This document appears to be a pricing schedule for a federal contract opportunity for fencing work. The contract opportunity is for the Bureau of Land Management to convert existing barbed wire fencing to wildlife-friendly fencing along the Blue Rim and Pine Grove areas in Sublette County, Wyoming.

The pricing schedule provides unit costs and estimated quantities for various fencing components, including 4-wire drop fence with wood line posts, 3-wire drop fence, end panels, stress panels, wildlife gates, and fence removal. The total estimated cost for the Blue Rim and Pine Grove fencing work is provided. The federal contract opportunity solicitation number is 140L0624R0057, and the estimated work is approximately 9.6 miles of fencing. The Department of the Interior Bureau of Land Management is the contracting agency for this requirement.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For the best experience, open this PDF portfolio in

Acrobat X or Adobe Reader X, or later.

Get Adobe Reader Now!

http://www.adobe.com/go/reader

UNITED STATES DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

SCHEDULE OF ITEMS

Blue Rim Fence N. and S. of HWY 351

Description N. of HWY 351 Unit Quantity Price Cost Amount

LF 14754.00

EA 11.00

End Panels EA 2.00

EA 2.00

LF 14520.00

Xgate Wildlife Gate EA 6.00

EA 1.00

Description S. of HWY 351 Unit Quantity Price Cost Amount 3 Wire drop fence with wood line posts LF 14771.00

EA 19.00

End Panels EA 1.00

EA 2.00

LF 14256.00

Xgate Wildlife Gate EA 14.00

EA 1.00

TOTAL CONTRACT COST:

Fence Removal

Wire Gates

Fence Removal

Wire Gates

4 Wire drop fence with wood line posts Stress Panels (H Brace)

3 post corner

Stress Panels (H Brace)

3 post corner

1 01505 (1) Mobilization/Demobilization 1 LS $ $

2 02825 (1) DRILL STEM Top Rail, Three Wire Fence 20,446 LF $ $

6 02825 (2) Three Post Corners 56 EA $ $

7 02825 (3) Lateral Support Brace 40 EA $ $

3 02825 (4) 16' Pipe Gates 7 EA $ $

4 02827 (1) Fence Removal (Wood Post Top Rail & Wire) 23,706 LF $ $

5 02827 (2) Fence Removal (Buck & Rail) 212 LF $ $

8 02881 (1) 12' Cattle Guard 1 EA $ $

$ TOTAL OF ITEMS, All or None

BID SCHEDULE

Pine Grove Exclosure Fencing

Item No.

Bid Item Number Description Estimated

Quantity Unit Unit Cost Total Cost