B08_Attachment_5_-_140P1525Q0156_Price_Schedule.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
ORPI RADIO TOWER INSTALLALLATION Federal contract opportunity
Solicitation number
140P1525Q0156
Issued by
Department of the Interior National Park Service Intermountain Region

About this file

This document is a Price Schedule attachment for a National Park Service project at Organ Pipe Cactus National Monument (ORPI). The solicitation (140P1525Q0156) is a Total Small Business Set-Aside for installing a 30' communications tower, with four primary line items: site preparation, foundation preparation, tower installation, and equipment mobilization/demobilization. Each line item is priced as a lump-sum contract, covering activities such as geotechnical surveys, soil testing, excavation, concrete work, tower assembly, grounding equipment installation, and site rehabilitation.

Key project details include a site visit scheduled for July 29, 2025, at 10:00am Arizona Time at the ORPI Visitor Center, with questions due electronically within three calendar days after the site visit. The project requires payment bonds for awards over $35,000, which must be submitted within ten days of award. The solicitation is issued by the Department of the Interior National Park Service Intermountain Region, focusing on comprehensive radio tower installation services with specific technical and logistical requirements.

View the file

Other files for this federal contract opportunity

Other files attached to ORPI RADIO TOWER INSTALLALLATION, newest first.
File Type Posted
Sol_140P1525Q0156_Amd_0001.pdf PDF
Sol_140P1525Q0156.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price List

Attachment 5, 140P1525Q0156 Price List
Organ Pipe Cactus National Monument (ORPI) Radio Tower Installation
National Park Service (NPS)
Contractor:(fill in orange blocks only)
UEI:
Date:
Point of Contact:
Email:
Line ItemNameDescriptionPrice
10Site PrepartionThis item includes payment for all activities associated with establishing a suitable site for tower installation. Item includes geotechnical survey, soil testing, soil resistivity testing, utility locates, vegetation removal and brush clearing. Payment will be made at contract lump-sum price.$ - 0
20Foundation PrepartionThis item includes payment for all activities associated with establishing a suitable foundation for tower installation. Item includes excavation & backfill, compaction testing, reinforcing and formwork, pouring of concrete pier and pad, rebar inspection and concrete testing. Payment will be made at contract lump-sum price.$ - 0
30Tower InstallationThis item includes payment for all activities associated with safely assembling tower to include, scaffolding, cranes, tower anchoring, erection and the installation of appropriate grounding equipment. Payment will be made at contract lump-sum price.$ - 0
40Equipment, Mobilization & DemobilizationThis item includes payment for equipment, costs to mobilize work crews to site, post-construction work to rehabilitate and clean up the site, containment methods to collect debris, the lawful disposal of generated waste materials, and demobilization activities. Payment will be made at contract lump-sum price.$ - 0
TOTAL$ - 0

File details come from the government source that posted it. Updated .