This document is a set of Questions and Responses related to a federal contract opportunity to Preserve and Rehabilitate the Historic Grange at Cumberland Island National Seashore in North Carolina. The contract requires the rehabilitation of the exterior envelope and structure of the Grange, including work on the windows, doors, roofing, and other building systems. Key details include:
The National Park Service will provide emergency medical services and first aid on the island, as well as transportation for medical emergencies. The contractor will be allowed to use the island's utilities, including water and power, subject to certain restrictions. The contractor may use the island's ramps and docks, but cannot leave vehicles or boats overnight. The contractor must follow protocols for abatement of lead-based paint and asbestos-containing materials. There are specific requirements for the rehabilitation of the historic windows, including treatment of lead components and asbestos glazing. The contract has a period of performance of 365 days from the notice to proceed.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RESPONSE
Are paramedic/first aid personnel stationed on the Island? NPS staff are on island most days and have First Aid training. Law Enforcement LE are EMS. 911 dispatches
NPS EMS and CCSO
Will the NPS provide emergency evacuation transportation off the Island for medical emergencies?
911 Dispatches NPS EMS and CCSO for medical emergencies and coordinates transportation off island.
Will the NPS provide transportation for the removal of trash and debris?
Construction waste is inidcated in 01 74 19 – CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
Are there restroom facilities available on the Island for contractor’s use? Bathrooms available within approximately 100 yards.
Contractor is allowed temporary facilities on‐site in SECTION 01 50 00 ‐ TEMPORARY FACILITIES AND
CONTROLS.
Will water at the project site be available for contractor’ use? Does it require separate metering?
Use of utilities and metering is indicated in SECTION 01 50 00 ‐ TEMPORARY FACILITIES AND CONTROLS.
Water is available on island and there are no meters. It is a potable well water system that cannot be used for construction purposes in large quantity. Recharge unknown if excessive water used. Contractor should be responsible for significant quantities if needed.
Can temporary power be obtained from the existing service? Does it require separate metering? Use of utilities and metering is indicated in SECTION 01 50 00 ‐ TEMPORARY FACILITIES AND CONTROLS. The work site has power.
Specialty wash stations for certain workers will be required. Where can these wash stations be located within the project site?
Construction limit lines are indicated on Sheet AS1.1. Contractor's use of the site is indicated in SECTION 01 11 00 ‐ SUMMARY OF WORK. Confirm exact locations of wash stations with C.O. during construction.
8 Are there any contaminated water (lead, asbestos, etc) waste disposal stations in the local area? Contractor means and methods.
Are there opportunities for personnel to “camp” overnight on the Island?
Construction camp uses is indicated in the SECTION 01 11 00 ‐ SUMMARY OF WORK.
Can the contractor utilize any of the multiple “ramps” on the Island for heavy equipment/material delivery?
Contractor may use the ramp at Dungeness for equipment and materials delivery. The ramp is tide dependent. Discretion must be used for deliveries around the public see specification: 01 31 00
Can a barge be moored/spudded near the Island for extended periods of time? Limitations on time and location? Previous contractors have moored/spudded a barge150‐200 Yrads off from Raccoon Keys. It is within our jursidictional boundary.
Will the NPS provide docking space for contractor’s watercraft at St. Mary’s waterfront and/or Cumberland Island waterfront? Dock space at Saint Mary's waterfront is only available at the public docks and is on a first come first serve basis. The National Park Service has public dock space available at Dungeness abd Sea Camp. First come first serve. No overnight docking. No boats over 25'.
What contractor vehicles will be permitted on site? Can contractor’s vehicles be left on the Island during non‐working days? i.e. Holidays and weekends? Contractor may use automobiles or Utility Terrain Vehicles (UTV) 4x4 highly recommended. Contractor will be permitted to leave vehicles on the island for the duration of the project. Parking at Captains house parking area or Staging area.
14 Can extended/adjusted work times be allowed due to tide schedules? Refer to specifications: 01 11 00
What are the requirements for contractor’s equipment removal in case of hurricane evacuation? While it is impracticle to require contractor to completely demobilize equipment during a hurricane evacuation, contractor assumes all risk of damage associated with leaving equipment on island during a weather event. Anticipated performance period is outside of typical Hurricane Season. Worksite should be secured by contractor.
16 Is there a Historic Structure Report or Condition Assessment Report available for the building? See attached report: "CUIS The Grange HSR Full Report 2014"
Some of the wallpaper surfaces tested positive for lead paint (on the substrate) and mold. Is it anticipated that the papers will be cleaned to remove the mold and left intact to encapsulate the LBP wherever present?
Yes, the intent is to clean and preserve the wallpaper and not impact the lead‐based paint. Surficial cleaning is indicated in SECTION 02 87 13 ‐ MOLD REMEDIATION
1 The Contract Price Schedule CLINs do not match the CLINs denoted in the Summary of Work See attached "Updated Contract Price Schedule" 2 Will the Rehabilitation of Windows be a Bid Option? SECTION 01 11 00 ‐ SUMMARY OF WORK indicates the work to be done as base bid
General Notes for both Level 1 and Level 2 Historic Window Rehabilitation sections list "Remove existing window assembly from existing opening". Does this note intend for contractor to completely remove entire window frame including trim/casing/stools/sills or is this note intended to communicate removal of window sash/parting bead/interior stop only? It is recommended to leave frame/interior trim components in place for rehabilitation and remove only sash/interior stop/parting bead for proper rehabilitation. Please clarify.
The intent is to retain as much of the historic fabric as possible in‐place. SECTION 08 03 52 ‐ HISTORIC TREATMENT OF WOOD WINDOWS AND DOORS defines sequencing and scheduling of historic treatment of wood windows.
Please confirm if intent is that all window sash are to be completely deglazed/reglazed. Per Note 9. under Spec Section 08 03 52 ‐ 2 Historic Treatment of Wood Windows and Doors ‐ 1.5 ‐ Sequencing and Scheduling, it is noted to "replace all glazing sealants". Per plans, Hazardous Material keynotes H‐3 and H‐6 indicate all windows are indicated to contain ACM. When referencing General notes on A8.3 ‐ Level 1 Rehabilitation does not indicate required abatement or removal of ACM glaze putty however, Level 2 does indicate full abatement of ACM putty.
This indicates 12 openings to have ACM glaze putty removed. Further, Under Spec section 02 82 00, Remediation 1.2 Description of Work B states “the intent of the Work is to remove limited quantities of identified ACM from the site as detailed herein….The SOW includes removal of ACM from the listed locations”, when referencing Line 7, it states “Exterior window glazing from approximately 42 windows. Additional window abatement may be performed as a bid option. When assessing both plans and specs, it is difficult to price according to conflicting documents.
Please provide further clarity to ensure equitable pricing in the bidding process:
Simply put:
a. Per Hazardous material plan designations, all 79 openings are indicated to contain ACM glaze putty.
b. Per remediation specs, only 42 openings should be priced for ACM glaze putty removal.
c. Per historic rehabilitation spec section, all window sash should be priced to have glaze putty fully removed and reapplied
d. Per plan notes referencing rehabilitation levels on window schedules, only 12 windows should receive ACM putty remova
e. Per Historic Window Rehabilitation Levels referenced, only Level 2 should have ACM glaze putty removed
Please confirm all openings on 18.3 that do not have “Replace window screen” noted, have existing screens to be repaired. Sheet A8.3 indicates all window screen work included in this project. Add to Sheet A8.3 window schedule comments "REPLACE WINDOW SCREEN" for windows 006, 011 and 045.
CUIS 258139 ‐ Preserve and Rehabilitate the Historic Grange
Abatement:
a. There are 64 windows listed for rehabilitation. B. Price 64 windows. Update to Sheet A8.3 General Notes HISTORIC WINDOW REHABILITATION ‐ LEVEL 1 add note to state "ENCAPSULATE, STABILIZE, OR ABATE LEAD WINDOW COMPONENTS AND EXTERIOR ASBESTOS WINDOW GLAZING" and update SECTION 02 82 00 ‐ ASBESTOS REMEDIATION 1.2.B.7 from 46 windows to 64 windows. C. Correct. D. Price 64 windows. E. Price 64 windows.
For the Historic Windows:
Bid Documents:
General:
QUESTIONS
Please provide clarity on storm window requirements, locations and basis of design to price. Storm windows are referenced 3 times in Spec Section 08 03 52 ‐ 2 Historic Treatement of Wood Windows and Doors but no location or other details are provided on elevations, window schedules or elsewhere. There are no storm windows in this project. Remove the words "storm window" from SECTION 08 03 52 ‐
HISTORIC TREATMENT OF WOOD WINDOWS AND DOORS 1.2.C. Remove 1.6.C and 2.8.C referencing storm windows from SECTION 08 03 52 ‐ HISTORIC TREATMENT OF WOOD WINDOWS AND DOORS.
Under Section 01 11 00 – 1 “Summary of Work”. 1.2 Work Covered by Contract Documents 1. Contract Line Item #01: Preserve and Rehabilitate the Historic Grange (Exterior Envelope & Structure) specifies intent is to achieve “the rehabilitation of the exterior of the windows and doors”. As other spec sections and plan notes infer, it appears the intent is for window and doors to be removed and rehabilitated; a plausible interpretation for pricing efforts is that only the exterior rehabilitation of these elements should be priced, and subsequent Contract Line Items indicate further interior work may be added separately. Pricing to only address exterior work with potential to add interior work as an option when dealing with removable elements will result in pricing inequity in the bidding process. Please confirm contractor should plan and price to rehabilitate both the interior and exterior surfaces of windows and doors to be removed consistent with Rehabilitation Classes listed on A8.3.
The intent is for the entire window/door to be rehabilitated
6 Is design intent to replace and replicate all windowsills and exterior/interior window casings/trim. ? Drawings indicate rehabilitation of windows.
i. Plan notes on A8.3 indicate removal and rehabilitation of “Window Assembly”, under Section 08 03 52 – Historic Treatment of Wood Windows and Doors 1.2 Definitions D. Wood Window and Door Component Terminology indicates under Definition D. Sills/exterior casing/casing/stool/ aprons/etc to receive historic treatment work. However, under Section Finish Carpentry 06 20 00 – 2.1 Finish Carpentry Items B. Exterior Woodwork Item lists 1. “Window Casing and Molding: Softwood; prepare for paint finish and under C. lists 1. Moldings, bases, casings and Misc. Trim: Match Existing and 3. Window Sills: Clear fir; prepare for transparent finish.
This is not a question. Please clarify.
Under Section 09 90 00 “Painting and Coating” Part 3 – Execution 3.1 Historic Treatment Procedures K. Wood Surfaces to be Painted: 2. Existing Wood states “Remove loose, flaking or failing paint to well adhered material however, under Section 08 03 52 – Historic Treatment of Wood Windows and Doors 1.5. Sequencing and Scheduling Item 7. General Wood‐Repair Sequence a.
Remove paint to bare wood, is noted. Should window elements have paint removed to bare wood or to sound substrate?
SECTION 08 03 52 ‐ HISTORIC TREATMENT OF WOOD WINDOWS AND DOORS indicates wood repair sequence when the wood needs to be repaired. 09 90 00 ‐ 7 PAINTING AND COATING indicates wood to be painted that does not need to be repaired.
Window Schedule on A8.3 indicates Frames are to be painted but no indication of sashes. Please provide clarity for paint system and means and methods desired to price for interior/exterior coating of window sashes to be rehabilitated. Under Section 09 90 00 “Painting and Coating”, multiple coating systems are listed for wood substrates for both exterior and interior, however, no specificity is given around window sash and window frames.
SECTION 06 20 00 ‐ FINISH CARPENTRY defines interior and exterior woodwork items and finish.
Please confirm window contractor may price and provide temporary protection per their standard means and methods, otherwise, please provide exact detail required by NPS for this project to ensure accurate pricing. Contractor means and methods.
Please provide clarification around material type/profiles of existing window weatherstripping. If no detail/material type is known, please provide linear foot quantity and basis material of design/manufacturer to allow for pricing an assumption. SECTION 08 03 52 HISTORIC TREATMENT OF WOOD WINDOWS AND DOORS indicates compression‐type weather stripping which includes vinyl, plastics, and silicone materials. Weatherstripping color to coordinate with window color. Drawings indicate window and door dimensions to price quantities.
Please clarify Historic Window Rehabilitation Note 1. It includes "ABATE LEAD WINDOW COMPONENTS" which seems to be contradictory to ‐"PREPARE EXISTING SURFACES FOR REPAINTING INCLUDING BUT NOT LIMITED TO, SCRAPING LOOSE/FLAKING PAINT AND SANDING." It is not the intent of this project to fully abate lead. Treatment of impacted window components shall comply with regulatory requirements to protect workers and minimize generation of lead dust while ensuring completion of rehabilitation scope requirements. Update to Sheet A8.3 General Notes HISTORIC WINDOW REHABILITATION ‐ LEVEL 1 to state "ENCAPSULATE, STABILIZE, OR ABATE LEAD WINDOW COMPONENTS AND EXTERIOR ASBESTOS WINDOW GLAZING" and General Notes HISTORIC WINDOW REHABILITATION ‐ LEVEL 2 to state "ENCAPSULATE, STABLIZE, OR ABATE LEAD WINDOW COMPONENTS
AND ABATE EXTERIOR ASBOESTOS WINDOW GLAZING."
13 please clarify, should Level 1 rehabilitations be only scraped and sanded or be completely stripped? Contractor means and methods.
In the context of this note on page 6 of the Hazmat report: "The window glazing is considered a Category II non‐friable material. Category II non‐friable materials are regulated if they have a high probability of becoming or have become crumbled, pulverized, or reduced to powder by the forces expected to impact the materials during the course of demolition activities. These materials must be removed by a licensed asbestos abatement contractor prior to disturbance."
This is not a question.
If we strip or scrape and sand lead paint on top of ACM Glazing will it render the glazing category I rather than Category II?
See responses above. All windows will require abatement of exterior, asbestos‐containing glazing.
If glazing is identified as Category II prior to any sash work commencing, is it acceptable to transport sash to a workshop off site and commence restoration work there? If acceptable, abatement licensing, regulations and requirements in the location of the work will prevail?
Contractor means and methods however all regulatory requirements for asbestos abatement, handling, transport, and disposal must be complied with.
When windows and doors are removed, does NPS have a minimum requirement for temporary protection? e.g. is plywood required or is plastic sheathing acceptable? Is natural light required? Contractor means and methods.
Some of the windows are very close to floor level. Does any of the glass need to be replaced with safety/tempered glass? If so, please provide glass specification and a schedule identifying where it is to be installed. No. Drawings and Specs do not indicate safety/tempered glass.
The window schedule A8.3 notes different levels of treatment for window assemblies. Please define components included in this scope of work and required levels of restoration e.g. sash, interior casing, stool, apron, head, jamb, brick mold, etc. SECTION 08 03 52 ‐ HISTORIC TREATMENT OF WOOD WINDOWS AND DOORS defines parts of a window.
SECTION 06 20 00 ‐ FINISH CARPENTRY defines interior and exterior woodwork items and finish.
Are windows required to be operational? Should we include an allowance for any replacement hardware or counterbalance systems?
SECTION 08 03 52 ‐ HISTORIC TREATMENT OF WOOD WINDOWS AND DOORS indicates operating hardware.
21 Are we hand loading the shingles from the boat to the job site or will there be equipment like a truck, atv or front loader to get the shingles to the site? Contractor means and methods.
How much are extra trips on the boat? SECTION 01 31 00 ‐ PROJECT MANAGEMENT AND COORDINATION indicates Contractor is responsible for own boat and transportation of crew daily and materials/equipment required to complete the work.
Are we disposing of the roof or asbestos?
Disposal of construction waste is by contractor. Refer to 02 82 33 REMOVAL AND DISPOSAL OF ASBESTOS‐ CONTAINING MATERIALS and 01 74 19 – CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
24 Will there be dumpsters or how do we coordinate bringing dumpsters? Contractor means and methods.
25 What kind of material are we using for the flat roof? Roof materials are indicated in the drawings and specifications.
Are we re‐wiring the entire house all new or are we just replacing devices with new devices(receptacles, switches etc.) Note 2 on the electrical demolition sheets indicate to remove all wiring back to source where there are new devices.
From what I can tell we are reusing the lights in place now for the most part. It specifies for us to take them down and secure them in a safe location to keep from damage so my question is will there be some type of storage unit for us to put them in? Division 1 specifications cover storage of materials.
If we are or do have to get inside of a wall what steps do we need to take to keep it historic and or who would be responsible for repairing the wall? Plaster repair detail is provided in the drawings. Responsibility of cutting and patching is indicated in
SECTION 01 40 00 ‐ QUALITY REQUIREMENTS
29 Is the Lead Based Paint (LBP) on Doors, Windows and Sashes being removed on site or off site? Contractor means and methods, comply with regulatory requirements.
30 If shipping Windows, with Lead Paint and Asbestos, what will be the protocol for handling and abatement for shipment? Contractor means and methods, comply with regulatory requirements.
There is no site specific identifying the Lead Paint, i.e. Stairwells and Railings, Windows, Inside and Outside Doors, Waynes Coat, Cabinetry throughout, Fireplaces with Ornate Work, Shoe Mold, Ceiling Mold and Chair Rails. Correct. Lead‐based paint readings and locations are detailed in the hazardous materials report.
32 Will there be power on property for Abatement Equipment? Park: Power at worksite 33 How many layers of Flat Roofing is to be removed? Drawings indicate removal of flat roof material down to substrate.
In the photos provided, the Asbestos Duct Wrap in basement was not visible on the site visit 8/13/24. Is there a Crawl Space that we were not made aware of? Photos and location of the duct wrap are provided in the hazardous material report, it is not in a crawl space.
Visible Microbial Growth on Wallpaper throughout the home, if the protocol required does not clean the Microbial Growth off the Wallpaper, do we remove the Wallpaper and what steps do we take? SECTION 02 87 13 ‐ MOLD REMEDIATION and drawings indicated mold remediation procedures.
36 Bathroom doors with Glass, throughout the home: Is the glass to be treated as Asbestos and Lead? No.
Current flow test results are needed to size piping and verify that a fire pump will or will not be necessary. Can you provide flow test results from the nearest water supply main (must be less than 12 months old)?
See spec section 21 31 13 Residential Pump and Tank Systems. This is a NFPA 13D system. The fire protection drawings show the tank.
Can we put a pump and water storage tank if no water supply is available?
Park: Water is available on island and there are no meters. It is a potable well water system that cannot be used for construction purposes in large quantity. Recharge unknown if excessive water used. Contractor should be responsible for significant quantities if needed within staging area.
39 Appears all piping will be exposed, correct? Exposed and concealed pipes are indicated in the drawings.
40 Appears all fire alarm system wiring will be exposed, correct? Exposed and concealed wiring are indicated in the drawings.
1 Do all door openings need to be brought up to compliance with ADA? Drawings indicate ABA compliance
Spec calls for new trim to match the original species of wood. All wood is painted and species cannot be determined by visual inspection. What is the species of wood for existing trim?
The wood species is unknown to the AE team.
3 Specification only calls for mold resistant drywall. This type of drywall is typically only used in bathrooms/ areas subject to moisture. Confirm use of green/purple board throughout. Confirmed.
Due to the windows panes needing removal for proper abatement & restoration purposes, should all glass below 18" be replaced with tempered and/or laminated units upon restoration to comply with current safety codes? No. Drawings and Specs do not indicate safety/tempered glass.
Due to hazardous materials present on current walls & ceilings per the hazardous material survey, should all ceilings be abated to accommodate the removal of existing utilities and plumbing?
This will also allow access for installation of the new fire suppression system, electrical, mechanical, plumbing & communications network. In addition, full abatement of the ceilings will provide the opportunity to achieve the highest possible quality finished product on restored areas for the customer.
Abate ceilings indicated in the hazmat drawings. Updated Hazmat Sheet H1.2 to show the dining room asbestos‐containing ceiling texture finish. Updated Sheet AD1.2 to show Note 9.6 "REMOVE EXISTING TEXTURED CEILING GYPSUM BOARD. REFER TO SPEC SECTION 02 82 00" in Dining Room. Updated Sheet A2.1 updated to show new ceiling in dining room. Update SECTION 02 82 00 ‐ ASBESTOS REMEDIATION 1.2.B.1 "Approximately 4,000 SF of textured ceiling finish from rooms E102 (Living Room), E104 (Sunroom), E101 (Main Hall), E105 (Dining Room), E206 (Guest Room), E207 (Guest Room), E202 (Primary Bedroom), E210 (Guest Bathroom), E201 (Hall), and E302 (Bedroom).
6 How many vehicles are allowed to be supplied by the contractor for access to and from site/dock for daily employee commute? 4
Section 01 11 00 Outlines work hours, restrictions, and required supervision on behalf of the contractor. It does not cover supervision required to be onsite on behalf of the government for work to commence. Will the government require their own representative to be present for work to commence? No, the government not require their own representative to be present for work to commence.
During the site visit, it was observed that it is roughly .5‐.75 miles from the dock to the project site. Please advise of any regulation not stated in the RFP or specifications for transporting fuels from the dock to the project location. Transport must comply with State and Federal Laws.
9 Please advise of any regulation not stated in the RFP or specifications as to allowable fuel tank size and fuel amounts allowed to be stored on site by the contractor. Storage must comply with State and Federal Laws.
Please advise ifthere is a designated area that the contractor will be required to store fuel tanks.
Construction limit lines are indicated on Sheet AS1.1. Contractor's use of the site is indicated in SECTION 01 11 00 ‐ SUMMARY OF WORK. Confirm exact locations of fuel storage with C.O. during construction.
The solicitation provides a period of performance of 365 days from receiving the NTP to complete the project. Please advise if this also includes bid option l (window abatement and refurbishment) or if additional time will be given to complete that scope of work if it is awarded.
SECTION 01 11 00 ‐ SUMMARY OF WORK states Project will be constructed under a single prime contract in the period of performance indicated.
Please advise if the hygienist and competent persons required for abatement/remediation work can be an employee of the abatement contractor pending the employee holding all required certifications, or if this person is required to be a 3rd party contractor contracted by the abatement contractor. IH shall be a third‐party and independent of the abatement contractor.
During the site visit it was mentioned that NPS would be responsible for trimming back the trees limbs that are currently rubbing against the roof at The Grange. Please confirm that this is accurate. This will be required in order to receive the full roof warranty. Confirmed.
Port‐a‐lets will be needed for all on site workers for the duration of this project. Please advise if there are any special regulations for cleaning/servicing of the port‐a‐lets and what is the best method for having this done. Should these be put on a trailer and transported to the dock for service. or is there a pump out station on the island?
Bathrooms available within approximately 100 yards. Contractor required to service and maintain port‐a‐let brought to island. No pump out station on island.
Contractor is allowed temporary facilities on‐site in SECTION 01 50 00 ‐ TEMPORARY FACILITIES AND
CONTROLS.
In the summary of work, interior demo for each contract line item is listed as "selective". Please advise if it is the intent of the project to demo as little as possible (walls, ceilings, etc.), or should these areas be completely Demo'd in order for the specified location to have a matching finish (i.e. one full wall of a room, entire ceilings space of a room, etc.) instead of applying a patch to an area that received selective demo?
Drawings indicate level of demolition and repair. The intent is to retain as much of the historic fabric as possible.
Please advise if contractor will be awarded additional time for days lost due to weather (i.e. rain, lightening, etc.). SECTION 01 32 16 – CONSTRUCTION SCHEDULE indicates what is included and accounted for such as weather in a construction schedule.
In relation to the question listed above, will it be considered a non‐work weather day if marine conditions do not allow for the safe transport of materials and personnel to the project site? SECTION 01 32 16 – CONSTRUCTION SCHEDULE indicates what is included and accounted for such as weather in a construction schedule.
Notes N3, N7, N8, and N9 reference existing termite damage to the building. Has the building been treated for termites since the damage was discovered? Is the contractor responsible for treating the building for termites? Is the contractor responsible for providing a termite bond? Unknown. Park would like to see cost options included. Defer to DSC for contract compatability.
Note N9 states to provide and allowance for stringer reinforcement. For apples to apples bidding purposes, is there a set amount the contractor should account for?
Update to Sheet S1.1 Note N9 to state "REMOVE MOLDING AT EXISTING STAIR STRINGER FOR INSPECTION OF TERMITE DAMAGE. ASSUME STRINGER REPLACEMENT FOR PRICING. NOTIFY C.O. FOR EXAMINATION
AFTER REMOVAL OF MOLDING TO DETERMINE IF STRINGER REINFORCEMENT IS FEASIBLE OR
REPLACEMENT IS REQUIRED. TREATMENT DETERMINED BY C.O."
20 Has the building been fully inspected for termites? ls the extent of the damage known? Unknown.