B08_ATTACHMENT_A_SOW.pdf
PDF 2 MB Posted
- Solicitation number
- 140P8125Q0038
About this file
This Scope of Work details a heat pump mini split installation project for the National Park Service at the Mojave National Preserve in California. The project involves installing seven (7) government-furnished HVAC mini split units across three locations: the Kessler 4-plex residential building (four units), the Rocking L house (one unit), and the Hole in the Wall Visitor Center (one unit).
The specific equipment includes three 18,000 BTU and three 12,000 BTU Pioneer ductless mini-split inverter heat pump systems, along with six decorative PVC line cover kits. The contractor must complete all installation tasks within 60 calendar days after notice to proceed, including electrical work, mounting condensers on concrete pads, installing refrigerant lines, restoring exterior building surfaces, and performing required testing. The project requires compliance with multiple codes and standards, including NFPA, California building energy efficiency standards, and OSHA requirements. Installers must hold current state HVAC/electrical contractor licenses and provide a one-year parts and labor warranty on workmanship and supplied materials.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08__ATTACHMENT_B_DB_Wage_Determination_CA20250026.pdf | ||
| Sol_140P8125Q0038.pdf | ||
| B08_ATTACHMENT_C_Asbestos_Report.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work Government Furnished Heat Pump Mini Split Installation
NATIONAL PARK SERVICE
Mojave National Preserve
San Bernardino County, California
MOJA – Install 7 HVAC mini split Units at MOJA
1. BACKGROUND
The Mojave National Preserve (MOJA) is located between Los Angeles and Las Vegas, south of the Interstate 15 freeway and about 75 east of Barstow CA. The Preserve is replacing the units due to the reduced maintenance requirements and cooling quality of air conditioner units compared to the existing evaporative coolers. See maps at end of this document for the areas within MOJA that are included in this scope:
- Kessler 4-plex residential building (Kessler Springs, CA) off Cima Rd
- Rocking L house (Nipton, CA) off Black Canyon Rd.
- Hole in the wall visitor center (Essex, CA) off Black Canyon Rd.
Installation of seven (6) new government furnished HVAC mini split units (6 condensers and 6 air handlers) in accordance with National Electric Code (NEC) and any supplemental codes per local jurisdiction. Units to be installed are:
- Four (4) HVAC mini splits at the Kessler 4-plex housing area (one per housing unit)
- One (1) HVAC mini split at the Rocking L house.
- One (1) HVAC mini split at the Hole in the Wall Visitor Center.
Each of the buildings is equipped with 240 volts / 100-amp electrical service. New branch circuits will need to be installed for the new HVAC units. Contractor shall conduct any electrical work on each building’s main panel to assure units will perform as expected and cool and heat appropriately for annual temperature variation of 20-120 degrees Fahrenheit.
2. PROJECT TASKS:
Contractor shall perform the following tasks:
1. Install seven (6) Government Furnished mini splits heat pump systems, including all electrical wire, conduit, breakers and other electrical and plumbing appurtenances and accessories needed for the operational need.
2. Install concrete precast pads to mount mini split condensers. Location of concrete pad shall be defined by contractor and approved by COR.
3. Provide copper refrigerant lines and additional refrigerant for the installation if the manufacturer supplied lines are too short. Provide any associated components needed to mount and install mini split unit.
4. Restore exterior siding of buildings where refrigerant lines penetrate and seal appropriately (filling holes in stucco siding, repairing damaged stucco texture, painting areas of discoloration or repair to blend with existing structure, and creating a uniform siding finish).
5. Perform vent testing procedures in accordance with American National Standard ANSI Z21.47 to assure proper venting.
6. Install vent/flue pipe at proper vent size and connectors.
7. Ensure that units are mounted so that proper draining of condensation can occur.
8. Install drain pan, trap, and PVC condensate lines per the manufacturer’s recommended configuration.
9. Install new branch circuits to condensers and air handlers. Electrical service lines shall be installed to conceal as much as possible in attic, crawl spaces, and walls.
10. Install copper refrigerant lines from air condensers to air conditioning heads. Line sets shall be installed to conceal as much as possible in attic, crawl spaces, and walls.
11. Paint/repair any interior or exterior wall/ceiling/floor surface damaged or installed to complete installation of HVAC systems including but not limited to caulk, flashing, transitions, or painted wood trim.
12. All installation will be in accordance with manufacturer specifications
13. Test newly installed HVAC system by performing manufacture gas pressure test, temperature rise test, A/C leak test, heating and cooling test.
3. GOVERNMENT FURNISHED EQUIPMENT
1. Three (3) Pioneer® EStar WYS018GMFI22RL-10 (18,000 BTU) Ductless Mini-
Split Inverter and Heat Pump System
2. Three (3) Pioneer® WYS012GMFI20RL-10 (12,000 BTU) Ductless Mini-Split
Inverter and Heat Pump System.
3. Six (6) Decorative PVC Line Cover Kits for Mini Split Air Conditioners & Heat
Pumps (9000-18000btu)
5. PROJECT LOCATION:
Kessler 4 plex (Kessler Springs, CA) GPS Coordinates: 35°17'46.24"N, 115°32'2.34"W
Building is a four-unit 3,247 gross square foot structure.
Unit 1: 1200 square feet; 2 Bedroom, 2 bathroom, living area, dining area, and kitchen Unit 2: 500 square feet, 1 Bedroom, 1 bathroom, living area, and kitchen Unit 3: 500 square feet, 1 Bedroom, 1 bathroom, living area, and kitchen Unit 4: 1200 square feet, 2 Bedroom, 2 bathroom, living area, dining area, and kitchen
Rocking L house (Nipton, CA) GPS Coordinates: 35° 4'26.33"N, 115°22'18.68"W
Hole in the Wall Visitor center (Essex, CA) 1 Black Canyon Rd – Essex, CA 92332
6. CONTRACTOR USE OF PREMISSES
Contractor shall always adhere to the following while working within the Preserve:
A. General: NOTICE: Project occurs in park housing area. Contractor must be respectful of the tenants of the housing area and confine workspace and areas to not impede on tenants. Noise will be kept at a minimum and access to indoor spaces will be at the request of the contractor. Contractor to schedule building access with COR at least 72 hours in advance.
B. Park Entry: The contractor shall furnish a list of personnel with phone contact information.
C. Site Access: Do not drive vehicles off road or access non-project areas without permission from the contracting officer representative.
D. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity
E. Working Hours: Work hours shall be available from 7:00 a.m. to 3:30 p.m. Monday through Friday, excluding government holidays. Work outside regular hours requires approval from the contracting officer
F. When accessing work inside park housing a NPS staff escort will be always onsite.
Contractor shall not access housing units without escort at any time.
G. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings, buildings under construction, and buildings under renovation. Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines
H. Staging and Storage: Confine storage of equipment and materials to the staging / lay-down / storage areas identified by the COR or as established at the preconstruction meeting
I. Parking: The contractor shall park vehicles and heavy equipment in designated areas for contractor use or as established at the preconstruction meeting
J. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles always
K. Preservation of Natural Features: Prevent damage to natural surroundings. Restored damaged areas and replace damaged trees, vegetation, and grass at no expense to the government
7. PERIOD OF PERFORMANCE & SUBMITTALS:
All tasks and deliverables, including release of claims and all inspections, shall be completed within 60 calendar days after notice to proceed.
After contract award, Notice to Proceed #1 will be issued for administrative submittals. The contractor will have 7 business days to submit the following. The CM16 transmittal form shall be used to submit:
- Certificate of Liability Insurance and Alternative Payment Protection (Payment Bond)
- Accident and safety plan
- SF-1413 Subcontractor Form (is applicable)
- Letter Designating PRIME Superintendent
- Project Schedule
- Schedule of Values (lump sum)
Once all submittals are approved, a preconstruction meeting will be scheduled.
It is expected that immediately following the preconstruction meeting, Notice to Proceed #2 will be issued to mobilize and begin on site work. This will begin the 60-day performance period.
8. COMPLIANCE
While performing work, the contractor shall comply with the latest applicable versions of the following:
• NFPA 101 (National Fire Protection Association's Life Safety Code)
• California Title 24 Building Energy Efficiency Standards
• California Refrigerant Management Program, Air Resources Board
• MUCTD Standards and Policies
• Occupational Safety and Health Administration (OSHA) requirements
• NFPA 58 Petroleum Gas Code
• NEC Code Article 690 with respect to California code
• CCR Title 16 Division 8
Additional Requirements:
1) Installers shall hold current applicable State General or HVAC/Electrical Contractor’s licenses.
2) All affected areas must be left in a clean and tidy condition. Any damages to government property shall be fixed and repaired at no cost to the government.
3) All new equipment, supplies, products must conform to the manufacturer’s instructions and guidelines.
4) Contractor shall provide one-year parts and labor warrantee on workmanship and contractor supplied materials/equipment.
10. PROJECT LOCATIONS
1. Kessler Springs
2.HITW visitor center
3.Rocking L