B08_Att_2_Price_Schedule_140P8625Q0073.docx
DOCX document 21 KB Posted
- Attached to
- Repair Elevator Fort Mason Building 201, GOGA
- Solicitation number
- 140P8625Q0073
About this file
This document is a Price Schedule for Request for Quote (RFQ) 140P8625Q0073 for elevator repair at Fort Mason Building 201 within Golden Gate National Recreation Area. The solicitation involves four base Contract Line Items (CLINs) and one optional item, with pricing to be submitted on a lump-sum basis for specific elevator maintenance and upgrade tasks: (1) removing and installing a new elevator control system component, (2) replacing shaft seals, (3) reconditioning brake shoes, and (4) replacing guide rollers. The optional fifth CLIN covers installing earthquake shoes. The solicitation is issued by the Department of the Interior National Park Service Pacific West Region, with the total pricing to be evaluated to determine price reasonableness, though option exercise is not guaranteed. Offerors are required to submit quotes that conform to solicitation documents, with pricing errors to be resolved using unit prices or corrected total amounts.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| RFQ 140P8625Q0073 | Repair Elevator Fort Mason Building 201 |
| Attachment 2 Price Schedule | Golden Gate National Recreation Area |
Instructions:
Notice: Offerors are required to submit, at minimum, a quote that conforms to the solicitation documents with pricing for the items. Failure to do so may render the quote unacceptable. On lump-sum line items, provide the total price only.
If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The total of the base price, plus all option prices are anticipated to be evaluated in order to determine price reasonableness. Evaluation of options shall not obligate the Government to exercise the option.
| Description |
| Unit of Measure |
| Total Price |
CLIN: 0001
Remove and dispose of existing HPV600 and install new compatible HPV900 or manufacturer’s recommended and integrate into existing elevator control system in accordance with (IAW) the Statement of Work (SOW)
| Lump Sum |
| $ |
CLIN: 0002
Remove worm shaft/remove old packing/seal & install new seals IAW the SOW
| Lump Sum |
| $ |
CLIN: 0003
Remove brake shoes and send to be re-lined, disassemble & clean components and reinstall IAW the SOW
| Lump Sum |
| $ |
CLIN: 0004
Replace all guides with rollers IAW the SOW
| Lump Sum |
| $ |
| Total Base Price (Add lines 0001 – 0004) |
| $ |
CLIN: 0005 Option Item A Install earthquake shoes IAW the SOW
| Lump Sum |
| $ |
| Total Base Price plus Option Item A Price (Add lines 0001 – 0005 |
| $ |
File details come from the government source that posted it. Updated .