B08_Att_2_Additional_Note_Aquatic_Park_Turf_and_Irrigation_Project_SAFR_226144B.pdf

PDF 264 KB Posted

Attached to
LAWN AND IRRIGATION SYSTEM REPLACEMENT SAFR Federal contract opportunity
Solicitation number
140P8622R0007
Issued by
Department of the Interior National Park Service Pacific West Region

About this file

This document provides revisions to specifications for a federal contract to replace the lawn and irrigation system at the Aquatic Park in San Francisco. The contract is identified as Solicitation Number 140P8622R0007 between the Department of the Interior National Park Service Pacific West Region and offerors. Revisions include shortening the required maintenance period after installation from 120 days to 90 days. Offerors must also protect installed areas from damage caused by raccoons in addition to other risks outlined in the original specifications.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of the Interior

NATIONAL PARK SERVICE

SAN FRANCISCO MARITIME NATIONAL HISTORICAL PARK

FORT MASON CENTER, BUILDING E

SAN FRANCISCO, CALIFORNIA 94123

IN REPLY REFER TO:

Aquatic Park Turf and Irrigation Project SAFR 226144B

To All Bidders:

Please note the following revisions to the document entitled, “FINAL CONSTRUCTION DOCUMENTS SPECIFICATIONS, Aquatic Park Irrigation – Contract Documents SAFR 226144 B”.

- SECTION 32 90 00 PLANTING

3.10 PLANTING ESTABLISHMENT MAINTENANCE

A. General Requirements

1. Maintenance Period: The planting establishment maintenance period required shall be 120 calendar days after all planting and irrigation is complete, turf is installed/seeded, and as approved by Contracting Officer’s representative.

REVISION: The maintenance period must be 90 calendar days.

- SECTION 32 90 00 PLANTING

3.10 PLANTING ESTABLISHMENT MAINTENANCE

A. General Requirements

3. Protect all areas against damage, including erosion, trespass, insects, rodents, disease, etc. and provide proper safeguards. Maintain and keep all temporary barriers erected to prevent trespass.

REVISION: In addition to items mentioned in point 3, protect all areas from damage must include protection from damage caused by raccoons.