This file is related to a federal solicitation for the construction of a comfort station and water supply systems at Yosemite National Park in California. The solicitation number is 140P2022R0038 and is being issued by the Department of the Interior National Park Service National Office. The project involves building a new comfort station and water supply systems at Bridalveil Fall in Yosemite National Park. Interested parties should review the specifications in attachment B08_Attach1_-_UPDATED_Specifications_Amd2_0002.pdf for requirements regarding construction materials, plumbing systems, septic systems, and a project completion date of October 2023.

View the file

Other files

File Type Posted
Sol_140P2022R0038_Amd_0005.pdf PDF
Sol_140P2022R0038_Amd_0004.pdf PDF
YOSE_215798_RFP_140P2022R0038_-_QR_Tracker_Amd4_0004.xlsx XLSX spreadsheet
Sol_140P2022R0038_Amd_0003.pdf PDF
B08_UPDATED_RFP_Body_-_YOSE_215798_Amd3_0003.pdf PDF
YOSE_215798_RFP_140P2022R0038_-_QR_Tracker_Amd3_0003.xlsx XLSX spreadsheet
STO18L80332_-_Bridalveil_Addendum_Letter_Amd3_0003.pdf PDF
Bridalveil_Donation_List_Kohler_Replacements_Amd3_0003.xlsx XLSX spreadsheet
MOD18R78466_Bridalveil_Falls_Report_5-17-18_Amd3_0003.pdf PDF
Sol_140P2022R0038_Amd_0002.pdf PDF
YOSE215798_PrePropolaslSiteWalk_SignIn_-_Amd2_0002.pdf PDF
YOSE_215798_RFP_140P2022R0038_-_QR_Tracker_Amd2_0002.xlsx XLSX spreadsheet
Sol_140P2022R0038_Amd_0001.pdf PDF
B08_Attach1_-_UPDATED_Specifications_Amd1_0001.pdf PDF
YOSE_215798_RFP_140P2022R0038_-_QR_Tracker_Amd1_0001.xlsx XLSX spreadsheet
B08_RFP_Body_-_YOSE_215798.pdf PDF
B08_Attach1_-_Specifications.pdf PDF
B08_Attach7_-_PastPerformanceQ.docx DOCX document
Sol_140P2022R0038.pdf PDF
B08_Attach5_-_Certification_Form.pdf PDF
B08_Attach2_-_Drawings.pdf PDF
B08_Attach8_-_GeneralReferences.doc DOC document
B08_Attach9_-_SubcontractingWorksheet.xlsx XLSX spreadsheet
B08_Attach3_-_CA20220018_WD.pdf PDF
B08_Attach6_-_ProjectExperienceQ.docx DOCX document
B08_Attach4_-_Implementation_Memo.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

YOSE – 215798 00 01 10 - 1

TABLE OF CONTENTS

TABLE OF CONTENTS

DIVISION 01: GENERAL REQUIREMENTS

01 10 00 CONTRACT MODIFICATION PROCEDURES

01 11 00 SUMMARY OF WORK

01 20 00 PAYMENT PROCEDURES

01 27 00 DEFINITION OF CONTRACT PRICE ITEMS

01 27 00.1 CONTRACT BID SCHEDULE W-ESTIMATE 55

01 31 00 PROJECT MANAGEMENT & COORDINATION

01 32 16 CONSTRUCTION SCHEDULE

01 33 23 SUBMITTAL PROCEDURES

01 35 23 SAFETY REQUIREMENTS

01 35 50 NATURAL, CULTURAL, AND PHYSICAL RESOURCES PROTECTION

01 40 00 QUALITY REQUIREMENTS

01 42 00 REFERENCES

01 50 00 TEMPORARY FACILITIES AND CONTROLS

01 55 26 TRAFFIC CONTROL

01 57 23 TEMPORARY STORM WATER POLLUTION PREVENTION PLAN

01 67 00 PRODUCT REQUIREMENTS

01 73 40 EXECUTION AND UTILITY MARKING

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 77 00 CLOSEOUT PROCEDURES

01 78 23 OPERATION AND MAINTENANCE DATA

01 79 00 SYSTEM STARUP, DEMOSTRATION AND TRAINING

01 91 14 TOTAL BUILDING COMMISSIONING

DIVISION 02 – EXISTING CONDITIONS

02 41 00 REMOVAL OF PAVEMENTS AND STRUCTURES

DIVISION 03 – CONCRETE

03 20 00 CONCRETE REINFORCEMENT

03 30 00 CAST-IN-PLACE CONCRETE

03 35 00 CONCRETE FINISH

DIVISION 04 – MANSORY

04 20 00 CONCRETE MANSORY UNITS

04 43 21 STONE VENEER ASSEMBLIES

YOSE – 215798 00 01 10 - 2

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

06 05 73 WOOD TREATMENT

06 10 00 ROUGH CARPENTRY

06 10 53 MISCELLANEOUS ROUGH CARPENTRY

06 15 16 WOOD ROOF DECKING

06 16 00 SHEATHING

06 19 00 PREFABRICATED WOOD TRUSSES

06 20 00 FINISH CARPENTRY

06 64 13 FIBERGLASS-REINFORCED PLASTIC PANELS

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 21 00 BUILDING INSULATION

07 25 00 WEATHER BARRIER

07 26 16 BELOW-GRADE VAPOR RETARDERS

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIER

07 31 29 WOOD SHINGLES

07 46 00 WOOD SIDING

07 60 00 FLASHING AND SHEET METAL

07 92 00 JOINT SEALANTS

DIVISION 08 – OPENINGS

08 11 13 HOLLOW METAL DOORS AND FRAMES

08 54 13 FIBERGLASS WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLASS GLAZING

DIVISION 09 – FINISHES

09 29 00 09 30 00 09 67 23 09 90 00

09 97 29 09 91 00

GYPSUM BOARD

TILING

RESINOUS FLOORING

PAINTING AND COATING (SITE)

PAINTING

CONCRETE FLOOR SEALING

DIVISION 10 – SPECIALTIES

10 14 00 SIGNAGE

10 21 13 SOLID POLYMER TOILET COMPARTMENTS

10 28 13 COMMERCIAL TOILET ACCESSORIES

10 44 00 FIRE PROTECTION SPECIALTIES

YOSE – 215798 00 01 10 - 3

DIVISION 13 – SPECIAL CONSTRUCTION

13 21 10 BOLTED STEEL TANKS, PIPING, AND APPURTENANCES

13 44 40 PRE-MANUFACTURED BUILDINGS

DIVISION 22 – PLUMBING

22 00 00 PLUMBING GENERAL REQUIREMENTS

22 05 17 SLEEVES AND SLEEVE SEAL FOR PLUMBING PIPING

22 05 18 ESCUTCHEONS FOR PLUMBING PIPING

22 05 29 HENGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT

22 05 33 HEAT TRACE FOR PLUMBING PIPING

22 05 48 VIBRATION AND SEISMIC CONTROLS FOR PLUMBING PIPING AND

EQUIPMENT

22 10 00 PLUMBING PIPING

22 32 00 DOMESTIC WATER FILTRATION EQUIPMENT

22 33 00 ELECTRIC, DOMESTIC-WATER HEATERS

22 42 00 PLUMBING FIXTURES

DIVISION 23 – HEATING VENTILATING AND AIR CONDITIONING

23 05 29 HANGERS AND SUPPORTS FOR HVAC DUCTWORK AND EQUIPMENT

23 05 48 VIBRATION AND SEISMIC CONTROLS FOR PIPING AND EQUIPMENT

23 05 53 IDENTIFICATION FOR HVAC EQUIPMENT

23 05 93 TESTING, ADJUSTING AND BALANCING OF HVAC SYSTEMS

23 07 13 DUCT INSULATION

23 31 00 HVAC DUCTS AND CASINGS

23 33 00 AIR DUCT ACCESSORIES

23 37 13 DIFFUSERS, REGISTERS, AND GRILLS

23 72 19 FIXED-PLATE AIR-TO-AIR ENERGY RECOVERY EQUIPMENT

DIVISION 26 – ELECTRICAL

26 05 00 BASIC ELECTRIC REQUIREMENTS

26 08 00 TESTING

26 24 00 SERVICE AND DISTRIBUTION SYSTEM

26 27 00 BASIC ELECTRICAL MATERIALS AND METHODS

26 51 01 LIGHTING

26 57 00 LIGHTING CONTROL SYSTEM

DIVISION 31 – EARTHWORK

31 11 00 CLEARING AND GRUBBING

31 23 00 SITE EXCAVATION AND GRADING

31 23 16 STRUCTURE EXCAVATIN AND BACKFILL

31 23 17 UTILITY TRENCHING AND BACKFILLING

31 37 10 RIPRAP

YOSE – 215798 00 01 10 - 4

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 11 23 AGGREGATE BASE

32 17 23 DETECTABLE WARNING TACTILE PANELS

DIVISION 33 – UTILITIES

33 05 13 NPS-UTILITY LINE MARKING

33 11 16 DUCTILE IRON PIPE

33 13 00 DISINFECTION OF WATER LINES

33 13 03 WATER PIPING AND APPURTENANCES

33 31 13 GRAVITY SEWER PIPING AND APPURTENANCES

33 31 16 TESTING OF WATER AND SEWER LINES

DIVISION 40 – PROCESS INTEGRATION

DIVISION 43 – PUMPS

43 21 52 WELL PUMPING FACILITIES

43 21 61 PACKAGE BOOSTER PUMP

DIVISION 44 – MOTORS

44 42 48 IN-LINE STATIC MIXER

DIVISION 46 – WATER AND WASTEWATER EQUIPMENT

46 33 43 MOTOR OPERATED DIAPHRAGM CHEMICAL FEED PUMPS

40 05 25 INSTRUMENTATION AND CONTROL SYSTEM REQUIREMENTS

BUTTERFLY VALVES

40 05 26 GATE VALVES

40 05 27 CHECK VALVES

40 20 10 PIPE SUPPORTS

40 90 00 INSTRUMENTATION AND CONTROL SYSTEM REQUIREMENTS

40 91 25 MAGNETIC FLOWMETER

40 94 27 PRESSURE MEASUREMENT

YOSE – 215798 01 10 00 - 1

CONTRACT MODIFICATION PROCEDURES

SECTION 01 10 00 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

YOSE – 215798 01 10 00 - 2

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums, such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation to be made available.

4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.

YOSE – 215798 01 10 00 - 3

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor must utilize the government provided Contractor’s Price Proposal Form for submission of the price proposal.

http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank

YOSE – 215798 01 10 00 - 4

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.

All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

YOSE – 215798 01 10 00 - 5

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated rental rates shall include the cost of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major overhaul is not included), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. The following percentages establish the maximum allowable markups (OH&P) for contractor self-performed work:

Overhead………………10% Profit………………5%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

YOSE – 215798 01 10 00 - 6

1.4 TIME IMPACT ANALYSIS FOR CONTRACT MODIFICATIONS CHANGES DELAYS

AND CONTRACTOR REQUESTS:

1. Requirements: When contract modifications or changes are initiated, delays are experienced, or the Contractor desires to revise the currently accepted Construction Schedule, the Contractor shall submit to the COR a written time impact analysis illustrating the influence of each modification, change, delay, or Contractor request on the contract time.

2. Time Extensions: Activity delays, which result in projecting a late completion date, shall not automatically mean that an extension of the contract time is warranted or due the Contractor. It is possible that a modification, change, or delay will not affect existing critical path activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of the available total float that may exist within an activity chain of the Schedule, thereby not causing any effect on the contract time. Time extensions will be granted in accordance with the terms of the contract.

3. Extension of the contract time will be granted only to the extent the equitable time adjustments to the activity or activities affected by the modification, change, or delay exceeds the total (positive or zero) float available on a particular activity.

4. Procedure: Each time impact analysis shall be submitted within the time period stated in a request for proposal, or the time period designated under the clauses entitled Changes or Default. In cases where the Contractor does not submit a written request for extension of time and a time impact analysis within the designated time, it is mutually agreed that the particular modification, change, delay, or Contractor request does not require an extension of the contract time. Upon acceptance, the time impact analysis shall be incorporated into the currently accepted Construction Schedule at the next monthly schedule update.

5. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragments to demonstrate the effect of the proposed change on the overall Construction Schedule.

1.5 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

2. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

YOSE – 215798 01 10 00 - 7

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 4 3 1 1 - - - - - 1 2 3

3. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in the paragraph, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the provisions of this contract.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 10 00

YOSE – 215798 01 11 00 - 1

SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work under other contracts.

3. Contractor use of premises.

4. Public use of site.

5. Work Site Limitations.

6. Occupancy requirements for buildings.

7. Work Restrictions.

8. Special Construction Requirements.

9. Soils Investigation Report.

1.2 DEFINITIONS

A. The following terms, when used in the Contract Documents, shall have the meanings listed:

1. COR – “Contracting Officer Representative”

2. YNP – “Yosemite National Park”

3. Acceptable – “acceptable to the Contracting Officer”

4. Perform – “perform all operations required to complete the work referred to in accordance with the intent of the Contract Documents"

5. Provide – “furnish and install the work referred to including proper anchorage, connection to required utilities or other work, testing, adjustment and startup ready to put in service and perform the intended function”

6. Required – “required by the Contract Documents or required to complete the Work and produce the intended results”

7. Satisfactory – “acceptable to the Contracting Officer”

8. Shown – “as indicated on the Drawings”

9. Site – “geographical location of the Project and land within the work area shown on the contract drawings and within which the Work will be installed or built”

10. Specified – “as written in the Contract Documents including the Specifications and the

Drawings”

11. Submit – “Submit to the Contracting Officer Representative”

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Bridalveil Fall Parking Lot on Highway 41, Yosemite Valley, Yosemite National Park, California.

YOSE – 215798 01 11 00 - 2

B. The Work consists of the following:

The Work includes construction of a new comfort station, associated grading and site improvements; furnish and installation of water chlorination/electrical prefabricated building and associated appurtenances; installation of electrical and communication wires between new chlorination/electrical building, water tank and well in existing conduits; installation of electrical wire between new comfort station and chlorination/electrical building in existing conduits;

installation of fiber optic cable between existing lift station and new chlorination/electrical building;

installation of a new submersible well pump in a newly constructed well drilled by others, furnish and installation of a new bolted steel water tank and associated grading and concrete slab; furnish and installation of SCADA control panel and VHF antenna in chlorination/electrical building and Turtleback Dome site; integrate and test the control system between existing lift station, chlorination/electrical building and Yosemite Valley existing SCADA system.

C. Project will be constructed under a single prime contract.

1.4 SEQUENCE OF WORK

A. The Work shall be conducted in accordance with the approved Contractor’s Baseline Schedule.

1.5 GOVERNMENT-FURNISHED MATERIAL

A. General requirements:

1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.

2. After delivery, Government will inspect delivered items for damage. Contractor shall be present for and assist in Government's inspection.

3. If Government-furnished items are damaged, defective, or missing, Government will arrange for replacement.

4. Contractor is responsible for receiving, unloading, and handling Government-furnished items at Project site.

5. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.

6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.

7. Contractor shall install and otherwise incorporate Government-furnished items into the Work.

B. Government-Furnished Products:

1. Part of the new Comfort Station plumbing fixtures as specified on specification section 22 42 00 “Plumbing Fixtures”.

1.6 CONTRACTOR USE OF SITE

B. General: The Contractor’s use of the premises is restricted to the designated work areas, including staging area(s) allocated for Contractor’s use and shown on the drawings or as approved by COR. In

YOSE – 215798 01 11 00 - 3

addition, and as specified below, the contractor may move personnel, equipment, and material on park roads for the purpose of performing the work, subject to restrictions described in the Contract Documents. General information about the use of YNP facilities is available in the following publications: Yosemite Official Map and Guide and Yosemite Guide. These are available at YNP entrance stations, visitor centers, and online at www.nps.gov/yose/index.htm. Contractor personnel shall at all times comply with all published regulations of YNP.

A. Storage of Materials: Confine storage of materials to areas indicated on Drawings or as approved by

COR.

B. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer’s Representative (COR) and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

C. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

D. Construction Camp: Establishment of a camp within the park will not be permitted.

E. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

F. Contractor Employee Parking: Contractor’s employee parking close to the job site is limited.

Contractor shall coordinate with COR for designated areas for employee parking and shall minimize the amount of employee’s vehicles parking within the designated areas.

1.7 PUBLIC USE OF SITE

A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and protect the public from all construction hazards. Road closures will NOT be permitted. Contractor shall work around traffic with an approved traffic control plan.

1.8 CONDUCT OF OPERATIONS

YOSE – 215798 01 11 00 - 4

A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.9 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 6:00 p.m., Monday through Friday, except when otherwise indicated.

1. If weekend, evening, or early morning hours are needed to complete project on schedule, Contractor shall obtain approval for proposed hours from COR.

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify COR not less than 14 days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without COR’s written permission.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.

1.10 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.

1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.

YOSE – 215798 01 11 00 - 5

1.11 SOILS INVESTIGATION REPORT

A. A soils investigation report by entitled Geotechnical Services, Proposed Bridalveil Fall Rehabilitation, Yosemite National Park, California and dated May 18, 2018 and supplemental letter Addendum dated June 22, 2018 have been prepared by Kleinfelder.

B. A copy of the report and addenda are available upon request to COR. While the records of data obtained may be considered by the Contractor to be correct, any conclusions or recommendations made in the reports are for information to the Design Engineer and are not a part of the Contract Documents.

END OF SECTION 01 11 00

YOSE-215798 01 20 00 - 1

PAYMENT PROCEDURES

SECTION 01 20 00 – PAYMENT PROCEDURES

PART 1 GENERAL

1 .1 SUMMARY

A. Section Includes: Procedures for estimating progress payments.

1 .2 PROGRESS ESTIMATES

A. Monthly payment requests shall be based upon information developed at monthly Application for Payment meetings and shall be prepared by Contractor. The approved Schedule of Values shall be the basis for Contractor’s payment requests.

B. Progress payments shall be based upon progress estimates by Contractor and verified by the Contracting Officer Representative of actual physical progress of the work, utilizing the Final Construction Schedule and the Schedule of Values approved by the Contracting Officer.

1 .3 CONDITIONS PRECEDENT TO PAYMENT REQUEST

A. The following conditions shall be precedent to the Contractor making application for payment.

Failure by the Contractor to perform any of the following requirements will result in the refusal of the request for payment and may incur liquidated damages as allowed by the Federal Acquisition Regulation (FAR).

1. Submittal of Final Construction Schedule

2. Submittal of monthly schedule update

3. Approval of Schedule of Values

4. Submission of in progress record drawings in accordance with Section 01 77 00: Closeout Procedures

PART 2 PRODUCTS NOT USED

PART 3 EXECUTION NOT USED

END OF SECTION 01 20 00

YOSE – 215798

01 27 00 - 1

DEFINITION OF CONTRACT PRICE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT PRICE ITEMS

A. The intent of this section is to explain, in general, what is and what is not included in the contract price proposal items, and the limits or cut-off points where one item ends, and another begins.

B. If no contract line item exists for a portion of the work, include the costs in the related item.

C. Each contract line item described below shall include all labor, material, and equipment required to complete the work.

D. Each contract line item and its sub-item will be paid on lump sum basis.

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

CONTRACT LINE ITEM No. 1 - COMFORT STATION BUILDING AND SITE

IMPROVEMENTS

1. Comfort Station Building: This item consists of construction of a comfort station, including but not limited to: site clearing and grading, SWPPP BMPs, foundation, exterior walls, exterior doors and windows, roof, interior partitions and doors, wall, floor, and ceiling finishes, lighting fixtures, plumbing fixtures and restroom accessories not furnished by Government, building signage, domestic water distribution system within building, sanitary waste within building (piping and clean outs), HRV system (including start-up, testing & commissioning), thermostats with covers, lighting & branch wiring, electrical service & distribution, and all temporary facilities for visitors, if required.

2. Site Improvements: This item includes but is not limited to concrete path and plaza around the new Comfort Station Building and coordination with other contractor for installation of Interpretation Items.

3. This bid item will be paid on a lump sum basis.

CONTRACT LINE ITEM No. 2 – WATER STORAGE TANK

1. This bid item consists of furnishing and installing a water storage tank as shown in Construction Drawings and specifications, including but not limited to: all labor, equipment and materials for site preparation and clearing, grading, SWPPP BMPs, groundwater control, excavation, 01 27 00 - 2 construction of tank slab as recommended by tank manufacturer and installation of a steel bolted water storage tank.

2. This bid item will be paid on a lump sum basis.

CONTRACT LINE ITEM No. 3 – CHLORINATION BUILDING AND WATER WELL

1. Chlorination Building: This bid item consists of furnishing and installing a prefabricated chlorination building, including but not limited to all labor, equipment and materials for site preparation and clearing, building installation and all chlorination system appurtenances as shown on construction drawings and specifications (including start-up, testing & commissioning of chlorination and distribution system).

2. Well Pump: This bid item consists of completing a water well, including but not limited to furnishing and installing a well pump, well pump housing and piping as shown on construction drawings and specifications, start-up, testing and commissioning of well.

3. This bid item will be paid on a lump sum basis.

CONTRACT LINE ITEM No. 4 – ELECTRICAL, COMMUNICATION AND SCADA

SYSTEM

1. Electrical System: This bid item consists of completing the electrical system for the new comfort station and water system as shown on construction drawings and specifications, including but not limited to: all labor, equipment and materials to install electrical wire in existing conduits; furnish and install electrical vaults as shown on drawings; furnish and install comfort station and water system dry transformers, furnish and install electrical panels and meters, connect to existing electrical systems, and test, start-up and commissioning the entire electrical system.

2. Communication System: This bid item consists of completing the communication and SCADA system for the water system and existing sewer lift station as shown on construction drawings, including but not limited to: all labor, equipment and materials to install fiber optic cable in existing conduits, furnish and install SCADA antenna and control panel in chlorination building and Turtleback Dome utility building, and test, start-up, integrate and commissioning the SCADA system.

3. Telephone Line: This bid item consists of furnishing and installing telephone cable in existing conduit as shown on drawings.

4. This bid item will be paid on a lump sum basis.

3.2 ALL OTHER ITEMS OF WORK

1. All work specified in construction drawings and specifications shall be included in the Contractor’s price proposal, such as but limited to: site restoration, cleanup, testing, final survey and As Built drawings, all electrical and control items and all other work to make the water system complete and functional.

2. Any items not specifically identified in the above descriptions shall be included as incidental to relevant Contract Line Items and in conformance with the individual sections of the technical specifications.

01 27 00 - 3

END OF SECTION 01 27 00

YOSE-215798 01 27 00.1-1

CONTRACT BID SCHEDULE

CONTRACT PRICE SCHEDULE

YOSEMITE NATIONAL PARK

GENERAL

Bridalveil Fall Rehabilitation – Utilities and Comfort Station Project Submit offer for all items; failure to do so may render the offer non-responsive. Limit amounts to zero decimal places (whole dollars). On lump-sum items, provide total price only. If no item exists for a portion of the work, include the costs in a related item. In case of error in summation, the total of the corrected bid amounts governs.

ITEM

NO. ITEM

QUANTITY & UNIT

OF MEASURE

AMOUNT OF

BID

BASE BID

1. COMFORT STATION BUILDING AND SITE IMPROVEMENTS

1.1 Comfort Station Building

1.2 Site Improvements

SUBTOTAL

LUMP SUM

LUMP SUM

LUMP SUM

2. WATER STORAGE TANK

2.1 Water Storage Tank

SUBTOTAL

LUMP SUM

LUMP SUM

3. CHLORINATION BUILDING AND WATER WELL

3.1 Chlorination Building

3.2 Water Well

SUBTOTAL

LUMP SUM

LUMP SUM

LUMP SUM

4. ELECTRICAL, COMMUNICATION AND SCADA SYSTEM

4.1 Electrical System

4.2 Communication System

4.3 Telephone Line

SUBTOTAL

LUMP SUM

LUMO SUM

LUMP SUM

LUMP SUM

TOTAL BASE BID OFFER

LUMP SUM

YOSE - 215798 01 31 00 - 1

PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination.

3. Coordination Drawings.

4. Requests for Information (RFIs).

5. Project Website.

6. Project meetings.

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 57 23 “Storm Water Pollution Prevention Plan”.

3. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

4. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

5. Section 01 91 14 “Total Building Commissioning” for coordinating the work with Owner’s Commissioning Authority.

A. COR: Contracting Officer Representative.

B. CMR” Construction Management Representative.

1.3 SUBMITTALS

A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer or COR will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

YOSE - 215798 01 31 00 - 2

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

8. Quality Control Plan.

9. Temporary Storm Water Pollution Prevention Plan (SWPP)

C. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base

Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer Representative (COR) for resolution of such conflicts.

c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.

e. Indicate required installation sequences.

2. Sheet Size: At least 8-1/2 by 11 inches but no larger than 30 by 42 inches.

3. Number of Copies: Submit two opaque copies of each submittal. COR will return one copy.

4. Refer to individual Sections for Coordination Drawing requirements for Work in those

Section

D. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans and Reflected Ceiling Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Show locations of visible ceiling-mounted devices relative to acoustical ceiling grid. Supplement plan drawings with section drawings where required to adequately represent the Work.

2. Plenum Space: Indicate subframing for support of ceiling and wall systems, mechanical and electrical equipment, and related Work. Locate components within ceiling plenum to accommodate layout of light fixtures indicated on Drawings. Indicate areas of conflict between light fixtures and other components.

3. Mechanical Rooms: Provide coordination drawings for mechanical rooms showing plans and elevations of mechanical, plumbing, fire-protection, fire-alarm, and electrical equipment.

4. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

5. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door

YOSE - 215798 01 31 00 - 3

floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

6. Mechanical and Plumbing Work: Show the following:

a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.

b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.

c. Fire-rated enclosures around ductwork.

7. Electrical Work: Show the following:

a. Runs of vertical and horizontal conduit 1-1/4 inches in diameter and larger.

b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.

c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.

d. Location of pull boxes and junction boxes, dimensioned from column center lines.

8. Review: COR will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility. If CO determines that coordination drawings are not being prepared in sufficient scope or detail, or are otherwise deficient, CO will so inform Contractor, who shall make changes as directed and resubmit.

9. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."

E. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:

1. File Preparation Format: Civil 3D 2012 .dwg file, operating in Microsoft Windows operating system.

2. File Submittal Format: Submit or post coordination drawing files using Portable Document

Format (PDF) file format.

3. COR will furnish Contractor one set of digital data files (AutoCAD.dwg) of Drawings for use in preparing coordination digital data files.

a. CO makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.

b. Digital Data Software Program: Drawings are available in AutoCAD.dwg.

1.4 CONSTRUCTION COORDINATION

A. Coordination with other contractors: NPS trail crews may be working on Bridalveil Fall Accessible trail simultaneously with this project. Contractor is responsible for coordinating with them at no additional cost to the Government. Additionally, Federal HWY contractor may be still performing some work in the area. Contractor is responsible for coordinating with them at no additional cost to the Government.

B. Coordination of work: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work.

Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

YOSE - 215798 01 31 00 - 4

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

C. Government Furnished Materials: It will be contractor responsibility to coordinate the receival and installation of Government furnish materials in order to avoid delays in the construction sequence and schedule.

D. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

E. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Permit requirements.

7. Pre-installation conferences.

8. Project closeout activities.

9. Commissioning activities.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form attached at the end of this section or use their own form. If Contractor choose to use their own form, it must at a minimum contain the same information shown on the provided form.

1. COR will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

YOSE - 215798 01 31 00 - 5

2. Date.

3. Project Name.

4. Contract Number.

5. RFI subject.

6. Specification Section number and title and related paragraphs, as appropriate.

7. Drawing number and detail references, as appropriate.

8. Field dimensions and conditions, as appropriate.

9. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

10. Contractor's signature.

11. Requested date for response.

12. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. COR’s Action: COR and/or CMR will review each RFI, determine action required, and respond. COR and/or CMR will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for…