This is a Statement of Work (SOW) for boiler fire tube replacement services at the McAlester Army Ammunition Plant (MCAAP) Building 165.
The contractor shall mobilize a certified boiler mechanic to replace fire tubes on two government-owned Cleaver-Brooks CB200-250-150ST boilers (Serial Numbers L54363 and L54362). The contractor must perform labor, cutting, welding, installation, and testing to return both units to safe operational status. Technical execution includes cutting two flush patches on each side of the fire tunnel per boiler (with tube ligament repair as secondary option), removing and replacing up to 180 fire tubes per boiler (360 total), performing seal welding in accordance with ASME codes, conducting a hydrostatic pressure test to verify structural integrity, and completing formal closing/sealing of both waterside and fireside of the vessels. The contractor must also supply all specialized tools, piping, hardware, and electrical components; maintain daily housekeeping and waste disposal; and comply with OSHA guidelines and USACE EM 385-1-1 safety regulations. Work shall be completed within 30 calendar days of mobilization during normal business hours, Monday through Friday, excluding federal holidays, unless authorized otherwise by the Contracting Officer.
The government will furnish 360 replacement fire tubes (2-1/2" x 131-1/2" x 0.105 wall thickness), electricity, water, sanitary facility access, and on-site dumpsters for waste disposal. The contractor is responsible for any damage caused directly by its personnel or equipment. All contractor personnel must be U.S. citizens and pass a background check for installation access; gate access and escort requirements must be coordinated with the Point of Contact at least two business days prior to mobilization.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08_Attachment_0000_Combined_Solicitation_Synopsis_26Q3178.pdf | ||
| B08_Attachment_ 0001 _MCAAP_Pricing_Matrix_26Q3178.xlsx | XLSX spreadsheet | |
| B08_Attachment_0002_Clauses_26Q3178.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replace Boiler Fire Tubes — Building 165 (MCAAP)
1.0 Background and Scope
The McAlester Army Ammunition Plant (MCAAP) has a requirement to replace the fire tubes on Boiler No. 1 and Boiler No. 2 located in Building 165. A severe leak in an isolated fire tube has rendered the units inoperable. The contractor shall mobilize a certified boiler mechanic to perform all necessary labor, cutting, welding, installation, and testing required to return both boilers to safe operational status.
2.0 Equipment Details
The work shall be performed on the following government-owned equipment:
Equipment Description Model Number Serial Number Location
Boiler No. 1 Cleaver-Brooks CB200-250-150ST L54363 Building 165
Boiler No. 2 Cleaver-Brooks CB200-250-150ST L54362 Building 165
3.0 Technical Requirements & Contractor Tasks
The Contractor shall perform the following tasks:
• Mobilization: Mobilize a qualified boiler mechanic to the job site. The contractor shall supply all necessary specialized tools, piping, hardware, and electrical components required to complete the installation.
• Technical Execution:
• Cut two (2) flush patches on each side of the fire tunnel. If a flush patch is technically unfeasible, a tube ligament repair shall be utilized as the secondary option.
• Remove legacy fire tubes and install the government-furnished replacement fire tubes. Up to 180 fire tubes are to be replaced per boiler, 360 total fire tubes.
• Perform seal welding of tubes as necessary in accordance with applicable ASME codes.
• Testing & Restoration:
• Perform a hydrostatic test ("hydro") of the boilers up to standard operating pressure to verify structural integrity.
• Complete the formal closing/sealing of both the waterside and fireside of the vessels.
• Housekeeping: Clean and restore the work area to its pre-work condition daily.
The contractor is responsible for disposing of contractor-generated waste into the government-provided dumpsters.
4.0 Government-Furnished Property (GFP) and Services
The Government will provide the following to facilitate the work:
• Materials: Replacement fire tubes (to be received, unloaded, hauled, and staged near the boilers by the Government).
• Fire tubes: 360 total fire tubes, 2-1/2" x 131-1/2" x 0.105 wall thickness
• Utilities: Electricity, water, and access to sanitary facilities.
• Disposal: On-site trash dumpsters for work-related waste.
5.0 Period of Performance and Hours of Work
• Hours: All work shall be performed during normal business hours, Monday through Friday, excluding federal holidays, unless authorized in writing by the Contracting Officer (KO).
• Timeline: The contractor shall complete all work within (30) calendar days of mobilization.
6.0 Safety and Liability
• Safety Standards: The contractor shall comply with all OSHA guidelines and USACE EM 385-1-1 safety regulations.
• Liability: The contractor is responsible for any damage caused directly by their personnel or equipment during execution. The contractor is not liable for pre-existing damage, or waste left behind by third parties.
7.0 Security Requirements (Installation Access)
• All contractor personnel must be U.S. citizens and must pass a background check to obtain entry credentials to MCAAP.
• The contractor shall coordinate gate access and escort requirements with the POC least (2) business days prior to mobilization.