B08_Attachment_8_Performance_Work_Statement.docx
DOCX document 41 KB Posted
- Attached to
- REPAIR OF WATER LEAK OF BURROWS POND
- Solicitation number
- 140G0125Q0029
About this file
This Performance Work Statement (PWS) outlines requirements for repairing a leaking underground water supply line at the USGS Conte Anadromous Fish Lab facility in Turners Falls, MA. The work involves excavation and repair of a leak in a 12" PVC pipe system that supplies water to concrete burrows ponds used for fisheries research. The leak is located at a 12"x6" reducer fitting and 6" butterfly valve connection, approximately 9-10 feet below grade.
The contract will be structured as both time-and-materials and firm-fixed price, with an 86-day period of performance. Key requirements include asphalt removal, excavation, leak testing, repairs, backfilling, and surface restoration. The contractor must be licensed in Massachusetts, provide a safety plan, and work during normal business hours (M-F, 7:00 am - 4:00 pm). A site visit is scheduled for February 12, 2025, with quotes due February 21, 2025. This is a 100% Small Business Set-Aside under NAICS 238910 with a $19.0 million size standard, with anticipated award date of March 3, 2025. The contract will be administered by the Department of Interior US Geological Survey Office of Acquisitions and Grants.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement Repair Burrows Ponds Process Water Supply Leak S.O. Conte Research Laboratory
1. Introduction: The Conte Lab has a requirement to repair a leaking underground supply water line for a burrows pond at the Conte Anadromous Fish Lab facility located at One Migratory Way, Turners Falls, MA 01376.
2. Background: The Conte Lab has a series of 3-8’ deep concrete burrows ponds for fisheries holding and experimentation, referred to as the “upper burrows ponds”. They are supplied by gravity fed water piping originating at the nearby power canal. Each pond has two 6” PVC supply lines, located at opposite corners. The main supply line is a 12” PVC pipe, there are 5-12”x6” tees with 6” butterfly valves and, at the end of the supply pipe, one 12”x6” reducer, then a 6” 90 and a 6” butterfly valve. It has been determined that a significant water leak is present at this last fitting and valve connection.
3. Scope of Work: This project involves excavation and repair of the leak, backfilling and compacting the excavation and resurfacing the area. The scope of the repair is impossible to determine until the area is uncovered.
Because the extent of the repairs cannot be reasonable estimated the Government anticipates a portion of this contract will be a time-and-materials and a firm-fixed price contract will be awarded for this work. Vendors must specify in their quotes fixed hourly rates that include wages, overhead, general and administrative expenses, and profit for each labor category proposed.
Applicable Documents: All persons performing excavation work will be licensed in the state of Massachusetts. Bidder must show proof of capability to complete project to be considered for contract award. Contractor must furnish a written safety plan in bid detailing the use of trench box or shoring, fall restraints, and PPE to minimize the possibility of injury to workers.
4. Technical Requirements:
· Mobilize to site.
· Determine boundaries of excavation, install barriers.
· Saw cut and remove asphalt, remove from site for recycling.
· Excavate around valve and fitting to a depth of approximately 9-10’ below grade.
· Perform leak test, determine location and extent of repair.
· Complete all repairs, test for leaks.
· Backfill using material from excavation if suitable, provide new material as needed. Backfill in 12” lifts and compact by mechanical means between lifts.
· Patch asphalt pavement with hot mix asphalt (HMA). If HMA is out of season and not available locally the excavated area shall be backfilled to grade of existing asphalt and paved when material becomes available.
· Provide construction fencing preventing access to excavation and install whenever site is unattended.
· If the scope of the repair is determined to be beyond a routine repair and involve extensive structural repairs or large-scale replacement of piping or components, or project is delayed for any other reasons such as availability of parts, weather related delays or any other unforeseen circumstances the contractor shall provide steel plates to cover excavated area.
· Demobilize from site, remove all equipment and construction debris, barriers and signage.
5. Deliverables: Contractor will furnish details on technical approach as part of bid package to include equipment needed for project, methodology of work and any other relevant details.
All work will be inspected and approved by the COR before the task is considered completed. Contractor will repair any deficiencies in materials provided or workmanship at their cost. The contractor will provide verbal progress reports to the COR or other representative authorized by Contracting Officer at regular intervals during the period of performance. Any delays or cost overruns will be communicated to the COR as soon as they are encountered. The customer reserves the right to have the project inspected for integrity and quality of workmanship by a third-party including county building inspector.
The project will be considered completed and authorized for payment only when approved by the COR.
All material and equipment are to be provided by the contractor. No tools, equipment or manpower will be provided by the facility. No government employees will assist contractor with unloading, installation or positioning of materials or equipment. Equipment may be stored in gated area surrounding job site during the period of performance, but the facility assumes no liability against loss or theft.
The contractor will complete the project within the period of performance (POP), any delays must be authorized in writing by the CO. Work may be stopped to avoid interfering with research projects. The work will be staged to allow access to the facility throughout the period of performance. Proper signage and barriers will be provided to restrict vehicle and pedestrian access to work areas and no hazardous conditions should be present in unguarded areas. All work must be performed during normal business hours, Monday-Friday 7:00 am to 4:00 pm. No weekend work may be performed unless authorized by COR. No work may be performed on Federal holidays without exception.
6. General Performance and Requirements:
· The contractor shall make efforts to protect existing structures.
· Contractor shall be responsible for the repair and replacement of damaged buried utility systems or components, or above ground structures resulting from the demolition or installation of items under this contract. Materials and methods shall match existing.
· The contractor shall ensure all roads, dikes, pond banks, and paths are restored to original configuration and elevation prior to work completion.
7. Supporting Information:
a. Place of Performance: Conte Anadromous Fish Lab facility located at One Migratory Way, Turners Falls, MA 01376.
b. Period of Performance: 86 days
c. Government Furnished Property (GFP): None
d. Special Considerations:
i. Any changes affecting the scope of work shall be originated from and approved by the contracting officer.
ii. Contractor is responsible for visiting the worksite to verify measurements and to ascertain the nature and location of the work to be performed, and the general and local conditions which can affect the work or cost thereof. Failure to do so will not relieve the contractor of his responsibility for estimating properly the difficulty or cost of successfully performing the work.
iii. The Contracting Officer’s Technical Representative reserves the right to stop all work under this order if established OSHA safety procedures are not followed to any equipment is deemed unsafe to use.