B08_Attachment_1_Specifications.pdf

PDF 15 MB Posted

Attached to
CUIS 258139 - Preserve and Rehabilitate the Histor
Solicitation number
140P2024R0143
Issued by

About this file

This document appears to be Attachment 1 - Specifications for the federal contract opportunity CUIS 258139 - Preserve and Rehabilitate the Historic Grange, Cumberland Island National Seashore, North Carolina, issued by the Department of the Interior National Park Service National Office.

The specifications outline the requirements for preserving and rehabilitating the historic Grange building located within the Cumberland Island National Seashore in North Carolina. Key requirements include roof repairs, masonry restoration, window replacement, and interior renovations to the building. The work must be completed in accordance with the Secretary of the Interior's Standards for the Treatment of Historic Properties. The solicitation has a response due date of November 15, 2024, with an anticipated award in January 2025. Pricing is to be submitted on a fixed-price basis. The procurement is set aside for small businesses. The incumbent contractor is not identified.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cumberland Island National Seashore

Preserve and Rehabilitate the Historic Grange

CUIS PMIS No. 258139 – MOD 001

GWWO Project No. 23002

CONSTRUCTION SPECIFICATIONS

NATIONAL PARK SERVICE

Prepared by GWWO, Inc. / Architects

May 31, 2024

05/31/24

05/31/2024

[This page left intentionally blank.]

May 31, 2024

TABLE OF CONTENTS

TAB 1 ............................................Specifications

APPENDIX A ..................................Closeout and Operation &

Maintenance Requirements

APPENDIX B ..................................Pre-alteration Hazardous Material

Survey

Tab 1: Specifications

CUIS-258139 00 01 10 - 1

PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 10 - TABLE OF CONTENTS

SPECIFICATIONS

DIVISION 01 -- GENERAL REQUIREMENTS

01 11 00 – SUMMARY OF WORK

01 26 01 – CONTRACT MODIFICATION PROCEDURES

01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

01 31 00 – PROJECT MANAGEMENT AND COORDINATION

01 32 16 – CONSTRUCTION SCHEDULE

01 32 33 – PHOTO DOCUMENTATION FOR HISTORIC PRESERVATION PROJECTS

01 33 23 – SUBMITTAL PROCEDURES

01 33 23A – SUBMITTAL LIST

01 35 13.22 – ARCHEOLOGICAL PROTECTION

01 35 23 – SAFETY REQUIREMENTS

01 35 91 – HISTORIC PRESERVATION TREATMENT PROCEDURES

01 40 00 – QUALITY REQUIREMENTS

01 40 00A – ACCESSIBILITY INSPECTION REPORT FORM

01 42 00 – REFERENCE STANDARDS

01 50 00 – TEMPORARY FACILITIES AND CONTROLS

01 57 19.11 – INDOOR AIR QUALITY MANAGEMENT

01 57 23 – UNDER AN ACRE POLLUTION PREVENTION

01 67 00 – PRODUCT REQUIREMENTS

01 73 40 – EXECUTION

01 74 19 – CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 74 19A – PROJECT WASTE MANAGEMENT PLAN WORKSHEET

01 74 19B – STANDARD SOLID WASTE CONVERSIONS

01 77 00 – CLOSEOUT PROCEDURES

01 78 23 – OPERATION AND MAINTENANCE DATA

01 79 00 – DEMONSTRATION AND TRAINING

01 81 13 – SUSTAINABLE DESIGN REQUIREMENTS FOR NON-LEED PROJECTS

01 91 14 – TOTAL BUILDING COMMISSIONING

CUIS-258139 00 01 10 - 2

DIVISION 02 -- EXISTING CONDITIONS

02 41 19 – SELECTIVE DEMOLITION

02 42 96 – HISTORIC REMOVAL AND DISMANTLING

02 81 00 – TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS

02 82 00 – ASBESTOS REMEDIATION

02 82 13 – ASBESTOS ABATEMENT

02 82 16 – ENGINEERING CONTROLS FOR ASBESTOS-CONTAINING MATERIALS

02 82 33 – REMOVAL AND DISPOSAL OF ASBESTOS-CONTAINING MATERIALS

02 83 13 – LEAD HAZARD CONTROL ACTIVITIES

02 84 16 – HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs AND

MERCURY

02 87 13 - MOLD REMEDIATION

DIVISIONS 03 -- CONCRETE

03 30 00 – CAST-IN-PLACE CONCRETE

DIVISION 04 -- MASONRY

04 72 00 – CAST STONE MASONRY

DIVISION 05 -- METALS

05 52 13 – PIPE AND TUBE RAILINGS

DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES

06 10 00 – ROUGH CARPENTRY

06 20 00 – FINISH CARPENTRY

DIVISION 07 -- THERMAL AND MOISTURE PROTECTION

07 21 00 – THERMAL INSULATION

07 31 13 – ASPHALT SHINGLES

07 53 00 – ELASTOMERIC MEMBRANE ROOFING

07 62 00 – SHEET METAL FLASHING AND TRIM

07 71 23 – MANUFACTURED GUTTERS AND DOWNSPOUTS

07 72 00 – ROOF ACCESSORIES

07 84 00 – FIRESTOPPING

07 90 05 – JOINT SEALERS

DIVISION 08 -- OPENINGS

08 03 52 – HISTORIC TREATMENT OF WOOD WINDOWS AND DOORS

08 14 33 – STILE AND RAIL WOOD DOORS

08 71 00 – DOOR HARDWARE

CUIS-258139 00 01 10 - 3

DIVISION 09 -- FINISHES

09 03 20 – HISTORIC TREATMENT OF PLASTER AND STUCCO

09 21 16 – GYPSUM BOARD ASSEMBLIES

09 30 00 – TILING

09 64 00 – WOOD FLOORING

09 64 29 – WOOD STRIP FLOORING

09 90 00 – PAINTING AND COATING

DIVISION 10 -- SPECIALTIES

10 28 00 – TOILET AND BATH ACCESSORIES

DIVISION 11 -- EQUIPMENT (NOT USED)

DIVISION 12 -- FURNISHINGS

12 35 30 - CASEWORK

DIVISIONS 13 THRU 14 (NOT USED)

DIVISION 21 -- FIRE SUPPRESSION

21 05 00 - COMMON WORK RESULTS FOR FIRE SUPPRESSION

21 05 23 - GENERAL-DUTY VALVES FOR WATER-BASED FIRE-SUPPRESSION PIPING

21 05 29 - HANGERS AND SUPPORTS FOR FIRE-SUPPRESSION PIPING AND EQUIPMENT

21 05 53 - IDENTIFICATION FOR FIRE-SUPPRESSION PIPING AND EQUIPMENT

21 13 13 - WET-PIPE SPRINKLER SYSTEMS

21 31 13 RESIDENTIAL PUMP AND TANK SYSTEMS

DIVISION 22 -- PLUMBING

22 05 00 – COMMON WORK RESULTS FOR PLUMBING

22 05 23 – VALVES FOR PLUMBING PIPING

22 05 29 – HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

22 05 53 – IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

22 05 93 – TESTING, ADJUSTING, AND BALANCING FOR PLUMBING

22 07 19 – PLUMBING PIPING INSULATION

22 08 00 – PLUMBING SYSTEMS COMMISSIONING

22 11 16 – DOMESTIC WATER PIPING

22 11 19 – DOMESTIC WATER PIPING SPECIALTIES

22 11 23 – INLINE, DOMESTIC-WATER PUMPS

22 13 16 – SANITARY WASTE AND VENT PIPING

22 13 19 – SANITARY WASTE PIPING SPECIALTIES

CUIS-258139 00 01 10 - 4

22 13 19.13 – SANITARY DRAINS

22 14 14 – STORM DRAINAGE PIPING

22 14 23 – STORM DRAINAGE PIPING SPECIALTIES

22 14 29 – SUMP PUMPS

22 33 00 – ELECTRIC DOMESTIC-WATER HEATERS

22 44 00 – PLUMBING FIXTURES & EQUIPMENT

DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

23 05 00 – COMMON WORK RESULTS FOR HVAC

23 05 29 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

23 05 48 – MECH SD & VIB CONTROLS

23 05 53 – IDENTIFICATION FOR MECHANICAL PIPING, DUCTWORK, AND EQUIPMENT

23 05 93 – TESTING, ADJUST & BAL

23 07 00 – HVAC INSULATION

23 08 00 – HVAC SYSTEM COMMISSIONING

23 23 00 REFRIGERANT PIPING

23 31 13 – DUCTWORK

23 33 00 – AIR DUCT ACCESSORIES

23 34 16 – FANS

23 37 13 – AIR OUTLETS & INLETS

23 81 29 – VARIABLE REFRIGERANT SYSTEMS

DIVISION 26 -- ELECTRICAL

26 00 50 – COMMON WORK RESULTS FOR ELECTRICAL

26 05 19 – LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

26 05 26 – GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 05 29 – HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

26 05 33 – RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

26 05 43 – UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL SYSTEMS

26 05 44 – SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING

26 05 53 – IDENTIFICATION FOR ELECTRICAL SYSTEMS

26 05 72 – OVERCURRENT PROTECTIVE DEVICE SHORT-CIRCUIT STUDY

26 05 74 – OVERCURRENT PROTECTIVE DEVICE ARC-FLASH STUDY

26 08 00 – COMMISSIONING OF ELECTRICAL SYSTEMS

26 09 23 – LIGHTING CONTROL DEVICES

26 24 16 – PANELBOARDS

26 27 13 – ELECTRICITY METERING

26 27 26 – WIRING DEVICES

26 28 13 – FUSES

CUIS-258139 00 01 10 - 5

26 28 16 – ENCLOSED SWITCHES AND CIRCUIT BREAKERS

26 29 13 – ENCLOSED CONTROLLERS

26 41 13 – LIGHTNING PROTECTION FOR STRUCTURES

26 43 13 – SURGE PROTECTION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS

26 51 00 – INTERIOR LIGHTING

26 51 10 – HISTORIC LUMINAIRE RESTORATION

DIVISION 27 -- COMMUNICATIONS

27 00 05 - STRUCTURED CABLING & SUPPORTING INFRASTRUCTURE

27 05 26 - GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS

27 05 28 - PATHWAYS FOR COMMUNICATIONS SYSTEMS

27 05 29 - HANGERS AND SUPPORTS FOR COMMUNICATIONS SYSTEMS

27 05 44 - SLEEVES & SEALS FOR COMMUNICATIONS PATHWAYS & CABLING

27 05 53 - IDENTIFICATION FOR COMMUNICATIONS SYSTEMS

27 11 00 - COMMUNICATIONS EQUIPMENT ROOM FITTINGS

27 13 23 - COMMUNICATIONS OPTICAL FIBER CABLING

27 15 13 - COMMUNICATIONS COPPER HORIZONTAL CABLING

DIVISION 28 -- ELECTRONIC SAFETY AND SECURITY

28 05 13 – CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY

28 46 21 – FIRE AND INTRUSION ALARM SYSTEM

DIVISION 31 -- EARTHWORK

31 20 00 – EARTH MOVING

DIVISION 32 -- EXTERIOR IMPROVEMENTS (NOT USED)

DIVISION 33 -- UTILITIES (NOT USED)

END OF SECTION 00 01 10

CUIS 258139 01 11 00 - 1

051121 SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Contractor Use of Site

3. Public Use of Site

4. Conduct of Operations

5. Work Restrictions

6. Additional Reports

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: The Grange at Cumberland Island National Seashore (Located off the east coast of St. Mary’s, GA). The project site is only accessible via boat. Contractor access to island should be coordinated with the NPS and is most easily accomplished via boats leaving from docks along St. Mary’s street in downtown St. Mary’s.

B. The Work consists of:

1. Contract Line Item Number 01: Preserve and Rehabilitate the Historic Grange (Exterior

Envelope & Structure)

a. This bid item consists of selective demolition pertaining to work in this option.

b. This bid items consists of structural repairs, painting the exterior, rehabilitation of the exterior windows and doors, replacing the roof, roof access and lighting protection system, and replacing the gutters and downspouts.

c. Demolition of exterior and basement plumbing. installation of exterior plumbing:

Installation of exterior sump pump and associated piping, exterior hose bibbs, sump pump in 004 Storage and associated piping, well pressure tank and water treatment system, new DWH, expansion tank, and hot water recirc pump, and all new piping in basement.

d. Electrical connections for the following plumbing equipment: Water heater, 30 GAL, DWH wiring, DS-DWH-1, chemical treatment, hot water recirc pump, sump pump

e. Abatement of asbestos hazardous materials on the interior and exterior of the building.

2. Contract Line Item 02: Mechanical

a. This bid item consists of selective demolition pertaining to work in this option.

b. This bid item consists of demolition of existing unit heaters and baseboard heaters, installation of housekeeping pads, installation of louvers and installation of

CUIS 258139 01 11 00 - 2

mechanical system including installation of VRF system (Heat pumps, fan coil units, piping, controls), installation of ductwork and air devices, installation of fans.

c. Includes electrical pertaining to the installation of the HVAC. Site Electrical Utilities: heavy-up of electrical service with utility company: Trench and duct bank from transformer to service entrance disconnect, Service entrance grounding and bonding. Electrical demolition: Remove Service Entrance Cable, Remove Panelboards, Remove Transfer Switch. New Electrical Service and Distribution: 2P- 400A F/SS Service Entrance Disconnect Switch, Distribution Panelboard, Panelboard RP1, Panelboard RP2, Meter Base, Associated feeders for panelboards.

Electrical Connections for mechanical HVAC: VRF Split System – Heat pump, VRF Split System - Ducted Indoor Unit, VRF Split System - Console Indoor Unit, Fans

– Inline, Fans - Roof Mounted, Motor Operated Dampers, Condensate Pump, GFI WP Receptacle, FCU Manual Switch, Combination motor starter CMS-EF, Exterior disconnect switches, FCU/EF Wiring/Conduit, ACC Wiring

d. Mold remediation on the interior of the building.

3. Contract Line Item 03: Fire Protection

a. This bid item consists of selective demolition pertaining to work in this option.

b. This bid item consists of installing the complete fire suppression system, installation of ump and tank and installation of piping, sprinklers, and accessories.

c. Includes electrical connections for residential fire pump and tank assembly. Fire alarm and intrusion detection system.

d. Includes plumbing connection to the fire suppression system.

4. Contract Line Item 04: Electrical and Telecommunications

a. This bid item consists of selective demolition pertaining to work in this option.

b. This bid item consists of replacing the electrical systems and telecommunication systems throughout and site distribution including lighting and branch wiring, interior luminaire restoration, exterior luminaire restoration, historic luminaire reproduction, wiring devices and branch circuits and communications.

c. Removal of Mercury bulbs on the interior of the building.

5. Contract Line Item 05: Exterior Ramp

a. This bid item consists of selective demolition pertaining to work in this option.

b. This bid item consists of installation of exterior concrete ramp and stairs.

c. Electrical installation of Ufer ground in ADA ramp footing

6. Contract Line Item 06: Kitchen and Baths Interior Finishes

a. This bid item consists of selective demolition pertaining to work in this option.

b. This bid item consists of new basement walls, doors and thresholds pertaining to bathrooms, kitchen and bath casework and accessories, kitchen and bathrooms floor, wall and ceiling finishes, plumbing and fixtures pertaining to the kitchen and bathrooms.

c. Demolition of all plumbing on the First Floor, Second Floor, and Attic. Installation of all new plumbing on the First Floor, Second Floor, and Attic.

d. Lead paint encapsulation on the interior of the building in the kitchen and bathrooms.

7. Contract Line Item 07: General Interior Finishes

CUIS 258139 01 11 00 - 3

a. This bid item consists of selective demolition pertaining to work in this option.

b. This bid item consists of rehabilitation of interior doors and thresholds, repairing and painting the interior, and interior floor, wall and ceiling finishes not previously included. Interior stairs renovation, finish carpentry and signage.

c. Lead paint encapsulation on the interior of the building not previously included.

C. Project will be constructed under a single prime contract.

1.3 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to areas coordinated with park staff and indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Coordinate with Contracting Officer (CO).

2. Limit site disturbance, including earthwork and clearing of vegetation, to 40 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.

B. Storage of Materials: Confine storage of materials to space indicated on site plan. The Contractor is responsible for ensuring public safety and access to open spaces between the existing ferry dock and building are preserved during construction.

C. Parking: Coordinate parking with park staff.

D. Stockpiling: Confine stockpiling to space indicated on site plan.

E. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with

Contracting Officer and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

F. Driveways and Entrances: Keep driveways, parking areas and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

CUIS 258139 01 11 00 - 4

G. Construction Camp: Establishment of a camp within park will not be permitted.

H. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

1. Park Road Speed Limit: 25 mph

2. Park Road Height Restriction: 9’ – 6”

I. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.

1.4 PUBLIC USE OF SITE

A. The building will be closed to the public during construction.

B. Contractor shall conduct his operations to ensure the least inconvenience to public. Building and road closures may be permitted, when required, upon specific approval of Contracting Officer.

1.5 CONDUCT OF OPERATIONS

A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 72 hours in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.6 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 4:00 p.m., Monday through Friday, except when otherwise indicated, or if determined otherwise in coordination with Park Staff.

1. Weekend Hours: Not permitted

2. Early Morning Hours: Not permitted

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

CUIS 258139 01 11 00 - 5

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than 3 business days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Hours and length of Utility Shutdowns: Coordinate with Contracting Officer.

D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within 25 feet of entrances, operable windows, or outdoor air intakes.

1.7 ADDITIONAL REPORTS

A. The report Pre-alteration Hazardous Material Survey, March 17, 2023, prepared by Arc Environmental is an appendix with this package.

B. In case of conflict between report and drawings or specifications, drawings and specifications govern.

PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

CUIS 258139 01 26 01 - 1

012721 CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The Project Manager (PM) is allowed to hold the positions of the Waste Management Coordinator and the Contractor Quality Control Manager. The Superintendent is allowed to hold the positions of the Environmental Manager, the Quality Control Manager, and the Safety Officer. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager (PM), Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

CUIS 258139 01 26 01 - 2

4. Engineers

5. Waste Management Coordinator

6. Travel, lodging, and per diem (as established by Federal Travel Regulations)

7. Scheduling

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

10. Boat rentals i.e. Transportation, Tugboat, and Barge

C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.

The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security

2) Medicare

3) Workers Compensation – Policy and company calculation to be made available.

CUIS 258139 01 26 01 - 3

4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.

5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.

6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.

Include as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank

CUIS 258139 01 26 01 - 4

Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.

3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.

5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. Labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for work being performed.

2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.

3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region) http://www.nps.gov/dscw/publicforms.htm

CUIS 258139 01 26 01 - 5

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.

6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.

8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.

Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10% Profit……………..……10%

2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

CUIS 258139 01 26 01 - 6

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012601

CUIS 258139 01 27 00 - 1

012721 DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. The Work consists of:

1. Contract Line Item Number 01: Preserve and Rehabilitate the Historic Grange (Exterior

Envelope & Structure)

a. This bid item consists of selective demolition pertaining to work in this option.

b. This bid items consists of structural repairs, painting the exterior, rehabilitation of the exterior windows and doors, replacing the roof, roof access and lighting protection system, and replacing the gutters and downspouts.

c. Demolition of exterior and basement plumbing. installation of exterior plumbing:

Installation of exterior sump pump and associated piping, exterior hose bibbs, sump pump in 004 Storage and associated piping, well pressure tank and water treatment system, new DWH, expansion tank, and hot water recirc pump, and all new piping in basement.

d. Electrical connections for the following plumbing equipment: Water heater, 30 GAL, DWH wiring, DS-DWH-1, chemical treatment, hot water recirc pump, sump pump

e. Abatement of asbestos hazardous materials on the interior and exterior of the building.

2. Contract Line Item 02: Mechanical

a. This bid item consists of selective demolition pertaining to work in this option.

b. This bid item consists of demolition of existing unit heaters and baseboard heaters, installation of housekeeping pads, installation of louvers and installation of mechanical system including installation of VRF system (Heat pumps, fan coil units, piping, controls), installation of ductwork and air devices, installation of fans.

c. Includes electrical pertaining to the installation of the HVAC. Site Electrical Utilities: heavy-up of electrical service with utility company: Trench and duct bank

CUIS 258139 01 27 00 - 2

from transformer to service entrance disconnect, Service entrance grounding and bonding. Electrical demolition: Remove Service Entrance Cable, Remove Panelboards, Remove Transfer Switch. New Electrical Service and Distribution: 2P- 400A F/SS Service Entrance Disconnect Switch, Distribution Panelboard, Panelboard RP1, Panelboard RP2, Meter Base, Associated feeders for panelboards.

Electrical Connections for mechanical HVAC: VRF Split System – Heat pump, VRF Split System - Ducted Indoor Unit, VRF Split System - Console Indoor Unit, Fans

– Inline, Fans - Roof Mounted, Motor Operated Dampers, Condensate Pump, GFI WP Receptacle, FCU Manual Switch, Combination motor starter CMS-EF, Exterior disconnect switches, FCU/EF Wiring/Conduit, ACC Wiring

d. Mold remediation on the interior of the building.

3. Contract Line Item 03: Fire Protection

a. This bid item consists of selective demolition pertaining to work in this option.

b. This bid item consists of installing the complete fire suppression system, installation of ump and tank and installation of piping, sprinklers, and accessories.

c. Includes electrical connections for residential fire pump and tank assembly. Fire alarm and intrusion detection system.

d. Includes plumbing connection to the fire suppression system.

4. Contract Line Item 04: Electrical and Telecommunications

a. This bid item consists of selective demolition pertaining to work in this option.

b. This bid item consists of replacing the electrical systems and telecommunication systems throughout and site distribution including lighting and branch wiring, interior luminaire restoration, exterior luminaire restoration, historic luminaire reproduction, wiring devices and branch circuits and communications.

c. Removal of Mercury bulbs on the interior of the building.

5. Contract Line Item 05: Exterior Ramp

a. This bid item consists of selective demolition pertaining to work in this option.

b. This bid item consists of installation of exterior concrete ramp and stairs.

c. Electrical installation of Ufer ground in ADA ramp footing

6. Contract Line Item 06: Kitchen and Baths Interior Finishes

a. This bid item consists of selective demolition pertaining to work in this option.

b. This bid item consists of new basement walls, doors and thresholds pertaining to bathrooms, kitchen and bath casework and accessories, kitchen and bathrooms floor, wall and ceiling finishes, plumbing and fixtures pertaining to the kitchen and bathrooms.

c. Demolition of all plumbing on the First Floor, Second Floor, and Attic. Installation of all new plumbing on the First Floor, Second Floor, and Attic.

d. Lead paint encapsulation on the interior of the building in the kitchen and bathrooms.

7. Contract Line Item 07: General Interior Finishes

a. This bid item consists of selective demolition pertaining to work in this option.

CUIS 258139 01 27 00 - 3

b. This bid item consists of rehabilitation of interior doors and thresholds, repairing and painting the interior, and interior floor, wall and ceiling finishes not previously included. Interior stairs renovation, finish carpentry and signage.

c. Lead paint encapsulation on the interior of the building not previously included.

END OF SECTION 01 27 00

CUIS 258139 01 31 00 - 1

012721 PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination

3. Submittals

4. Coordination Drawings

5. Requests for Information (RFIs)

6. NPS/DSC Project Website

7. Project Meetings

8. Environmental Coordination

9. Permits

B. Related Requirements:

1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.

4. Section 01 91 14 "Total Building Commissioning" for coordinating the work with

Contracting Officer’s Commissioning Authority.

1.2 DEFINITIONS

A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

http://www.nps.gov/dscw/definitionsdc_a.htm http://www.nps.gov/dscw/definitionsdc_c.htm http://www.nps.gov/dscw/definitionsdc_g.htm

CUIS 258139 01 31 00 - 2

3. Make provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:

1. Preparation of Contractor's Construction Schedule

2. Preparation of the Schedule of Values

3. Installation and removal of temporary facilities and controls

4. Delivery and processing of submittals

5. Progress meetings

6. Permit requirements

7. Pre-installation conferences

8. Project closeout activities

1.4 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.

c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.

d. Show location and size of access doors required for access to concealed dampers, valves, and controls.

e. Indicate required installation sequences.

2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 millimeters) but no larger than 30 by 40 inches (750 by 1000 millimeters).

CUIS 258139 01 31 00 - 3

3. Number of Copies: Submit 2 opaque copies of each submittal. Contracting Officer will return one copy.

4. Refer to individual Sections for Coordination Drawing requirements for Work in those Section.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans and Reflected Ceiling Plans: Show architectural, structural, mechanical, plumbing, fire-protection, fire-alarm, and electrical elements. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.

2. Plenum Space: Indicate sub-framing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.

3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.

4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

6. Mechanical and Plumbing Work:

a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.

b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.

c. Fire-rated enclosures around ductwork.

7. Electrical Work:

a. Runs of vertical and horizontal conduit 1-1/4 inches (32 millimeters) in diameter and larger.

b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.

c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.

d. Location of pull boxes and junction boxes, dimensioned from column center lines.

8. Fire-Protection System:

a. Locations of standpipes, mains piping, branch lines, pipe drops, and sprinkler heads.

9. Review: Contracting Officer will review coordination drawings to confirm Work is being coordinated; details of coordination are Contractor's responsibility. If Contracting Officer determines coordination drawings are not prepared in scope or detail, or are otherwise deficient, Contracting Officer will inform Contractor, who shall make changes and resubmit.

CUIS 258139 01 31 00 - 4

10. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."

C. Coordination Digital Data Files: Prepare coordination digital data files according to:

1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.

2. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.

3. Contracting Officer will furnish Contractor one set of digital data files (AutoCad.dwg) of Drawings for use in preparing coordination digital data files.

a. Contracting Officer makes no representations as to accuracy or completeness of digital data files as they relate to Drawings.

b. Digital Data Software Program: Drawings are available in AutoCad.dwg.

D. Division 1 documents: The following items shall be submitted a minimum of one week prior to Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for Pre- Construction Conference.

1. Letter designating Project Superintendent

2. Construction Schedule

3. A Comprehensive Schedule of Values

4. Accident Prevention Plan

5. A List of Subcontractors for this project

6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.

7. Certificates of Insurance or SF1413 for Contactor and all Subcontractors

8. Waste Management Plan

9. Quality Control Plan

10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP)

11. Historic Preservation Treatment Plan (HPTP)

12. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit

b. Agency(ies) with Jurisdiction issuing the permit

c. Information required from Government to complete permit application

E. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Contractor shall prepare and submit an RFI utilizing form created on NPS/DSC management software website.

CUIS 258139 01 31 00 - 5

1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date

3. RFI subject

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract

Time or Contract Sum, Contractor shall state impact in RFI.

8. Contractor's signature

9. Requested date for response

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Form: Complete RFI Form on NPS/DSC Project Website as follows:

1. Enter general information at the top of the form.

2. Under the "Action" section at the bottom of the form, select "Question" then select "CMR" in drop-down of "Send to" box.

3. Enter details of question and attach related documents.

4. Select "Submit Form" at bottom of page.

D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in Contract Documents.

e. Requests for adjustments in Contract Time or Contract Sum.

f. Requests for interpretation of Contracting Officer's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.

3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.

CUIS 258139 01 31 00 - 6

1.6 PROJECT WEB SITE

A. Use NPS/DSC management software website for communication throughout contract period on:

1. Project directory

2. Project correspondence

3. Meeting agendas and minutes

4. Contract modifications forms and logs

5. RFI form and processing

6. Task and issue management

7. Photo documentation

8. Baseline schedule, schedule updates and calendar management

9. Submittal form and processing

10. Payment coordination documentation

11. Drawing and specification document hosting, viewing, and updating

12. Online document collaboration

13. Reminder and tracking functions

14. Archiving functions

15. Notification of submittal and RFI statuses and current responsible party

16. Permits and addendums

B. Some documents are not suitable to be shared using the NPS/DSC management software website.

Documents containing…

This is the start of the file's text. The full file is on GovTribe.