This Statement of Work (SOW) details a fire main repair project at Joshua Tree National Park Headquarters. The project involves replacing approximately 100 linear feet of 8-inch ductile iron fire suppression water pipe that was damaged, potentially by an earthquake. The contractor will be required to remove and replace the pipe section, including cutting and removing approximately 155 square feet of asphalt and a 6-foot wide by 64-foot long concrete sidewalk section. The replacement pipe will be high-density polyethylene (HDPE) rated for 250 PSI working pressure, with thermal fusion joints.
Key project requirements include identifying underground utilities before excavation, installing the new pipe with all necessary fittings, restoring the excavated area with compacted backfill, and replacing the removed asphalt and concrete surfaces. A National Park Service archeologist must be present during excavation, and the project must be completed within 60 days after the Notice to Proceed. The contractor must be a state-licensed General or Plumbing Contractor, provide a one-year labor warranty, and respond to warranty service calls within 3 calendar days. Work is restricted to 6:00 AM-5:30 PM Monday through Friday, excluding government holidays, and must comply with all park regulations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work – Headquarters Fire Main Repair
1.1 Background & Scope of Work
Joshua Tree Headquarters has an 8-inch fire main that provides fire suppression water during times of need. Recently it is believed that an earthquake ruptured the fire main after water began to seep to the surface. Flow is shutoff on to the north side of the Head Quarters compound, and on to the south side of the HQ compound. In August of 2024 it was determined the water main had sprung a leak and a repair was required. Upon excavation it was determined that the pipe was too degraded to perform standard repair techniques and the entire 100-ft section, between valves, would need to be replaced from valve to valve.
This project is to replace approximately 100 linear feet of 8-inch ductile iron pipe used to supply water to the fire suppression system for Joshua Tree National Park’s law enforcement; museum and cultural; sciences and Resources; and facilities management buildings . The section of pipe to be replaced has one 90-degree turn and shall be replaced with a section that starts from shut off valve to ending section with shut off valve, including all required fittings, adapters, couplings, etc. Contractor to dispose of all demolition material, offsite.
The contractor shall cut, remove and dispose of asphalt measuring approximately 155-square feet along with a section of 4-inch concrete sidewalk measuring 6-feet wide x 64-feet long to gain access to underground fire main. The fire main will be exposed and then repaired to allow for proper flow. Any underground concrete thrust block shall be replaced/repoured. After the fire main repair is complete the area shall be backfilled, compacted and asphalt replaced. The removed sidewalk section(s) shall be framed, poured, edge-troweled and broom finished, to match existing. Concrete shall be non-tinted.
1.2 HIGH DENSITY POLYETHYLENE (HDPE) PIPE
A. Pipe shall be high molecular weight, high-density polyethylene pipe. The material shall conform to AWWA C906, PPI designation PE 3408 and have a cell classification of 345444C as described in ASTM D3350 and shall be, TYPE III, Grade PE34. The pipe shall contain no recycled compound except that generated in the manufacturer’s own plant from resin of same specification from the same raw material pipe. Polyethylene pressure pipe shall also conform to the applicable requirements of ASTM F714.
B. Pipe shall be rated for 250 PSI working pressure minimum.
C. The pipe inside diameter shall not be less than the nominal diameter specified or shown.
E. All joints for the buried polyethylene pipe shall be of the thermal fusion type.
F. Polyethylene fittings shall conform to ASTM D3261. Each fitting shall be clearly labeled to identify its size and dimension ratio.
1.2.1 PERFORMANCE VERIFICATION TEST (PVT)
A. PVT Testing to be conducted in partnership with Joshua Tree National Park Engineer and/or maintenance division for visual performance test of flow and no leaks.
1.3 COMPACTION
A. Compact the top 2.5 feet of fills to minimum of 95 percent of the maximum density as determined by ASTM D1557, at plus or minus 2 percent of the optimum moisture content.
B. Compact fills below the top 2.5 feet of fills scarified ground surface to 90 percent of maximum density.
1.4 BACKFILL AND COMPACTION
A. Place bedding and backfill materials true to the lines, grades, and cross-sections excavated areas and compacted to the degree specified. Place bedding and backfill materials in horizontal lifts not to exceed 8 to 12 inches in thickness measured before compaction. The difference in level on either side of a pipe or duct shall not to exceed 4 inches.
1.5 COMMERCIAL AGGREGATE BASE COURSE
A. Class 2 Aggregate Base, 3/4-inch maximum; as per Section 26-1.02 A, CDT Standard Specifications.
1.6 BACKFILL / IMPORTED BACKFILL
A. Before placing fill, scarify ground surface to a minimum depth of 12 inches, bring to a moisture content of plus or minus 2 percent of optimum, and compact to 90 percent relative compaction to provide ample bond between old and new material.
Place embankment material in layers not exceeding 8 inches loose measurement.
Compact each layer before placing the next layer. As the compaction of each layer progresses, continually level and manipulate to ensure uniform moisture and density.
Add water to obtain optimum moisture content.
B. Clean, readily compactible non-expansive soil or soil aggregate, free of organic materials, with all particles passing a 2-inch square opening and not more than 40 percent by weight passing a No. 200 sieve, as determined by ASTM D422-63. The plasticity index shall not be greater than 12, as determined by ASTM D4318-95.
Minimum R value of 50. Use all suitable existing native backfill material before importing backfill material.
See following maps and photos this scope of work.
THERE ARE UNDERGROUND UTILITIES RUNNING PERPENDICULAR TO THE
FIRE MAIN THAT WILL NEED TO BE IDENTIFIED BEFORE EXCAVATION.
CONTRACTOR SHALL COORDINATE ALL UTILITY LOCATES.
Part 2: Contractor Tasks & Supplies
The contractor will conduct the following:
• Identify underground utilities that run across the construction site so they are not struck by bucket while excavating to water main.
• Ensure construction area is blocked from visitors and employees by 4 foot tall temporary fencing.
• Removed existing asphalt over pipe (approx. 155-sf).
• Remove section of concrete sidewalk measuring approximately 6-f tx 54-ft wide.
• Remove small side section of concrete sidewalk measuring approximately 5.5-ft x 4-ft wide.
• Excavate down to pipe to locate leak.
• Remove any thrust blocks that might be in place to conduct repair.
• Replace 100-ft of 8-inch fire main with HDPE Polyethylene.
• Restore and conduct Pressure Verification Test water flow to ensure leak is repaired.
• Replace any thrust blocks that may have been removed for leak repair.
• Backfill excavated area and compact.
• Remove any excess native spoils and dispose legally, offsite.
• Replace removed asphalt with cold mix asphalt patch and sealant where appropriate.
• Replace removed concrete sidewalk with non-tinted concrete to match existing.
• Finish concrete with broom finish that matches the original sidewalk.
• A permit from the local jurisdiction is required for this work and must be submitted after award and before preconstruction meeting for issuance of the notice to proceed for onsite work.
• A National Park Service archeologist will be required to be on site to examine excavated earth while any excavation occurs.
• Contractor shall partner with park maintenance division and archeologist during excavation activities.
• Archeologist will be provided by the park at no expense to the contractor.
Prime Contractor is responsible for directly superintending the project, onsite, all days in which work is being done. Subcontractors will not be permitted to work without direct Prime oversight.
Part 3: Contractor Use of Premises The Contractor Shall always adhere to the following while working within Joshua Tree National Park.
i. The Contractor shall be identifiable with uniforms, name tags, marked vehicles, high-visibility vests, hats, or hardhats with company logo, or similar, and maintain a professional decorum and appearance.
ii. Do not drive vehicles off road or access non-project areas without permission from the contracting officer’s representative.
iii. Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.
iv. Working hours shall be 06:00-17:30 Monday through Friday, excluding Government holidays. Work outside regular hours requires approval from the contracting officer’s representative. Requests for work outside of regular hours must be submitted not-less-than two working days in advance.
v. NPS personnel will unlock and lock the building before and after contractor work times, daily.
vi. Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings, buildings under construction, and buildings under renovation. Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.
vii. Confine storage of equipment and materials to the staging / lay-down/ storage areas identified by the COR or as established at the preconstruction meeting.
viii. The contractor shall park vehicles and heavy equipment in designated areas for contractor use or as established at the preconstruction meeting.
ix. The Contractor shall keep driveways and entrances serving the premises clear and available to the Government, government employees, tenants, the public, and emergency vehicles always.
x. Prevent damage to natural surroundings. Restore damaged areas and replace damaged vegetation and landscape items, at no expense to the Government.
Part 5: Period of Performance
Project shall be completed, with closed out permits (submittal item), within 60 days after
NTP.
After contract award, Notice to Proceed #1 will be issued for administrative submittals.
The contractor will have 10 business days to submit the following, to schedule a preconstruction meeting:
- Certificate of Liability Insurance
- Payment Bond
- Accident & Safety Plan
- Local Jurisdiction Permit
- Project Schedule
- SF-1413 Subcontractor Form
- Letter Designating PRIME Superintendent
- Schedule of Values (to match Bid Schedule)
It is expected that immediately following the preconstruction meeting, Notice to Proceed
#2 will be issued to mobilize, begin on site work and begin the period of performance.
Part 6: Compliance
a. While performing work, the Contractor shall comply with all laws, regulations, and policies, to include, but not be limited to, the latest applicable versions of applicable federal, state and local codes.
i. Licensure: All work shall be performed by workers who hold appropriate licenses in one of the 50 States, the District of Columbia, Puerto Rico, or other
US territory. Where allowed by the state issuing the license, work may be conducted by unlicensed workers provided the work is overseen by a licensed worker. The Prime or Subcontractor must be a State licensed General or
Plumbing Contractor.
ii. All affected areas must be left in a clean and tidy condition. Any damages to
Government property will be fixed and repaired at no cost to the Government.
iii. All new equipment, supplies, and products must conform to the manufacturer’s instructions and guidelines.
iv. Contractor shall provide one-year labor warranty.
v. Contractor shall respond to warranty service calls within 3 calendar days.
5. ASBESTOS AND HAZARDOUS MATERIALS
a. A survey of asbestos containing materials (ACM) is not available for this area. There are no known ACMs present.
b. The Contractor shall conduct all work that impacts asbestos or hazardous materials, including lead-based or lead-containing paint and animal droppings or carcasses according to applicable laws, regulations, and policies, and by adhering to industry best practices.
c. Impacts to known asbestos containing material, known hazardous materials, or materials reasonably expected to contain hazardous materials or animal waste shall be conducted at no additional cost to the Government.
d. Asbestos or hazardous materials not reasonably expected to be encountered shall be treated as a differing site condition.
Joshua Tree National Park Fire Main Location
7 mi
N
N Image © 2025 Airbus
Image © 2025 Airbus
Joshua Tree National Park Fire Main Location
200 ft
N
N Image © 2025 Airbus
File details come from the government source that posted it. Updated .