Estimated pipe length 32’ 3/8”. BLM will stake exact position of culvert.

b. Install rock armor along culvert inlet and outlet: 4’ long x 18” deep x variable height vee-shaped wingwall configuration on inlet and outlet of existing culvert to prevent depositional erosion and undermining of pipe.

c. Install one ~80 ft long rock armored rolling dip. BLM to stake out position.

d. Install and compact 3” Road Base 110’ x 20’ through rolling dip and culvert cross drain area.

SOW Page 9

Task 4: Treatment Site #4 - One (1) new culvert 18” diameter and Rolling Dip

a. Scarify road surface, excavate, install 18” Aluminized 12 gauge CMP, 45° skew from road, minimum 3% slope to outlet. Estimated pipe length 32’ 3/8”. BLM will stake exact position of culvert.

b. Install rock armor along culvert inlet and outlet: 4’ long x 18” deep x variable height vee-shaped wingwall configuration on inlet and outlet of existing culvert to prevent depositional erosion and undermining of pipe.

c. Install one ~80 ft long rock armored rolling dip. BLM to stake out position.

Task 5: Treatment Site #5 - One (1) new culvert 18” diameter and Rolling Dip

a. Scarify road surface, excavate, install 18” Aluminized 12 gauge CMP, 45° skew from road, minimum 3% slope to outlet. Estimated pipe length 32’ 3/8”. BLM will stake exact position of culvert.

b. Install rock armor along culvert inlet and outlet: 4’ long x 18” deep x variable height vee-shaped wingwall configuration on inlet and outlet of existing culvert to prevent depositional erosion and undermining of pipe.

c. Install one ~80 ft long rock armored rolling dip. BLM to stake out position.

Additive Item – Road Grading 4.7 miles

a. Reshape and grade the remaining ~4.7 miles of road between Treatment Site 5 and the BLM Communication Towers at the top of the peak. Contractor shall scarify, reshape, and grade to promote drainage to existing drain ditches and culverts. Any leftover rock from Treatment Sites 1 – 5 can be used to shore up areas that have evidence of rutting and washing out.

SOW Page 10

SOW 5.0 Delivery / Performance Schedule

The Contractor shall complete all road treatments and any awarded additive items within

60 calendar days after notice to proceed. All work must occur between April 15 and

October 31.

Final Inspection and Acceptance. The Contracting Officer’s Representative (COR) will review all work. At the conclusion of the work, the Contracting Officer (CO), or their representative, will inspect all sites for conformance with the specifications and requirements. The Contractor will be asked to demonstrate dimensions for compliance with specifications such as those described in Error! Reference source not found.. Any deficiencies noted during the inspection will require correction prior to release of final payment. Prior to final payment the Contractor will have properly disposed of all waste materials.

Any staging and storage areas will be restored to pre-disturbance topography and left in a free draining condition.

SOW 6.0 Government-Furnished Property, Materials, Services

General:

The Contractor shall furnish all personnel, materials, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the work tasks defined in this Performance Work Statement, except for those items specified as government furnished.

Materials:

The Government will not be furnishing any materials to assist the Contractor in meeting the requirement of this contract.

Equipment:

The Government will not be furnishing any equipment to assist the Contractor in meeting the requirement of this contract.

Services:

The Government COR will provide stake markers to delimit the exact locations and boundaries of each of the six Treatment Sites, see Figure 2.

Applicable Publications (Current Editions) Contractor will abide by all stream crossing and rolling dip specifications outlined in the “Handbook for Forest, Ranch &

Rural Roads” (Pacific Watershed Associates 2014) and available online at:

https://www.pacificwatershed.com/roadshandbook

SOW Page 11

These specifications are provided in Error! Reference source not found. and shall be incorporated into the treatments.

SOW 7.0 Security and Administrative Matters

The bulk of this project is located on an all-season public road that will not require special security arrangements. There is a few hundred feet of road above the BLM

Communication Tower gate that BLM staff will provide access to when the Contractor is ready to grade it. The Contractor shall coordinate with BLM COR to arrange these work access times.

Security:

The Contractor shall be responsible for safeguarding all Government property provided for Contractor use or under their control, including securing all facilities the Contractor may access after normal business hours.

Contractor shall coordinate work schedule with Contracting Officers Representative to plan road closures and traffic disruptions while minimizing public and employee ingress/egress to the construction areas.

Safety:

The Contractor shall not require, or allow any employee, engaged in the performance of this Contract to work under conditions which are unsanitary, hazardous, or dangerous to his/her health or safety, as determined under safety and health standards promulgated by the Secretary of Labor under Section 107 of the Contract Work Hours and Safety

Standards Act (40 U.S.C. 327 et seq.) as amended and other Federal, State and applicable local government safety standards.

Department of Labor Code of Federal Regulations Title 29 and other Federal, State and local government safety standards will apply in its entirety to the Contractor.

Examples of applicable safety standards are OSHA 29 CFR 1910, OSHA 29 CFR 1926, California Title 19, "Public Safety", California Title 8, "General Industry Safety Orders", and 41 CFR, Subpart B, "Public Contracts, General Safety and Health Standards."

The Contractor shall also use the “BLM SAFETY AND HEALTH STANDARDS” (The

Yellow Book) for reference.

Should the Contractor fail to comply with any of these standards and regulations, the

Contractor shall be found to have defaulted on the terms of the contract.

SOW Page 12

Contingency Plan:

Sudden or unusual events could result in a negative impact to the delivery / performance of these requirements.

As an aid to properly plan for such events, the Contractor shall prepare and submit for approval a Contingency Plan for each Place of Performance for these requirements.

The Contractor will outline in detail the method(s) that the Contractor shall use in meeting Contract requirements in the following circumstances:

• a natural disaster occurs which impacts upon the Contractor's ability to perform

• a labor strike occurs which impacts upon the Contractor's ability to perform.

• a hazardous materials spill which impacts the Contractor’s ability to perform or which may affects public safety

• an incident which causes major damage which impacts the Contractor's ability to perform

• other unforeseen circumstances

In all cases, the Contractor will assume that government cannot provide supplemental forces and continues to need the same or additional performance under the Contract, which the Contractor must meet.

This Contingency Plan shall be submitted as a part of the Contractor proposal.

Emergency Response:

Response to emergency service calls outside of the normal business hours shall not exceed four (4) hours regardless of the time during the day or night, weekends or holidays.

Response to emergency service during normal business hours shall not exceed two (2) hours.

Response is defined as having all personnel and equipment required to correct an emergency at the site of the emergency or at a pre-approved staging area, ready, willing, and able to perform the emergency work. The Contractor will provide a draft emergency response plan prior to Contract start date.

Emergency Services:

On occasion, services may be required to support an activation or exercise of contingency plans outside the normal business hours described above. The Contractor's responsibilities for emergency support will be in accordance with the contingency plan.

Hazardous Materials and Hazardous Response:

The Contractor will conform to all Bureau, Federal, State, and local regulations in the use and disposal of hazardous materials and hazardous waste. The Contractor will provide the appropriate response to any emergency involving hazardous materials at any of the facilities covered by this Contract.

SOW Page 13

The Contractor will provide proof/certification of its personnel qualified to work with hazardous materials and wastes to the Bureau. The Contractor will notify the Bureau immediately upon discovering a release of hazardous waste into the environment.

Public contact:

Contractor personnel may encounter adjacent landowners or members of the public during the performance of their work.

Contractor personnel will present a professional appearance and be able to provide appropriate identification, including display of proper identification by each employee.

All Contractor and Subcontractor personnel shall comply with all Federal and State laws relative to citizenship.

Contractor personnel shall inform any trespassers along the right of way of hazards and, as necessary and appropriate, ask trespassers to leave fenced off or restricted areas.

If Contractor personnel may encounter emergency personnel, policemen, or firemen along the right of way, the Contractor personnel shall notify the On-Site Foreman

If Contractor personnel encounter the news media, they should refer all questions to the

On-Site Foreman, who shall keep the COR informed of all news media contacts.

Government Observations:

Government personnel other than COR may from time to time observe, photograph, or otherwise record Contract operations.

However, these personnel will not interfere with Contractor performance.

Regular Work Hours:

The performance period established for this contract is based upon all work being conducted during regular working hours between 8:00am and 4:30pm, Monday through

Friday, excluding government holidays.

If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and government holidays, a request must be submitted to the COR in sufficient time to allow satisfactory arrangements to be made for access to the work site.

Communications:

“Time” for communications received after 3:00pm, after 12:00 pm locally on Fridays, or after 12:00 pm locally prior to a holiday will not start until the next business day. All times are local Pacific Standard Time.

SOW Page 14

Federal Holidays:

The following eleven Federal Legal Holidays are observed:

New Year’s Day Martin Luther King, Jr. Day Christmas Day

President’s Day Memorial Day Thanksgiving Day

Independence Day Labor Day Veterans Day

Columbus Day Juneteenth Day

Fire Danger Season:

If the Contracting Officer Representative (COR) allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.

Drawings:

Typical Drawings: Any drawings titled typical are general only and dimensions of each structure will be fixed by the Contracting Officer to adapt the design to existing conditions at the structure location.

Reduced Size Drawings: Any drawings identified as "REDUCED SIZE DRAWINGS" are photographically reduced in size. Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown. Prospective bidders desiring to review a copy of the full size drawings may contact the Contracting Officer identified in the solicitation.

SOW Page 15

SOW 8.0 Technical Exhibits and Definitions

Standard Definitions:

Physical Condition

The Physical appearance of Federal equipment or facilities that considers cracks, chips, dents, abrasions, rust, corrosion, general cleanliness, vibration, operating temperature, and discoloration and other items as identified by the COR.

Physical condition may be determined by visual as well as diagnostic means.

Contracting Officer (CO)

The Secretary of the Interior or designated authorized representative who is the only agent capable of signing a federal award or obligating funds.

Contracting Officer’s Representative (COR)

The Contracting Officer’s designated representative as indicated in a delegation of authority letter.

Quality Assurance (QA)

Surveillance of Contractor performance to determine performance requirements are met.

Technical Evaluation Factors (see EXHIBIT 2: TECHNICAL EVALUATION

FACTORS below)

This identifies the key performance indicators of the Contract that will be evaluated by the Government to assure Contract performance standards are met by the Contractor.

Quality Control

Those actions taken by the Contractor to control the production of goods or services so that they meet the requirements of the performance work statement.

Technical Exhibits:

EX 1: Maps of Project Area and Treatment Site Locations

EX 2: Technical Evaluation Factors

EX 3: Pacific Watershed Associates Roadwork Specifications

SOW Page 16

EXHIBIT 1: MAPS OF PROJECT AREA AND TREATMENT SITE LOCATIONS

Figure 1. Cahto Peak Rd approx. 6 miles west of Laytonville in Mendocino County, CA.

SOW Page 17

Figure 2. Treatment Sites 1 - 5. Site 1 is 0.7 miles from the turnoff at Branscomb Rd.

SOW Page 18

EXHIBIT 2: TECHNICAL EVALUATION FACTORS

The Government will evaluate technical acceptability in accordance with the following non-price factors:

1 FACTOR ACCEPTABLE UNACCEPTABLE

A Experience and

Capability to

Complete

Project

Quoter provides at least one project(s), similar in nature, that clearly demonstrates their experience and capability to complete the project.

No information provided or information provided does not demonstrate the quoter’s capability to complete the project, e.g. project provided has no similarity to this project.

B Equal

Specifications

Demonstrate the successful completion of the required work specified in SOW 4.0

Specific Tasks to the COR within the Period of

Performance.

Fails to demonstrate successful completion of required work specified in SOW 4.0 Specific

Tasks or fails to complete the project within the required timeline specified in Period of

Performance.

C Schedule Provide description that identifies the important steps to complete the project and demonstrates the necessary understanding to complete the project within the required timeframe specified in Period of Performance.

No information provided or information provided does not demonstrate the quoter’s understanding of a schedule required to complete the project within the required timeline specified in Period of

Performance.

D Licenses Provide copies of License(s) and License Number(s) that show contractor is licensed to perform work in the state of

Ca.

No information provided or information provided does not demonstrate proof of

License(s) and License

Number(s) that show contractor is licensed to perform work in the state of

CA.

SOW Page 19

EXHIBIT 3: PWA HANDBOOK SPECIFICATIONS

STANDARD DETAILS AND SPECIFICATIONS

Schematics for Typical Treatments

Specified in the Scope of Work

From:

Handbook for Forest, Ranch & Rural Roads

Pacific Watershed Associates 2014

Available online at:

SOW Page 20

SOW Page 21

SOW Page 22

SOW Page 23

SOW Page 24

SOW Page 25

SOW Page 26

SOW Page 27

SOW Page 28

SOW Page 29

SOW Page 30

SOW Page 31

SOW Page 32

END OF SOW