This document contains a past performance questionnaire for a federal construction contract opportunity. The opportunity is for the YOSE 215798 - Bridalveil Fall Comfort Station and Water Supply Systems project located in Yosemite National Park, California. The solicitation number is 140P2022R0038. The past performance questionnaire is to be completed by an offeror and their identified reference and returned to the contracting officer, Amber Hughes at the National Park Service - Denver Service Center, by April 15, 2022. The questionnaire contains questions regarding the offeror's performance on a prior contract relating to quality, schedule, cost control, management, small business subcontracting and regulatory compliance. The reference is asked to provide ratings and comments for the offeror's performance in these areas on their previous contract and an overall recommendation for whether they would recommend the offeror for similar contracts going forward.

View the file

Other files

File Type Posted
Sol_140P2022R0038_Amd_0005.pdf PDF
Sol_140P2022R0038_Amd_0004.pdf PDF
YOSE_215798_RFP_140P2022R0038_-_QR_Tracker_Amd4_0004.xlsx XLSX spreadsheet
Sol_140P2022R0038_Amd_0003.pdf PDF
B08_UPDATED_RFP_Body_-_YOSE_215798_Amd3_0003.pdf PDF
YOSE_215798_RFP_140P2022R0038_-_QR_Tracker_Amd3_0003.xlsx XLSX spreadsheet
STO18L80332_-_Bridalveil_Addendum_Letter_Amd3_0003.pdf PDF
Bridalveil_Donation_List_Kohler_Replacements_Amd3_0003.xlsx XLSX spreadsheet
MOD18R78466_Bridalveil_Falls_Report_5-17-18_Amd3_0003.pdf PDF
B08_Attach1_-_UPDATED_Specifications_Amd2_0002.pdf PDF
Sol_140P2022R0038_Amd_0002.pdf PDF
YOSE215798_PrePropolaslSiteWalk_SignIn_-_Amd2_0002.pdf PDF
YOSE_215798_RFP_140P2022R0038_-_QR_Tracker_Amd2_0002.xlsx XLSX spreadsheet
Sol_140P2022R0038_Amd_0001.pdf PDF
B08_Attach1_-_UPDATED_Specifications_Amd1_0001.pdf PDF
YOSE_215798_RFP_140P2022R0038_-_QR_Tracker_Amd1_0001.xlsx XLSX spreadsheet
B08_RFP_Body_-_YOSE_215798.pdf PDF
B08_Attach1_-_Specifications.pdf PDF
Sol_140P2022R0038.pdf PDF
B08_Attach5_-_Certification_Form.pdf PDF
B08_Attach2_-_Drawings.pdf PDF
B08_Attach8_-_GeneralReferences.doc DOC document
B08_Attach9_-_SubcontractingWorksheet.xlsx XLSX spreadsheet
B08_Attach3_-_CA20220018_WD.pdf PDF
B08_Attach6_-_ProjectExperienceQ.docx DOCX document
B08_Attach4_-_Implementation_Memo.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAST PERFORMANCE QUESTIONNAIRE

Solicitation: 140P2022R0038 – YOSE 215798 INSTRUCTIONS: Offeror to complete Sections A and B and transmit questionnaire to reference.

Reference to complete Sections C and D and transmit back to Contracting Officer listed in section E.

A. CONTRACTOR INFORMATION

Company Name
Company
Street Address
Address
City
City
State
State
Zip Code
XXXXX
DUNS Number
XXXXXXX
Point of Contact
Name, Email, Phone

B. CONTRACT INFORMATION

Project Title
Title
Contract Number
XXXXXXXXXX
Contract Type
Firm Fixed Price / Time & Materials / Cost Reimbursable / Other
Awarded Contract Price
$X,XXX,XXX
Current / Final Price
$X,XXX,XXX
Contract Award Date
XX/XX/XXXX
Contract Completion Date
XX/XX/XXXX
Period of Performance
XX/XX/XXX – XX/XX/XXX
Project Location
Park or Street address, City, State
Client / Owner
Company
Brief description of the contract & work effort:
Scope of work description

C. REFERENCE:

Name
First, Last
Position / Title
Title
Organization
Agency or Company
Phone Number
XXX-XXX-XXXX
Email Address
Email
Signature
Signature
Date
XX/XX/XXXX

D. EVALUATION

Rating
Definition
Exceptional
Performance met contractual requirements and exceeded many to the owner’s benefit. The element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
Very Good
Performance met contractual requirements and exceeded some to the owner’s benefit. The element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
Satisfactory
Performance met contractual requirements. The element being assessed contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
Marginal
Performance did not meet some contractual requirements. The element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions.
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The element being assessed contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
Evaluation Area
Rating

Quality

Quality of workmanship (including subcontractors)?
Choose an item.
Quality of and adherence to quality control plan?
Choose an item.
Quality of informational and technical submittals?
Choose an item.
Overall Quality Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of exceptional, marginal, & unsatisfactory are especially helpful.):

Schedule (& Time Management)

Met project schedule milestones?
Choose an item.
Responded to owner requests in a timely manner?
Choose an item.
Informational and technical submittals submitted timely?
Choose an item.
Promptly addressed scheduling issues?
Choose an item.
Overall Schedule (& Time Management) Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of exceptional, marginal, & unsatisfactory are especially helpful.):

Cost Control

Addressed differing & unforeseen site conditions so as to minimize additional costs?
Choose an item.
Provided fair and reasonable pricing for contract modifications?
Choose an item.
Submitted accurate and complete invoices?
Choose an item.
Promptly paid subcontractors and suppliers?
Choose an item.
Overall Cost Control Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of exceptional, marginal, & unsatisfactory are especially helpful.):

Management

General oversight by project manager and superintendent?
Choose an item.
Coordination with and control of subcontractors?
Choose an item.
Avoidance of accidents & safety violations?
Choose an item.
Addressed location factors (especially remote locations)?
Choose an item.
Maintained good working relationship with owner representatives?
Choose an item.
Demonstrated flexibility, innovativeness and cooperation in resolving potential problems?
Choose an item.
Overall Management Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of exceptional, marginal, & unsatisfactory are especially helpful.):

Small Business Subcontracting (& Labor Standards)

Met regulatory and contractual labor standards?
Choose an item.
Successfully contracted with small and socio-economically disadvantaged businesses?
Choose an item.
Quality and adherence to applicable subcontracting plans?
Choose an item.
Overall Small Business Subcontracting (& Labor Standards) Rating
Choose an item.
Comments (Please provide comments supporting the above ratings. Comments supporting ratings of exceptional, marginal, & unsatisfactory are especially helpful.):

Regulatory Compliance

Met building and life safety codes?
Choose an item.
Overall Regulatory Compliance Rating
Choose an item.
Overall Recommendation:
Given what I know today about the contractor's ability to perform in accordance with the contract’s most significant requirements, I would recommend them for similar contracts:
Choose an item.
Overall Comments:

E. RETURN:

Return by
12:00 pm Mountain Time (MT) on April 15, 2022
Name
Amber Hughes
Title
Contracting Officer
Organization
National Park Service – Denver Service Center
Email
Amber_Hughes@nps.gov