This document is a Schedule of Items for the Blue Rim and Pine Grove Fencing construction project under Solicitation Number 140L0624R0057 issued by the Department of the Interior Bureau of Land Management National Office.
The project involves converting approximately 5.6 miles of existing barbed wire fence to a wildlife-friendly fence north and south of Highway 351, as well as removing and constructing 4 miles of 3-wire fencing for three separate exclosures at the Pine Grove location. The Schedule of Items lists the detailed line items and quantities for the fencing work, including fence removal, wire gates, stress panels, and a 12' cattle guard. Pricing is provided for each line item. The total contract cost is not specified. The solicitation is for a Civilian agency requirement located in Sublette County, Wyoming.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For the best experience, open this PDF portfolio in
Acrobat X or Adobe Reader X, or later.
Get Adobe Reader Now!
http://www.adobe.com/go/reader
UNITED STATES DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
SCHEDULE OF ITEMS
Blue Rim Fence N. and S. of HWY 351
Description N. of HWY 351 Unit Quantity Price Cost Amount
LF 14754.00
LF 14520.00
EA 9.00
EA 3.00
End panel EA 2.00 Drainage Crossing EA 1.00 Xgate Wildlife Gate includes 2 H-braces EA 15.00
EA 1.00
Description S. of HWY 351 Unit Quantity Price Cost Amount 3 Wire drop fence with wood line posts LF 14771.00
LF 14256.00
EA 3.00
EA 13.00
Xgate Wildlife Gate includes 2 H-braces EA 11.00
EA 1.00
TOTAL CONTRACT COST:
Fence Removal
Wire Gates
Fence Removal
Wire Gates
4 Wire drop fence with wood line posts
Stress Panels (H Brace) 3 post corner
Stress Panels (H Brace) 3 post corner
1 01505 (1) Mobilization/Demobilization 1 LS $ $
2 02825 (1) DRILL STEM Top Rail, Three Wire Fence 20,446 LF $ $
6 02825 (2) Three Post Corners 56 EA $ $
7 02825 (3) Lateral Support Brace 40 EA $ $
3 02825 (4) 16' Pipe Gates 7 EA $ $
4 02827 (1) Fence Removal (Wood Post Top Rail & Wire) 23,706 LF $ $
5 02827 (2) Fence Removal (Buck & Rail) 212 LF $ $
8 02881 (1) 12' Cattle Guard 1 EA $ $
$ TOTAL OF ITEMS, All or None
BID SCHEDULE
Pine Grove Exclosure Fencing
Item No.
Bid Item Number Description Estimated
Quantity Unit Unit Cost Total Cost