This is a set of fire protection construction drawings for the Eisenhower National Historic Site, dated March 3, 2022, prepared by the U.S. Department of the Interior, Northeast Regional Office. The drawings provide comprehensive technical specifications for installing dry pipe sprinkler suppression systems to replace existing fire protection equipment at Farm 1 Barn and Farm 2 Show Barn at the historic site. The scope includes detailed plans, sections, details, and equipment schedules for two separate dry sprinkler systems with nitrogen generators serving approximately 263 gallons (Farm 1) and 424 gallons (Farm 2) of system volume. Both systems utilize quick-response sprinkler heads in various configurations (upright, pendent, and horizontal sidewall types) at specified 5.6 K-factor ratings and temperature ratings of 155°F and 200°F, with a combined total of 244 sprinkler heads across both buildings.
The technical drawings (Sheets F2-F9) include lower-level floor plans, upper-level demolition plans, building sections, details, site plans, staging plans, and system riser diagrams. Key equipment specifications indicate use of existing 6-inch water services with backflow preventers, Viking brand dry valve assemblies for Farm 1, and Tyco nitrogen generators for both locations. The drawings establish detailed hydraulic calculations showing design densities of 0.12 and 0.13 gallons per minute per square foot for light hazard occupancies, with system safety factors of 6.5 PSI. Installation requirements mandate compliance with NFPA 13 standards, coordination with the contracting officer prior to pipe installation, appropriate drain placement for complete system drainage, and intermediate temperature-rated sprinkler heads in mechanical and electrical spaces. Contractor staging areas are defined on aerial photographs, and detailed construction specifications address penetrations, hangers, connections, and testing protocols.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site_Visit_Sign_In-EISE_Fire_Suppression_Repairs_0002.pdf | ||
| B08_Attachment_7_-_140P4226Q0005_Project_Experience_0002.docx | DOCX document | |
| Sol_140P4226Q0005_Amd_0002.pdf | ||
| Sol_140P4226Q0005_Amd_0001.pdf | ||
| Sol_140P4226Q0005.pdf | ||
| B08_Attachment_1_-_EISE_Barns_Fire_Suppression_Repairs_SOW_V_2.pdf | ||
| B08_Attachment_6_-_Q_A_Document.xlsx | XLSX spreadsheet | |
| B03_Attachment_4_-_WD_PA20260073.pdf | ||
| B08_Attachment_2_-_Specifications_Reference_Only.pdf | ||
| B08_Attachment_5_-_Subcontracting_Percentage_Worksheet.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
O
A
D
P
U
M
P
I
N
G
R
O
B
E
R
T
A
F
A
M
A
D
E
I
S
E
N
H
O
W
E
R
BUS
M
A
R
S
H
C
R
E
E
K
FARM #2
W
I
L
L
O
U
G
H
B
Y
FARM #4
S
T
A
T
I
N
A
D
S
C
O
T
T
R
O
A
D
R
O
C
K
FARM
#1
R
E
D
R
O
A
D
R
U
N
W
A
Y
E
I
S
E
N
H
O
W
E
D
I
V
E
R
I
D
G
E
W
E
S
T
C
N
F
E
D
E
R
A
T
E
A
V
E
E
M
M
I
T
S
B
U
G
A
D
FARM #3
P
I
L
Z
E
S
U
N
T
A
V
E
A
D
VISITOR CENTER
HEADQUARTERS &
GETTYSBURG N.M.P.
M
I
L
L
E
R
S
T
O
W
N
R
O
A
D
BUS
TO
V.C.
LEGEND
HQ.
GETTYSBURG N.M.P.
INFORMATION CENTER
PARK HEADQUARTERS
VISITOR CENTER
RANGER STATION
CREEK OR RIVER
UNPAVED ROAD
PARK BOUNDARY
STATE LINE
HQ.
SCALE OF
MILES
10 0 10
PENNSYLVANIA
V
I
R
G
I
N
I
A
W
E
S
T
P
E
N
N
S
Y
L
V
A
N
I
A
MARYLAND
PENNSYLVANIA
M
O
N
O
C
A
C
Y
I
V
E
R
CHESAPEAKE
BALTIMORE
FREDERICK
P
O
T
O
M
A
C
V
I
R
G
I
N
I
A
70S
R
I
V
E
R
M
A
R
Y
L
A
N
D
70N
BAY
MARYLAND
PENNSYLVANIA
YORK
HARRISBURG
SITE
HISTORIC
NATIONAL
EISENHOWER
HAGERSTOWN
T
U
R
N
P
I
K
E
GETTYSBURG
EISENHOWER NATIONAL HISTORIC SITE
B
A
R
N
HOUSE
L
O
A
F
I
N
G
S
H
E
D
HOUSE
C
R
I
B
C
O
R
N
B
A
R
N
PROJECT SITE
FARM 1 BARN
PROJECT SITE
FARM 2
SHOW BARN
M S N
D R A W I N G S F I R E
P R O T E C T I O N F
F I R E
P R O T E C T I O N
C O V E R
S H E E T D W G
P M
PROJECT SITE
FARM 1 BARN
PROJECT SITE
FARM 2
SHOW BARN
3/3/2022
AC - AIR COMPRESSOR
ACC - ACCESS
ACV - ALARM CHECK VALVE
ADJ - ADJUSTABLE
AFF - ABOVE FINISHED FLOOR
ALT - ALTERNATE
AHJ - AUTHORITY HAVING
JURISDICTION
AP - ACCESS PANEL
APPROX - APPROXIMATE
ARCH - ARCHITECTURAL
ASSY - ASSEMBLY
ATS - AUTOMATIC TRANSFER SWITCH
BLDG - BUILDING
BOP - BOTTOM OF PIPE
BOT - BOTTOM
BTWN - BETWEEN
CFCI - CONTRACTOR FURNISHED
CONTRACTOR INSTALLED
CL - CENTERLINE
CLG - CEILING
CONN - CONNECTION / CONNECT
CONTR - CONTRACTOR
CORR - CORRIDOR
CU - COPPER
D - DRAIN LINE
DCBP - DOUBLE CHECK
BACKFLOW PREVENTER
DDBP - DOUBLE DETECTOR
BACKFLOW PREVENTER
DET - DETAIL
DIA - DIAMETER
DIM - DIMENSION
DN - DOWN
DSPR - DRY SPRINKLER PIPE
DWG - DRAWING
EA - EACH
ELEV - ELEVATION
EQUIP - EQUIPMENT
ETR - EXISTING TO REMAIN
EXT - EXTERIOR
F - FIRE SUPPLY
FACP - FIRE ALARM CONTROL PANEL
FDC - FIRE DEPARTMENT CONNECTION
FDV - FIRE DEPARTMENT VALVE
FHC - FIRE HOSE CABINET
FHR - FIRE HOSE RACK
FLR - FLOOR
FMG - FACTORY MUTUAL GLOBAL
FPC - FIRE PUMP CONTROLLER
FPTH - FIRE PUMP TEST HEADER
FS - FLOW SWITCH
FT - FEET
FTG - FOOTING
FVC - FIRE VALVE CABINET
GA - GAUGE
GAL - GALLON
GALV - GALVANIZED
GPM - GALLONS PER MINUTE
HD - HUB DRAIN
IBC - INTERNATIONAL BUILDING CODE
ID - INSIDE DIAMETER
IE - INVERT ELEVATION
IFC - INTERNATIONAL FIRE CODE
IN - INCHES
JP - JOCKEY PUMP
JPC - JOCKEY PUMP CONTROLLER
L - LENGTH
LBS - POUNDS
MAX - MAXIMUM
MEZZ - MEZZANINE
MFR - MANUFACTURER
MIN - MINIMUM
MISC - MISCELLANEOUS
MTD - MOUNTED
MTG - MOUNTING
NC - NORMALLY CLOSED
NFPA - NATIONAL FIRE PROTECTION
ASSOCIATION
NO - NORMALLY OPEN
NOM - NOMINAL
NPT - NATIONAL PIPE THREAD
NTS - NOT TO SCALE
OC - ON CENTER
OD - OUTSIDE DIAMETER
OFCI - OWNER FURNISHED
CONTRACTOR INSTALLED
OFOI - OWNER FURNISHED
OWNER INSTALLED
PIV - POST INDICATOR VALVE
PLBG - PLUMBING
PRESS - PRESSURE
PRV - PRESSURE REDUCING VALVE
PSF - POUNDS PER SQUARE FOOT
PSI - POUNDS PER SQUARE INCH
PSIG - POUNDS PER SQUARE INCH
GAUGE
RAD - RADIUS
REC - RECESSED
REQD - REQUIRED
RI - ROUGH-IN
RPM - REVOLUTIONS PER MINUTE
RPBP - REDUCED PRESSURE ZONE
BACKFLOW PREVENTER
RV - RELIEF VALVE
SCH - SCHEDULE
SHT - SHEET
SPEC - SPECIFICATION
SPR - SPRINKLER
SQ - SQUARE
S/S - STAINLESS STEEL
STRU - STRUCTURAL / STRUCTURE
TEMP - TEMPERATURE
TC - TEST CELL
TOB - TOP OF BEAM
TOD - TOP OF DECK
TOJ - TOP OF JOIST
TOS - TOP OF SLAB / TOP OF STEEL
TYP - TYPICAL
UBC - UNIFORM BUILDING CODE
UFC - UNIFORM FIRE CODE
UNO - UNLESS NOTED OTHERWISE
V - VALVE
VEL - VELOCITY
VESDA - VERY EARLY SMOKE
DETECTION APPARATUS
VOL - VOLUME
W - WIDTH
W/ - WITH
W/O - WITHOUT
ABBREVIATIONS
FIRE PROTECTION SYMBOLS AND ABBREVIATIONS
SYMBOLS INDICATED HERE AND NOT USED IN THE CONTRACT DOCUMENTS DO
NOT APPLY TO THIS PROJECT.
FIRE PROTECTION SYMBOLS
SPRINKLER PIPE TEXT
(TOP INDICATES PIPE SIZE)
(BOTTOM INDICATES
CENTER TO CENTER PIPE
LENGTH)
FIRE HOSE CABINET
SPRINKLER ZONE
BOUNDARY
PIPE HANGER
FHC
PIPE SIZE
PIPE LENGTH
PUMP (FLOOR PLAN)
PUMP (FLOW DIAGRAM)
ECCENTRIC REDUCER
CONCENTRIC REDUCER
TEE UP
TEE DOWN
ELBOW UP
ELBOW DOWN
SUPERVISED BUTTERFLY
VALVE
SHUTOFF VALVE (SUPERVISED)
CHECK VALVE
PIPE CAP OR FLUSHING
CONNECTION
PIPE SLEEVE
PRESSURE GAUGE
(WITH GAUGE VALVE)
FLOW SWITCH
FIRE SUPPLYF
DRY SPRINKLER PIPE
DSPR
PREACTION SPRINKLER PIPEPSPR
CLEAN AGENT SYSTEMCA
WATER SERVICEW
VALVE IN VERTICAL
REDUCED PRESSURE
BACKFLOW PREVENTER
(RPBP)
DOUBLE CHECK
BACKFLOW PREVENTER
(DCBP)
SUPERVISED OS&Y VALVE
SUPERVISED POST
INDICATOR VALVE (PIV)
ALARM CHECK VALVE
INSPECTOR'S TEST AND
DRAIN ASSEMBLY
INSPECTOR'S TEST
ASSEMBLY
ROOFTOP TEST HEADER
FIRE DEPARTMENT VALVE
STORZ CONNECTION
FLUSH MOUNTED CONNECTION
WALL MOUNTED
CONNECTION
DRY PIPE VALVE ASSEMBLY
PREACTION VALVE ASSEMBLY
DELUGE VALVE ASSEMBLY
SPRINKLER ZONE CONTROL
VALVE ASSEMBLY
FIRE HOSE RACK
FHR
FIRE VALVE CABINET
FVC
EXISTING VALVE CABINET
EVC
BUTTERFLY VALVE
DRAIN LINED
SPRINKLER PIPESPR
SHEET SYMBOLS
A/15B-6
SPECIALTY ITEMS
(I.E. GAUGE FILTER, ETC.)
REFER TO EQUIPMENT LIST
M-1
ROOM NAME & NUMBER
DESIGNATION
SECTION DESIGNATION.
-TOP INDICATES SECTION NUMBER,
-BOTTOM INDICATES ON WHICH
SHEET SECTION APPEARS
MATCHLINE
DESIGNATION
DETAIL REFERENCE.
-TOP INDICATES SECTION NUMBER,
-BOTTOM INDICATES ON WHICH
SHEET SECTION APPEARS
REVISION REFERENCE.
REFER TO SHEET REVISION
BLOCK
SHEET KEYNOTE REFERENCE
PLAN CONTINUATION REFERENCE.
-BOTTOM INDICATES ON WHICH
SHEET CONTINUATION APPEARS
CONSTRUCTION BULLETIN
REVISION NUMBER
SCHEDULED EQUIPMENT DESIGNATION.
-TOP INDICATES EQUIPMENT
ABBREVIATION
-BOTTOM INDICATES EQUIPMENT
NUMBER
REFER TO EQUIPMENT SCHEDULES
ELEVATION DESIGNATION.
REFERENCE OFFICIAL
PROJECT DATUM
EQ
POINT OF NEW
CONNECTION TO EXISTING
REFER
M-1
M-1
DETAIL REFERENCE.
-TOP INDICATES SECTION NUMBER,
-BOTTOM INDICATES ON WHICH
SHEET SECTION APPEARS
ROOM NAME
HALFTONE LIGHT LINE
INDICATES EXISTING WORK
HEAVY DASHED LINE WITH
HATCH INDICATES
EXISTING WORK TO BE
DEMOLISHED
HEAVY LINE INDICATES
NEW WORK
HYDRAULIC ZONE
BOUNDARY
CLEAN AGENT EXTINGUISHING
SYSTEM
CAES
DELUGE SPRINKLER SYSTEMDELS
HANGER SPACING
STEEL PIPE*
N/A
1"
12-0
12-0
15-0
2"
15-0
15-0
3"
15-0
15-0
4"
15-0
5"
15-0
6"
15-0
8"
15-0
*EXCEPT THREADED LIGHTWALL PIPE
REFER TO DRAWING SPRINKLER HEAD LEGEND FOR TYPE
DRY PENDENT SPRINKLER
SPRINKLER HEAD SYMBOLS
WHITE 5.6 200° F 27
FINISH K-FACTOR TEMP. QTY.SPRINKLER TYPESYMBOL
DRY HORIZONTAL SIDEWALL SPRINKLER WHITE 5.6 155° F 7
QR
RESPONSE
QR
UPRIGHT SPRINKLER WHITE 5.6 200° F 197
QR
WHITE 5.6 155° F 13 QRDRY PENDENT SPRINKLER WITH ESCUTCHEON
TR1
DV1
BR1
BFD
UG
FIRE PROTECTION EQUIPMENT
1 EXISTING 6" WATER SERVICE
BACKFLOW PREVENTER WITH BUTTERFLY VALVES & TAMPER SWITCHES
(N.O.)
FDC BYPASS BUTTERFLY VALVE WITH TAMPER SWITCH (N.C.)
4 FDC CHECK VALVE
5 EXISTING FDC TO REMAIN
EXISTING 6" BUTTERFLY VALVE WITH TAMPER SWITCH (N.O.) TO BE REUSED
7 EXISTING 6" VIKING DRY VALVE ASSEMBLY TO BE REUSED
6" BUTTERFLY VALVE WITH TAMPER SWITCH (N.O.)
4" BUTTERFLY VALVE WITH TAMPER SWITCH (N.O.)
10 4" VIKING DRY VALVE ASSEMBLY
NITROGEN GENERATOR CABINET WITH INTEGRATED COMPRESSOR RATED
FOR 800 GALLON SPRINKLER SYSTEM (ECS PGEN-10 IS BASIS OF DESIGN)
S117
C11
C01
M110
S101S102S103
S105
S106
S107
S113
S108
S123
S114
S115S116
S119S120S121S122
S124
C05
C02
C03
C04
S104
C06
C07
C08
S110S111S112 S109
S118
R125
S126
C09
C10
C12
C13
C14
C15 C16
TR1 DV1 BR1
BFD UG
S125
F2
GENERAL NOTESKEY NOTES
LEGEND
DRY PENDENT SPRINKLER 0
QTY.SPRINKLER TYPESYMBOL
HORIZONTAL SIDEWALL SPRINKLER 7
UPRIGHT SPRINKLER 78
13DRY PENDENT SPRINKLER WITH ESCUTCHEON
1. INSTALLATION OF SPRINKLER SYSTEM SHALL BE IN ACCORDANCE
WITH NFPA 13, INSTALLATION OF SPRINKLER SYSTEMS.
2. CONTRACTOR SHALL NOT INSTALL PIPE PRIOR TO COORDINATION
WITH CONTRACTING OFFICER.
3. SPRINKLERS IN LIGHT HAZARD OCCUPANCIES SHALL BE OF THE
QUICK-RESPONSE TYPE.
4. SPRINKLERS SHALL BE INSTALLED UNDER FIXED OBSTRUCTIONS
OVER 4 FEET WIDE, SUCH AS DUCTS, DECKS, OPEN GRATE FLOORING,
CUTTING TABLES, AND OVERHEAD DOORS.
5. SPRINKLER SYSTEMS SHALL BE INSTALLED WITH THE APPROPRIATE
AMOUNT AND LOCATIONS OF DRAINS TO FACILITATE FULL DRAINING
OF THE SPRINKLER SYSTEM.
6. PROVIDE INTERMEDIATE TEMPERATURE RATED SPRINKLER HEADS IN
ALL MECHANICAL, ELECTRICAL OR SIMILAR BACK OF HOUSE SPACES
WHERE AMBIENT TEMPERATURE ARE HIGHER THAN NORMAL
COMMON SPACE ENVIRONMENTS, UNLESS NOTED OTHERWISE.
7. PROVIDE THE APPROPRIATE HYDRAULIC NAMEPLATES AT THE BASE
OF EACH SYSTEM RISER. NAMEPLATES SHALL INCLUDE LOCATION OF
REMOTE AREA, NUMBER OF SPRINKLERS FLOWING, DESIGN DENSITY,
AND REQUIRED GPM AND PSI AT THE BASE OF EACH SYSTEM RISER
OR CONTROL VALVE ASSEMBLY.
8. NO SERVICE SHALL BE INTERRUPTED WITHOUT WRITTEN PERMISSION
FROM THE CONTRACTING OFFICER.
9. WHERE DEMOLITION WORK INTERFERES WITH OWNER'S USE OF
PREMISES, SCHEDULE WORK THROUGH CONTRACTING OFFICER TO
MINIMIZE INCONVENIENCE TO OWNER. OWNER MUST APPROVE
SCHEDULE BEFORE CONTRACTOR BEGINS ANY SUCH WORK.
10. REMODEL OF SPACE IDENTIFIED ON DRAWINGS REQUIRES THAT
COORDINATION OCCUR BETWEEN FIRE PROTECTION CONTRACTOR
AND OWNER. AT THE END OF EACH WORK DAY, SPRINKLER FITTER
MUST COORDINATE WITH OWNER SO THE FIRE PROTECTION SYSTEM
IS RE-ACTIVATED FOR EACH NIGHT.
11. REFER TO SPECIFICATION 21 1314 - AUTOMATIC FIRE SPRINKLER
SYSTEM FOR ADDITIONAL INFORMATION.
12. FIRE PROTECTION CONTRACTOR SHALL HAVE APPROVED
SPRINKLER SUBMITTAL DRAWINGS FROM ARCHITECT AND ENGINEER
PRIOR TO STARTING INSTALLATION ON THIS PROJECT. ANY WORK
THAT HAS BEEN INSTALLED PRIOR TO RECEIVING THE APPROVALS
MAY BE REMOVED, AT THE CONTRACTORS EXPENSE.
13. AREAS OF WOOD FRAMING SHALL BE CONSIDERED COMBUSTIBLE
OBSTRUCTED IF THE BEAM SPACING IS LESS THAN 15'-0” ON CENTER.
THESE AREAS SHALL BE LIMITED TO 130 SQ/FT MAXIMUM SPACING.
F5
GENERAL NOTES
KEY NOTES
LEGEND
1. INSTALLATION OF SPRINKLER SYSTEM SHALL BE IN ACCORDANCE
WITH NFPA 13, INSTALLATION OF SPRINKLER SYSTEMS.
2. CONTRACTOR SHALL NOT INSTALL PIPE PRIOR TO COORDINATION
WITH CONTRACTING OFFICER.
3. SPRINKLERS IN LIGHT HAZARD OCCUPANCIES SHALL BE OF THE
QUICK-RESPONSE TYPE.
4. SPRINKLERS SHALL BE INSTALLED UNDER FIXED OBSTRUCTIONS
OVER 4 FEET WIDE, SUCH AS DUCTS, DECKS, OPEN GRATE FLOORING,
CUTTING TABLES, AND OVERHEAD DOORS.
5. SPRINKLER SYSTEMS SHALL BE INSTALLED WITH THE APPROPRIATE
AMOUNT AND LOCATIONS OF DRAINS TO FACILITATE FULL DRAINING
OF THE SPRINKLER SYSTEM.
6. PROVIDE INTERMEDIATE TEMPERATURE RATED SPRINKLER HEADS IN
ALL MECHANICAL, ELECTRICAL OR SIMILAR BACK OF HOUSE SPACES
WHERE AMBIENT TEMPERATURE ARE HIGHER THAN NORMAL
COMMON SPACE ENVIRONMENTS, UNLESS NOTED OTHERWISE.
7. PROVIDE THE APPROPRIATE HYDRAULIC NAMEPLATES AT THE BASE
OF EACH SYSTEM RISER. NAMEPLATES SHALL INCLUDE LOCATION OF
REMOTE AREA, NUMBER OF SPRINKLERS FLOWING, DESIGN DENSITY,
AND REQUIRED GPM AND PSI AT THE BASE OF EACH SYSTEM RISER
OR CONTROL VALVE ASSEMBLY.
8. NO SERVICE SHALL BE INTERRUPTED WITHOUT WRITTEN PERMISSION
FROM THE CONTRACTING OFFICER.
9. WHERE DEMOLITION WORK INTERFERES WITH OWNER'S USE OF
PREMISES, SCHEDULE WORK THROUGH CONTRACTING OFFICER TO
MINIMIZE INCONVENIENCE TO OWNER. OWNER MUST APPROVE
SCHEDULE BEFORE CONTRACTOR BEGINS ANY SUCH WORK.
10. REMODEL OF SPACE IDENTIFIED ON DRAWINGS REQUIRES THAT
COORDINATION OCCUR BETWEEN FIRE PROTECTION CONTRACTOR
AND OWNER. AT THE END OF EACH WORK DAY, SPRINKLER FITTER
MUST COORDINATE WITH OWNER SO THE FIRE PROTECTION SYSTEM
IS RE-ACTIVATED FOR EACH NIGHT.
11. REFER TO SPECIFICATION 21 1314 - AUTOMATIC FIRE SPRINKLER
SYSTEM FOR ADDITIONAL INFORMATION.
12. FIRE PROTECTION CONTRACTOR SHALL HAVE APPROVED
SPRINKLER SUBMITTAL DRAWINGS FROM ARCHITECT AND ENGINEER
PRIOR TO STARTING INSTALLATION ON THIS PROJECT. ANY WORK
THAT HAS BEEN INSTALLED PRIOR TO RECEIVING THE APPROVALS
MAY BE REMOVED, AT THE CONTRACTORS EXPENSE.
13. AREAS OF WOOD FRAMING SHALL BE CONSIDERED COMBUSTIBLE
OBSTRUCTED IF THE BEAM SPACING IS LESS THAN 15'-0” ON CENTER.
S101
S102
S103
S104
S105
S106
S107
S108
S128
S124
S125
S129
S126
S130
S127
S109
S110
S111
S112
S113
S114
S115
S116
S117
S118
S119
S120
S121
S122
M101
M102
M103
M105
M107 M108
M109
M110 M111 M112
M113
M114
M106
TR1
S202
S201
S204
S203
S206
S205
R208
S207
S210
S209
S212
S211
S214
S213
S216
S215
S218
S217
S220
S219
S222
S223
S224
S225
S226
S227
S228
S229
S230
S231
S232
S234
S235
S236
S237
S221
S238
S239
S240
M201
M202 M203
M204 M205
M206
M207
M208
M209
M210
M213
M214
M215
M216
M217 M218
M115
M116
M117
M219
M211
M222
M220
M212
S208
R229 R226
R223
S123
M104
RA1
A1
RA2
A2
RA3
A3
RA4
A4
RA5
A5
RA6
A6
A7
BFD
UG
RN1 RN2
RN3
RN4
S233
M221
X1
X2
S241
R241
F5
F5
F5
F4
DV1
FIRE PROTECTION EQUIPMENT
1 EXISTING 6" WATER SERVICE
BACKFLOW PREVENTER WITH BUTTERFLY VALVES & TAMPER SWITCHES
(N.O.)
FDC BYPASS BUTTERFLY VALVE WITH TAMPER SWITCH (N.C.)
4 FDC CHECK VALVE
5 EXISTING FDC TO REMAIN
6 EXISTING 6" VIKING DRY VALVE ASSEMBLY TO BE REUSED
SKID-MOUNTED NITROGEN GENERATOR WITH INTEGRATED COMPRESSOR
(TYCO NG-1 1000 IS BASIS OF DESIGN)
BFD
UG
TR1
DRY PENDENT SPRINKLER 26
QTY.SPRINKLER TYPESYMBOL
HORIZONTAL SIDEWALL SPRINKLER 0
UPRIGHT SPRINKLER 119
0DRY PENDENT SPRINKLER WITH ESCUTCHEON
1. INSTALLATION OF SPRINKLER SYSTEM SHALL BE IN ACCORDANCE
WITH NFPA 13, INSTALLATION OF SPRINKLER SYSTEMS.
2. CONTRACTOR SHALL NOT INSTALL PIPE PRIOR TO COORDINATION
WITH CONTRACTING OFFICER.
3. SPRINKLERS IN LIGHT HAZARD OCCUPANCIES SHALL BE OF THE
QUICK-RESPONSE TYPE.
4. SPRINKLERS SHALL BE INSTALLED UNDER FIXED OBSTRUCTIONS
OVER 4 FEET WIDE, SUCH AS DUCTS, DECKS, OPEN GRATE FLOORING,
CUTTING TABLES, AND OVERHEAD DOORS.
5. SPRINKLER SYSTEMS SHALL BE INSTALLED WITH THE APPROPRIATE
AMOUNT AND LOCATIONS OF DRAINS TO FACILITATE FULL DRAINING
OF THE SPRINKLER SYSTEM.
6. PROVIDE INTERMEDIATE TEMPERATURE RATED SPRINKLER HEADS IN
ALL MECHANICAL, ELECTRICAL OR SIMILAR BACK OF HOUSE SPACES
WHERE AMBIENT TEMPERATURE ARE HIGHER THAN NORMAL
COMMON SPACE ENVIRONMENTS, UNLESS NOTED OTHERWISE.
7. PROVIDE THE APPROPRIATE HYDRAULIC NAMEPLATES AT THE BASE
OF EACH SYSTEM RISER. NAMEPLATES SHALL INCLUDE LOCATION OF
REMOTE AREA, NUMBER OF SPRINKLERS FLOWING, DESIGN DENSITY,
AND REQUIRED GPM AND PSI AT THE BASE OF EACH SYSTEM RISER
OR CONTROL VALVE ASSEMBLY.
8. NO SERVICE SHALL BE INTERRUPTED WITHOUT WRITTEN PERMISSION
FROM THE CONTRACTING OFFICER.
9. WHERE DEMOLITION WORK INTERFERES WITH OWNER'S USE OF
PREMISES, SCHEDULE WORK THROUGH CONTRACTING OFFICER TO
MINIMIZE INCONVENIENCE TO OWNER. OWNER MUST APPROVE
SCHEDULE BEFORE CONTRACTOR BEGINS ANY SUCH WORK.
10. REMODEL OF SPACE IDENTIFIED ON DRAWINGS REQUIRES THAT
COORDINATION OCCUR BETWEEN FIRE PROTECTION CONTRACTOR
AND OWNER. AT THE END OF EACH WORK DAY, SPRINKLER FITTER
MUST COORDINATE WITH OWNER SO THE FIRE PROTECTION SYSTEM
IS RE-ACTIVATED FOR EACH NIGHT.
11. REFER TO SPECIFICATION 21 1314 - AUTOMATIC FIRE SPRINKLER
SYSTEM FOR ADDITIONAL INFORMATION.
12. FIRE PROTECTION CONTRACTOR SHALL HAVE APPROVED
SPRINKLER SUBMITTAL DRAWINGS FROM ARCHITECT AND ENGINEER
PRIOR TO STARTING INSTALLATION ON THIS PROJECT. ANY WORK
THAT HAS BEEN INSTALLED PRIOR TO RECEIVING THE APPROVALS
MAY BE REMOVED, AT THE CONTRACTORS EXPENSE.
13. AREAS OF WOOD FRAMING SHALL BE CONSIDERED COMBUSTIBLE
OBSTRUCTED IF THE BEAM SPACING IS LESS THAN 15'-0” ON CENTER.
SCALE:
SCALE:
NOT TO SCALE
FIRE DEPARTMENT CONNECTION W/ FULL FLOW BYPASS
SCALE:
NOT TO SCALE
EXTERIOR WALL PENETRATION - BELOW GRADE
SCALE:
NOT TO SCALE
EXTERIOR WALL PENETRATION - ABOVE GRADE
SCALE:
NOT TO SCALE
PIPE THROUGH INTERIOR WALL
SCALE:
NOT TO SCALE
DRY PIPE VALVE ASSEMBLY
SCALE:
NOT TO SCALE
EXTERIOR DRAIN THROUGH WALL
SCALE:
SCALE:
NOT TO SCALE
SIDE SCREW PIPE HANGER
SCALE:
NOT TO SCALE
VERTICAL SCREW PIPE HANGER
PIPE
WATERSTOP SLEEVE
SEAL PENETRATION
AT EACH SIDE
PIPE
WATERSTOP SLEEVE
SEAL PENETRATION
AT EACH SIDE
CHROME SPLIT WALL PLATE
GWB CEILING
WOOD JOIST
LISTED WOOD SCREW
ALL THREAD ROD
HANGER RING
WOOD JOIST
LISTED WOOD SCREW
ALL THREAD ROD
HANGER RING
F I R
E
M
A I N
WATER SOURCE
SUPERVISED OS&Y
SHUTOFF VALVES
NOT TO SCALE
DOUBLE CHECK BACKFLOW PREVENTER
THREADED ROD
FOR TWO HOLE
NOTES:
1. PRESSURE REDUCING BACKFLOW IS ONLY LISTED FOR
INSTALLATION IN THE HORIZONTAL POSITION.
2. COORDINATE LOCATION WITH PLUMBING CONTRACTOR.
FOR PLUMBERS
FROM FIRE
PROTECTION
SYSTEM
REFER TO ARCHITECTURAL
DRAWINGS FOR FLOOR TYPE
AND DIMENSIONS
BYPASS FOR FORWARD FLOW
TEST OF BACKFLOW PREVENTER
CHECK VALVE
TO FIRE DEPARTMENT
CONNECTION
ROUTE BALL DRIP TO
DISCHARGE TO EXTERIOR.
SUPERVISED SHUTOFF
VALVE W/ TAMPER,
NORMALLY CLOSED
PROVIDE SUPPORT AS
REQUIRED
BUILDING
SPACE
BELOW
GRADE
THUNDERLINE CORPORATION. USE 316 SS NUTS AND BOLTS.
"LINK-SEAL" MODULAR WALL AND CASING SEAL BY(1)
NOTES:
(2)
(3)
BETWEEN PIPE AND OPENING WITHOUT SLEEVE. SIZE OPENING
FOR CORE DRILLED HOLE, INSTALL "LINK-SEAL" SEAL
AS RECOMMENDED BY SEAL MANUFACTURER.
FOR LINED PIPE, EXTEND LINING TO SEAL AT BOTH
SIDES.
BUILDING
SPACE
ABOVE
GRADE
NOTE:
REFER TO SPECIFICATION FOR ADDITIONAL INFORMATION.
BACKING MATERIAL
SEALANT
PIPE
REFER TO ARCHITECTURAL
DRAWINGS FOR WALL TYPE
AND DIMENSIONS
NOTE:
1. WHERE WALL IS FIRE RATED, PROVIDE A LISTED PENETRATION ASSEMBLY.
2. PROVIDE PLASTIC WALL PLATES OVER PENETRATIONS WHEN EXPOSED TO
VIEW.
F I R
E
M
A I N
DRY PIPE SPRINKLER
SYSTEM VALVE
ASSEMBLY
UL 2125 LISTED,
FLOOR MOUNTED
AIR COMPRESSOR
REFER TO
ARCHITECTURAL
DRAWINGS FOR WALL
AND FLOOR TYPE AND
DIMENSIONS
SUPERVISED SHUTOFF
VALVE W/ TAMPER
SWITCH
AIR MAINTENANCE
DEVICE
SUPERVISED SHUTOFF
VALVE W/ TAMPER
SWITCH TO ISOLATE
SYSTEM DURING
TESTING
HUB DRAIN
(REFER TO PLUMBING
DRAWING FOR
LOCATION)
AUXILIARY DRAIN
PROVIDE SUPPORT AS
REQUIRED
TO DRAIN LOCATION
GALVANIZED
THREADED 45° ELBOW
SEAL PENETRATION
AT EACH SIDE
90° ELBOW
INTERIOR FLOOR
EXTERIOR
DRAIN RISER
CHROME SPLIT WALL PLATE
GALVANIZED PIPE
REFER TO ARCHITECTURAL
DRAWINGS FOR WALL AND FLOOR
TYPES AND DIMENSIONS.
WATERSTOP SLEEVE
LOCATE 18"-36" ABOVE
FINISHED GRADE
SEAL PENETRATION
AT EACH SIDE
PROVIDE SPLASH BLOCK TO
LOCATIONS W/ EXPOSED SOIL
SYSTEM PIPING
VALVE (NORMALLY OPEN)
VALVE (NORMALLY CLOSED)
ROUTE DRAIN TO AN
APPROVED LOCATION
PROVIDE WITH SMALLEST
SPRINKLER HEAD ORIFICE ON
DRY SYSTEM FOR TESTING
WHEN REQUIRED BY NFPA
STANDARDS
2" PIPE
THREADED REDUCER
THREADED REDUCER
NOT TO SCALE
LOW POINT DRAIN
LISTED WOOD SIDE SCREW
ALL THREAD ROD
HANGER RING
WOOD JOIST
EISENHOWER HOME
BARN
RECEPTION CENTER
GUEST HOUSE
FARM 1 BARN CONTRACTOR
STAGING AREA
LIMITS OF FARM 1 BARN
CONSTRUCTION/STAGING AREA
CHAIN LINK CONSTRUCTION
FENCE BY CONTRACTOR
EXTENDED BETWEEN
PERMANENT PARK FENCES
SHOW BARN
LOAFING BARN
SELF FEEDER
MATERNITY BARN
HERDSMAN'S HOME
(PARK HEADQUARTERS)
CHAIN LINK CONSTRUCTION
FENCE BY CONTRACTOR
EXTENDED BETWEEN
PERMANENT PARK FENCES
FARM 2 BARN CONTRACTOR
STAGING AREA
LIMITS OF FARM 2 BARN
CONSTRUCTION/STAGING AREA
0 25 50 100 Feet 0 30 60 120 Feet
BFD
UG
TEST
CONTINUES TO
SHOW BARN
WATER METER
GATE VALVE
GATE VALVE
CONTINUES
TO FARM 3
6" WATER SERVICE
HYDRANT
6" WATER MAIN
6" WATER MAIN
6" WATER MAIN
6" WATER MAIN
GENERAL NOTES
KEY NOTES
LEGEND
1. INSTALLATION OF SPRINKLER SYSTEM SHALL BE IN ACCORDANCE
WITH NFPA 13, INSTALLATION OF SPRINKLER SYSTEMS.
2. CONTRACTOR SHALL NOT INSTALL PIPE PRIOR TO COORDINATION
WITH CONTRACTING OFFICER.
3. SPRINKLERS IN LIGHT HAZARD OCCUPANCIES SHALL BE OF THE
QUICK-RESPONSE TYPE.
4. SPRINKLERS SHALL BE INSTALLED UNDER FIXED OBSTRUCTIONS
OVER 4 FEET WIDE, SUCH AS DUCTS, DECKS, OPEN GRATE FLOORING,
CUTTING TABLES, AND OVERHEAD DOORS.
5. SPRINKLER SYSTEMS SHALL BE INSTALLED WITH THE APPROPRIATE
AMOUNT AND LOCATIONS OF DRAINS TO FACILITATE FULL DRAINING
OF THE SPRINKLER SYSTEM.
6. PROVIDE INTERMEDIATE TEMPERATURE RATED SPRINKLER HEADS IN
ALL MECHANICAL, ELECTRICAL OR SIMILAR BACK OF HOUSE SPACES
WHERE AMBIENT TEMPERATURE ARE HIGHER THAN NORMAL
COMMON SPACE ENVIRONMENTS, UNLESS NOTED OTHERWISE.
7. PROVIDE THE APPROPRIATE HYDRAULIC NAMEPLATES AT THE BASE
OF EACH SYSTEM RISER. NAMEPLATES SHALL INCLUDE LOCATION OF
REMOTE AREA, NUMBER OF SPRINKLERS FLOWING, DESIGN DENSITY,
AND REQUIRED GPM AND PSI AT THE BASE OF EACH SYSTEM RISER
OR CONTROL VALVE ASSEMBLY.
8. NO SERVICE SHALL BE INTERRUPTED WITHOUT WRITTEN PERMISSION
FROM THE CONTRACTING OFFICER.
9. WHERE DEMOLITION WORK INTERFERES WITH OWNER'S USE OF
PREMISES, SCHEDULE WORK THROUGH CONTRACTING OFFICER TO
MINIMIZE INCONVENIENCE TO OWNER. OWNER MUST APPROVE
SCHEDULE BEFORE CONTRACTOR BEGINS ANY SUCH WORK.
10. REMODEL OF SPACE IDENTIFIED ON DRAWINGS REQUIRES THAT
COORDINATION OCCUR BETWEEN FIRE PROTECTION CONTRACTOR
AND OWNER. AT THE END OF EACH WORK DAY, SPRINKLER FITTER
MUST COORDINATE WITH OWNER SO THE FIRE PROTECTION SYSTEM
IS RE-ACTIVATED FOR EACH NIGHT.
11. REFER TO SPECIFICATION 21 1314 - AUTOMATIC FIRE SPRINKLER
SYSTEM FOR ADDITIONAL INFORMATION.
12. FIRE PROTECTION CONTRACTOR SHALL HAVE APPROVED
SPRINKLER SUBMITTAL DRAWINGS FROM ARCHITECT AND ENGINEER
PRIOR TO STARTING INSTALLATION ON THIS PROJECT. ANY WORK
THAT HAS BEEN INSTALLED PRIOR TO RECEIVING THE APPROVALS
MAY BE REMOVED, AT THE CONTRACTORS EXPENSE.
13. AREAS OF WOOD FRAMING SHALL BE CONSIDERED COMBUSTIBLE
OBSTRUCTED IF THE BEAM SPACING IS LESS THAN 15'-0” ON CENTER.
BFD
TEST
UG
1. INSTALLATION OF SPRINKLER SYSTEM SHALL BE IN ACCORDANCE
WITH NFPA 13, INSTALLATION OF SPRINKLER SYSTEMS.
2. CONTRACTOR SHALL NOT INSTALL PIPE PRIOR TO COORDINATION
WITH CONTRACTING OFFICER.
3. SPRINKLERS IN LIGHT HAZARD OCCUPANCIES SHALL BE OF THE
QUICK-RESPONSE TYPE.
4. SPRINKLERS SHALL BE INSTALLED UNDER FIXED OBSTRUCTIONS
OVER 4 FEET WIDE, SUCH AS DUCTS, DECKS, OPEN GRATE FLOORING,
CUTTING TABLES, AND OVERHEAD DOORS.
5. SPRINKLER SYSTEMS SHALL BE INSTALLED WITH THE APPROPRIATE
AMOUNT AND LOCATIONS OF DRAINS TO FACILITATE FULL DRAINING
OF THE SPRINKLER SYSTEM.
6. PROVIDE INTERMEDIATE TEMPERATURE RATED SPRINKLER HEADS IN
ALL MECHANICAL, ELECTRICAL OR SIMILAR BACK OF HOUSE SPACES
WHERE AMBIENT TEMPERATURE ARE HIGHER THAN NORMAL
COMMON SPACE ENVIRONMENTS, UNLESS NOTED OTHERWISE.
7. PROVIDE THE APPROPRIATE HYDRAULIC NAMEPLATES AT THE BASE
OF EACH SYSTEM RISER. NAMEPLATES SHALL INCLUDE LOCATION OF
REMOTE AREA, NUMBER OF SPRINKLERS FLOWING, DESIGN DENSITY,
AND REQUIRED GPM AND PSI AT THE BASE OF EACH SYSTEM RISER
OR CONTROL VALVE ASSEMBLY.
8. NO SERVICE SHALL BE INTERRUPTED WITHOUT WRITTEN PERMISSION
FROM THE CONTRACTING OFFICER.
9. WHERE DEMOLITION WORK INTERFERES WITH OWNER'S USE OF
PREMISES, SCHEDULE WORK THROUGH CONTRACTING OFFICER TO
MINIMIZE INCONVENIENCE TO OWNER. OWNER MUST APPROVE
SCHEDULE BEFORE CONTRACTOR BEGINS ANY SUCH WORK.
10. REMODEL OF SPACE IDENTIFIED ON DRAWINGS REQUIRES THAT
COORDINATION OCCUR BETWEEN FIRE PROTECTION CONTRACTOR
AND OWNER. AT THE END OF EACH WORK DAY, SPRINKLER FITTER
MUST COORDINATE WITH OWNER SO THE FIRE PROTECTION SYSTEM
IS RE-ACTIVATED FOR EACH NIGHT.
11. REFER TO SPECIFICATION 21 1314 - AUTOMATIC FIRE SPRINKLER
SYSTEM FOR ADDITIONAL INFORMATION.
12. FIRE PROTECTION CONTRACTOR SHALL HAVE APPROVED
SPRINKLER SUBMITTAL DRAWINGS FROM ARCHITECT AND ENGINEER
PRIOR TO STARTING INSTALLATION ON THIS PROJECT. ANY WORK
THAT HAS BEEN INSTALLED PRIOR TO RECEIVING THE APPROVALS
MAY BE REMOVED, AT THE CONTRACTORS EXPENSE.
13. AREAS OF WOOD FRAMING SHALL BE CONSIDERED COMBUSTIBLE
OBSTRUCTED IF THE BEAM SPACING IS LESS THAN 15'-0” ON CENTER.
| F0 - FIRE PROTECTION - COVER SHEET |
| Sheets and Views |
| Layout1 |
| F1 - FIRE PROTECTION - SYMBOLS AND ABBREVIATIONS |
| Sheets and Views |
| Layout1 |
| PLOT |
| F2 - FIRE PROTECTION - FARM 1 BARN LOWER LEVEL PLAN |
| Sheets and Views |
| Layout1 |
| PLOT |
| F3 - FIRE PROTECTION - FARM 1 BARN UPPER LEVEL DEMOLITION PLAN |
| Sheets and Views |
| Layout1 |
| F4 - FIRE PROTECTION - FARM 2 SHOW BARN PLAN |
| Sheets and Views |
| Layout1 |
| PLOT |
| F5 - FIRE PROTECTION - BUILDING SECTIONS |
| Sheets and Views |
| Layout1 |
| PLOT |
| F6 - FIRE PROTECTION - DETAILS |
| Sheets and Views |
| FIRE PROTECTION DETAILS |
| PLOT |
| F7 - FIRE PROTECTION - STAGING PLAN |
| Sheets and Views |
| Staging Plan |
| VIEW |
| F8 - FIRE PROTECTION - FARM 1 BARN SITE PLAN |
| Sheets and Views |
| Layout1 |
| PLOT |
| F9 - FIRE PROTECTION - FARM 2 SHOW BARN SITE PLAN |
| Sheets and Views |
| Layout1 |
| PLOT |
File details come from the government source that posted it. Updated .