B08_Att_1_Specifications.pdf
PDF 11 MB Posted
- Solicitation number
- 140P2024R0058
About this file
This document appears to be the Specifications attachment for a federal contract opportunity identified as Solicitation Number 140P2024R0058, titled "GOGA 253655 Rehabilitate the Deteriorated China Beach Bath House, and Terrace". The opportunity is being issued by the Department of the Interior National Park Service National Office, a civilian federal agency, to rehabilitate the China Beach Bath House and Terrace at Golden Gate National Recreation Area in San Francisco, CA. The solicitation provides detailed specifications for the required rehabilitation work, including structural, architectural, and site improvements. No information is provided regarding response dates, award dates, pricing terms, set asides, or incumbent contractors. This appears to be a standalone technical specifications document and does not contain details on the overall procurement requirements.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Architecture
Planning
Conservation
FINAL CONSTRUCTION DOCUMENTS SUBMITTAL
China Beach Rehabilita on Golden Gate Na onal Parks Conservancy | June 25, 2024
CLIENT:
Golden Gate National Parks Conservancy
Fort Mason, Building 201
San Francisco, CA 94123
ARCHITECT:
Architectural Resources Group, Inc.
Pier 9, The Embarcadero, Suite 107
San Francisco, CA 94111
CIVIL ENGINEER:
Sherwood Design Engineers
58 Maiden Lane, 3rd Floor
San Francisco, CA 94108
LANDSCAPE:
SWA Group
301 Ba ery Street, 2 Mezzanine
San Francisco, CA 94111
STRUCTURAL/GEOTECHNICAL:
Rutherford + Chekene
375 Beale Street, Suite 310
San Francisco, CA 94105
MECH/ELEC/PLUMB ENGINEER:
Interface Engineering
135 Main Street, Suite 400
San Francisco, CA 94105
COST ESTIMATOR:
TBD Consultants
111 Pine Street, Suite 1315
San Francisco, CA 94111
HAZMAT INVESTIGATION:
Vista Environmental Consulting
2984 Teagarden Street
San Leandro, CA 94577
CHINA BEACH REHABILITATION
SAN FRANCISCO, CA
FINAL CONSTRUCTION DOCUMENTS
JUNE 25, 2024
TABLE OF CONTENTS 1
TABLE OF CONTENTS
Division 1 General Requirements
01 11 00 Summary of Work
01 26 00 Contract Modification Procedures
01 27 00 Definition of Contract Line Items
01 31 00 Project Management and Coordination
01 32 16 Construction Schedule
01 32 33 Photo Documentation
01 33 23 Submittal Procedures
01 34 00 Natural Habitat Requirements
01 35 13 Archeological Protection
01 35 23 Safety Requirements
01 35 91 Historic Preservation Treatment Procedures
01 40 00 Quality Requirements
01 42 00 References
01 43 39 Mock-Ups
01 45 00 Environmental Protection
01 50 00 Temporary Facilities
01 50 02 Trucking
01 50 04 Soil Management, Import and Export
01 56 00 Temporary Barriers and Controls
01 56 39 Temporary Tree and Plant Protection
01 57 19 Noise & Exterior Lighting Management
01 57 23 Temporary Storm Water Pollution Prevention
01 63 00 Product Substitution Procedures
01 67 00 Product Requirements
01 73 29 Cutting and Patching
01 73 40 Execution
01 74 19 Construction Waste Management and Disposal
01 77 00 Closeout Procedures
01 78 23 Operation and Maintenance Data
01 79 00 Demonstration and Training
01 81 13 Sustainable Design Requirements
01 91 14 Total Building Commissioning
Division 2 Existing Conditions
02 41 13 Selective Demolition
02 41 16 Selective Building Demolition
02 81 00 Hazardous Materials Remediation
TABLE OF CONTENTS 2
Division 3 Concrete
03 03 00 Restoration of Historic Concrete
03 10 00 Concrete Forming
03 12 36 Glass Fiber Reinforced Concrete Element
03 20 00 Concrete Reinforcing
03 30 00 Cast-In-Place Concrete
03 32 00 Landscape Cast-In-Place Concrete
03 33 00 Architectural Concrete
03 37 00 Shotcrete
03 61 00 Grouted Dowels in Concrete
Division 4 Masonry
DIVISION NOT USED
Division 5 Metals
05 01 70 Maintenance of Decorative Metal
05 05 25 Post-Installed Concrete Anchors
05 12 00 Structural Steel Framing
05 50 00 Metal Fabrications
05 52 13 Pipe and Tube Railings
05 73 00 Decorative Metal
05 75 13 Decorative Perforated Panels
Division 6 Wood, Plastics & Composites
06 10 00 Rough Carpentry
06 20 00 Finish Carpentry
06 41 00 Architectural Wood Casework
06 64 00 Plastic Paneling
Division 7 Thermal and Moisture Protection
07 21 00 Building Insulation
07 51 00 Built-Up Bituminous Roofing
07 62 00 Sheet Metal Flashing and Trim
07 71 00 Roof Specialties
07 92 00 Joint Sealants
Division 8 Openings
08 01 51.91 Steel Window and Louver Restoration
08 11 13 Hollow Metal Doors and Frames
08 11 16 Aluminum Doors
08 36 13 Sectional Doors
08 51 23 Steel Windows and Doors
08 71 00 Door Hardware
08 80 00 Glazing
08 91 00 Louvers
TABLE OF CONTENTS 3
Division 9 Finishes
09 01 30.91 Tile Restoration
09 02 10.01 Interior Plaster and Gypsum Board Restoration
09 22 16 Non-Structural Metal Framing
09 24 23 Exterior Cement Plaster Restoration
09 29 00 Gypsum Board
09 30 00 Tiling
09 51 00 Acoustical Ceilings
09 61 23 Concrete Vapor Emission Treatment
09 65 00 Resilient Flooring
09 67 00 Fluid-Applied Flooring
09 72 00 Wall Covering
09 77 23 Fabric Wrapped Panels
09 91 23 Interior Painting
09 97 00 Special Coatings
09 97 29 Concrete Floor Sealing
Division 10 Specialties
10 14 00 Signage
10 21 13.19 Plastic Toilet Compartments
10 28 00 Toilet, Bath and Laundry Accessories
10 44 00 Fire Protection Specialties
10 51 26 Plastic Benches
10 51 43 Wire Mesh Storage Lockers
10 75 00 Flagpoles
Division 11 Equipment
11 30 13 Residential Appliances
Division 12 Furnishings
12 36 00 Countertops
12 93 00 Site Furnishings
Division 13 Special Construction
Division 14 Conveying Equipment
Division 21 Fire Suppression
21 00 00 Fire Suppression Basic Requirements
21 05 00 Common Work Results for Fire Suppression
21 13 00 Fire Suppression Sprinkler Systems
Division 22 Plumbing
TABLE OF CONTENTS 4
22 00 00 Plumbing Basic Requirements
22 05 13 Common Motor Requirements for Plumbing Equipment
22 05 19 Plumbing Devices
22 05 23 General-Duty Valves for Plumbing Piping
22 05 29 Hangers and Supports for Plumbing Piping and Equipment
22 05 48 Vibration and Seismic Controls for Plumbing Piping and Equipment
22 05 53 Identification for Plumbing Piping and Equipment
22 05 93 Testing, Adjusting and Balancing for Plumbing
22 07 00 Plumbing Insulation
22 10 00 Plumbing Piping
22 30 00 Plumbing Equipment
22 40 00 Plumbing Fixtures
Division 23 Heating, Ventilation and Air Conditioning
23 00 00 Heating, Ventilation and Air Conditioning (HVAC) Basic Requirements
23 05 29 Hangers and Supports for HVAC Piping, Ductwork and Equipment
23 05 48 Vibration and Seismic Controls for HVAC
23 05 53 Identification for HVAC Piping, Ductwork and Equipment
23 05 93 Testing, Adjusting and Balancing for HVAC
23 07 00 HVAC Insulation
23 09 33 Electric and Electronic Control System for HVAC
23 21 13 HVAC Piping
23 31 00 HVAC Ducts and Casings
23 33 00 Air Duct Accessories
23 34 00 HVAC Fans
23 37 00 Air Outlets and Inlets
23 62 01 Variable Refrigerant Flow/Volume (VRF/VRVP) Systems
23 82 16 Air Coils
Division 25 Integrated Automation
Division 26 Electrical
26 00 00 Electrical Basic Requirements
26 05 09 Equipment Wiring
26 05 19 Low-Voltage Electrical Power Conductors and Cables
26 05 26 Grounding and Bonding for Electrical Systems
26 05 29 Hangers and Supports for Electrical Systems and Equipment
26 05 33 Raceways
26 05 34 Boxes
26 05 53 Identification for Electrical Systems
26 05 73 Electrical Distribution System Studies
26 08 10 Building Lighting Acceptance Testing and Documentation
26 09 00 Contactors and Control Devices
26 09 23 Occupancy and Vacancy Sensors
TABLE OF CONTENTS 5
26 09 25 Digital Lighting Controls
26 24 16 Panelboards
26 27 13 Electrical Metering
26 28 00 Overcurrent Protective Devices
26 28 16 Enclosed Switches and Circuit Breakers
26 33 23 Central Battery Equipment
26 51 00 Lighting
Division 27 Communications
27 00 00 Communications Basic Requirements
27 05 28 Pathways for Communications Systems
27 05 28.01 Communications Raceway System
27 05 28.28 Firestopping for Communications Systems
27 05 43 Underground Ducts and Raceways for Communication Systems
27 11 01 Communication Equipment Rooms
27 13 00 Communications Backbone Cabling
27 15 00 Communications Horizontal Cabling
Division 28 Electronic Safety and Security
28 00 00 Electronic Safety and Security Basic Requirements
28 08 01 Commissioning and Testing of Security System
28 10 00 Access Control and Intrusion Detection
28 23 00 Video Surveillance
28 31 00 Fire Detection and Alarm
Division 31 Earthwork
31 10 00 Site Clearing
31 20 00 Earth Moving
31 22 19 Landscape Grading
31 23 00 Structural Excavation and Fill
31 23 17 Utility Trenching and Backfilling
Division 32 Exterior Improvements
32 13 13 Vehicular Concrete Paving
32 31 36 Security Gates and Barriers
32 84 00 Planting Irrigation
32 91 13 Soil Preparation
32 93 00 Planting
32 98 13 Landscape Establishment
Division 33 Utilities
33 11 16 Water Systems
33 30 00 Sanitary Sewer
33 41 00 Site Storm Drainage Systems
33 43 00 Landscape Drainage
33 46 00 Subdrainage
SUMMARY OF WORK 01 11 00 - 1
PART 1 - GENERAL
SUMMARY
SECTION 01 11 00
SUMMARY OF WORK
2.1 THIS SECTION INCLUDES THE FOLLOWING:
A. Work covered by the Contract Documents
B. Work under other contracts
C. Government-furnished materials
D. Contractor use of the site
E. Public access and use of site
F. Work restrictions
G. Special construction requirements.
H. Field verification
I. Storm Water Pollution Prevention Plan
2.2
WORK COVERED BY CONTRACT DOCUMENTS
A. Location: The project site is located at China Beach in the Seacliff neighborhood of San
Francisco. The site is federal parkland managed by the National Park Service (NPS).
B. Scope: The work covered by these contract documents is the rehabilitation of the historic China
Beach Bathhouse and site improvements. The scope includes, but is not limited to, installation of architectural improvements, seismic upgrades, new mechanical, electrical, plumbing, and fire protection systems, repair and replacement of historic concrete elements, landscape design, and other elements described in the Contract Documents.
C. A hazardous Material Assessment Report has been conducted in the project area and is included as an Appendix to the Contract Documents. The Contractor must review the report to become familiar with known environmental and safety issues related to hazardous materials.
D. All aspects of this project shall be appropriately staged and phased to allow for maximum public access during the construction process.
1. Project will be constructed under a single prime Contract.
SUMMARY OF WORK 01 11 00 - 2
2.3 WORK UNDER OTHER CONTRACTS
A. General: The National Park Service may, during this Contract, have other construction work in progress at this project site. The Contractor shall work with the Contracting Officer and other contractors as necessary to coordinate activities.
B. Retaining walls, parking lot improvements, stormwater treatment, and associated work on the hillside above the Bathhouse and Terrace level will be constructed as part of a separate project by the Federal Highway Administration immediately preceding this project. Use of the site entry road, parking lot, and general site areas shall be closely coordinated.
2.4 GOVERNMENT-FURNISHED MATERIALS
A. Items to be furnished by the Government include: Signage regarding project construction.
2.5 CONTRACTOR USE OF SITE
A. The Contractor’s use of the premises is restricted to the designated work area. Materials and equipment must be stored inside the work area. Maintain all equipment and materials within lockable fence and provide 6’-0” temporary panel fence around the work area. Contractor shall maintain control of the site during the period of construction by creating perimeter control through fences per Section 01 56 00-Temporary Barriers and Controls.
B. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
C. Storage of Materials: Confine storage of materials to the staging area noted on the drawings or as approved by the Contracting Officer.
D. Temporary facilities: Refer to Section 01 50 00 – Temporary Facilities.
E. Staging Area: Contractor shall work with NPS to identify appropriate staging areas.
F. Preservation of Cultural, Historic, and Natural Resources:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect all cultural and historic resources in accordance with Section 01 56 00 – Temporary Barriers and Controls.
3. Protect all archaeological resources as identified by the NPS archaeologist in accordance
Section 01 35 13 – Archeological Protection.
SUMMARY OF WORK 01 11 00 - 3
4. Protect all historic resources in accordance with Section 01 35 91 – Historic Preservation
Treatment
5. Carefully supervise excavating, grading, filling, and other construction operations near sensitive plant species, cultural resources, and historic resources.
6. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times.
Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
7. Construction Camp: Establishment of a camp within the park will not be permitted.
8. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials.
Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
9. Contractor shall provide OSHA and other required postings regard safety at the site.
10. All Contractor employees and subcontractor employees shall be advised of the rules and regulations of the National Park Service.
11. Contractor and subcontractor vehicles not required on the worksite itself shall be parked in a location to be reviewed and approved by NPS.
2.6 PUBLIC USE OF SITE
A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public. Road closures may be permitted, when required, upon specific approval of Contracting
Officer. Submit closure request to Contracting Officer at least seven calendar days in advance of requested closure date.
1. Public access to the beach shall be provided throughout the construction period.
B. Emergency Vehicle Access: Contractor must always maintain access for emergency vehicles unless specifically exempted as a condition within the project contract. Any exemption should be limited to minimal temporary delays and include notification to park dispatch. Contractor will stop all work as necessary to allow passage of emergency vehicles and direct traffic flow to accommodate immediate passage of these vehicles. For those projects in which trenching is required, the Contractor shall have a sufficient number of steel plates on hand to bridge any gap necessary for emergency vehicle access.
SUMMARY OF WORK 01 11 00 - 4
2.7 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Partial Government Occupancy: Government may occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with
Government during construction operations to minimize conflicts and facilitate
Government usage. Perform the Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.
b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
2.8 CONDUCT OF OPERATIONS
A. Contractor personnel shall comply with all Federal and State law and regulations, including the
Golden Gate National Recreation Area Superintendent’s Compendium. Any exception must be specifically justified and approved in writing by the Contracting Officer.
1. The Superintendent’s Compendium can be found at this internet address:
http://home.nps.gov/goga/learn/management/upload/2014_Superintendent-s-
CompendiumV2_access.pdf
B. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
2.9 WORK RESTRICTIONS
A. On Site Work Hours: The 40-hour work week shall be generally performed during normal business working hours of 7 a.m. to 6:00 p.m., Monday through Friday, except when available daylight does not permit such or otherwise indicated.
1. Work will be permitted in the evenings or weekends by prior authorization of the NPS
Contracting Officer only. Submit requests 48 hours in advance of the work to the
Contracting Officer for approval.
2. Proposed exterior lighting for night work should be reviewed/approved by NPS
Contracting Officer. See section 01 57 19 Noise and Exterior Lighting Management.
3. No onsite work shall be performed during federal holiday periods unless otherwise authorized by the Contracting Officer.
http://home.nps.gov/goga/learn/management/upload/2014_Superintendent-s-CompendiumV2_access.pdf http://home.nps.gov/goga/learn/management/upload/2014_Superintendent-s-CompendiumV2_access.pdf http://home.nps.gov/goga/learn/management/upload/2014_Superintendent-s-CompendiumV2_access.pdf
SUMMARY OF WORK 01 11 00 - 5
4. Early Morning Hours: See section 01 57 19 Noise and Exterior Lighting
Management.
5. Hours for Loud activities: See section 01 57 19 Noise and Exterior Lighting
Management.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
a. See Spec Section 017340, item 3.2 “Execution” for utility marking and coordination with other utility providers.
4. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by
Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
a. Notify Contracting Officer not less than 5 working days in advance of proposed
b. utility interruptions.
c. Do not proceed with utility interruptions without Contracting Officer’s written permission.
5. Smoking: Smoking is not permitted within buildings or within 25 feet of entrances, operable windows, or outdoor air intakes. Designated smoking areas shall be approved by the Contracting Officer.
2.10 FIELD VERIFICATION
A. See Section 01 73 40 Execution.
2.11 SPECIAL CONSTRUCTION REQUIREMENTS
A. A. Hot Work Permit: A hot work permit is required for any cutting, welding or heat gun work.
No open flame torch work will be allowed. The NPS Fire Inspection office will issue the permit to the Contractor. Permit will be good through completion of work. The Contractor will be responsible for ensuring that all workers and subcontractors follow permit conditions.
SUMMARY OF WORK 01 11 00 - 6
2.12 STORM WATER POLLUTION PREVENTION PLAN
A. Government will supply the project SWPPP in conformance with Section 01 57 23
“Stormwater Pollution Prevention.”
B. Implement all appropriate requirements of the SWPPP per Section 01 57 23 “Stormwater
Pollution Prevention.”
PART 2 - (NOT USED) PART 3 - (NOT USED)
END OF SECTION
CHINA BEACH REHABILITATION FINAL CONSTRUCTION DOCUMENTS
SAN FRANCISCO, CA JUNE 25, 2024
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 1
SECTION 01 26 00
CONTRACT MODIFICATION PROCEDURES
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 2
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens; this includes insurance and taxes that the business must pay on behalf of the worker, such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from http://en.wikipedia.org/wiki/Employee
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 3
bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces.
This is not reimbursed by the Government and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Proposals must be received in the format and within the time frame specified in the Request for
Proposal letter. Costs or delays resulting from failure of Contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate
Form, or their own form, provided that it contains the same information and level of detail as the provided form. The government form is available at:
http://www.nps.gov/dscw/upload/ContractorEstimateForm_1-24-13.xls
3. Requests for extensions of contract time as a result of this change must be justified with a Time
Impact Analysis (TIA). TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the Contracting Officer. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the
Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work. Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct http://www.nps.gov/dscw/publicforms.htm#ct http://www.nps.gov/dscw/upload/ContractorEstimateForm_1-24-13.xls
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 4
be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the Government.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown more than $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated rental rates shall include the cost of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance
(cost of major overhaul is not included), depreciation, storage, insurance, and all incidentals.
Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 3, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit. Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31.
Profit percentages are based on risk factors found in FAR Part
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 5
31 which have been applied to the specific type of work included in this project. The following percentages establish the maximum allowable markups (OH&P) for contractor self- performed work:
Overhead - 10%
Profit – 6.8%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The Government will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the
Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS (not used)
PART 3 - EXECUTION (not used)
DEFINITION OF CONTRACT LINE ITEMS 01 27 00 - 1
SECTION 01 27 00
DEFINITION OF CONTRACT LINE ITEMS
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. Include all work shown or specified in the bid. If no contract line item exists for a portion of the work, include the costs in a related item.
1.2 MEASUREMENT AND PAYMENT
1. The total bid price shall cover all work required by the Contract Documents. All costs in connection with the proper and successful completion of the work, including furnishing all materials, equipment, supplies, and appurtenances; providing all construction, equipment, and tools; and performing all necessary labor and supervision to fully complete the work, shall be included in the unit and lump sum prices bid. All work not specifically set forth as to a bid item in the bid form shall be considered subsidiary obligations of Contractor and all costs in connection therewith shall be included in the bid prices.
2. Measurement for each bid item is shown on the List of Contract Line Items herein.
3. Payment shall be made in accordance with individual Contract Line Items herein for each unit installed, complete, and in place.
1.3 LIST OF CONTRACT LINE ITEMS (BASE BID)
A. Contract Line Item 1: Rehabilitation of China Beach Bathhouse –Structure, Exterior Envelope, and
Electrical Room
1. Base Bid: This item includes, but is not limited to, furnishing all materials, equipment, and labor for the rehabilitation of the historic China Beach bathhouse including all structural and exterior envelope improvements. The structural scope includes seismic upgrades, replacement of concrete elements, and structural repair work. The building envelope scope includes all architectural improvements, doors and windows, windscreens, roofing, railings, lighting, decontamination shower, and envelope repairs and finishes for a complete exterior rehabilitation. Installation of all main electrical equipment in room
116 and installation of all under slab piping throughout the building are included.
2. Measurement for payment will be by lump sum.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item 2: Rehabilitation of China Beach Bathhouse –Public Facilities
1. Base Bid: This item includes, but is not limited to, furnishing all materials, equipment, and labor for the rehabilitation of the public facilities in the China Beach Bathhouse. The scope includes all architectural, structural, mechanical, electrical, lighting, and plumbing work for a
DEFINITION OF CONTRACT LINE ITEMS 01 27 00 - 2
complete installation at rooms 116, 117, 118, 119, 120, 121, 123, 125, 127, 128, 129, and
130.
C. Contract Line Item 3: Rehabilitation of China Beach Bathhouse –Sitework
1. Base Bid: This item includes, but is not limited to, furnishing all materials, equipment, and labor for the rehabilitation of the China Beach site. The sitework scope includes all civil, utilities, and landscape improvements except elements identified as Bid Options. Installation of concrete paving P1 in lieu of P4 is included.
D. Contract Line Item 4: Concrete Repairs – Crack Repair and labor for the repair of 500 lineal feet of cracks in existing concrete on exterior walls, underside of overhangs, remaining observatory elements, bridge, window sills and stairs.
2. Measurement for payment will be on a lineal foot basis of repairs completed.
3. Payment will be made at the contract unit price.
E. Contract Line Item 5: Concrete Repairs – Spall Repair without Rebar Damage and labor for the repair of 150 square feet spalls without rebar damage in existing concrete on exterior walls, underside of overhangs, remaining observatory elements, bridge, window sills, and stairs.
2. Measurement for payment will be on a square foot basis for repairs completed.
F. Contract Line Item 6: Concrete Repairs – Spall Repair with Moderate Rebar Damage and labor for the repair of 150 square feet of spalls with moderate rebar damage in existing concrete on exterior walls, underside of overhangs, remaining observatory elements, bridge, window sills, and stairs.
G. Contract Line Item 7: Concrete Repairs – Spall Repair with Significant Rebar Corrosion and labor for the repair of 150 square feet spalls with significant rebar damage in existing concrete on exterior walls, underside of overhangs, remaining observatory elements, bridge, window sills, and stairs.
DEFINITION OF CONTRACT LINE ITEMS 01 27 00 - 3
1.4 BID OPTIONS
A. Bid Option 1: Interior Bathhouse Construction – Boat Storage, Lobby, Office, Hall 104, and
Mechanical Room
1. Bid Option 1: This item includes, but is not limited to, furnishing all materials, equipment, and labor for the completion of rooms 100, 102, 103, 104, 105, 107, and 109, including all architectural, mechanical, electrical, lighting, and telecommunications work. Installation of the entire fire sprinkler and alarm systems, and mechanical system are included. Installation of one light fixture closest to the entry door of the remaining shell spaces is included.
B. Bid Option 2: Interior Bathhouse Construction - Staff Locker/Shower/Rest Room
1. Bid Option 2: This item includes, but is not limited to, furnishing all materials, equipment, and labor for the completion of rooms 110, 111, 111A, 112, 113, 114 and
115 including all architectural, mechanical, electrical, lighting, and telecommunications work.
C. Bid Option 3: Interior Bathhouse Construction – Remainder of Interior Spaces
1. Bid Option 3: This item includes, but is not limited to, furnishing all materials, equipment, and labor for the completion of the remaining interior spaces, including all architectural, mechanical, electrical, lighting, and telecommunications work.
D. Bid Option 4: Sea Wall Repair
1. Bid Option 4: This item includes, but is not limited to, furnishing all materials, equipment, and labor for repair of damaged areas to the concrete cap of the historic sea wall. Repair will include patching spalled sections of the wall cap to match the material, finish, and profile of the historic wall. Include cap replacement due to exposed or delaminated concrete at 15% of the wall length and repair of horizontal cracking between the cap and top of wall at 10% of the wall length. Include allowance for concrete crack repair at 25 lineal feet at control joints in the sea wall.
2. Measurement for payment will be by unit price.
3. Payment will be based on the contract unit price.
E. Bid Option 5: Construct Terrace Extension Stair
1. Bid Option 5: This item includes, but is not limited to, furnishing all materials, equipment, and labor for the installation of the Terrace Extension Stair, including landing, handrails, and perimeter walls. Refer to sheet L7.10-L7.13 and associated structural drawings.
F. Bid Option 6: Construct Counters and Stools at Seawall
DEFINITION OF CONTRACT LINE ITEMS 01 27 00 - 4
1. Bid Option 6: This item includes, but is not limited to, furnishing all materials, equipment, and labor for the installation counters, stools, and companion seating at three locations.
Refer to sheet L7.8 and L7.9 for enlarged plans and details.
G. Bid Option 7: Concrete Repairs at Existing Seawall Stairs
1. Bid Option 7: This item includes, but is not limited to, furnishing all materials, equipment, and labor for the installation damaged areas to the concrete stairs connecting the terrace to the beach. Repair will include patching spalled sections of the wall cap to match the material, finish, and profile of the historic wall at 10% of the wall length. Include repairs to 20% of the stair treads having exposed corroded reinforcement and delaminated concrete.
2. Measurement for payment will be by unit price.
H. Bid Option 8: New Handrails at Existing Seawall Stairs
4. Bid Option 8: This item includes, but is not limited to, furnishing all materials, equipment, and labor for the installation of new metal handrails at the existing stairs leading from the terrace level to the beach. Handrails are to be provided on both sides of each stair and meet accessibility requirements. The paint system for the handrails shall match that of the new roof deck railings. Refer to sheets L1.1 and L1.2 for locations. Match elevations 6/L7.3 and detail 4/L7.3 for new railings.
5. Measurement for payment will be by lump sum.
6. Payment will be made at the contract lump sum price.
I. Bid Option 9: Replace Existing Guardrail and Handrail at Bottom of Trail Stair
1. Bid Option 9: This item includes, but is not limited to, furnishing all materials, equipment, and labor for the installation of new metal handrails at the existing stairs at the bottom of the mid-slope trail. Handrails are to be provided on both sides of each stair and meet accessibility requirements. The paint system for the handrails shall match that of the new roof deck railings. Bid option includes removal of existing railings and patching of concrete at removal locations. See details 4,5,6,7/A7.3 for new railings. Assume 20’-0” length of guardrail and handrails.
J. Bid Option 10: Replace Existing Stair at West End of Terrace
1. Bid Option 10: This item includes, but is not limited to, furnishing all materials, equipment, and labor for the installation of new code-compliant stair between the terrace level and beach. Provide guardrails and handrails both sides of stair per details
4,5,6,7/A7.3. Provide new level asphalt landing at tops of stairs and grade to meet adjacent concrete paving elevations. Bid option includes removal of existing stair and railings.
DEFINITION OF CONTRACT LINE ITEMS 01 27 00 - 5
K. Bid Option 11: Provide Graphic Concrete at West Terrace
1. Bid Option 11: This item includes, but is not limited to, furnishing all materials, equipment, and labor for the installation graphic concrete Type P4 at the west terrace in lieu of P1. Refer to sheet L7.2.
L. Bid Option 12: Concrete Repairs at Existing Ramp
4. Bid Option 12: This item includes, but is not limited to, furnishing all materials, equipment, and labor for the installation damaged areas to the concrete stairs connecting the terrace to the beach. Repair will include patching spalled sections of the wall cap to match the material, finish, and profile of the ramp at 100% of the wall length. Include repair of 25 square feet of spalls, cracks at control joints, and replacement of corroded reinforcement.
5. Measurement for payment will be by unit price.
6. Payment will be made at the contract unit price.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 1
SECTION 01 31 00
PROJECT MANAGEMENT AND COORDINATION
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Construction Coordination.
2. Submittals.
3. Coordination Drawings.
4. Requests for Information (RFIs).
5. Project meetings.
6. Environmental Coordination.
7. Permits.
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
PART 2 - PRODUCTS (Not Used)
3.1 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 2
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
9. Commissioning activities.
3.2 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the
Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-
Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Site Specific Safety and Health Plan (SSSHP).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses
(SF 1413).
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the
Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. List of required construction permits. Include the following information for each permit:
a. Name of permit.
b. The agency(ies) with jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held.
If all of these documents have not been received one week prior to the scheduled Pre- Construction
Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting
Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
3.3 CONTRACTOR’S USE OF CAD FILES
A. General: At Contractor’s written request, copies of CAD files will be provided to Contractor for
Contractor’s use in connection with Project, subject to the following conditions:
1. CAD files will be provided as is; no format or content changes to drawings, or changes to the objects in the drawing will be made by the Government.
2. Availability of CAD files may be subject to ownership and use restrictions by the Architect and other consultants responsible for their development.
3.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract
PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 3
Documents, Contractor shall prepare and submit an RFI electronically utilizing the NPS standard RFI format, with attachments in either Word or PDF format as necessary. Contractor’s own RFI form may be used if approved by the Contracting Officer.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by
Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.
1. Contracting Officer's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
2. Contracting Officer's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
3. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
3.5 PROJECT MEETINGS
A.…