This is a Past Performance Questionnaire for RFQ 140P5126Q0050 issued by the National Park Service, Contracting Operations (ConOps) East. The questionnaire is designed to gather reference information from previous clients regarding a contractor's performance on similar work.
The solicitation pertains to roadside vegetation removal and trimming services at Mammoth Cave National Park in Kentucky. The work scope includes removal of overgrown brush and vegetation from six park roads: Mammoth Cave Parkway (6 miles), Green River Ferry Road South (2 miles), Brownsville Road, Route 015 (4 miles), Flint Ridge Road, Route 101 (4 miles), Park Ridge Road, Route 106 (4 miles), and Cave City Road, Route 016 (3 miles). Responses must be submitted via email to the Contracting Officer, Edward Dingle, at edward_dingle@nps.gov. The questionnaire requests contractor information including contract number, contract value, period of performance, and work description. Evaluators assess contractor performance across five key areas using a six-point rating scale: (1) overall ability to meet requirements; (2) timeliness of product delivery; (3) ability to resolve timeliness problems; (4) quality of work and task requirements; and (5) overall contractor performance across requirements, schedule, and price. Rating options are Exceptional, Very Good, Satisfactory, Marginal, Unsatisfactory, and Not Applicable, each with defined criteria. Respondents are encouraged to provide explanatory narratives with their ratings.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P5126Q0050_Amd_0001.pdf | ||
| B09_Attachment_0006_Questions_and_Answers_140P5126Q0050__0001.docx | DOCX document | |
| Sol_140P5126Q0050.pdf | ||
| B08_Attachment_0005_SVI_140P5126Q0050_MACA_HTR.pdf | ||
| B03_Attachment_0002_WDOL_WD_140P5126Q0050_MACA_HTR.pdf | ||
| B08_Attachment_0003_Price_Sheet140P5126Q0050_MACA_HTR.pdf | ||
| A04_Attachment_0001_SOW_44035831_MACA_HTR.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 0004 RFQ# 140P5126Q0050
PAST PERFORMANCE QUESTIONNAIRE
Solicitation# 140P5126Q0050
Please complete this Questionnaire and e-mail to edward_dingle@nps.gov
We are currently in the process of preparing our quote for the National Park Service, Contracting
Operations (ConOps) East, Solicitation Number: 140P5126Q0050 for the removal of Overgrowth of
Vegetation from Roadsides to Mitigate Potential Safety Hazards Roadside trimming on six of Mammoth
Caves roads entails the removal (trimming and brushing) of overgrown, encroaching, brush and vegetation. The work will be accomplished on Mammoth Cave Parkway (6 miles), Green River Ferry
Road south (2 miles), Brownsville Road, Rt 015(4 miles), Flint Ridge Road, Rt 101(4 miles), Park
Ridge Road, Rt 106(4 miles) and Cave City Road, Rt 016(3 miles) for Mammoth Cave National Park
Mammoth Cave, Kentucky in accordance with the attached statement of work (SOW) for Mammoth
Cave National Park Mammoth Cave, Kentucky per the attached statement of work. As part of our quote, we have listed you as a reference on our performance for this type of service with your agency under the previous/current contract listed below. Your input on our performance is therefore requested.
Please complete this Questionnaire and e-mail to Contracting Officer, e-mail: edward_dingle@nps.gov
Alternate POC name:
Alternate POC phone number:
Alternate POC e-mail address:
Thank you.
NAME OF OFFEROR:
Phone: Fax:
E-Mail:
I. Current or Historical Contract Information
CONTRACT REFERENCED:
1. Contract or Identifying Number:
2. Contract Value:
3. Period of Performance:
4. Brief description of items provided:
5. Name of Person Completing Questionnaire:
Agency/Company:
Title: Phone:
E-mail:
mailto:Please%20complete%20this%20Questionnaire%20and%20e-mail%20to%20edward_dingle@nps.gov mailto:%20edward_dingle@nps.gov
II. EVALUATION. Please rate the Contractor utilizing the guide below. Explanatory narratives for as many responses as possible would be appreciated. These narratives need not be lengthy, just detailed. Attach additional pages if more space is needed.
Evaluation Definitions –
The following definitions should be used in the assessment of Contractor performance.
EXCEPTIONAL
Performance EXCEEDS MOST contractual requirements. The performance of areas being assessed was accomplished with few minor issues or concerns.
VERY GOOD
Performance EXCEEDS SOME contractual requirements. The performance of areas being assessed was accomplished with few minor issues or concerns, for which the Contractor’s corrective actions were highly effective.
SATISFACTORY
Performance MEETS contractual requirements. The performance of the areas being assessed contains minor issues or concerns, for which corrective actions taken by the Contractor were effective.
MARGINAL
Performance MEETS SOME contractual requirements. The performance of the areas being assessed includes significant problems, issues, or concerns for which corrective actions taken by the Contractor were only somewhat effective.
UNSATISFACTORY
Performance DOES NOT MEET contractual requirement. The performance of the areas being assessed includes serious problems, issues, or concerns for which the Contractor’s corrective actions were ineffective.
NOT APPLICABLE (N/A)
Performance information not recent or relevant as defined in the Solicitation. Unable to provide assessment.
Past Performance Evaluation
Question 1. Performance
What is your assessment of the Contractor’s ability to meet your requirements?
Exceptional Very Good Satisfactory Marginal Unsatisfactory N/A
Performance
Comments, if any.
Questions 2 and 3. Timeliness
What is your assessment of the Contractor’s ability to provide products in a timely manner?
Timeliness
Ability to
Resolve Timeliness Problems
Question 4. Quality of Work
What is your assessment of the Contractor’s ability to meet requirements of tasks and the overall quality of the work?
Quality of
Shipments
Question 5. Overall Rating of Contractor’s performance
What is your overall rating of Contractor’s performance (requirements, schedule, and price) on contract being assessed?
Exceptional Very Good Satisfactory Marginal Unsatisfactory
General Comments: