B08_Attachment_1_140P8423R0005_Specifications.pdf

PDF 4 MB Posted

Attached to
North Junction Rehabilitation, NPS-CRLA
Solicitation number
140P8423R0005
Issued by

About this file

This solicitation package requests proposals for rehabilitation of visitor facilities at North Junction Viewpoint in Crater Lake National Park, Oregon. Key details include:

  • The work includes site rehabilitation and improvements to create accessible pathways and overlooks, install signage and fencing, and construct a precast concrete vault toilet.

  • A mandatory site visit will be held on May 10, 2023 at 11:00 AM Pacific Time. Offerors must RSVP to the point of contact.

  • The full solicitation and attachments are available for download. Questions must be submitted in writing by the deadline.

  • Proposals are due by June 15, 2023. The period of performance is from June 1, 2020 to September 15, 2020, weather permitting.

  • The National Park Service Pacific West Region is the contracting agency. Work will be performed at Crater Lake National Park in Klamath County, Oregon.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CRATER LAKE NATIONAL PARK

REHABILITATE VISITOR FACILITIES AT NORTH

JUNCTION VIEWPOINT FOR SAFETY AND

RESOURCE PROTECTION

CRLA PMIS 309838_229427

FINAL

CONSTRUCTION DOCUMENTS

NATIONAL PARK SERVICE

PACIFIC WEST REGION

CRLA - 229427 TABLE OF CONTENTS - 1

TABLE OF CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 11 40 Work Restrictions 01 27 00 Definition of Contract Price Items 01 31 00 Project Management & Coordination 01 31 00A RFI Form 01 32 16 Construction Schedule 01 33 23 Submittal Procedures 01 33 23A CM-16 Submittal Form 01 35 23 Safety Requirements 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 50 00 Temporary Facilities & Controls 01 56 00 Temporary Barriers 01 57 23 Temporary Storm Water Pollution Prevention 01 57 23A UPPP Guideline 01 73 40 Execution 01 74 19 Construction Waste Management & Disposal 01 77 00 Closeout Procedures Appendix A Submittal List Appendix B List of Closeout Requirements Appendix C NAISMA Weed Free Standards

DIVISION 02 – EXISTING CONDITIONS

02 05 00 General Site Construction Requirements 02 41 00 Demolition & Abandonment

DIVISION 03 – CONCRETE

03 31 00 Normal Weight Structural Concrete 03 48 00 Precast Vault Toilet

DIVISION 04 – MASONRY

04 20 00 Unit Masonry 04 43 00 Stone Masonry Rock

DIVISION 06 – WOOD, PLASTICS & COMPONENTS

06 10 00 Rough Carpentry 06 16 00 Sheathing

DIVISION 07 – THERMAL & MOISTURE PROTECTION

07 31 29 Wood Shingles and Shakes 07 62 00 Sheet Metal Flashing

CRLA - 229427 TABLE OF CONTENTS - 2

DIVISION 09 – FINISHES

09 90 00 Painting

DIVISION 10 – SPECIALTIES

10 14 00 Signage 10 14 01 Crater Lake Bronze Tactile Map Structure

DIVISION 31 – EARTHWORK

31 05 16 Aggregates for Earthwork 31 10 00 Site Clearing & Grading 31 23 00 General Excavation & Fill 31 23 33.10 Restoration of Surfaces 31 25 00 Soil Erosion & Sedimentation Control 31 25 00.10 Watering

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 12 16 Asphalt Paving 32 14 40 Stone Paving 32 16 19 Curbs, Gutters, and Sidewalks

END OF SECTION

DIVISION 01

GENERAL REQUIREMENTS

CRLA - 229427 01 11 00 - 1

SUMMARY OF WORK

SECTION 01 11 00

PART 1 – GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Crater Lake National Park, Oregon.

B. The work covered by this project was originally developed as three separate projects.

Accordingly, there are three separate plan sets that were each developed at different times. Due to funding considerations these three projects are combined as one construction project. While the plan sets are provided separately, the project specifications have been combined into a single document to eliminate duplications. The contractor shall become familiar with all three plan sets and coordinate construction activities for all work simultaneously.

C. The Work includes the following:

Plant Set Part 1

The Work includes rehabilitating and improving two existing overlooks at the crater rim. This work will include constructing new pavements to reduce erosion, correcting site deficiencies, and adding new architectural features to enhance aesthetics and improve visitor experience.

Plan Set Part 2

The Work includes construction of a new accessible trail and overlook. The new trail will extend from the west end of the existing Merriam Point Overlook parking lot south, approximately 140 feet, to a new accessible overlook near the crater rim. This work will include the completion of existing parking lot and sidewalk modifications, excavation and grading for the proposed trail and overlook improvements, installation of a new asphalt surfaced accessible trail and overlook and installation of fencing and visitor amenities in accordance with the project plans. Finally, a new bronze tactile map will be placed near the overlook.

Plan Set Part 3

The work includes a new precast concrete vault toilet near the overlook entrance. The vault toilet will include architectural enhancements corresponding to the park’s architectural standards.

1.2 GOVERNMENT-FURNISHED ITEMS

A. The Government may furnish products and materials for incorporation into the work.

1. The government will arrange and pay for delivery of government furnished items to the project site based on the contractor’s approved construction schedule.

CRLA - 229427 01 11 00 - 2

2. After delivery, the government will inspect delivered items for damage. If items are damaged, defective, or missing, the government will arrange for replacement.

3. The contractor is responsible for receiving, unloading, and handling government furnished items at project site for use in the work.

4. The contractor is responsible for protecting government furnished items during storage, handling, and the work, including damage from exposure to the elements.

5. If government furnished items are damaged as a result of the contractor’s operations, the contractor shall repair or replace the items in-kind.

B. Government-Furnished Items: The government will furnish the following products or materials for use on the contract:

1. Bronze Tactile Relief Map and Structural Base – The Bronze Tactile Relief Map and

Structural Base shall be installed as part of the Accessible Overlook (Plan Set Part 2).

Both items are currently in storage at the park.

1.3 PUBLIC USE OF SITE

A. General: The project site will be closed to the public during construction. The contractor shall at all times conduct his operations to ensure the least inconvenience to the public.

1.4 CONTRACTOR USE OF SITE

A. General: Limit use of the site during the construction period to the project area limits as outlined on the project plans. Do not disturb portions of the site beyond the project area limits.

B. Site Access: The contractor shall access the project site as outlined on the project plans. Do not drive vehicles off pavement or access non-project areas without permission from the contracting officer.

C. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.

D. Working Hours: Regular work hours shall be limited to daylight hours from 7:00 a.m. until

5:00 p.m. Monday through Friday, excluding government holidays. Work outside regular hours requires approval from the contracting officer.

E. Construction Season: June 1, 2020 – September 15, 2020 as weather and snow conditions permit.

F. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings, buildings under construction, and buildings under renovation. Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.

CRLA - 229427 01 11 00 - 3

G. Staging and Storage: Confine storage of equipment and materials to the paved staging / lay-down / storage areas identified on the project plans or as established at the preconstruction meeting.

H. Parking: The contractor shall park vehicles and heavy equipment in designated areas for contractor use or as established at the preconstruction meeting. Vehicles are not permitted within long-term or overnight parking along roads or in associated overlooks / pull-outs.

I. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.

J. Preservation of Natural Features: Prevent damage to natural surroundings. Restored damaged areas and replace damaged trees, vegetation, and grass at no expense to the government.

K. Refer also to Section 01 11 40 Work Restrictions and Section 01 50 00 Temporary Facilities

& Controls.

PART 2 – PRODUCTS (not used)

PART 3 – EXECUTION (not used)

CRLA - 229427 01 11 40 - 1

WORK RESTRICTIONS

SECTION 01 11 40

1.1 PARK REGULATIONS

A. General: The Contractor must comply with the following rules and conditions:

1. Ensure personnel (contractors or subcontractors) working in the park become familiar with and obey all park regulations, wear hard hats in designated areas, and do not enter any restricted areas unless required to do so and until cleared for such entry.

2. Ensure equipment is conspicuously marked for identification.

3. The Contractor shall restrict employees / representatives to the work site and control travel directly to and from the work site.

4. Restore all traffic / parking / security signs and markings, including space numbers, designations, and lines, to their original form if such signs / markings are defaced or deleted during construction / repair.

5. Control and provide security of Contractor-owned equipment and materials at the work site. Report immediately missing / lost / stolen property.

6. Vehicles / Heavy Equipment:

a. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings.

Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.

b. Vehicle Parking: Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts. Vehicles and heavy equipment will be permitted at designated parking areas only.

c. Vehicle Exhaust: All vehicles will be properly maintained to insure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.

d. Spills: Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. Contractor must immediately notify the Contracting Officer of spills.

CRLA - 229427 01 11 40 - 2

e. Commercial Vehicle Safety Inspections: The Contractor, employees, contractors, and subcontractors shall fully cooperate regarding safety inspections of commercial vehicles within the Park. Commercial vehicle safety inspections are conducted unannounced for employee and visitor safety. Vehicles are checked for safety and mechanical deficiencies and for compliance with current state and federal laws and regulations. Driver licenses and medical certificates are also checked.

f. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.

g. Slow Vehicles: The Contractor is to notify the Contracting Officer of slow vehicles that may cause traffic delays or extended traffic lines so that traffic impacts can be reviewed and planned for accordingly.

h. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road). Oversized vehicles must not exceed the clearances along the Park road corridor. Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The Contractor is to notify the Contracting Officer of oversized vehicles, scheduled dates and estimated arrival times at the park entrance, and the identity of who is escorting the vehicle (e.g., police, contractor, etc.). Vehicles that are oversized are requested to enter the Park AFTER 2:00 p.m.

and exit the Park BEFORE sunset.

i. Road Work: Contractor shall provide adequate traffic control, including flaggers on either side of any work performed on the road. Any workers on or near the road must wear highly visible, bright clothing. (See Section 01 50 00 for additional details).

j. Law Enforcement: Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity. Contractor must immediately comply with any instructions issued by a park law enforcement ranger.

k. Road & Weight Restrictions: All vehicle load, weight and size limitations, as established by State law, apply to vehicles operated on the County roads (36 CFR § 4.11). No loads heavier than the current load rating for County roads will be permitted.

7. Emergency Medical and Accident Reporting:

a. The Contractor or subcontractor shall contact Park Headquarters for any medical emergency or traffic accident occurring within the Park.

Emergency number: Dial 911 as needed.

b. The Contractor or subcontractor is required to report ANY personal injury and / or property damage incident occurring within the park. This report must be made to a Law Enforcement Ranger at the first available opportunity before leaving the park:

CRLA - 229427 01 11 40 - 3

1.2 RESOURCE PROTECTION

A. General: The park is committed to protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:

1. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the park.

All Contractor located fill material (gravel, sand, aggregate, rock etc.) for this project shall be free of weeds as listed on Crater Lake’s “Watch List” in Table 1 attached to the end of this document. Materials obtained from outside sources shall be newly mined from locations in the source pit that have the least potential to harbor weed seed or propagules. If the source pit has not been recently mined, the over burden will be removed to a minimum depth of 3 feet and only the newly mined material will be removed and used for this project. Material will not be sourced from stockpiles of materials.

Fill material used in projects on NPS lands must be inspected for presence of invasive plants. Certified weed free materials though existing state and national certification processes are generally not applicable because the Crater Lake list includes a number of species that are not on most state lists. However, sites with weed-free certifications from our certifying agencies will likely be acceptable, and sourcing from these sites is encouraged.

An onsite inspection must be conducted at the site of origin for the fill material by the Contractor, NPS personnel, or an inspector from a certifying agency. Therefore, one of the following options for inspection will be chosen by the NPS for the project:

Option 1 – The Contractor is responsible for onsite inspection of fill materials for invasive weeds according to the State’s noxious weed list and/or a specific weed list provided by the NPS. Contractor-provided expertise and methods to establish weed-free status must be appropriate for weeds of concern in the local area. Inspections shall be in accordance with the following North American Invasive Species Management Association (NAISMA) standards as follows:

• The pit owner/operator meets with Inspector at the gravel/borrow pit site for first inspection.

• The entire border shall be walked or driven.

• All storage areas, gravel/sand piles shall also be inspected and meet the standards.

• Area around all equipment, crushers, and working areas must be inspected to meet the standards.

CRLA - 229427 01 11 40 - 4

• Areas shall be inspected annually with a minimum of one inspection in the growing season.

• An inspector will follow all safety protocols set forth by the owner/operator while on site.

• An inspector may not inspect a material site of which said inspector has ownership or financial interest.

• Responsible party will control prohibited weeds within the entire area of property, this includes stockpiles regardless of origin, parking area and driving area.

Option 2 – The NPS is responsible for approval of fill material sources based on inspection of proposed sources by a NPS invasive species coordinator or other qualified specialist (botanist, range specialist, etc.) to determine weed-free status.

Materials found to contain prohibited plants will be rejected. The contractor shall then either a) find an alternate source or b) modify means and methods to collect material from a different part of the pit, c) process the material to remove weeds, d) propose other methods that are acceptable to the NPS.

The contractor is required to thoroughly clean all vehicles, equipment, tools, supplies, and materials prior to entering the park. The park requires, and will perform, inspections to ensure non-transport of non-native species PRIOR to arriving at the park entrance.

Contact the Contracting Officer or their representative at least (3) three days in advance of park entry to arrange for inspection(s) at the loading dock or point of origin. There shall be absolutely no mud, dirt, soil, organic debris, sand, gravel, or plant part on the equipment or vehicle being inspected.

Vehicles and equipment found with mud, dirt, soil, organic debris, sand, gravel, or plant parts shall be rejected, and shall not be allowed to enter the park. No additional compensation shall be made to the contractor for rejected vehicles.

Haul trucks will have their loads covered during transport.

2. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and keep an eye out for animals on or alongside road. Contact park headquarters at immediately if an animal is hit or injured or will not move off of the road.

Whitebark Pine: Protect whitebark pine from all impacts. The Contractor shall coordinate with the Park Botanist to ensure whitebark pine within the project area and any staging areas are identified and coordoned off (including rooting zones). NPS will identify the areas to for exclusion, and the contractor shall mark the areas with marking ribbon or temporary barrier fence. Keep equipment and personnel out of marked areas.

Do not remove any whitebark pine (including seedlings), prune branches, or cause disturbance within the rooting zone.

CRLA - 229427 01 11 40 - 5

3. Archaeological Resources: Archaeological resources are physical evidences of past human activity, including evidences of the effects of that activity on the environment.

Archaeological resources are found above and below ground and underwater. The Park will provide an archeological monitor when deemed necessary. If the monitor discovers resources, the contractor shall stop work or relocate work to a non-sensitive area and contact the contracting officer immediately. The contractor shall avoid any areas of discovery until such a time until continuation of work in that area is approved by the contracting officer. Archaeological resources typically found in the park or at the project site(s) will be discussed further at the preconstruction meeting.

4. Soundscape / Noise: The contractor shall minimize noise levels at the project site to protect the soundscape of the park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the contracting officer.

CRLA - 229427 01 11 40 - 6

Table 1. Crater Lake National Park List of Non-Native, Invasive Plant Species and “Watch” Species.

Family Scientific Name Common Name Ranunculaceae Adonis aestivalis Pheasant eye Poaceae Agrostis capillaris Browntop Poaceae Agrostis gigantea Redtop Poaceae Alopecurus pratensis Meadow foxtail Brassicaceae Alyssum desertorum Desert alyssum Boraginaceae Anchusa officinalis Common bugloss Poaceae Anthoxanthum oderatum Sweet vernalgrass Asteraceae Arctium minus Common burdock Poaceae Arrhenatherum elatius var. elatius Tall oatgrass Brassicaceae Barbarea vulgaris Bitter winter cress Brassicaceae Brassica napus Canola Brassicaceae Brassica rapa Field mustard Poaceae Bromus diandrus Ripgut brome Poaceae Bromus hordeaceus Soft chess Poaceae Bromus inermis Smooth brome Poaceae Bromus tectorum Cheatgrass Brassicaceae Capsella bursa-pastoris Shepherd's purse Asteraceae Carduus acanthoides Plumeless thistle Asteraceae Carduus nutans Musk thistle Asteraceae Centaurea diffusa Diffuse knapweed Asteraceae Centaurea solstitialis St. Barnaby's thistle Asteraceae Centaurea stoebe ssp. micranthos Spotted knapweed Asteraceae Centaurea x gerstlaueri Meadow knapweed Caryophyllaceae Cerastium fontanum ssp. vulgare Common mouse-ear chickweed Amaranthaceae Chenopodium album Lamb's quarters Asteraceae Chondrilla juncea Rush skeletonweed Asteraceae Cichorium intybus Chicory Asteraceae Cirsium arvense Canada thistle Asteraceae Cirsium vulgare Bull thistle Convolvulaceae Convolvulus arvensis Field bindweed Boraginaceae Cynoglossum officinale Beggar's lice Fabaceae Cytisus scoparius Scotch broom Poaceae Dactylis glomerata Orchard grass Apiaceae Daucus carota Queen Anne's lace Brassicaceae Descurainia sophia Flixweed Dipsacaceae Dipsacus fullonum Fuller's teasel Amaranthaceae Dysphania botrys Feather geranium Poaceae Elymus repens Quackgrass Geraniaceae Erodium cicutarium African filaree Euphorbiaceae Euphorbia esula Leafy spurge Polygonaceae Fallopia convolvulus Climbing knotweed

CRLA - 229427 01 11 40 - 7

Poaceae Festuca rubra ssp. rubra Red fescue Poaceae Festuca trachyphylla Hard fescue Asteraceae Filago pyramidata var. pyramidata Broadleaf cottonrose Asteraceae Hieracium aurantiacum Devil's paintbrush Asteraceae Hieracium caespitosum Yellow king-devil Poaceae Holcus lanatus Velvetgrass Hypericaceae Hypericum perforatum Common St. John's wort Asteraceae Hypochaeris radicata Hairy cat's-ear Iridaceae Iris pseudacorus Yellow flag Brassicaceae Isatis tinctoria Dyers woad Asteraceae Lactuca canadensis Canadian wild lettuce Asteraceae Lactuca serriola Prickly lettuce Lamiaceae Lamium amplexicaule Common deadnettle Brassicaceae Lepidium campestre Field cress Brassicaceae Lepidium draba Heart-podded hoary cress Brassicaceae Lepidium heterophyllum Purple-anther field pepperweed Brassicaceae Lepidium latifolium Broad-leaved peppergrass Brassicaceae Lepidium ruderale Narrow-leaved peppergrass Asteraceae Leucanthemum vulgare Ox-eye daisy Plantaginaceae Linaria dalmatica ssp. dalmatica Dalmatian toadflax Plantaginaceae Linaria vulgaris Butter and eggs Poaceae Lolium perenne Perennial ryegrass Fabaceae Lotus corniculatus Common bird's-foot trefoil Juncaceae Luzula multiflora Common woodrush Caryophyllaceae Lychnis coronaria (Silene coronaria) Mullein pink Asteraceae Matricaria discoidea Pineapple weed Fabaceae Melilotus albus White sweetclover Fabaceae Melilotus officinalis Yellow sweetclover Asteraceae Mycelis muralis Wall lettuce Haloragaceae Myriophyllum spicatum Eurasian water milfoil Poaceae Nardus stricta Matgrass Menyanthaceae Nymphoides peltata Yellow floating heart Onagraceae Oenothera laciniata Cutleaf evening primrose Polygonaceae Persicaria lapathifolia Pinkweed Poaceae Phalaris arundinacea Reed canarygrass Poaceae Phleum pratense Timothy Plantaginaceae Plantago lanceolata Buckhorn plantain Plantaginaceae Plantago major Common plantain Poaceae Poa annua Annual bluegrass Poaceae Poa bulbosa Bulbous bluegrass Poaceae Poa compressa Canada bluegrass Poaceae Poa pratensis ssp. irrigata Dryland Kentucky bluegrass Poaceae Poa pratensis ssp. pratensis Typical Kentucky bluegrass Polygonaceae Polygonum aviculare ssp. depressum Common knotweed Rosaceae Potentilla norvegica Norwegian cinquefoil

CRLA - 229427 01 11 40 - 8

Rosaceae Potentilla recta Erect cinquefoil Ranunculaceae Ranunculus repens Double flowered creeping buttercup Rosaceae Rosa canina Dog rose Rosaceae Rubus bifrons Himalayan blackberry Polygonaceae Rumex acetosella Sheep sorrel Polygonaceae Rumex crispus Curly dock Amaranthaceae Salsola tragus Prickly Russian thistle Lamiaceae Salvia aethiopis African sage Poaceae Schedonorus arundinaceus Tall fescue Asteraceae Senecio jacobaea Stinking willie Asteraceae Senecio sylvaticus Wood groundsel Asteraceae Senecio vulgaris Common groundsel Asteraceae Silybum marianum Milk thistle Asteraceae Sonchus asper Prickly sow-thistle Caryophyllaceae Spergularia rubra Red sand-spurrey Poaceae Taeniatherum caput-medusae Medusahead Asteraceae Tanacetum vulgare Common tansy Asteraceae Taraxacum officinale Common dandelion Poaceae Thinopyrum intermedium Intermediate wheatgrass Asteraceae Tragopogon dubius Yellow salsify Zygophyllaceae Tribulus terrestris Land caltrop Fabaceae Trifolium aureum Golden clover Fabaceae Trifolium hybridum Alsike clover Fabaceae Trifolium pratense Red clover Fabaceae Trifolium repens Dutch clover Asteraceae Tripleurospermum inodorum Scentless chamomile Poaceae Triticum aestivum Wheat Poaceae Ventenata dubia North Africa grass Scrophulariaceae Verbascum thapsus Cowboy toilet paper

CRLA - 229427 01 27 00 - 1

DEFINITION OF CONTRACT PRICE ITEMS

SECTION 01 27 00

DEFINITION OF CONTRACT LINE ITEMS

1.1 SUMMARY

A. The intent of this section is to set a schedule of values and to explain, in general, what is and what is not included in the contract and for determining whether the price set forth is fair and reasonable.

PART 3 – EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS (BASE BID – ACCESSIBLE OVERLOOK)

A. Contract Price Item No. 1 – Construct Accessible Overlook

1. This item includes providing all labor, materials, and equipment required to construct the fully functional pathway and accessible overlook amenities in accordance with the project plans and specifications (Plan Set Part 2). This Work includes, but is not limited to, installation of all temporary stormwater pollution prevention measures, completion of all required site clearing and grading, completion of all gravel, asphalt and concrete surfacing improvements, installation of rock edging, installation of informational/orientation kiosk and installation of all designated fencing.

2. No separate measurement will be made.

3. Payment will be made at the contract lump sum price.

B. Contract Price Item No. 2 – Construct Overlooks A & B

1. This item includes providing all labor, materials, and equipment required to construct the fully functional pathways and overlook amenities in accordance with the project plans and specifications (Plan Set Part 1) for Overlooks A & B. This Work includes, but is not limited to, installation of all temporary stormwater pollution prevention measures, completion of all required site clearing and grading, completion of all gravel, asphalt and concrete surfacing improvements, installation of rock edging, installation of informational/orientation kiosk and installation of all designated fencing.

3.2 BID OPTIONS

A. Bid Option No. 1 – Construct Vault Toilet

CRLA - 229427 01 27 00 - 2

DEFINITION OF CONTRACT PRICE ITEMS

1. This item includes providing all labor, materials, and equipment required to construct the fully functional vault toilet in accordance with the project plans and specifications (Plan Set Part 3). This Work includes, but is not limited to, installation of all temporary stormwater pollution prevention measures, completion of all required site clearing and grading, completion of all gravel, asphalt and concrete surfacing improvements, installation of rock edging, installation of informational/orientation kiosk and installation of all designated fencing.

CRLA – 229427 01 31 00 - 1

PROJECT MANAGEMENT & COORDINATION

SECTION 01 31 00

1.1 SUBMITTALS

A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

1.2 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form as directed by the Contracting Officer.

1. Contracting Officer will not respond to RFIs submitted by other entities controlled by

Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

CRLA – 229427 01 31 00 - 2

7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Contracting Officer's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. Contracting Officer's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

Request for Information (RFI) Form, 2-18-20 page 1 of 1

Request for Information (RFI) Form National Park Service (NPS) - Denver Service Center (DSC) | 2-18-20

RFI Number:

Project:

Contract Number:

Date:

To:

Carbon Copy (CC):

From:

Subject:

Please provide the following information or clarification:

Response Required By:

Date:

To:

From:

Subject: Response to RFI Number:

Response:

CRLA – 229427 01 32 16 - 1

CONSTRUCTION SCHEDULE

SECTION 01 32 16

A. This Section includes Construction Schedule requirements including but not limited to the following:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.

1.2 SUBMITTALS

A. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.

B. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit a baseline schedule, large enough to show entire schedule for entire construction period.

C. Construction Schedule Updates: Prior to progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data.

1.3 COORDINATION

A. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontractors, payment request, and other required schedules and reports.

PART 2 – PRODUCTS

2.1 SCHEDULE OF VALUES

A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal

CRLA – 229427 01 32 16 - 2

the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.

B. Do not break down unit price items. Use only the contract price for unit price items.

C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.

D. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting

Officer before the first progress payment is processed.

2.2 CONSTRUCTION SCHEDULE REQUIREMENTS

A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized scheduling software.

1. Construction Baseline Schedule shall show submittal review, construction start date, work activities / staff resources, activity durations, major milestones, inspection dates, closeout activities, and project end date.

2. Establish procedures for updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.

3. Contracting Officer may request an updated Construction Schedule at any time to confirm progress of the work.

PART 3 –EXECUTION (not used)

Transmittal Form (CM-16) National Park Service (NPS) - Denver Service Center (DSC) | 10-7-20 ACRONYMS: A/E: Architect/Engineer; CMR: Construction Management Representative; FAR: Federal Acquisition Regulation; LEED: Leadership in Energy & Environmental Design; N/A: Not Applicable; PMIS: Project Management Information System

Submittal Number: PARK Acronym: PMIS Number: Project: Contract Number: Date: Sheet: 1 of 2 Transmittal Number:

Construction Contractor: Subcontractor / Supplier:

Ac tio n

Su bm itt al

In fo rm at io na l S ub m itt al

Ite m

N um be r

Sp ec ifi ca tio n

Se ct io n

N um be r

Pa ra gr ap h N um be r

Description of Item (Size, Type, Name, Manufacturer, Use, etc.) Al te rn at e M at er ia ls

Pr op os ed

A/E ACTION

Action Submittal

Ap pr ov ed

Ap pr ov ed w ith

N ot at io ns

D is ap pr ov ed

R es ub m it

NPS ACTION

Action Submittal

Ap pr ov ed

Ap pr ov ed w ith N ot at io ns

D is ap pr ov ed

R es ub m it

Informational Submittal

Ac ce pt

R ej ec t

Construction Contractor - Name, Title, & Signature: Date:

I hereby certify this submittal has been reviewed for accuracy, completeness, and compliance with contract requirements. FAR 52-236-21

CMR - Name, Title, & Signature: Date:

A/E - Name, Title, & Signature: Date:

Review Comments - Name: Comment(s):

Recommended By - NPS COR or Alternate COR - Name, Title, & Signature: Date:

Action By - NPS Name, Title, & Signature: Date:

Approval of this submittal is subject to the provisions of the contract drawings and specifications.

This action is for general concurrence only and the Government is not responsible for errors or omissions.

Date Received: Date to Construction Contractor:

Distribute 1 copy each: CMR Interim, A/E, DSC, & Construction Contractor.

NPS Review Comments - Name: Comment(s):

Transmittal Form (CM-16) - Continuation National Park Service (NPS) - Denver Service Center (DSC) | 10-7-20 ACRONYMS: A/E: Architect/Engineer; CMR: Construction Management Representative; FAR: Federal Acquisition Regulation; LEED: Leadership in Energy & Environmental Design; N/A: Not Applicable; PMIS: Project Management Information System

Submittal Number: PARK Acronym: PMIS Number: Project: Contract Number: Date: Sheet: 2 of 2 Transmittal Number:

Construction Contractor: Subcontractor / Supplier:

Ac tio n

Su bm itt al

In fo rm at io na l S ub m itt al

Ite m

N um be r

Sp ec ifi ca tio n

Se ct io n

N um be r

Pa ra gr ap h N um be r

Description of Item (Size, Type, Name, Manufacturer, Use, etc.) Al te rn at e M at er ia ls

Pr op os ed

A/E ACTION

Action Submittal

Ap pr ov ed w ith N ot at io ns

D is ap pr ov ed

R es ub m it

NPS ACTION

Action Submittal

Ap pr ov ed w ith N ot at io ns

D is ap pr ov ed

R es ub m it

Informational Submittal

Ac ce pt

R ej ec t

Review Comments - Name: Comment(s):

CRLA – 229427 01 33 23 - 1

SUBMITTAL PROCEDURES

SECTION 01 33 23

SUBMITTAL PROCEDURES

1.1 GENERAL SUBMITTAL PROCEDURES

A. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:

1. CM-16 Transmittal Form: All submittals shall be transmitted using National Park

Service Form CM-16 which is attached to the end of this specification section. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form.

Complete the general information at the top of the form.

a. Provide all required information based on the submittal type.

b. Attach all related documents.

c. Sign the CM-16 form in the contractor section at the bottom of the form.

2. Physical Samples: Complete the CM-16 form as outlined above and deliver the physical sample to the CO (or designee) on site for processing. All comments and actions will be documented on the CM-16 form.

CRLA – 229427 01 35 23 - 1

SAFETY REQUIREMENTS

SECTION 01 35 23

A. This section includes establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.

1.2 SUBMITTALS

A. Accident Prevention Plan: After contract award and before the Pre-Construction conference, submit for review, an Accident Prevention Plan. The Contracting Officer will review the proposed Plan. If the plan requires any revisions or corrections, the Contractor shall resubmit the Plan within ten (10) days. No progress payments will be made until the Plan is accepted.

1.3 QUALITY ASSURANCE

A. Comply with contract clauses entitled "Accident Prevention" and "Permits and Responsibilities". In case of conflicts between Federal, State, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.

B. Qualifications of Employees:

1. All employees must be physically qualified and able to perform their assigned duties in a safe manner.

2. Do not allow employees to perform work whose ability or alertness is impaired because of prescription or illegal drug use, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

3. Operators of vehicles, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be fully capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.

1.4 ACCIDENT REPORTING

A. Reportable Accidents: A project reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, fires, and property damage by accident in excess of one hundred dollars ($100). Notify Contracting Officer immediately in the event of a reportable accident. Within 7 days of a reportable accident, fill out and forward to Contracting

CRLA – 229427 01 35 23 - 2

Officer an Accident/Property Damage Report (Form CM-22). Form may be obtained from the Contracting Officer.

2.1 ACCIDENT PREVENTION PLAN

A. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:

1. Name of responsible supervisor to carry out the program.

2. Weekly and monthly safety meetings.

3. First aid procedures.

4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase.

5. Training, both initial and continuing.

6. Planning for possible emergency situations, such as floods, fires, cave-ins, slides, explosions, power outages, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.

2.2 FIRST AID FACILITIES

A. Provide adequate facilities for the number of employees and the hazards associated with the types of ongoing construction work at the site.

2.3 PERSONNEL PROTECTIVE EQUIPMENT

A. Meet requirements of applicable ANSI standards.

3.1 EMERGENCY INSTRUCTIONS

A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

3.2 FIRE AND LIFE SAFETY

A. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations).

CRLA – 229427 01 35 23 - 3

B. All Hot Work will require permitting from the park. It shall be the contractor’s responsibility to coordinate this work and the associated permitting with park staff. All Hot Work to comply with requirements of OSHA 29 CFR 1910.252.

C. Store hazardous materials in accordance with manufacturer’s and OSHA recommendations.

Maintain readily available, on site, MSDS for each chemical.

1. Immediately report all spills of hazardous materials to the park.

2. Maintain a spill emergency response kit.

3. Train employees how to respond to a spill and use the emergency response kit.

3.3 PROTECTIVE EQUIPMENT

A. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair personal items, as appropriate, before issuing them to another individual.

B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.

3.4 SAFETY MEETINGS

A. As a minimum, conduct weekly fifteen (15) minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the Contracting Officer within one day after the meeting.

B. Conduct monthly safety meetings for all levels of supervision. Meetings shall be attended by all contractors and subcontractors performing work on the site. Notify the Contracting Officer of meeting dates and times. These meetings shall be used to review the effectiveness of the Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the Accident Prevention Plan. The Contracting Officers Representative will attend the meeting and enter the results of the meetings into the daily log.

3.5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS

A. A hard hat area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.

B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary personal protective equipment at all times. As a minimum, provide three (3) hard hats for use by visitors.

3.6 TRAINING

A. First Aid: Provide adequate training to an adequate number of personnel to ensure prompt and efficient first aid.

CRLA – 229427 01 35 23 - 4

B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.

CRLA – 229427 01 40 00 - 1

QUALITY REQUIREMENTS

SECTION 01 40 00

A. This Section includes administrative and procedural requirements for quality assurance and quality control.

B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements. The quality of all work shall be the responsibility of the Contractor.

1. Specified tests, inspections, and related actions do not limit Contractor's other quality assurance and control procedures that facilitate compliance with the Contract Document requirements.

C. Parking and access routes must meet federal accessibility standards. These standards are available at https://www.access-board.gov/guidelines-and-sites/about-the-aba-standards/aba-standards/chapter-5-general-site-and-building-elements.

D. See Divisions 02 through 48 Sections for specific test and inspection requirements.

1.2 DEFINITIONS

A. Quality Assurance Services: Activities, actions, and procedures performed before and during execution of the work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.

B. Quality Control Services: Tests, inspections, procedures, and related actions during and after execution of the work to evaluate that actual products incorporated into the work and completed construction comply with requirements.

C. Preconstruction Testing: Tests and inspections that are performed specifically for the project before products and materials are incorporated into the work to verify performance or compliance with specified criteria.

D. Product Testing: Tests and inspections that are performed by a Nationally Recognized Testing Laboratory (NRTL), a National Voluntary Laboratory Accreditation Program (NVLAP), or a testing agency qualified to conduct product testing, to establish product performance and compliance with industry standards.

E. Source Quality Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory, or shop.

CRLA – 229427 01 40 00 - 2

F. Field Quality Control Testing: Tests and inspections that are performed on-site for installation of the work and for completed work.

G. Testing Agency or Laboratory: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.

H. Mockups: Full-size physical assemblies constructed on-site. Mockups are constructed from selections made under Sample submittals; to demonstrate aesthetic effects and, where indicated, qualities of materials and execution; to review coordination, testing, or operation; to show interface between dissimilar materials; and to demonstrate compliance with specified installation tolerances. Mockups are not Samples. Approved mockups establish the standard by which the Work will be judged, unless otherwise indicated.

I. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.

1. Using a term such as “carpentry” does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as “carpenter.” It also does not imply that requirements specified apply exclusively to trades people of the corresponding generic name.

1.3 CONFLICTING REQUIREMENTS

A. Reference Standards: If compliance with two (2) or more standards is specified and the standards establish different or conflicting requirements for minimum quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to Contracting Officer for a decision before proceeding.

B. Minimum Quality Levels: The quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Contracting Officer for a decision before proceeding.

1.4 SUBMITTALS

A. Quality Control Plan:

1. After contract award and before the Pre-Construction conference, submit for approval a written Contractor Quality Control (CQC) plan.

2. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within ten (10) days.

3. The Government reserves the right to require changes in the plan during the contract period as necessary to obtain the quality specified.

4. No change in the approved plan may be made without written concurrence by the

CRLA – 229427 01 40 00 - 3

B. Qualification Data: For testing agencies specified in “Quality Assurance” Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.

C. Contractor's Quality Control Daily Reports: Submit showing all inspections and tests on the first workday following the date covered by the report.