This is Amendment 0002 to Solicitation 140P4226Q0005, issued by the National Park Service (Northeast Regional Contracting, South/Philadelphia MABO) for PARK PMIS 191784 – EISE Barns Fire Suppression Repair. The amendment is effective March 18, 2026, with a new closing date and time of Thursday, April 2, 2026, by 1700 Eastern Time. The contract period of performance is April 20, 2026, to October 14, 2026.

The amendment incorporates three primary additions: a Questions and Answers document addressing 28 contractor inquiries received after the site visit; a site visit signing sheet; and Attachment 7 containing the 140P4226Q0005 Project Experience requirements. Key technical clarifications from the Q&A include confirmation that municipal permits are not required; PA licensure is not required for fire suppression contractors on this federal project; bid bonds are not required; only scissor lifts (not boom lifts) are permitted for interior access, with specific plywood floor protection requirements; all replacement piping shall be Schedule 40 black steel (galvanized piping is not permitted due to corrosion concerns in agricultural settings); sprinkler head guards are required; and backflow preventers will be replaced rather than retained. The government clarified that Historic Preservation Treatment Plans are not required with quotes but may be requested post-award, and that pre-proposal questions must be submitted 7 calendar days prior to the RFQ due date. All other terms and conditions of the original solicitation remain unchanged.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Wendy De Leon

See continuation page

DOI, NPS, NERO & NER SOUTH MABO

National Park Service Northeast Regional Contracting South/Philadelphia MABO 1234 Market Street, 20th Floor Philadelphia PA 19107

PNC

140P4226Q0005

03/18/2026

02/19/2026

1 9

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P4226Q0005/0002

The purpose of Amendment 0002 is to:

1. Incorporate "140P4226R0005 - Questions and

Answers" document that addresses Contractor's questions received after the site visit.

2. Provide the site visit signing sheet and solicitation Attachment 5 - 140P4226Q0005

Project Experience.

3. Extend the closing date and time to

Thursday, April 2, 2026, by 1700 Eastern Time.

All other terms and conditions remain unchanged as a result of this Amendment 0002.

Period of Performance: 04/20/2026 to

10/14/2026

Solicitation No.

Amendment 0002

Document Title PARK PMIS 191784 – EISE Barns Fire Suppression Repair

PART III – LIST OF DOCUMENTS, EXHIBITS, AND

OTHER ATTACHMENTS

SECTION J – LIST OF ATTACHMENTS

Document Title Date Pages Attachment 1 EISE Barns Fire Suppression Repairs

SOW

01/29/2026 3

Attachment 2 Specifications_Reference Only 03/03/2022 51 Attachment 3 Drawings_Reference Only 03/03/2022 10 Attachment 4 Wage Determination, PA20260073 1/09/2026 8 Attachment 5 Subcontracting Percentage

Worksheet 2/19/2026 1

Attachment 6 Q&A Document 2/19/2026 1 Attachment 7 140P4226Q0005 Project Experience 3/17/2026 1

Amendment 0002

Document Title

Questions & Answers Document

140P4226Q0005 EISE HQ HVAC Replacement and Barns Fire Suppression Repair # Contractor Question Government Response

Please confirm that municipal permits will not be required.

Reference: Scope of work 1.d - Prevailing Wages

Municipal permits not required.

Please confirm that PA Licensure is not a requirement for the contractor.

Reference: Scope of work 1.d - Prevailing Wages

PA Does not issue licensing for fire suppression contractors and this is a federal project that will adhere to Director’s Order 58, NFPA 13, NFPA 25B. Please see certifiation requirements in section

1.4 Quality Assurance, sub section B. in the

provided specifications packet.

Instructions, E.3. Factor 2 Project Experience references an attached "Project Experience" form. Please provide referenced form.

Reference: Instructions for the Submission of Quoatation, "Project Experience" form has been added as "B08 Attachment 7 - 140P4226Q0005 Project Experience"

SF1442 states an offer guarantee is not required.

Instruction for Submission, F. Volume II, item 3 lincludes a bid bond in the list of documents. 3.

Contents does not provide for bid bond. Please confirm a offer guarantee(bid bond) is not required.

Reference: Solicitation

Bid Bond is not required for this project.

Barn #1 – Fire Protection Riser Room – Based on the current configuration of the room, the new nitrogen generator is to be located on the wall adjacent to where the existing air compressor is provided. Please confirm that egress is not required for the access to this generator system.

Accessibility will be required for any component that requires routine maintenance. Full egress is not required; however, components must be readily accessible for maintenance. The nitrogen gnerators are replacing the air compressors accordingto the specifications. There should be room if installed in the curent compressor location. This site has a concuurent storage space that can be used if needed as well.

Barn #1 – Drawing Accuracy – The fire protection drawing F2 (Sheet 3 of 10) was utilized during the site visit and it was found that there was discrepancies between the existing system and that of the drawings.

These items included the configuration of the piping and the sizing of the piping. Please confirm that the drawings are to be utilized for the overall pricing of the project and that any changes from the sizes shown would be considered a change to the contract or should the pricing be reflective of the existing site conditions?

Use the drawings for sizing and bidding. The provided drawings were completed in 2022. The appropriate flow tests should have been performed to determine piping and equipment specifications at that time.

Questions & Answers Document

# Contractor Question Government Response

Amendment 0002

Document Title

Barn #1 – 4” Supply – On the drawing F2 (Sheet 3 of

10) there is a 4” supply that traverses the barn and was shown to supply the small adjacent building. This building was recently renovated and has a water supply of its own. Please confirm that the 4” supply that is shown on these drawings is not required. If the supply is not required, please confirm that only one (1) dry pipe valve is required.

The adjacent building was completely renovated recently. Duirng that renovation, it was seperated from this structures fire suppresion system and tied directly into the water main. All associated lines and equipment that would have provided fire suppression to that structure are no longer needed.

Barn #1 – Restroom Area – the current restroom area is provided with a tongue and groove wood ceiling. For the removal of the ceiling, is the ceiling removal to be completed by the contractor or by the Park Service?

Prior to work commencing, the contractor will coordinate with the NPS to detemine what access is needed and what material will need to be removed to prevent delay for this project. The NPS will remove this material prior to the contractor commencing work so as to not interfere with the contractor team members or project timeline.

Barn #1 – Piping slope – As part of the site visit that occurred it was noted that several areas of the existing dry pipe system were installed as level. As stated in the scope of work, the piping is to follow the same pathways as much as possible, however the piping per NFPA-13 and the contract documents, the piping shall be sloped at a ½” per every 10 ft. Based on this sloping requirements, please note that this shall change the elevation of numerous pipes and shall require several locations to require the patching and cutting of the existing walls that the piping penetrates. Please confirm this this cutting and patching shall be part of this scope of work or as part of the NPS scope of work due to the historical nature of the work.

Any additional modification to historic material, will need to go through cmpliance for approvals. It will also need to be determined, prior to the start of the project, if structural components will be affected by these elevation changes. Depending on the volume and circumstance, it could take 30 days for changes to be approved. The contractor will determine all modificationes requried to the structure within 14 days of accepting the award, and submit them to the CO/COR so they can be forwarded to the appropriate goverment authoriites to expepdite decisions. Installing new fasteners in new locations will not be considered a modification to the structure for this contract.

Barn #1 – Office/Display – this space has an existing ceiling structure, is the cost to remove this ceiling and patch it part of the contract scope or is this part of the NPS scope?

Prior to work commencing, the contractor will coordinate with the NPS to detemine what access is needed and what material will need to be removed to prevent delay for this project. The NPS will remove this material prior to the contractor commencing work so as to not interfere with the contractor team members or affect the project timeline.

Barn #1 – Upper Level – As per the site visit it was discussed that that upper level of the barn is to not have the sprinkler system replaced. Please confirm that only the demolition of the piping is required on the upper level.

Barn 1, high bay/upper level, is being demoed only.

Not reinstalled.

Questions & Answers Document

Amendment 0002

Document Title

Show Barn – Riser Room – Based on the existing configuration of the equipment within the small sprinkler room there is extremely limited space for the nitrogen generator to be placed. Based on the room limitation, the nitrogen air compressor can be placed within the room, but being able to stand in front of the generator may be difficult. Please confirm that the room size is not to be modified and it is acceptable to have the generator placed in the room without having to stand directly in front of the panel and have a means of egress path.

According to the specifications, the compressor is being removed and nitorgen generator installed in its location. There is a door currently infront of the compressor for access. The wall space above the compressor is clear for use as well. This should allow enough access for future service. Once equipment has been selected, verify access with the COR/CO prior to scheduling installation sothere will be rerasonable time for modifications if needed.

Show Barn – Wash down room – the existing main is located at an elevation that is below the existing plaster ceiling. The lines then rise up from the main and supply the dry pendent in the aisle way and also the dry pendents that protect the room. Based on the current configuration and pathways of the piping, the existing plaster ceiling is going to need to be cut and patched. Is this cutting, patching and paining part of this scope or due to the historical nature of the space, is NPS to perform this work?

If the current elevation can be maintained for this branch line, then it will be. If possible upon determination by the contractor, only the sprinkler heads will be replaced and appropriate covers used.

If additional drywall/plaster needs to be removed, the contractor will notify the NPS prior to the project commencing so the work can be coordinated to prevent NPS team members from interferring with the contractor's team or impacting the project timeline.

Show Barn – Historical office space – The existing main is located against the wall near the aisle way and the lines rise up and are located above the existing plaster ceiling. Based on the current configuration and pathways of the piping, the existing plaster ceiling is going to need to be cut and patched. Is this cutting, patching and paining part of this scope or due to the historical nature of the space, is NPS to perform this work?

If the current elevation can be maintained for this branch line, then it will be. If possible upon determination by the contractor, only the sprinkler heads will be replaced and appropriate covers used.

If additional drywall/plaster needs to be removed, the contractor will notify the NPS prior to the project commencing so the work can be coordinated to prevent NPS team members from interferring with the contractor's team or impacting the project timeline.

Show Barn – Main piping crossing aisle way – as the new piping is required to be sloped at a ½” per every 10 feet, the piping that is required to cross the aisle way near the riser room is required to be at an elevation lower than the existing cross beams that run parallel to the aisle way. From rough calculations this piping would be located at approximately 8’-3” +/- above the finish floor. Please confirm that this elevation is acceptable to allow the one portion of the barn to drain back to the riser, if not, this shall require an additional drum drip to be provided that shall be located inside of the stall area and shall be provided along the face of one of the existing columns.

Bid to add drum drip. Either having the crossover line or the drum drip visible will have to goto compliance for approval. We will start that conversation now so as to not impact the project timeline once work commences. Plan on doing drum drip behind the nearest stall post to attemp to hide it from center aisle veiw.

Questions & Answers Document

Amendment 0002

Document Title

Show Barn – stainless steel piping – as per the contract documents and the statement of work, the piping that is located in the portion of the barn that is furthest from the riser room. This entire area is provided as grooved stainless steel piping. After review of the piping configuration, the entire system in this area is run level, it is recommended that this piping be re-pitched to allow for the system to drain back to a drum drip assembly that is located where the two portions of the barn meet.

Please confirm if the piping in this area should be pitched to meet the ½” per every 10 feet slope requirements.

Yes. The piping elevation will be adjusted for proper drainage. Within 5 days of the project commencing, the contractor will coordinate with the on site NPS POC/COR to move equipment as needed for contractor work. Planning and good coordination will be needed as it will take multiple team mmebersa and several hours to move the equipment around.

Show Barn – Stainless steel piping sprinklers – As no work in this area is indicated, should the existing sprinklers in the area be replaced with new sprinklers?

Yes. All sprinkler heads will be replaced. Only stainless piping will be reused/stay in place.

Show Barn – Inspector’s test valve off of the stainless steel piping – the current configuration has the piping coming down off the bottom of the most remote line.

As per the Figure A.16.14.2 in NFPA-13 2022 Edition, the inspector’s test valve is to riser up off of the line piping to help limit any condensation in the drop piping for the inspector’s test valve. Based on the field survey, this line does appear to be slightly trapped currently and would require also a drum drip at this location, per code this piping should come off the bottom of the piping.

Please confirm if this piping should be replaced with the code compliant configuration and if this new piping is to be provided as stainless steel piping. Please note that threaded stainless steel piping does have a tendency to leak due to the inherent course threads of the piping.

Yes. Update this test valve and associated components so they concur with the appropriate regulations. Carbon steel/black piping may be used.

Ensure the proper dielectric fittings or isolations couplings are used between the stainless steel and carbon/black steel materials to prevent galvonic corrosion in the system.

Both Barns – Nitrogen Monitoring – As required by the specifications and the drawings, the dry pipe system is to be monitored and shall provide the alarming of a low nitrogen level. The basis of the design is that of a ECS PGEN-10 or an equivalent. All of the different nitrogen generator systems all require a power requirement for the remote monitoring panel. Shall this work be provided on a separate circuit or is there a circuit that would allow this to be connected to? If the work is required to be connected to a breaker panel, please confirm the panel is capable of providing another electrical breaker and if so, where is the location of the electrical breaker panel in relation to the fire sprinkler riser room.

The drawings call for the removal of the current air compressor circuit(s) back to the panel(s) and installation of a new line for the nitrogen generator.

If the remote monitoring panel requires 120v power, both structures have panels within 50' of the riser rooms with available space. Typical panels within the site are residential grade Square D QO.

All electrical wiring will be in FMC or EMT.

Questions & Answers Document

Amendment 0002

Document Title

Both Barns – Piping type – As per the specifications all new piping specification section 211314 – 2.2.B.1.it states that all piping shall be provided as schedule 40 piping, however no reference is made to the type of piping (black or galvanized). The Scope of work 4.a it states that all mains are to be provided as schedule 10 and schedule 40 for the lines. As per the Park Service design guide, all piping is to be provided as Schedule

40. Please confirm the piping requirement and if the new piping is to be provided as Galvanized or Black steel.

NFPA 13 requires sprinkler system piping to be suitable for the environment and protected against corrosion. The existing dry systems in this agricultural setting have experienced premature internal corrosion and pinhole failures in galvanized piping, consistent with known corrosion behavior in dry systems where oxygen and moisture are present and encourage bacterial growth.

In addition, agricultural and exposed environments are recognized as corrosive conditions, requiring more durable materials for long-term performance.

Therefore, galvanized piping will not be permitted.

All replacement piping shall be Schedule 40 black steel to provide increased wall thickness, lower probability of encouraging internal bacterial growth, and extended service life in accordance with NFPA 13 intent and industry best practice

Both Barns – head Guards – Due to the nature of the barns and the numerous locations that have the sprinklers located within 7’-6” of the finish floor, should all sprinklers (minus pendent sprinklers in the restrooms and office areas) be provided with head guards as to protect them from mechanical damage?

Yes. Installation according to industry standards and best practices is expected.

Both barns – fire department connections – As per the detail # on F6 (sheet 7 of 10) the fire department connects are to be provided with a by-pass valve to allow for the forward flow testing of the backflow preventer. Based on the existing fire department connections they both have clappers provided in the body which will prevent the forward flowing of water through the connection. Is the design intent for the fire department connections to be replaced with a type that does not have a clapper? If so, should clapper snoots be provided on the inlet connection of the connections on the fire department connection? Or should a separate connection be provided adjacent to the fire department connection for the forward flow testing of the backflow?

The work environment is historic. Due to the nature of the environment, it is discouraged to install anything that changes the appearance of how things were in 1968 (The period of significance for this site). Although the fire suppression was not present in 1968, it is the mission to keep the impact as small as possible. Therefore, use the same location through the wall to the exterior and install the device that best adheres to this compliance standard.

Both barns – backflow preventers – Please confirm that the existing backflows are to remain as previously installed? If they are to remain, do they need to be tested to verify their current condition?

The back flow preventers will be replaced. The dry valves and other components were in the specifications. These components were installed around 2002. They are beyond their useful life.

Backflows removed will be turned over to the site

POC/COR.

Questions & Answers Document

Amendment 0002

Document Title

General Comment – AutoCAD Files – Please confirm if upon award the AutoCAD files from the contract documents can be provided to assist with the shop drawing process

NPS EISE does not currently have the AutoCAD files. They have been requested from the engineering firm. There is no guarantee at this time they will be available.

General Comment – Permit – Please confirm that no local permits are required as this project is located on government controlled land.

No local permits are required, however, there will be an acceptance inspection, and functions check once the systems have been installed and put into service. This is a standard requirement for the Authority Having Jurisdiction (AHJ). The AHJ for this project is the NPS Regional Fire Marshal, Patrick Wilcox, unless otherwise delegated.

Are pre proposal questions due 7 calendar days or 7 business days prior to the RFQ due date?

pre proposal questions are due 7 calendar days prior to the RFQ due date

Does the government require us to submit Historic Preservation Treatment Plan with our Quote?

Reference: Specifications Reference Only, 1.15 pg.12

Historic Preservation Treatment Plan is not required with your Quote. This might be requested after award.

For access to the sprinkler piping in the Main Barn, can the Government confirm whether contractors will be permitted to use equipment such as scissor lifts or boom lifts inside the building, or if access will be required via scaffolding?

Only scissor lifts are permitted for interior access within the bank barn. Boom lifts are prohibited.

Prior to operation, the contractor shall install a continuous load-distribution layer consisting of minimum 3/4-inch plywood or approved equivalent over the plank flooring. Plywood shall be placed to fully support all wheel paths and turning areas, with joints staggered and tightly butted to prevent point loading.

This requirement is necessary not only to protect historic flooring, but also to enhance personnel and equipment safety by reducing the risk of lift wheels becoming caught in gaps, weak areas, or irregularities in the plank floor, and to minimize the potential for wheel breakthrough or instability during operation.

Contractor shall ensure loads are distributed across multiple planks and structural members and shall be responsible for preventing damage to historic flooring. Any damage shall be repaired at contractor expense.

Contractor shall submit the make, model, and total operating weight of all proposed lifts for approval prior to use. Use of equipment exceeding approved weights or omission of floor protection is not permitted without prior written approval.

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))