B08_Attachment_1_Statement_of_Work_(SOW).docx

DOCX document 25 KB Posted

Attached to
LE BUCKSHOTS ANNUAL SERVICE Federal contract opportunity
Solicitation number
140L1226Q0016
Issued by
Department of the Interior Bureau of Land Management California Region

About this file

This is a Statement of Work for the annual maintenance of two Buckshot Model X5R Law Enforcement sand rails (LE1 and LE2) operated by the Bureau of Land Management California's El Centro Field Office in Imperial County. The contractor must perform comprehensive preventive maintenance and repairs to ensure both vehicles remain operational throughout the FY27 season (October 1, 2026 – May 31, 2027) for use in Federal and State Law Enforcement patrols and emergency medical and rescue services in the Imperial Sand Dunes Recreation Area.

The scope of work encompasses fourteen specific known issues requiring attention, including seat refurbishment, radiator pressure testing and coolant leak repairs, airbag replacement, complete fluid and filter service, hose replacement, battery inspection and replacement, front-end alignment, engine inspection, shifter adjustment or replacement, and rear tire replacement with Sand Tires Unlimited Sand Blaster Tires (36"x17 NO.2). Additionally, the contractor must perform comprehensive inspections and maintenance across seven major systems: frame/body/electrical (including rust treatment, light functionality, and wiring connections), engine (spark plugs, compression testing), controls (steering, brakes, clutch, throttle), drivetrain (transaxle, CV joints, service hubs), suspension (components, bushings, brake lines), miscellaneous items (fastener torquing, greasing, leak repair), and tires. The BLM will deliver and retrieve the vehicles within a 30-mile radius of the field office, with drop-off by June 1, 2026, and all work completed by September 30, 2026. The contractor must furnish all personnel, materials, equipment, and supplies, work regular hours (7:00 AM – 4:00 PM, Monday-Friday), submit detailed invoices for each vehicle matching all SOW items with line-item descriptions, parts costs, labor hours, and engine hour meter readings, and return all removed usable parts to the BLM for emergency use during the dunes season.

View the file

Other files for this federal contract opportunity

Other files attached to LE BUCKSHOTS ANNUAL SERVICE, newest first.
File Type Posted
B08_Attachment_1_Statement_of_Work_(SOW)_revised_v1_0002.docx DOCX document
Sol_140L1226Q0016_Amd_0002.pdf PDF
B08_Attachment_1_Statement_of_Work_(SOW)_revised_0001.docx DOCX document
Sol_140L1226Q0016_Amd_0001.pdf PDF
B03_Attachment_2_Wage_Determination_2015-5607_Rev_29.pdf PDF
B08_Attachment_3__Sand_Rails_Specs.docx DOCX document
Sol_140L1226Q0016.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work for LE1(I00687LE) and LE2 (I00688LE) Sand Rail Annual Maintenance Summer 2026 Background on Government’s Requirement The Bureau of Land Management (BLM)-California, El Centro Field (Imperial County) has a need for maintenance for their Law Enforcement Sand Rails (LE1 I00688LE) and LE2 I0068LE).

General Scope of Work The general scope is to ensure the following Buckshot Model X5R LE1 (I00688LE) and LE2 (I00687LE) BLM Law Enforcement sand rails will remain in service over the 2026-2027 Imperial Sand Dunes Recreation Area season to provide Federal and State Law Enforcement patrols and emergency medical and rescue services. Please see Attachment 3 for specifications of the Sand Rails.

Although BLM understands there can be unavoidable breakdowns and driver errors that cause damage to the vehicle, the objective of this procurement is to minimize the chance of mechanical failure and ensure vehicles are safe for employee operation for the duration of the FY27 use season from October 1, 2026 - May 31, 2027.

Place of Performance/period of performance The BLM will drop off and pick up vehicles/trailers within a 30-mile radius of their field office. The drop-off dates and times will be done by June 1, 2026, and all work completed by September 30, 2026.

Specific Tasks Specific Known Issues to Be Addressed for LE1 and LE2 Sand Rails:

1. Inspect and refurbish LE1 and LE2 seats.

2. LE1 and LE2 - Inspect/ Pressure Test Radiator (coolant leak from either coolant return hose or Radiator Return inlet)

3. Inspect and replace all airbags as necessary.

4. Drain and replace all engine fluids and replace all belts and filters.

5. Drain and replace all coolant, brake, clutch, and steering fluids.

6. Replace all hoses (including air, fuel, and coolant) with like kind hoses as needed.

7. Inspect both batteries and replace if necessary.

8. Align front end.

9. Inspect both engines.

10. Inspect and adjust shifter/ shift linkage. (Replace Shifter if needed) (2nd Gear and Reverse difficult to shift into)

11. Replace air and fuel filters.

12. Clear and treat any corrosion on LE1 and LE2

13. Replace rear tires of LE1and LE2.

The following apply to all sand rail The vendor will inspect, adjust, repair, replace, or consult with BLM on the maintenance items below. If there are other systems on the vehicle that need maintenance, the vendor will consult with BLM for guidance. If there are items that the vendor determines will not need maintenance (i.e. replacing shifter, the vendor will advise BLM. At a minimum, the vendor will address the following:

1. Frame/Body/Electrical

a. Inspect frame and welds for rust, damage, cracks, and structural integrity.

b. Fix side panels and scratches along with any paint / powder coat touch up to frame.

c. Check all lights to make sure they are in working order, including emergency lights, gauge lights, head lights, and dome light.

d. Inspect and clean all wiring connections.

e. Ensure all side panels and instrument covers are securely mounted and fasteners are torqued and tightened with “Locktight” or comparable product.

2. Engine: Inspection and test and notify BLM of the results

a. New spark plugs installed

b. Compression test, report compression for all cylinders

3. Controls: Exterior visual inspection and test

a. Steering components including but not limited to, bushings, front wheel alignment, rack and pinion, seals, hoses, seals, mounting components, power steering pump, etc.

b. Brake, clutch, throttle pedal assembly

c. Test and inspect all brakes and controls

4. Drive train: Exterior visual inspection and test

a. Trans axel, adjustment if necessary

b. Axel CV joints

c. Service hubs/ CV axels

5. Suspension: Exterior visual inspection and test

a. All suspension components, front and rear, including but not limited to, seals, joints, bearings, etc.

b. Inspect and test all brake lines.

c. Replace suspension bushings if necessary (suspension should operate without squeaks)

d. Inspect all brakes.

6. Misc

a. Inspect all seats for any failures that may compromise structural integrity to ensure employee safety.

b. Inspect all rubber boots and replace if necessary.

c. All fasteners tightened and/or re-torqued.

d. All bearings greased.

e. Inspect and repair all leaks (fluids, exhaust, air, etc.).

f. Replace any missing fasteners.

g. Test all emergency equipment and lighting and buggy whips.

h. Ensure all rails have working hour meters on all vehicles.

7. Tires

a. Inspect front tires and replace if necessary

b. Replace rear tires on LE1 and LE2 with Sand Tires Unlimited Sand Blaster Tires 36”x17 NO.2

The following is a description of the steps needed to complete this job and receive payment.

Procurement Procedures

1. BLM will coordinate and deliver sand rails to contractor.

2. In the event that work exceeds the task I the Statement of Work, the Contactor will contact BLM (CA State Office and El Centro Field Office) before any additional work is completed.

3. The contractor will send BLM (CA State Office and El Centro Field Office) a copy of the final invoice for completed work. Each copy will include at a minim, but not limited to:

a. Separate invoices for each vehicle for all work completed.

b. Match all the items addressed in the SOW.

c. An invoice number for each vehicle.

d. Vehicle license plate number.

e. Date.

f. Engine hour meter readings.

g. Clearly understandable notes and documentation for each item in the SOW so BLM can understand what work was completed and the results of work completed.

h. A column for the line-item number that matches the SOW, work description column, parts amount column, labor hour amount column, labor rate per hour, parts total, labor total, and a grand total.

4. The contract will contact BLM to arrange delivery of vehicles once work has been completed.

5. BLM will inspect vehicles and compare the SOW to work described in copy of final invoice

6. The vendor will submit final invoice through Internet Payment Platform (IPP) for payment.

7. All removed usable parts will be labeled and returned to BLM to be used in case of emergency during the dunes season.

Delivery/Performance Schedule This is a non-personal service, and the Contractor will furnish all equipment, labor, and supplies to provide the necessary maintenance and repairs to the two (2) LE Sand Rails. BLM will deliver vehicles to the repair shop and pick them up once maintenance/repairs are completed.

Government-Furnished Property, Materials

General :

The Contractor shall furnish all personnel, materials, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the work tasks defined in this Statement of Work.

Materials:

The Government shall not furnish any materials.

Equipment:

The Government shall not furnish any materials.

Security and Administrative Matters

Regular Work Hours:

The performance period established for this contract is based upon all work being conducted during regular working hours between 7:00am and 4:00pm, Monday through Friday, excluding government holidays. If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and government holidays, a request must be submitted to the Contracting Officer in sufficient time to allow satisfactory arrangements to be made for access to the work site.

Communications:

“Time” for communications received after 3:00pm, after 12:00 pm locally on Fridays, or after 12:00 pm locally prior to a holiday will not start until the next business day. All times are local Pacific Standard Time.

Federal Holidays:

The following Federal Legal Holidays are observed:

New Year’s DayMartin Luther King, Jr. Day
President’s DayMemorial Day
JuneteenthIndependence Day
Labor DayColumbus Day
Veterans DayThanksgiving Day

Christmas Day

PWS 8.0 Technical Exhibits and Definitions

Standard Definitions:

Physical Condition The Physical appearance of Federal equipment or facilities that considers cracks, chips, dents, abrasions, rust, corrosion, general cleanliness, vibration, operating temperature, and discoloration and other items as identified by the COR. Physical condition may be determined by visual as well as diagnostic means.

Contracting Officer (CO) The Secretary of the Interior or designated authorized representative who is the only agent capable of signing a federal award or obligating funds.

Contracting Officer’s Representative (COR) The Contracting Officer’s designated representative as indicated in a delegation of authority letter.

Quality Assurance (QA) Surveillance of Contractor performance to determine performance requirements are met.

Performance Requirements Summary (PRS) (see Technical Exhibit below) The PRS identifies the key performance indicators of the Contract that will be evaluated by the Government to assure Contract performance standards are met by the Contractor.

Quality Control Those actions taken by the Contractor to control the production of goods or services so that they meet the requirements of the performance work statement.