This document contains a price schedule template for a federal contract solicitation to conduct structural flood mitigation work at Cottonwood Cove within Lake LAKE 158678. The solicitation number is 140P2021R0057 and is being issued by the National Park Service National Office within the Department of the Interior. The price schedule template includes line items for a berm and channel system, soil cement, and a remuneration fee totaling a base price of $75,000. It also contains eight optional line items that are unspecified. Offerors are required to submit pricing for all base and option line items. The total proposed price should include the base price plus all option prices.
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule Template
| CONTRACT PRICE SCHEDULE | |||||
| SOLICITATION NUMBER: 140P2021R0057 | |||||
| PARK - PMIS: LAKE - 158678 | |||||
| DEVELOPED AREA: Cottonwood Cove | |||||
| PROJECT TITLE: Structural Flood Mitigation at Cottonwood Cove | |||||
| Notice: Refer to FAR Clause 52.217-5, Evaluation of Options, as prescribed in FAR 17. Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting Officer to offer the best value to the Government. | |||||
| In addition to the offer that conforms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identity why the acceptance of the alternate proposal would be advantageous to the Government, see FAR Clause 52.215-1, Instructions to Offerors - Competitive Acquisition-Alternate II and DSC-36 Clause (Instructions for Submission of Offers and Other Information) in Section L of the Solicitation. | |||||
| CONTRACT LINE ITEM NUMBER (CLIN) | CONTRACT LINE ITEM (CLI) TITLE | QUANTITY | UNIT OF MEASURE | UNIT PRICE | TOTAL PRICE |
| 1 | Berm and Channel System | 1 | LS | $0.00 | $0.00 |
| 2 | Soil Cement | 1 | LS | $0.00 | $0.00 |
| 3 | Remuneration Fee | 1 | LS | $75,000.00 | $75,000.00 |
| TOTAL BASE PRICE (Contract Line Item Number 1 through 3) ----------------------------- | $0.00 | ||||
| 4 | NO OPTIONS/Alternatives | _ | _ | _ | $0.00 |
| 4 | OPTION B, (CLI Title) | - 0 | |||
| 5 | OPTION C, (CLI Title) | - 0 | |||
| 6 | OPTION D, (CLI Title) | - 0 | |||
| 7 | OPTION E, (CLI Title) | - 0 | |||
| 8 | OPTION F, (CLI Title) | - 0 | |||
| 9 | OPTION G, (CLI Title) | - 0 | |||
| 10 | OPTION H, (CLI Title) | - 0 | |||
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 4) -------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through 3) ---- | $0.00 | ||||
| All measurement and payment information is included in the project specifications, Section 012700. |