This combined synopsis and solicitation requests proposals for ship repair services for the sailing vessel Friendship of Salem located at the Salem Maritime National Historic Park in Salem, Massachusetts. The solicitation seeks a contractor to supply all labor, equipment, materials, supervision, and travel to perform repairs to maintain the vessel's seaworthiness and potential future certification as a small passenger vessel, as outlined in the attached statement of work. Quotes are due by August 13, 2021. The period of performance is from November 1, 2021 to August 31, 2022. Evaluation will be based on lowest price technically acceptable. The selected contractor will be responsible for all aspects of the repair work in accordance with the statement of work and Service Contract Act provisions.
View the file
Other files for this federal contract opportunity
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IGE worksheet deck etc. 201
| Proposal Bid Sheet - Main deck, transom and bulwarks repair on SV Friendship of Salem, Salem Maritime NHS, Salem, MA, PMIS 163908A | ||
| 5/27/21 | ||
| Item from SOW | Bid line totals | |
| Section |
Measurement is responsibility of the contractor.
10 General
20 Design and Install cover and outboard access
30 Remove and replace all deteriorated transom framing and planking
| 40 | Remove and replace stanchions, hull, bulwark planks, caprails, planksheer and change frame/stanchion connection |
| A | remove and pattern the caprail, bulwark planks, chesstrees, planksheer, stanchions and timberheads. |
B Hull, 126 SF mesured on inner layer
C make and install 57 new stanchions and timberheads
D Bulwarks waterway and caprail
E coatings and utilities
| 50 | Replace the main deck top layer, portions of the three sub-deck layers and associated beam repairs |
| A | General and removals |
B Capstan
C Beam and related repair
D Sub-deck and camber
E Install main deck and covering boards
60 Remove and replace Hatch coamings
(CLIN 10) TOTAL THIS PROJECT BASE CONTRACT
| OPTIONS: | |
| A | (CLIN 20) Related to SOW Section 00030, transom |
| Aa | Remove and reinstall; great cabin settee and rudder post box, transom interior trim and paneling, making small repairs and replacement as needed. |
| Ab | Remove and replace tiller box and its top, |
| Ac | prepare and paint all exerior transom carvings prior to re-installation |
| B | (CLIN 30) Related to SOW Section 00040, bulwarks, stanchions, hull, etc | |||
| Ba | Remove and store rail and bulwark attachments | |||
| Bb | reinstall items from line Ba | |||
| Firm fixed unit price options | Not to exceed quantity | Unit Price | ||
| Bc | Additional frame repairs, full thickness 1' removed plus scarph, in addition to 10 from base contract, per repair. Price each not to exceed (NTE) 10. | 10 | column C total NTE, column D Unit price | |
| Bd | Additonal up to 1/2 thickness frame repair, 1' removed plus scarphs, in addition to 20 from base contract, per repair. Price each not to exceed (NTE) 10. | 10 | column C total NTE, column D Unit price | |
| Be | Major additional frame repair to remove and replace, with 6:1 or better scarph, 1-3’ of full width/thickness deterioration below the main deck. Price each not to exceed (NTE) 5. | 5 | column C total NTE, column D Unit price | |
| Bf | Major additional frame repair to remove and replace, with 6:1 or better scarph, 3-5’ of full width/thickness deterioration below the main deck. Price each not to exceed (NTE) 5. | 5 | column C total NTE, column D Unit price | |
| Bg | Additional hull planking replacement measured on the inner layer, including required overlaps on other layers, above the wale plank, per 5 SF unit. Price each 5 SF unit, not to exceed (NTE) 100 SF (20 units). | 20 | column C total NTE, column D Unit price | |
| Bh | Remove and reinstall backstay staples and backing iron. Price each location, not to exceed (NTE) 4. | 4 | column C total NTE, column D Unit price | |
| Bi | Remove and replace a main or fore chain-wale and associated. Price each location, not to exceed (NTE) 4. | 4 | column C total NTE, column D Unit price | |
| Bj | Make and install one new pinrail. Price each location, not to exceed (NTE) 4. | 4 | column C total NTE, column D Unit price |
C (CLIN 40) Related to SOW Section to 00050, Deck, beams…
| Ca | Beam-end dutchmen if more than 10 from the base contract are required. Price each location, not to exceed (NTE) 5. | 5 | column C total NTE, column D Unit price |
| Cb | Beam repair up to full thickness and up to 3’ athwartships with scarphed Dutchman. Price each location, not to exceed (NTE) 5. | 5 | column C total NTE, column D Unit price |
| Cc | Repair major beam deterioration more than 3’ athwartships, requiring up to full replacement. Price each location, not to exceed (NTE) 3. | 3 | column C total NTE, column D Unit price |
| Cd | replace one set of mast partners and carlins. Price each location, not to exceed (NTE) 2. | 2 | column C total NTE, column D Unit price |
| Ce | Remove and replace sub-deck layers beyond base bid proposal amounts, cost per 1 SF of sub-deck, per layer. Price each SF section, not to exceed (NTE) 3050 SF. | 3050 | column C total NTE, column D Unit price |
| Cf | Remove and replace deterioration in beam tops, not at an end, of approx.1’ length and not more than ½ of cross section, using scarphed Dutchmen. Price each, not to exceed (NTE) 5. | 5 | column C total NTE, column D Unit price |
| CG | PT Blocks between frames spanning covering board to planksheer | ||
| CH | Replace windlass posts and fore fife rails (2) and belfry, rough timber supplied by NPS |
| D | (CLIN 50) Related to SOW Section MISC. OPTIONS |
| Da | Remove, replace and paint all aft deck house exterior wood components… |
| Db | Perform two laser scans, one before and one after work under this project. |
| Total options (CLINS 20, 30, 40, 50) | |
| Total base plus options (CLINS 10, 20, 30, 40, 50) |